Description 7.1 Should not have incurred any loss in more than two years during the last five years ending 31st March 2024 Audit report of last five years duly audited by C.A |
Description 7.2 Should have a solvency of Rs. 273643808.00 certified by his Bankers (The contracting firm/Agency Should have produce Bankers solvency certificate or revenue solvency certificate of value not less than 40% of the estimated cost) Attached Banker' certificate issued on or after Date of tender publish. |
Description 7.3 (a) Amount of Existing Commitments and ongoing works in Rupees. Attached as per sec 2- 1.4(b) bidders must declarer themselves their all excising commitment hiding fact be sufficient cause for rejection. (b) Amount of work for which bid already submitted in Rupees. Attached as per sec 2- 1.4(b) bidders must declarer themselves their all excising commitment hiding fact be sufficient cause for rejection. |
Description 7.4 Bidding Capacity = (AxNx3-B) should be equal to or more than the cost of the work and where N=Time of copletion of the project. Refer Audit report of last five year for A= Maximum value of construction works executed in any one year ending the last five years and Refer Form 'C' for B=Value of existing commitments and ongoing works to be completed during the period of completion of work for which pre-qualification has been invited. A B N B.C |
Description 3(a)(i) The contracting firm/agency shall be a well established and reputed firm specialised in the trade and registered as a legal entity for a minimum period of 10 years and having experience and capacity in the execution of similar works company - Memorandum and articles of association/ certificate of Incorporation. Firm- Partnership deed. Individual- Registration |
Description 3(a)(ii) In case of joint venture analysis based on joint venture documents only should be submitted ( The documents will be submitted as per RCD letter no 8131 dt 24.7.12 related to J.V) Name of organisation should not vary in the different document presented also should satisfy J.V guidelines laid in said letter. |
Description 3(b) Contractor/ firms should have achieved during last five years in any one year a minimum Annual financial turn over (In all classes of Civil Engineering Construction works only) at least 50% of the cost of work Balance Sheet, Profit and Loss & Audit Report (to be Indexed at the Rate of 8% for a year) |
Description 3( c) The contracting Firm/Agency should have satisfactorily completed as a Prime contractor during the last five years, ending (one month before date of tender) Three similar works each costing not less than 40% (forty percent) of the estimated cost or completed two similar works each costing not less than 60% (sixty percent) of the estimated cost or completed one similar work costing not less than 80% (eighty percent) of the estimated cost. Form 'B' Similar works completed(Escalataion factor applicable as per letter no 7291 dated 08/08/2019 of Building Construction Dept. As annexed ) |
Description 3( c)i a) Contractors/Firm's should have completed 3 - works costing not less than 40% of Estimated cost. Rs. 273643808.00 OR, 3( c)ii b) Contractors/Firm's should have completed 2 - works costing not less than 60% of Estimated cost. Rs. 410465712.00 OR, 3( c)iii b) Contractors/Firm's should have completed 1 - work costing not less than 80% of Estimated cost. Rs. 547287616.00 |
Description 3 (c) iv Note:- The completion certificate shall be issued by employer not below the rank of Executive Engineer or project manager. In case of private client the completion certificate and Valuation of Project issued by employer should be certified by the Retired Engineer/ Registered Valuer of Nationalised Bank/Insurance Company/ Income Tax Department. The bidders shall have to also submit good quality digital photographs of the completed projects. |
Description 3(c )v Contractor/ firms should have adequate capacity of carrying out electrical works (electrical contractor) . They should also indicate name of specialised fire-fighting agency. Should submit certificates for capacity of work and?1A? Class electrical contractor. Should submit certificate of capacity of electrical works |
Description 3(d) Firm should have required experience only in any state of India. 3(e) The contracting firm /agengy should produce evidence of accesss to lines of credit and availability of other financial resources facilties ( 10% of cost of work) certificate issue by bank as per prescribe format in Sec-2 |
Description 3(f) The bidders shall furnish under taking that he would be able to invest a minimum cash up to 25% of cost of work. Undertaking should be submitted |
Description 8.2 Not abandoning work, not properly completing the contract , or financial failures/weaknesses etc. "Form G" ATTACHED AFFIDAVIT ON AND AFTER PUBLISH TENDER 9 NOC FOR DEBAR ATTACHED SELF DECLARATION 10 Oath of follow labour Rule and Regulations as per Govt. norms ATTACHED AFFIDAVIT ON AND AFTER PUBLISH TENDER 11 Personal and Establishment form 'E' and E-I as per Sec 2 -1.6 attached necessary certificate and affidavit of both employee and employer on and after publish of tender 12 PLANTS AND EQUIPMENT form 'F' as per Sec 2- 1.5 MAX. AGE 5 YEARS.ATTACHED OWNED VOUCHER AND AFFIDAVIT IN CASE OF LEASE HIRE ON AND AFTER PUBLISH DATE OF TENDER |