noticeInvitingTenderDTO
createdTs1708608329507
version3
createdDateNone
modifiedDateNone
tenderTypeRFQ
evaluationTypeTWO_COVER
evaluationTypeTextTwo Cover
invitingStrategyOPEN
invitingStrategyTextOpen
taxTypeINCLUSIVE_TAX
tenderFee1420.00
emd133400.00
bidValueTypeITEM_WISE
bidValueTypeTextItem wise
tenderReceiptClose05-03-2024 16:30:00
tenderQueryClose04-03-2024 16:30:00
technicalBidOpen06-03-2024 17:00:00
publishedDate26-02-2024 16:59:48
publishedByPostPWD_EE_DIV_CKM
publishedByUserKPE11164 - D N SRIDHAR
bidValidityPeriod90
noOfCalls1
preBidMeetingDateNone
preBidMeetingYnFalse
preQualificationBidOpenNone
denominationTypeRUPEES
denominationTypeTextRupees
retenderedYnNone
percentageRateTypeTextNone
contactPersonD N Sridhar
splitEmdRequiredYnTrue
emdBankGuarantee33400.00
emdCash100000.00
bgValidityPeriod135
hideWeightageNone
multipleCurrencySelectionAllowedYnFalse
isTechWeightageAllowedFalse
highestBidderSelectionFalse
isVariableEmdAllowedNone
qcbsTenderYnNone
itemwiseEmdRequiredYnNone
sampleSubmissionDateNone
officeNumber08262234028
mobileNumberNone
tenderSupplierListNone
tenderSchedule
createdTs1708608329537
version5
createdDateNone
modifiedDateNone
tenderNumberPWD/2023-24/RD/WORK_INDENT8964
titleReconstruction of road and Protection Works for SH-65 Malpe-Molakalmuru Road (from ch 72.00 -84.45km) in selcted reaches in Sringeri Constituency
descriptionReconstruction of road and Protection Works for SH-65 Malpe-Molakalmuru Road (from ch 72.00 -84.45km) in selcted reaches in Sringeri Constituency
categoryWORKS
categoryTextWorks
ecv5651386.34
deptNamePublic Works Department
statusPUBLISHED
statusTextPublished
remarksNone
csrValueNone
ecvtenderYnTrue
location1699
locationNamePWD Division Office Chikkamagaluru
provisionalAmount7000000.0
groupOverheadTotal0.0
fileNumberAEE/PWD/KOPPA/2023-24/3054/SH/MM
tenderSubEstimateList
createdTsversioncreatedDatemodifiedDateworkCategoryNamesubEstimateNameestimateTotalitemList
17086083300000NoneNoneRoadsReconstruction of road and Protection Works for SH-65 Malpe-Molakalmuru Road (from ch 72.00 -84.45km) in selcted reaches in Sringeri Constituency5651386.34
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
276731088216None3.5Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of scarified material by Mechanical Means using Hydraulic excavator with in all lifts and lead ( Vol-3, I.No. 3.5 Pg No:17) ---- Including cost and conveyance of all materials Labour Hire charges of Machineries and Equipments with all lead and lifts, loading and unloading charges etc.. Complete as directed as per specification and direction of Engineer in-charge of the work.Sqm6.726.72605.0FalseNoneNoneFalseNoneFalse4065.60
276731188216None4.17Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver/grader in sub-base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. '( Vol-3, I.No. 4.17 Pg No:26) ---- Including cost and conveyance of all materials Labour Hire charges of Machineries and Equipments with all lead and lifts, loading and unloading charges etc.. Complete as directed as per specification and direction of Engineer in-charge of the work.Cum2866.082866.08136.12FalseNoneNoneFalseNoneFalse390130.80960
276731288216None5.1Providing and applying primer coat with SS1 grade Bitumen Emulsion on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.90 kg per m2 using mechanical means. '( Vol-3, I.No. 5.1 Pg No:31) ---- Including cost and conveyance of all materials Labour Hire charges of Machineries and Equipments with all lead and lifts, loading and unloading charges etc.. Complete as directed as per specification and direction of Engineer in-charge of the work.Sqm45.9245.92605.0FalseNoneNoneFalseNoneFalse27781.60
276731388216None5.3Tack coat on Bituminous surface Providing and applying tack coat with RS1 Bituminous Emulsion using emulsion pressure distributor at the rate of 0.20 kg/m2 on the prepared bituminous surface cleaned with mechanical broom ( Vol-3, I.No. 5.3 Pg No:31) ---- Including cost and conveyance of all materials Labour Hire charges of Machineries and Equipments with all lead and lifts, loading and unloading charges etc.. Complete as directed as per specification and direction of Engineer in-charge of the work.Sqm13.4413.444345.0FalseNoneNoneFalseNoneFalse58396.80
276731488216None5.8CBituminous Macadam Grading - II for traffic lesser than 20 MSA Providing and laying Bituminous Macadam with 40/60 TPH capacity hot mix plant using crushed aggregates of specified grading premixed with bituminous binder VG-30 @ 3.4% by weight of mix, transported to site, laid over a previously prepared surface with mechanical paver finisher to the required grade, level and alignment and rolled as per clauses 501.6 and 501.7 to achieve the desired compaction ( Vol-3, I.No. 5.8.c Pg No: 33) ---- Including cost and conveyance of all materials Labour Hire charges of Machineries and Equipments with all lead and lifts, loading and unloading charges etc.. Complete as directed as per specification and direction of Engineer in-charge of the work.Cum8580.328580.32269.22FalseNoneNoneFalseNoneFalse2309993.75040
276731588216None5.31Providing and laying Semi Dense Bituminous Concrete with 40/60 TPH capacity hot mix plant batch type using crushed aggregates of specified grading premixed with bituminous binder VG-30 @ 5% by weight of mix and filler, transported to site, laid over a previously prepared surface with mechanical paver finisher to the required grade, level and alignment and rolled as per MoRTH V revision. '( Vol-3, I.No. 5.31 Pg No: 43) ---- Including cost and conveyance of all materials Labour Hire charges of Machineries and Equipments with all lead and lifts, loading and unloading charges etc.. Complete as directed as per specification and direction of Engineer in-charge of the work.Cum11370.2411370.24123.75FalseNoneNoneFalseNoneFalse1407067.20
276731688216None3.6Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2 '( Vol-3, I.No. 3.6 Pg No: 17) ---- Including cost and conveyance of all materials Labour Hire charges of Machineries and Equipments with all lead and lifts, loading and unloading charges etc.. Complete as directed as per specification and direction of Engineer in-charge of the work.Cum552.16552.16540.0FalseNoneNoneFalseNoneFalse298166.40
276731788216None1.14.2Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work Depth 3 m to 6 m '( Vol-1, I.No. 1.14.2 Pg No:8) ---- Including cost and conveyance of all materials Labour Hire charges of Machineries and Equipments with all lead and lifts, loading and unloading charges etc.. Complete as directed as per specification and direction of Engineer in-charge of the work.Cum131.04131.0496.53FalseNoneNoneFalseNoneFalse12649.29120
276731888216None2.1.3Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications.Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates '( Vol-1, I.No. 2.1.3 Pg No:15) ---- Including cost and conveyance of all materials Labour Hire charges of Machineries and Equipments with all lead and lifts, loading and unloading charges etc.. Complete as directed as per specification and direction of Engineer in-charge of the work.Cum6707.686707.6810.12FalseNoneNoneFalseNoneFalse67881.72160
276731988216None2.11 hSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification SFor Other works '( Vol-1, I.No. 2.11.h Pg No:18) ---- Including cost and conveyance of all materials Labour Hire charges of Machineries and Equipments with all lead and lifts, loading and unloading charges etc.. Complete as directed as per specification and direction of Engineer in-charge of the work.Tonne88492.3288492.323.91FalseNoneNoneFalseNoneFalse346004.97120
276732088216None2.4.3Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates '( Vol-1, I.No. 2.4.3 Pg No:16) ---- Including cost and conveyance of all materials Labour Hire charges of Machineries and Equipments with all lead and lifts, loading and unloading charges etc.. Complete as directed as per specification and direction of Engineer in-charge of the work.Cum7096.327096.3214.85FalseNoneNoneFalseNoneFalse105380.3520
276732188216None2.4.3Formwork, Centering & Scaffloding For Drain Stem3% ---- Including cost and conveyance of all materials Labour Hire charges of Machineries and Equipments with all lead and lifts, loading and unloading charges etc.. Complete as directed as per specification and direction of Engineer in-charge of the work.Cum212.89212.8914.85FalseNoneNoneFalseNoneFalse3161.41650
276732288216None2.4.3Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates '( Vol-1, I.No. 2.4.3 Pg No:16) ---- Including cost and conveyance of all materials Labour Hire charges of Machineries and Equipments with all lead and lifts, loading and unloading charges etc.. Complete as directed as per specification and direction of Engineer in-charge of the work.Cum7096.327096.3215.0FalseNoneNoneFalseNoneFalse106444.80
276732388216None2.4.3Formwork, Centering & Scaffloding 10% For Drain Raft ---- Including cost and conveyance of all materials Labour Hire charges of Machineries and Equipments with all lead and lifts, loading and unloading charges etc.. Complete as directed as per specification and direction of Engineer in-charge of the work.Cum709.63709.6315.0FalseNoneNoneFalseNoneFalse10644.450
276732488216None12.3Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates ---- Including cost and conveyance of all materials Labour Hire charges of Machineries and Equipments with all lead and lifts, loading and unloading charges etc.. Complete as directed as per specification and direction of Engineer in-charge of the work.Cum7096.327096.3231.84FalseNoneNoneFalseNoneFalse225946.82880
276732588216None2.4.3Formwork, Centering & Scaffloding 8% For Culvert ---- Including cost and conveyance of all materials Labour Hire charges of Machineries and Equipments with all lead and lifts, loading and unloading charges etc.. Complete as directed as per specification and direction of Engineer in-charge of the work.Cum567.71567.7131.84FalseNoneNoneFalseNoneFalse18075.88640
276732688216None2.4.3Providing and laying of Filter media with granular materials/ stone crushed aggregates satisfying the requirements laid down in clause 2504.2.2. of MoRTH specifications to a thickness of not less than 600 mm with smaller size towards the soil and bigger size towards the wall and provided over the entire surface behind abutment, wing wall and return wall to the full height compacted to a firm condition complete as per drawing and Technical Specification. '( Vol-3, I.No. 12.4 Pg No: 117) ---- Including cost and conveyance of all materials Labour Hire charges of Machineries and Equipments with all lead and lifts, loading and unloading charges etc.. Complete as directed as per specification and direction of Engineer in-charge of the work.Cum2998.242998.2420.25FalseNoneNoneFalseNoneFalse60714.360
276732788216None1.8Construction of Embankment by excavating the available approved Gravel/ Murrum deposited at a place or borrow pits during or prior excavation with all lifts and lead, transportation to site, spreading, grading to required slope and compacting to meet the requirement complete as per specifications, including cost of labour,rolling,water,all materials,usage& all other appurtenaces required to complete the work. ( Vol-1, I.No.1.8 Pg No:7) ---- Including cost and conveyance of all materials Labour Hire charges of Machineries and Equipments with all lead and lifts, loading and unloading charges etc.. Complete as directed as per specification and direction of Engineer in-charge of the work.Cum530.88530.8875.0FalseNoneNoneFalseNoneFalse39816.00
276732888216None8.5(ii)Providing and fixing of retro- reflectorised cautionary, mandatory and informatory sign as per IRC:67:2012 made of Class B Type IV retro reflective sheeting fixed over 2 mm thick aluminium sheeting vide clause 803.1, 3mm/4mm thick Aluminium composite material sheet depending on the size of the sign fixed over the back support frame of min 25 x 25 x 3mm angle mounted on a mild steel circular pipe 65 NB, 3.2 mm thickness firmly fixed to the ground by means of properlydesigned foundation with M25 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing.The sign shall be maintained as per section 12 of IRC:67:2012. 90 cm equilateral triangle '( Vol-3, I.No. 8.5(ii) Pg No: 64) ---- Including cost and conveyance of all materials Labour Hire charges of Machineries and Equipments with all lead and lifts, loading and unloading charges etc.. Complete as directed as per specification and direction of Engineer in-charge of the work.Nos5246.085246.086.0FalseNoneNoneFalseNoneFalse31476.480
276732988216None8.5(vi)Providing and fixing of retro- reflectorised cautionary, mandatory and informatory sign as per IRC:67:2012 made of Class B Type IV retro reflective sheeting fixed over 2 mm thick aluminium sheeting vide clause 803.1, 3mm/4mm thick Aluminium composite material sheet depending on the size of the sign fixed over the back support frame of min 25 x 25 x 3mm angle mounted on a mild steel circular pipe 65 NB, 3.2 mm thickness firmly fixed to the ground by means of properlydesigned foundation with M25 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing.The sign shall be maintained as per section 12 of IRC:67:2012. 90 cm circular ( Vol-3, I.No. 8.5(vi) Pg No: 64) ---- Including cost and conveyance of all materials Labour Hire charges of Machineries and Equipments with all lead and lifts, loading and unloading charges etc.. Complete as directed as per specification and direction of Engineer in-charge of the work.Nos7060.487060.486.0FalseNoneNoneFalseNoneFalse42362.880
276733088216None8.8Direction and Place Identification Signs with size more than 0.9 m2 size Board. Providing and erecting direction and place identification retroreflectorised sign as per IRC:67:2012 made of high intensity grade sheeting vide clause 801.3, fixed over aluminium sheeting, 2 mm thick or Aluminium composite material sheet with overall thickness of 4mm with area exceeding 0.9 m2 fixed over back support frame of min 40 x 40 x 5mm angle mounted on a mild steel circular pipe 65 NB, firmly fixed tothe ground by means of properly designed foundation with M25 grade cement concrete 45 x 45 x 60 cm, 60 cm below ground level as per approved drawing ( Vol-3, I.No. 8.8Pg No: 65) ---- Including cost and conveyance of all materials Labour Hire charges of Machineries and Equipments with all lead and lifts, loading and unloading charges etc.. Complete as directed as per specification and direction of Engineer in-charge of the work.Sqm10866.2410866.245.76FalseNoneNoneFalseNoneFalse62589.54240
276733188216None8.17Supplying and installation of delineators (road way indicators, hazard markers, object markers), 80-100 cm high above ground level, painted black and white in 15 cm wide strips, fitted with 80 x 100 mm rectangular or 75 mm dia circular reflectorised panels at the top, buried or pressed into the ground and conforming to IRC-79 and the drawings ( Vol-3, I.No. 8.17 Pg No: 67) ---- Including cost and conveyance of all materials Labour Hire charges of Machineries and Equipments with all lead and lifts, loading and unloading charges etc.. Complete as directed as per specification and direction of Engineer in-charge of the work.Each2263.522263.5210.0FalseNoneNoneFalseNoneFalse22635.20
generalCriterionList
createdTsversioncreatedDatemodifiedDatecriterionTypedescriptiontenderEligibilityCriterionDocumentList
17086083300000NoneNoneELIGIBILITYTenders from Joint ventures are not acceptable.None
17086083300000NoneNoneELIGIBILITYBidders shall not be under a declaration of ineligibility for corrupt and fraudulent practices issued by Government of Karnataka None
17086083300000NoneNoneELIGIBILITYBidders shall ensure upload of relevant document certifying his/her status as Scheduled Caste/ Scheduled Tribe/other reserved category as prescribed in the tender document.None
17086083670000NoneNoneELIGIBILITYBidders shall ensure upload of relevant document as prescribed in the tender document in Complete Manner.None
17086083810000NoneNoneELIGIBILITYThe tenderer should be a PWD registered Contractor - also Contractors should have Registration of GST, Employers Provident Fund and tenderer should submit Registration Certificate along with technical bid.None
17086083890000NoneNoneELIGIBILITYAs per Karnataka state Government order LD/300/LET/2006 Bangalore dated 01.01.2007 and Government letter no PW/134/BMS/2007 dated 27.07.2007, a sum amounting to 1% of the bill amount will be deducted towards constructions labor welfare fund and Contractors should follow strictly prevailing rules of labor act.None
17086083960000NoneNoneELIGIBILITYConditional tenders will not be accepted.None
17086084030000NoneNoneELIGIBILITYRoyalty on construction materials and other taxes will be deducted as per prevailing Government orders. The item rates quoted shall include cost of royalty charges on construction materials & other taxes as per the rates provided in prevailing cost & conveyance of all materials, Curing, Watering, unloading with all leads & lifts labor, hire charges of machinery equipment etc., complete including all incidental charges. All the items shall be executed as directed by the Engineer in charge of the work.None
17086084110000NoneNoneELIGIBILITYThe bidder shall bear all costs associated with the preparation and submission of his tender, and the employer will in no case be responsible and liable for those costs. The tender fee is non-refundable and The employer is not responsible for any delay in accessing KPP portal.None
17086084200000NoneNoneELIGIBILITYOnly Original documents to be scanned and uploaded, Executive Engineer reserves the right verify the Original Documents before approval, 0riginal documents / Certificates for qualification shall be produced when called for during evaluation of tender.None
17086084280000NoneNoneELIGIBILITYThe Tenderer should maintain the Work during defective liability period as indicated in The Contract DataNone
17086084350000NoneNoneELIGIBILITYThe materials like bitumen, Steel, Cement etc., required for the work shall be procured by the tenderer themselves and should be got tested by the Quality Control Authority before use on the workNone
17086084430000NoneNoneELIGIBILITYTenderer shall obtain the Work done Certificate in the prescribed format from the Competent Authority not below the rank of Executive Engineer (District Level Officer) and scan the Original Certificate and attach the scanned file to the tender. The Original Certificate shall be produced at the time of opening of Technical Bids for physical verification, if sought.None
17086084500000NoneNoneELIGIBILITYAs per Government order FD 447 EXP-12 2022 dated 30/07/2022, 18% GST will be added to the Contract amount separately. And Increase in GST shall not be paid in the extended period of contract for which the contractor alone is responsible for delay as determined by the authority while granting the extension of time.None
17086084600000NoneNoneELIGIBILITYEstimate rates are excluding GST as per Common SR 2023-24 and prevailing GST (18% of Amount Put to tender) amount is kept in form of Lump sum in sanctioned estimate according to guidelines in Common SR (GO:PWD 51 RDF 2019 Bangaluru Dt:18.03.2022). Therefore, amount put to Tender and ECV amount are excluding GST. KPPP-PORTAL format has No Options to add GST Separately at stage of Draft Tender Schedule Process for Over All amount put to Tender, tender has been inviting through an Option with INCLUSIVE. But the item wise rates do not include GST. Hence, GST will be paid separately for the quoted amount accordingly. Declaration Certificate must be attached mandatorily.None
17086084670000NoneNoneELIGIBILITYThe employer reserves the rights to reject one or all tenders without assigning any reason.None
17086084770000NoneNoneELIGIBILITYIn case if the death of a contractor, after executing the agreement / commencement of the work, his legal heir, is an eligible registered contractor and is willing, can execute and complete the work, at the accepted tender rates, irrespective of the cost of the work.None
17086084860000NoneNoneELIGIBILITYPERFORMANCE SECURITY - The successful tenderer shall furnish Performance Security Deposit (Achievement Guarantee) at 5% of the amount put to tender with in 20 days after approve of tender as per rule 29.5 of the tender and clause 44 of the agreement in the form of FDR/Bank Guarantee duly pledged in the nature of EXECUTIVE ENGINEER, PWD Chikmagalur Division.None
17086084970000NoneNoneELIGIBILITYAll safety precautions, warning signs, night illumination, reflectors, deployment of security guards has to be ensured so that no untoward incident happens on account of negligence or any project activity. Contractor should indemnify the client to that extent.None
17086085120000NoneNoneELIGIBILITYItem for which no rates or price has been entered in will not be paid for by the Employer when executed & shall be deemed covered by the other rates & prices in the bill of quantities.None
17086085200000NoneNoneELIGIBILITYThe tender validity period is 90Days from the date of opening of TenderNone
17086085280000NoneNoneELIGIBILITYContractors has to upload the EPF Registration with January 2024 Challan Copy. Contractors has to submit their labour EPF details with every Running BillNone
17086085360000NoneNoneELIGIBILITYThe intending contractors are requested to note that they should abide by the detailed instructions and conditions contained in the Standard Bid document.None
17086085420000NoneNoneELIGIBILITYThe rates are exclusive of GST. The contractors has to quote the rates without GST. GST will be paid separately as per prevailing Government order.None
17086085510000NoneNoneELIGIBILITYTHE CONTRACTOR SHALL SUBMIT THE DETAILS OF TECHNICAL STAFF EMPLOYED BY HIM.None
17086085590000NoneNoneELIGIBILITYTHE WORK COMPLETION PERIOD IS 9 MONTHS (INCLUDING MONSOON)None
17086085670000NoneNoneELIGIBILITYBIDDER SHOULD ESTABLISH A FIELD LABORATORYNone
17086085740000NoneNoneELIGIBILITYContractor must have 2graduate engineers and also engineers must worked with firm atleast 5years supervision, certificate should be enclosedNone
17086086140000NoneNoneELIGIBILITYEMD FOR RS. 1,00,000/- SHALL BE PAID THROUGH KARNATAKA PUBLIC PROCUREMENT PORTAL (KPPP) AND THE BALANCE OF RS.33,400.00/- BY BANK GUARANTEE ISSUED BY NATIONALISED/SCHEDULED BANK. CONTRACTOR SHOULD UPLOAD THE SCANNED COPY OF ORIGINAL BANK GUARANTEE ISSUED BY NATIONALISED/SCHEDULED BANK IN KPPP. THE CONTRACTOR HAS TO SUBMIT THE ORIGINAL BANK GUARANTEE BEFORE ENTERING THE AGREEMENT, IF AWARDED.None
17086857930000NoneNoneELIGIBILITYItem No-5.1 should be Read as Providing and applying primer coat with SS1 grade Bitumen Emulsion on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70kg/m2 using mechanical means.None
preQualCriterionListNone
technicalCriterionList
createdTsversioncreatedDatemodifiedDatedescriptioncriterionCategoryTextcriterionTypeOthersValuetenderTechnicalCriterionDocumentList
NoneNoneNoneNoneMinimum financial turnover (civil engineering construction works) not less than two times the annual payments from this contract (Rs. xxxxx Lakhs)NoneNone
NoneNoneNoneNoneSatisfactoriy completed (atleast 90%) as prime contractor at-least one such similar work of value not less than Rs. xxxxxxx (80% of estimated cost of tender)NoneNone
NoneNoneNoneNoneExecuted in any one year the following minimum quantities of work (Cement Concrete - xxxx cum, Earthwork - xxxx cum, etc) (80% of peak rate of construction)NoneNone
NoneNoneNoneNoneTenderer or his identified Sub Contractor should possess valid Electrical License for executing building electrificatio works and should have executed similar electrical works totallng Rs. xxxxxx (not less than 50% of electrical works) n any one yearNoneNone
NoneNoneNoneNoneTenderer or his identified Sub Contractor should possess valid license for executing water supply / sanitary engineering works and should have executed similar works totallng Rs. xxxxxx (not less than 50% of electrical works) n any one yearNoneNone
NoneNoneNoneNoneOwning the following key and critical equipment for this work (xxxx, xxxx, xxxx)NoneNone
NoneNoneNoneNoneLiquid assets and /or availability of credit facilities of no less than Rs. xxxxxx Lakhs (estimated cash flow for 3 months of peak construction period)NoneNone
NoneNoneNoneNoneTotal value of civl engineering works executed and payments received in the last five years (year-wise)NoneNone
NoneNoneNoneNoneList of existing commitments and ongoing worksNoneNone
NoneNoneNoneNoneList of works for which tenders already submittedNoneNone
NoneNoneNoneNoneBanker Details for referenceNoneNone
NoneNoneNoneNoneConstruction equipment owned by the tenderer and equipment proposed to be deployed on this contract, if awardedNoneNone
NoneNoneNoneNoneReports on the financial standing of the tenderer, such as profit and loss statements and auditor’s reports for the last five yearsNoneNone
NoneNoneNoneNoneQualification and experience of the key technical and management personnel in permanent employment with the tenderer and those that are proposed to be deployed on this contract, if awardedNoneNone
NoneNoneNoneNoneList of Financial Resources with CertificatesNoneNone
NoneNoneNoneNoneMandating Satisfactory completion as a prime contractor, for at least one similar nature of work such as Asphalt Road /Protection Wall / Retaining Wall Work of value not less than Rs.33.34Lakhs. from 2018-2019 to 2022-2023Past ExperienceNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneWork Done Certificate
NoneNoneNoneNoneexecuted in any one financial year (FROM 2018-19 TO 2022-23) the following minimum quantities of work 1) Earthwork/Embankment/subgrade-570.00Cum 2)WMM - 109.00Cum 3) BM/SDBC-215.00 Cum 4)PCC/RCC-57.00 Cum5)STEEL-3.14TonnePast ExperienceNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneWork Done Certificate
NoneNoneNoneNoneexisting commitments and on-going works to be completed during the next 9 months in the prescribed format from the Competent Authority not below the rank of Executive Engineer/District Level OfficerPast ExperienceNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneWork Done Certificate
NoneNoneNoneNoneKPWD Class III and above Registration copyPast ExperienceNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNonePWD Registration Certificate (Class I/II/III/IV)
NoneNoneNoneNoneQualification and experience of the key technical and management personnel in permanent employment with the tenderer and those that are proposed to be deployed on this contract, if awardedCapabilities of VendorNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneOthers -- work experience certificate
NoneNoneNoneNoneshould have in the last five years from 2018-2019 to 2022-2023, achieved in at least in TWO financial year a minimum financial contract turnover,in all classes of civil engineering construction works only of Rs. 66.68lakhs, Approved by CA with balance sheets & UDIN NoFinancial StatusNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneAudited CA Certificate of Annual Turnover
NoneNoneNoneNoneliquid assets and /or availability of credit facilities of not less than Rs 20.00Lakhs in the prescribed format in KWFinancial StatusNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneLine of Credit
NoneNoneNoneNoneEPF registration certifIcate with January 2024 challan copyFinancial StatusNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneValid EPF Certificate
tenderCriterionDocumentList
documentNameoptionaldocumentTypeText
Annual Turnover Certificate with balance sheets showing contract receipts approved by CA with UDIN number from 2018-19 to 2022-23TrueTechnical Bid
KPWD Class III and above RegistrationTrueTechnical Bid
liquid assets and /or availability of credit facilities of not less than Rs 20.00Lakhs in the prescribed format in KWTrueTechnical Bid
Mandating Satisfactory completion as a prime contractor, for at least one similar nature of work such as Asphalt Road /Protection Wall / Retaining Wall Work of value not less than Rs.33.34Lakhs. from 2018-2019 to 2022-2023TrueTechnical Bid
Tenderers will only be qualified, if their available tender capacity is more than the total tender value. i.e. AXNX2.5 - B, as per KW-3 Document for computing the value of A and B for the last five years i.e.,2018-2019 to 2022-2023TrueTechnical Bid
Executed in any one Financial Year, the minimum quantities of work as prescribed in Bid document from 2018-19 to 2022-23TrueTechnical Bid
GST declaration FormTrueTechnical Bid
EPF registration certifIcate with January 2024 challan copyTrueTechnical Bid
tenderWorkLocationList
tenderAddressNone