tenderSubEstimateList | createdTs | version | createdDate | modifiedDate | workCategoryName | subEstimateName | estimateTotal | itemList |
---|
1710251640000 | 0 | None | None | Roads | PKG-783 (A)Improvements to Road from Mandya-Thendekere road to Chinakuralli-Melukote road via Narayanapura Kammanayakanahalli Sanaba road PDP-31 at Ch0.00 KM to 5.10 KM In Selected reaches In Pandavapura Taluk of Mandya District. - Road Works | 100629425.77 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3015899 | 100785 | None | Item No 2.5, Page no 9, Vol 3, PWD Common SR 2023 | Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness. (ii) By Mechanical Means using Dozer (a) In area of light jungle
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | 100 Sqm | 463.74 | 463.74 | 121.92 | False | None | None | False | None | False | 56539.1808 | 0 | 3015900 | 100785 | None | Item No 3.5, Page no 17, Vol 3, PWD Common SR 202 | Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of scarified material by Mechanical Means using Hydraulic excavator with in all lifts and lead
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 7.08 | 7.08 | 19155.0 | False | None | None | False | None | False | 135617.4 | 0 | 3015901 | 100785 | None | Item No 1.12, Page no 8, Vol 1, PWD Common SR 202 | Earth work in surface excavation by mechanical means for lowering & leveling the ground for all works other than foundation in all kinds of soils & upto depth not exceeding 300mm as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenances required to complete the work.-In all kinds of soils upto 300 mm depth)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 112.1 | 112.1 | 8653.51 | False | None | None | False | None | False | 970058.471 | 0 | 3015902 | 100785 | None | Item No 1.7, Page no 7, Vol 1, PWD Common SR 2023 | Construction of Embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded with desired compaction.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 140.42 | 140.42 | 6654.75 | False | None | None | False | None | False | 934459.995 | 0 | 3015903 | 100785 | None | Item No 1.8, Page no 7, Vol 1, PWD Common SR 2023 | Construction of Embankment by excavating the available approved Gravel/Murrum deposited at a place or borrow pits during or prior excavation with all lifts and lead, transportation to site, spreading, grading to required slope and compacting to meet the requirement complete as per specifications, including cost of labour,rolling,water,all materials,usage& all other appurtenaces required to complete the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 559.32 | 559.32 | 11802.41 | False | None | None | False | None | False | 6601323.9612 | 0 | 3015904 | 100785 | None | Item No 3.6, Page no 17, Vol 3, PWD Common SR 202 | Construction of sub-grade and earthen shoulders with approved material ( CBR min 10 %) obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 581.74 | 581.74 | 8126.3 | False | None | None | False | None | False | 4727393.762 | 0 | 3015905 | 100785 | None | Item No 4.2 (v), Page no 23, Vol 3, PWD Common SR | By Mix in Place Method
Construction of Granular Sub-Base of required grading as per design spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with front end loader at OMC and compacting with vibratory roller to achieve the desired density, complete as per clause 401 For Grading -V Material"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 2783.62 | 2783.62 | 7666.31 | False | None | None | False | None | False | 21340093.8422 | 0 | 3015906 | 100785 | None | Item No. 4.17 Page No. 26 Vol.03 | Wet Mix Macadam (Plant Mix Method) Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver/grader in sub-base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. (Item No. 4.17/ Page No. 26/Vol.03/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 3019.62 | 3019.62 | 9516.53 | False | None | None | False | None | False | 28736304.3186 | 0 | 3015907 | 100785 | None | Item No 5.1 A (I), Page no 31, Vol 3, PWD Common | Providing and applying primer coat with SS1 grade Bitumen Emulsion on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70 kg per m2 using mechanical means.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 48.38 | 48.38 | 36754.11 | False | None | None | False | None | False | 1778163.8418 | 0 | 3015908 | 100785 | None | Item No 5.4, Page no 31, Vol 3, PWD Common SR 202 | Providing and applying tack coat with RS1 Bituminous Emulsion using emulsion pressure distributor at the rate of 0.25 kg/m2on Granular surface
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 16.52 | 16.52 | 36754.11 | False | None | None | False | None | False | 607177.8972 | 0 | 3015909 | 100785 | None | Item No 5.12 (B ), Page no 35, Vol 3, PWD Common | Dense Graded Bituminous Macadam Grading - II for traffic20 MSA Providing and laying Dense Graded Bituminous Macadam with40/60 TPH capacity HMP using crushed aggregates of specifiedgrading, premixed with bituminous binder VG-30, @ 4.5 per centby weight of total mix and filler, transporting the hot mix to worksite, laying with mechanical paver finisher to the required grade,level and alignment, rolling with smooth wheeled, vibratory andtandem rollers to achieve the desired compaction as per MoRTHspecification clause No. 505 complete in all respects."
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 11149.82 | 11149.82 | 1837.71 | False | None | None | False | None | False | 20490135.7122 | 0 | 3015910 | 100785 | None | Item No 5.24 B (ii), Page no 40, Vol 3, PWD Commo | Bituminous Concrete Grading II for traffic 20 MSAProviding and laying Bituminous Concrete with 40/60 TPH capacity hot mix plant using crushed aggregates of specifiedgrading, premixed with bituminous binder VG-30, @ 5.4 percent of mix and filler, transporting the hot mix to work site,laying with mechanical paver finisher to the required grade,level and alignment, rolling with smooth wheeled, vibratory andtandem rollers to achieve the desired compaction as per MORTHspecification clause No. 507 complete in all respects
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 12925.72 | 12925.72 | 1102.62 | False | None | None | False | None | False | 14252157.3864 | 0 |
| 1710251640000 | 0 | None | None | Roads | Road Furnitures | 3657981.12 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3015911 | 100786 | None | Item No 8.15, Page no 67, Vol 3, PWD Common SR 20 | Road Marking with Hot Applied Thermoplastic Compound with Reflectorising Glass Beads on Bituminous SurfaceProviding and laying of hot applied thermoplastic compound2.5 mm thick including reflectorising glass beads @ 250 g/m2area, thickness of 2.5 mm is exclusive of surface applied glassbeads as per IRC:35:2015.The finished surface to be level,uniform and free from streaks and holes.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 625.4 | 625.4 | 1220.0 | False | None | None | False | None | False | 762988.0 | 0 | 3015912 | 100786 | None | Item No 16.29, Page no 150, Vol 3, PWD Common SR | Project Display Board
i) The board will be a composite unit consisting of three plates of Aluminium Composite Materials (ACM), material specifications as per Clause 1701.3.7. The top most platewill be in Rectangular shape of 600mm x 600 mm size, riveted over welded M.S. angle iron frame of 25 mm x 25mm x 5 mm size on back on edges. The middle plate will be 1200 mm x 150 mm size riveted over welded M.S. angle iron frame of 25mm x 25mmx 5 mm size on back on edges. The main lower most plate will be 1500 mm x 600 mm size, riveted over welded M.S. angle iron frame of 25 mm x 25 mm x 5 mm size. Welding of all the sheets over angle iron frame will be done neatly to have plain surface on one side. The angle iron frames of the lower most plate and the middle plate will be welded to two nos. 75 mm x 75 mm (12 SWG) sheet tubes posts placed at 1125 mm apart centre to centre. The top of the middle plate will be flushed with the top of 75 mm dia medium steel tube posts and these posts will be embedded in cement concrete M15 grade blocks of 450 mm x 450 mm x 600 mm below ground level. The height of bottom of the lower most plate will be 1200 mm from normal ground level and the bottom of middle plate will be 100 mm above the top level of the lower most plate. The Rectangular shaped plate mounted over angle iron frame will be connected to middle plate by square medium steel section of 47 mm x 47 mm thickness 12 SWG having a spacing of 100 mm between the Rectangular shaped plate and middle plate and this square section will be welded to the bottom point of the Rectangular shaped plate. (ii) The lettering and borders, etc. of middle and bottom plate, SHDP logo on top plate shall be as per clause 1701.4.6 essages/Borders. All the sections of frame and posts will be painted with primer and two coats of Epoxy paint. The steel tube below ground level will be painted with three coats of Epoxy paint. The design, painting and lettering shall be done as per approved drawing. (iii) For warranty and durability the clause 1701.5 and for maintenance the clause 1911 shall be applicable. (iv) A reference number along with the month and year of installation should be placed on the back of a sign in
a contrasting colour or by stamping in characters not exceeding 50 mm in height.485777/2019/Dir(Tech) 7Retro Reflective Trafic Sign As per IRC 67 Clause 1701.3.8.1 Class A Type 1 (Item No. 16.29/ Page No. 149/Vol.03/Common SR-2023-24) - as per the direction of Engineer-in-charge. - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work."
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Each | 18115.36 | 18115.36 | 2.0 | False | None | None | False | None | False | 36230.72 | 0 | 3015913 | 100786 | None | Item No 8.7, Page no 65, Vol 3, PWD Common SR 202 | Direction and Place Identification Signs upto 0.9 m2 SizeBoard.Providing and erecting direction and place identification retroreflectorisedsign as per IRC:67:2022 made of high intensitygrade sheeting vide clause 801.3, fixed over aluminiumsheeting, 2 mm thick or Aluminium composite material sheetwith overall thickness of 4mm with area not exceeding 0.9m2 fixed over back support frame of min 35 x 35 x 3mm anglemounted on a mild steel circular pipe 65 NB, firmly fixed to theground by means of properly designed foundation with M25grade cement concrete 45 x 45 x 60 cm, 60 cm below ground
level as per approved drawing"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 10631.8 | 10631.8 | 5.4 | False | None | None | False | None | False | 57411.72 | 0 | 3015914 | 100786 | None | Item No 8.5 ii, Page no 64, Vol 3, PWD Common SR | Retro-Reflectorised Traffic SignsProviding and fixing of retro- reflectorised cautionary,mandatory and informatory sign as per IRC:67:2022 madeof Class B Type XI retro reflective sheeting fixed over 2 mmthick aluminium sheeting vide clause 801.3, 3mm/4mm thickAluminium composite material sheet depending on the size ofthe sign fixed over the back support frame of min 25 x 25 x3mm angle mounted on a mild steel circular pipe 65 NB, 3.2mm thickness firmly fixed to the ground by means of properlydesigned foundation with M25 grade cement concrete 45 cmx 45 cm x 60 cm, 60 cm below ground level as per approveddrawing.The sign shall be maintained as per section 12 ofIRC:67:2022. (ii) 90 cm equilateral triangle
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Each | 5527.12 | 5527.12 | 36.0 | False | None | None | False | None | False | 198976.32 | 0 | 3015915 | 100786 | None | Item No 8.5 viii, Page no 64, Vol 3, PWD Common S | Retro-Reflectorised Traffic SignsProviding and fixing of retro- reflectorised cautionary,mandatory and informatory sign as per IRC:67:2022 made
of Class B Type XI retro reflective sheeting fixed over 2 mmthick aluminium sheeting vide clause 801.3, 3mm/4mm thickAluminium composite material sheet depending on the size ofthe sign fixed over the back support frame of min 25 x 25 x3mm angle mounted on a mild steel circular pipe 65 NB, 3.2mm thickness firmly fixed to the ground by means of properlydesigned foundation with M25 grade cement concrete 45 cmx 45 cm x 60 cm, 60 cm below ground level as perapproveddrawing.The sign shall be maintained as per section 12 ofIRC:67:2022. (viii) 60 cm circular"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Each | 5070.46 | 5070.46 | 6.0 | False | None | None | False | None | False | 30422.76 | 0 | 3015916 | 100786 | None | Item No 8.43, Page no 74, Vol 3, PWD Common SR 20 | Supplying and Fixing of Molded Shank Raised PavementMarkers / Cat's Eye made of polycarbonate and ABS mouldedbody and reflective panels with micro prismatic lens capable ofproviding total internal reflection of the light entering the lensface and shall support a load of 16000 kg tested in accordanceto ASTM D 4280 Type H and complying to Specifications ofCategory A of MORTH Circular No RW/NH/33023/10-97DO III Dt 11.06. 1997. The height, width and length shall notexceed 50 mm, 100 mm and 102 +/- 2 mm and with minimumreflective area of 13 cm2 on each side and the slope to thebase shall be 35 +/- 5 degree. The strength of detachment ofthe integrated cylindrical shanks, (of diameter not less than19 +/- 2 mm and height not less than 30+/- 2 mm) fromthe body is to be a minimum value of 500 Kg. Fixing will beby drilling holes on the road for the shanks to go inside,without nails and using epoxy resin based adhesive as permanufacturer's recommendation and complete as directed bythe engineer.The contractor shall submit a two year warrantyfor satisfactory field performance including stipulatedretro-reflectance of the reflecting panel, to the Engineer.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 430.7 | 430.7 | 720.0 | False | None | None | False | None | False | 310104.0 | 0 | 3015917 | 100786 | None | Item No 8.16 (ii), Page no 67, Vol 3, PWD Common | Kilometre Stone Reinforced cement concrete M15grade kilometre stone oftandard design as per IRC:8-1980, fixing in position including painting and printing etc- (ii) Ordinary kilometer stone (precast)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Each | 3453.86 | 3453.86 | 4.0 | False | None | None | False | None | False | 13815.44 | 0 | 3015918 | 100786 | None | Item No 8.16 (iii), Page no 67, Vol 3, PWD Commo | Kilometre Stone Reinforced cement concrete M15grade kilometre stone ofstandard design as per IRC:8-1980, fixing in position includingpainting and printing etc- (iii) 200 m stone (precast)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Each | 993.56 | 993.56 | 20.0 | False | None | None | False | None | False | 19871.2 | 0 | 3015919 | 100786 | None | Item No. 8.5 A xv) Page No. 65 Vol.03 | Retro-Reflectorised Traffic Signs Providing and fixing of retro- reflectorised cautionary, mandatory and informatory sign as per IRC:67:2022 made of Class B Type XI retro reflective sheeting fixed over 2 mm thick aluminium sheeting vide clause 801.3, 3mm/4mm thick Aluminium composite material sheet depending on the size of the sign fixed over the back support frame of min 25 x 25 x 3mm angle mounted on a mild steel circular pipe 65 NB, 3.2 mm thickness firmly fixed to the ground by means of properly designed foundation with M25 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing.The sign shall be maintained as per section 12 of IRC:67:2022. (xv) 90 cm high octagon (Item No. 8.5 A (xv)/ Page No. 65/Vol.03/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Each | 7672.36 | 7672.36 | 10.0 | False | None | None | False | None | False | 76723.6 | 0 | 3015920 | 100786 | None | Item No. 8.48 Page No. 76Vol.03 | Chevron Boards Supply and installation of retro- reflective Chevron signboards of 600x450mm made out of cube corner micro prismatic grade sheeting confirming to Type XI standards of IRC:67:2022 & ASTM D 4956-09 specification & fixed over 3 mm thick Aluminium Composite Panel sheet having minimum 0.30 mm thick aluminum skin on both sides & fixed over back support frame of 25x25x3mm MS angle frame. Supported on 75 mm dia OR 75x75x6mm Mild steel with clear height of not less than 2.1 m from the ground level to the bottom of the Sign board & 60 cm below ground level. The sign post should be painted with one coat of red oxide paint and two coats of synthetic enamel paint of black and white colour with bands of 30 cm height, firmly fixed to the ground by means of foundation with M 20 grade cement, concrete foundation size of 45cm x 45 cm x 60 cm including cost & conveyance of all materials, equipment,machinery & Labour with all leads and lifts for satisfactory completion of the work as directed by Engineer incharge. (Item No. 8.48/ Page No. 76/Vol.03/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 4231.48 | 4231.48 | 20.0 | False | None | None | False | None | False | 84629.6 | 0 | 3015921 | 100786 | None | Item No. 8.16 (i) Page No. 67 Vol.03 | Reinforced cement concrete M15grade kilometre stone of standard design as per IRC:8-1980, fixing in position including painting and printing etc 5th kilometre stone (precast) (Item No. 8.16 (i)/ Page No. 67/Vol.03/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Each | 5995.58 | 5995.58 | 2.0 | False | None | None | False | None | False | 11991.16 | 0 | 3015922 | 100786 | None | Item No. 6.8.2 Page No. 51Vol.03 | Precast Cement Concrete Interlocking Blocks Providing and laying 80mm thick factory made precast M -30 grade Cement Concrete Paver Block as per IRC SP 63:2018 & IS 15658 for Commercial Traffic Axle load repetitions upto 10MSA & for Residential Streets of approved shape and colour, laid in required pattern and including over 40mm thick compacted bed of coarse sand, filling the joints with fine sand etc. all complete as per the direction of Engineer-in-charge. (WMM/WBM Base to be paid separately as per relevant technical specification) (Item No. 6.8.2/ Page No. 51/Vol.03/Common SR-2023-24) - as per the direction of Engineer-in-charge. - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 1369.98 | 1369.98 | 1176.0 | False | None | None | False | None | False | 1611096.48 | 0 | 3015923 | 100786 | None | Item No. 8.42.6 Page No. 74 Vol.03 | Kerb Stones Supplying and fixing M15 grade precast cement concrete Kerb stones for Roadway, Sidewalls and gutters fixed with CM 1:3 fixed and finsihed in line as per direction of Engineer in charge. (The cost of PCC shall be paid extra) (Item No. 8.42.6/ Page No. 74/Vol.03/Common SR-2023-24) - as per the direction of Engineer-in-charge. - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | m | 546.34 | 546.34 | 140.0 | False | None | None | False | None | False | 76487.6 | 0 | 3015924 | 100786 | None | Item No. 8.60.2 (iii) Page No. 80 Vol.03 | Providing Speed Breakers/Raised pedestrian crossings in Trapezoidal section with 2.5 m Top width and transition length of 0.8 m length and height of 0.1 m as per IRC 99:2018 using Dense Bituminous Macadam (DBM) Gr II and Bituminous Concrete (BC) Gr II for entire formation width & WBM Gr II for Shoulder hump portion only (150 mm thick), completing with road marking paint with applied thermoplastic compound with reflecting glass beeds on bituminous surface and providing 2 Nos. retro reflective traffic signs as per IRC 67 -2022 Two lane with formation width of 9.00 m (Item No. 8.60.2 (iii) / Page No. 80/Vol.03/Common SR-2023-24) - as per the direction of Engineer-in-charge. - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 61205.42 | 61205.42 | 6.0 | False | None | None | False | None | False | 367232.52 | 0 |
| 1710251640000 | 0 | None | None | Roads | RCC Drain | 7063602.7 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3015925 | 100787 | None | Item No 1.14.1, Page no 8, Vol 1, PWD Common SR 2 | Earth work excavation for Foundationdepth upto 3 m, as per drawing and technicalout, shoring, strutting, barricading,excavated surfaces, disposing off or & stacking the selected earth for reusem including cost of labour, tools, usagerequired to complete the workIn all kinds of soils Depth upto 3 m
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 120.36 | 120.36 | 1632.95 | False | None | None | False | None | False | 196541.862 | 0 | 3015926 | 100787 | None | Item No 2.1.3, Page no 15, Vol 1, PWD Common SR 2 | Providing and laying in position Cement Concrete for levelling course forall works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators,including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the otherappurtenances required to complete the work as per technical specifications.- Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 7067.02 | 7067.02 | 233.4 | False | None | None | False | None | False | 1649442.468 | 0 | 3015927 | 100787 | None | Item No. 2.4.2 Page No. 16 Vol.01 | Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates (Item No. 2.4.2/ Page No. 16/Vol.01/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 7461.14 | 7461.14 | 94.0 | False | None | None | False | None | False | 701347.16 | 0 | 3015928 | 100787 | None | Item No 2.4.2, Page no 15, Vol 1, PWD Common SR 2 | Providing and laying in position Cement Concrete for all Sub structures ofbuilding, Irrigation works, Sub structure works of bridges, Drain works &other parallel works from 0.50m to 3.50 m height. The granite/trap/basaltcrushed graded coarse aggregates and fine aggregates as per relevant ISCodes machine mixed with super plasticisers, laid in layers, well compactedusing needle vibrators, providing weep holes wherever necessary, includingall lead & lifts, cost of all materials of quality, confirming to the requirementsof relevant IS codes, labour, Usage charges of machinery, curing and all otherappurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 10072.54 | 10072.54 | 151.44 | False | None | None | False | None | False | 1525385.4576 | 0 | 3015929 | 100787 | None | Item No 2.5.1, Page no 16, Vol 1, PWD Common SR 2 | Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 9388.08 | 9388.08 | 111.82 | False | None | None | False | None | False | 1049775.1056 | 0 | 3015930 | 100787 | None | Item No 2.11 h, Page no 18, Vol 1, PWD Common SR | Steel FabricationSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification.All other type of structures
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | MT | 93232.98 | 93232.98 | 20.82 | False | None | None | False | None | False | 1941110.6436 | 0 |
| 1710251640000 | 0 | None | None | Roads | Water Supply | 1429158.42 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3015931 | 100788 | None | Item No 1.17.1, Page no 10, Vol 1, PWD Common SR | Earth work excavation for pipeline trenches in all kinds of soils by mechanical means as per drawing and technical specifications, including setting out, construction of shoring, strutting, barricading, caution lights, bracing, using sight rails & bonding rods at every 100 mm wherever necessary as directed, removal of stumps and other deleterious matter, dressing of sides and levelling the bottom of trench to the extent required , utilising the available excavated earth locally for the work etc., and all other appurtenances complete in the followingstrata
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 309.16 | 309.16 | 849.6 | False | None | None | False | None | False | 262662.336 | 0 | 3015932 | 100788 | None | Item No 9.2.1, Page no 96, Vol 5, PWD Common SR 2 | Providing, laying and jointing HDPE pipes of specified grade and conforming to IS 4984-2016 with latest ammendments and conveying to work site including loading and unloading at both destinations and rolli g and lowering into trenches, laying true to line and jointing of pipes and specials with electrofusion welding, giving hydraulic test as per relevant ISS with all lead and lifts including encasing the pipe alround to a depth of not less than 15 cms. with soft gravel or selected earth available from the excation, testing and commissioning. The rate is exclusive of required specials and fittings wherever necessary like saddle Tee, stub ends, flanged sets, bedns, reducers etc. complete (Contractor will make his own arrangements for procuring water for t e s t i n g ) e t c . c o m p l e t e HDPE Grade PE80-PN8.0, 63mm dia
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Rmtr | 258.42 | 258.42 | 300.0 | False | None | None | False | None | False | 77526.0 | 0 | 3015933 | 100788 | None | Item No 1.1, Page no 7, Vol 1, PWD Common SR 2023 | Refilling available earth around trenches/pipelines, cables in layers not exceeding 20 cms in depth, compacting each deposited layer by ramming after watering with a lead upto 50 m, and lift upto 1.5 m. Including cost of alllabour complete as per specifications
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 188.8 | 188.8 | 849.6 | False | None | None | False | None | False | 160404.48 | 0 | 3015934 | 100788 | None | Item No. 19.2.3 Page No. 96 Vol.05 | Providing, laying and jointing HDPE pipes of specified grade and conforming to IS 4984-2016 with latest ammendments and conveying to work site including loading and nloading at both destinations and rolling and lowering into trenches, laying true to line and jointing of pipes and specials with electrofusion welding, giving hydraulic test as per relevant ISS with all lead and lifts including encasing the pipe alround to a depth of not less than 15 cms. with soft gravel or selected earth available from the excation, testing and commissioning. The rate is exclusive of required specials and fittings wherever necessary like saddle Tee, stub ends, flanged sets, bedns, reducers etc. complete (Contractor will make his own arrangements for procuring water for testing) etc. complete. NOTE: Upto 110mm dia Coil shall be used. For: HDPE Grade PE80-PN8.0,90mm dia (Item No. 19.2.3/ Page No. 96/Vol.05/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | m | 450.76 | 450.76 | 2060.0 | False | None | None | False | None | False | 928565.6 | 0 |
| 1710251640000 | 0 | None | None | Roads | Construction of Box Culverts | 10104946.23 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3015935 | 100789 | None | Item No 1.14.1, Page no 8, Vol 1, PWD Common SR 2 | Earth work excavation for Foundationdepth upto 3 m, as per drawing and technicalout, shoring, strutting, barricading,excavated surfaces, disposing off or& stacking the selected earth for reusem including cost of labour, tools, usagerequired to complete the workIn all kinds of soils Depth upto 3 m
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 120.36 | 120.36 | 748.8 | False | None | None | False | None | False | 90125.568 | 0 | 3015936 | 100789 | None | Item No 2.1.3, Page no 15, Vol 1, PWD Common SR 2 | Providing and laying in position Cement Concrete for levelling course forall works in foundation. The granite/trap/basalt crushed graded coarseaggregates and fine aggregates as per relevant IS Codes machine mixed, laid inlayers not exceeding 150 mm thickness, well compacted using plate vibrators,including all lead & lifts, cost of all materials of quality, labour, Usage charges ofmachinery, curing, and all the otheappurtenances required to complete thework as per technical specifications.-Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 7067.02 | 7067.02 | 103.68 | False | None | None | False | None | False | 732708.6336 | 0 | 3015937 | 100789 | None | Item No 2.4.3, Page no 15, Vol 1, PWD Common SR 2 | Providing and laying in position Cement Concrete for all Sub structures ofbuilding, Irrigation works, Sub structure works of bridges, Drain works &other parallel works from 0.50m to 3.50 m height. The granite /trap/ basaltcrushed graded coarse aggregates and fine aggregates as per relevant ISCodes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, includingall lead & lifts, cost of all materials of quality, confirming to the requirementsof relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. .M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 8971.78 | 8971.78 | 375.84 | False | None | None | False | None | False | 3371953.7952 | 0 | 3015938 | 100789 | None | Item No 2.11 h, Page no 18, Vol 1, PWD Common SR | Steel FabricationSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification.All other type of structures
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | MT | 93232.98 | 93232.98 | 44.58 | False | None | None | False | None | False | 4156326.2484 | 0 | 3015939 | 100789 | None | Item No 8.1, Page no 66, Vol 3, PWD Common SR 202 | Painting Two Coats on New Concrete Surfaces Painting two coats after filling the surface with synthetic enamel paint in all shades on new plastered concrete surfaces
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 128.62 | 128.62 | 86.4 | False | None | None | False | None | False | 11112.768 | 0 | 3015940 | 100789 | None | Item No 8.4, Page no 15, Vol 1, PWD Common SR 202 | Printing New letter and Figures of any Shade
Printing new letter and figures of any shade with synthetic
enamel paint black or any other approved colour to give an
even shadeper cm height"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Per cm Height Per Letter | 1.06 | 1.06 | 5760.0 | False | None | None | False | None | False | 6105.6 | 0 | 3015941 | 100789 | None | Item No. 2.11 (ii) A Page No. 10 Vol.03 | Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead By Mechanical Means (A)Dismantling Brick / Tile work / rubble masonry / pitching / etc bymechanical means (Item No. 2.11 (ii) A/ Page No. 10/Vol.03/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 212.4 | 212.4 | 156.48 | False | None | None | False | None | False | 33236.352 | 0 | 3015942 | 100789 | None | Item No. 2.17 (ix) B Page No. 11 Vol.03 | Removing all type of Hume Pipes and Stacking including Earthwork and Dismantling of Masonry Works. Above 600 mm to 900 mm dia (Item No. 2.17 (ix) B/ Page No. 11/Vol.03/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | m | 1293.28 | 1293.28 | 172.5 | False | None | None | False | None | False | 223090.8 | 0 | 3015943 | 100789 | None | Item No. 2.5.2Page No. 16 Vol.01 | Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates (Item No. 2.5.2/ Page No. 16/Vol.01/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 9689.69 | 9689.69 | 152.06 | False | None | None | False | None | False | 1473414.2614 | 0 | 3015944 | 100789 | None | Item No. 2.8 (ii) a Page No. 10Vol.03 | Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead By Mechanical Means (a)Cement Concrete Grade M-15 & M-20 (Item No. 2.8 (ii) a/ Page No. 10/Vol.03/Common SR-2023-24) - as per the direction of Engineer-in-charge. - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 848.42 | 848.42 | 8.1 | False | None | None | False | None | False | 6872.202 | 0 |
| 1710251640000 | 0 | None | None | Roads | Electrical SHifting | 1563846.08 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3015945 | 100790 | None | 1.02 | Line Supports (Pole)
RCC Pole - 9 Mtr Long, 150 Kg WL Sq Section (Dwg No. BESCOM/GM/QS&S/51 Dtd 24.11.2018) as per IS-785. ( Common SR - 2023-24, Item No 1.02 Page No 03/81 Material No -200106)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 9812.88 | 9812.88 | 21.0 | False | None | None | False | None | False | 206070.48 | 0 | 3015946 | 100790 | None | 2.02 | Erection of Poles
Erection of RCC/PSCC Pole of 9 to 10 Mtr long in a pit of 1.8 Mtr depth ( Common SR - 2023-24, Item No 2.02 Page No 44/81 Material No -)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 1313.34 | 1313.34 | 21.0 | False | None | None | False | None | False | 27580.14 | 0 | 3015947 | 100790 | None | 1.05 | Line Supports (Pole)
PSCC Pole - 8 Mtr Long, 200 Kg WL (Dwg No. BESCOM/GM/QS&S/49 Dtd 24.11.2018) as per REC Standards. ( Common SR - 2023-24, Item No 1.05 Page No 03/81 Material No -200004)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 4364.82 | 4364.82 | 7.0 | False | None | None | False | None | False | 30553.74 | 0 | 3015948 | 100790 | None | 2.01 | Erection of Poles
Erection of RCC/PSCC Pole of 7.5 to 8 Mtr long in a pit of 1.5 Mtr depth ( Common SR - 2023-24, Item No 2.01 Page No 44/81 Material No -)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 1087.96 | 1087.96 | 7.0 | False | None | None | False | None | False | 7615.72 | 0 | 3015949 | 100790 | None | 1.07 | Line Supports (Pole)
Pre-Stressed Tubular Spun Pole - 11 Mtr Long, 500 Kg WL (Dwg No. BESCOM/GM/QS&S/45 Dtd 24.11.2018) as per IS-13158: 1991 ( Common SR - 2023-24, Item No 1.07 Page No 03/81 Material No -200120)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 20888.36 | 20888.36 | 4.0 | False | None | None | False | None | False | 83553.44 | 0 | 3015950 | 100790 | None | 2.05 | Erection of Poles
Erection of 11 Mtr long Concrete Spun Pole in a pit of 2.5 Mtr depth (Mechnised Labour) ( Common SR - 2023-24, Item No 2.05 Page No 44/81 Material No -)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 3001.92 | 3001.92 | 4.0 | False | None | None | False | None | False | 12007.68 | 0 | 3015951 | 100790 | None | 2.01 | 1 kV, Horizontal Cross Arm - Mild Steel (MS) (Dwg No. BESCOM/GM/QS&S/04 Dtd 24.11.2018). ( Common SR - 2023-24, Item No 2.01 Page No 03/81 Material No -279020)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 438.96 | 438.96 | 36.0 | False | None | None | False | None | False | 15802.56 | 0 | 3015952 | 100790 | None | 2.11 | HT ST Support 50x6 mm Flat - MS (Dwg No. BESCOM/GM/QS&S/04 Dtd 24.11.2018). ( Common SR - 2023-24, Item No 2.11 Page No 04/81 Material No -279092)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 107.38 | 107.38 | 107.0 | False | None | None | False | None | False | 11489.66 | 0 | 3015953 | 100790 | None | 5.06 | Fixing of HT/LT Single Top Support ( Common SR - 2023-24, Item No 5.06 Page No 45/81 Material No -)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Each | 132.16 | 132.16 | 107.0 | False | None | None | False | None | False | 14141.12 | 0 | 3015954 | 100790 | None | 2.07 | LT 2 Pin Cross Arm - MS (Dwg No. BESCOM/GM/QS&S/32 Dtd 24.11.2018). ( Common SR - 2023-24, Item No 2.07 Page No 04/81 Material No -279012)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 155.76 | 155.76 | 21.0 | False | None | None | False | None | False | 3270.96 | 0 | 3015955 | 100790 | None | 2.05 | LT 4 Pin Cross Arm - MS
(Dwg No. BESCOM/GM/QS&S/32 Dtd 24.11.2018) ( Common SR - 2023-24, Item No 2.05 Page No 04/81 Material No -279014)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 341.02 | 341.02 | 21.0 | False | None | None | False | None | False | 7161.42 | 0 | 3015956 | 100790 | None | 5.01 | Fixing of 2 Pin cross arm with Insulator and Braces fixing / Fixing of 4 Pin cross arm with Insulator and Braces fixing ( Common SR - 2023-24, Item No 5.01 & 5.02 Page No 45/81 Material No -)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 188.8 | 188.8 | 42.0 | False | None | None | False | None | False | 7929.6 | 0 | 3015957 | 100790 | None | 6.1 | 11 kV, 45 kN Polymeric Insulator . ( Common SR - 2023-24, Item No 6.1 Page No 05/81 Material No -283320)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 219.48 | 219.48 | 18.0 | False | None | None | False | None | False | 3950.64 | 0 | 3015958 | 100790 | None | 6.06 | 11 kV, 5 kN Composite/Polymeric Pin Insulator. ( Common SR - 2023-24, Item No 6.06 Page No 05/81 Material No -283008)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 241.9 | 241.9 | 43.0 | False | None | None | False | None | False | 10401.7 | 0 | 3015959 | 100790 | None | 7.02 | Rabbit ACSR conductor ( Common SR - 2023-24, Item No 7.02 Page No 05/81 Material No -284108)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Km | 60731.06 | 60731.06 | 3.0 | False | None | None | False | None | False | 182193.18 | 0 | 3015960 | 100790 | None | cost data | Erection of 3 Phase, 11kV/433V, 63 kVA BEE - 4/5 Star Rated Distribution Transformer Centre Using 9 Mtr RCC Pole DPTC ( WithOut Transformer) - Cost Data Sheet - 25 ( Common SR - 2023-24, )
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Set | 115431.14 | 115431.14 | 5.0 | False | None | None | False | None | False | 577155.7 | 0 | 3015961 | 100790 | None | 51.01 | GI Grounding pipe, B - Class, 42 mm dia, 2.5 Mtr long, 3.2 mm thick with bolt, nut, GI Strips and washer complete Minimum Weight of GI Pipe: 7.3 Kg ( Common SR - 2023-24, Item No 51.01 Page No 22/81 Material No -281674)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 880.28 | 880.28 | 10.0 | False | None | None | False | None | False | 8802.8 | 0 | 3015962 | 100790 | None | 51.02 | Good Quality well burnt Charcoal for grounding purposes packed in non returnable gunny bag of 30 Kg each ( Common SR - 2023-24, Item No 51.02 Page No 22/81 Material No -600095)" ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 797.68 | 797.68 | 10.0 | False | None | None | False | None | False | 7976.8 | 0 | 3015963 | 100790 | None | 51.03 | Good Quality Salt for grounding purposes packed in 50 Kg gunny bag ( Common SR - 2023-24, Item No 51.03 Page No 22/81 Material No -607054)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Bag | 365.8 | 365.8 | 10.0 | False | None | None | False | None | False | 3658.0 | 0 | 3015964 | 100790 | None | 51.04 | Rod type of earthing using 40 mm Dia, 3 Mtr long MS rod as ground rod, in earth pit of 300 mm width and 3300 mm depth and using 50x6 mm flat welded to ground rod as terminal & connected to equipment ground terminal using PVC Al wire as specified ( Common SR - 2023-24, Item No 51.04 Page No 23/81 Material No -281685)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 2562.96 | 2562.96 | 10.0 | False | None | None | False | None | False | 25629.6 | 0 | 3015965 | 100790 | None | 1.2.2 | Digging of Pit - Digging of Pit 1.6 Mtr depth for erection of 7.5/8 Mtr Long Steel/RCC/PSCC supports as per approved Drawing. - Hard Soil ( Common SR - 2023-24, Item No 1.2.2 Page No 43/81 Material No -)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Per Pit | 1187.08 | 1187.08 | 71.0 | False | None | None | False | None | False | 84282.68 | 0 | 3015966 | 100790 | None | 9 mt | R&R of 9mt pole ( Common SR - 2023-24, Item No Page No Material No -)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 2495.35 | 2495.35 | 50.0 | False | None | None | False | None | False | 124767.5 | 0 | 3015967 | 100790 | None | arm | R&R of X-Arm ( Common SR - 2023-24, Item No Page No Material No -)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 358.72 | 358.72 | 36.0 | False | None | None | False | None | False | 12913.92 | 0 | 3015968 | 100790 | None | htst | R&R of HTST ( Common SR - 2023-24, Item No Page No Material No -)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos. | 251.1 | 251.1 | 142.0 | False | None | None | False | None | False | 35656.2 | 0 | 3015969 | 100790 | None | 7.02 | R&R of Rabbit ( Common SR - 2023-24, Item No 7.02 & 7.04 Page No 46/81 Material No -)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Km | 9880.14 | 9880.14 | 6.0 | False | None | None | False | None | False | 59280.84 | 0 |
| 1710251640000 | 0 | None | None | Roads | 1st year Maintanance | 0.0 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3015970 | 100791 | None | 2.5(ii) a | Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness. By Mechanical Means using Dozer A) In area of light jungle Inclusive of all lift and leads and all complete as per direction of Engineer-in-charge.
UNI SR 2023-24, V-3, Page No. 9, Item No. 2.5(ii) a (Quantity to be executed 43.36) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | 100 Sqm | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3015971 | 100791 | None | 16.19 | Maintenance of Drains - The maintenance of drains include erosion, repair, clearing, cleaning, reshaping, regrading, deepening of side drains as well as catch water drains as per technical specification Clause 1908. Inclusive of all lift and leads and all complete as per direction of Engineer-in-charge.
UNI SR 2023-24, V-3, Page No. 147, Item No. 16.19 (Quantity to be executed 3252) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Rmtr | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3015972 | 100791 | None | 10.3 | Maintenance of Earth Shoulder (stripping excess soil)-Stripping excess soil from the shoulder surface to a minimum depth of 150mm to achieve the approved level and compacting with plate compactor including cost of materials, labour, HOM complete as per specifications. MORTH Specification No. 3003. Inclusive of all lift and leads and all complete as per direction of Engineer-in-charge.
UNI SR 2023-24, V-3, Page No. 91, Item No. 10.3(Quantity to be executed =2710) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3015973 | 100791 | None | 10.2 | Maintenance of Earthen Shoulder (filling with fresh soil) - Making up loss of material I irregularities on shoulder to a minimum depth of 150mm to the design level by adding fresh approved soil and compacting it with appropriate equipment including cost of materials, labour, HOM complete as per specifications etc. MORTH Specification No.3003. Inclusive of all lift and leads and all complete as per direction of Engineer-in-charge.
UNI SR 2023-24, V-3, Page No. 91, Item No. 10.2.(Quantity to be executed =2710) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3015974 | 100791 | None | 10.5 | Filling Pot-holes and Patch Repairs with BituminousRemoval of all failed material, trimming of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 504 using HMP 40/60 TPH Capacity compacting, trimming and finishing the surface to form a smooth continuous surface, all as per clause 3004.2
UNI SR 2023-24, V-3, Page No. 91, Item No. 10.5.(Quantity to be executed =298.10) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3015975 | 100791 | None | 1.12 | Nala Training: Earthwork in surface excavation by mechanical means for lowering & leveling the ground for all works other than foundation in all kinds of soils & upto depth not exceeding 300mm as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking thes elected earth for re use inaradius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenances required to complete the work.In all kinds of soils upto 300 mm depthUNI SR 2023-24, V-1, Page No. 8, Item No. 1.12(Quantity to be executed =225) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 |
| 1710251640000 | 0 | None | None | Roads | 2nd Year Maintainance | 0.0 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3015976 | 100792 | None | 2.5(ii) a | Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness. By Mechanical Means using Dozer A) In area of light jungle Inclusive of all lift and leads and all complete as per direction of Engineer-in-charge.
UNI SR 2023-24, V-3, Page No. 9, Item No. 2.5(ii) a(Quantity to be executed =65.04) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | 100 Sqm | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3015977 | 100792 | None | 16.19 | Maintenance of Drains - The maintenance of drains include erosion, repair, clearing, cleaning, reshaping, regrading, deepening of side drains as well as catch water drains as per technical specification Clause 1908. Inclusive of all lift and leads and all complete as per direction of Engineer-in-charge.
UNI SR 2023-24, V-3, Page No. 147, Item No. 16.19(Quantity to be executed =4336) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Rmtr | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3015978 | 100792 | None | 10.3 | Maintenance of Earth Shoulder (stripping excess soil) - Stripping excess soil from the shoulder surface to a minimum depth of 150mm to achieve the approved level and compacting with plate compactor including cost of materials, labour, HOM complete as per specifications. MORTH Specification No. 3003 . Inclusive of all lift and leads and all complete as per direction of Engineer-in-charge.
UNI SR 2023-24, V-2, Page No. 91, Item No. 10.3.(Quantity to be executed =813) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3015979 | 100792 | None | 10.2 | Maintenance of Earthen Shoulder (filling with fresh soil) - Making up loss of material I irregularities on shoulder to a minimum depth of 150mm to the design level by adding fresh approved soil and compacting it with appropriate equipment including cost of materials, labour, HOM complete as per specifications etc. MORTH Specification No.3003. Inclusive of all lift and leads and all complete as per direction of Engineer-in-charge.
UNI SR 2023-24, V-3, Page No. 91, Item No. 10.2.(Quantity to be executed =2710) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3015980 | 100792 | None | 10.5 | Filling Pot-holes and Patch Repairs with BituminousRemovalofallfailedmaterial,trimmingofcompletedexcavationtoprovidefirmverticalfaces,cleaningofsurface,paintingoftackcoatonthesidesandbaseofexcavationasperclause503,backfillingthepotholeswithhotbituminousmaterialasperclause504usingHMP40/60TPHCapacitycompacting,trimmingandfinishingthesurfacetoformasmoothcontinuoussurface,allasperclause 3004.2
UNI SR 2023-24, V-3, Page No. 91, Item No. 10.5(Quantity to be executed =379.40) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3015981 | 100792 | None | 1.12 | Nala Training : Earth work in surface excavation by mechanical means for lowering & leveling the ground for all works other than foundation in all kinds of soils & upto depth not exceeding 300mm as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenances required to complete the work.In all kinds of soils upto 300 mm depth
UNI SR 2023-24, V-1, Page No. 8, Item No. 1.12(Quantity to be executed =225) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 |
| 1710251640000 | 0 | None | None | Roads | 3rd Year Maintenance | 641894.88 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3015982 | 100793 | None | Item No.VOL-III-2.6 Page No. 9 | Clearing & grubbing road land including vegetation, bushes, shrubs, saplings by using weed cutter / minor equipment.
PWD SoR for Roads & Bridges - 2023-24 ( Item No.VOL-III-2.6 / Page No. 9)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | 100 Sqm | 519.39 | 519.39 | 73.32 | False | None | None | False | None | False | 38081.6748 | 0 | 3015983 | 100793 | None | tem No.VOL-III-16.19 Page No. 147 | Maintenance of Drains - The maintenance of drains include erosion, repair, clearing, cleaning, reshaping, regrading, deepening of side drains as well as catch water drains as per technical specification Clause 1908.
PWD SoR for Roads & Bridges - 2023-24 ( Item No.VOL-III-16.19 / Page No. 147)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Rmtr | 7.93 | 7.93 | 4888.0 | False | None | None | False | None | False | 38761.84 | 0 | 3015984 | 100793 | None | tem No.VOL-III-10.3 Page . 91 | Maintenance of Earth Shoulder (stripping excess soil) - Stripping excess soil from the shoulder surface to a minimum depth of 150mm to achieve the approved level and compacting with plate compactor including cost of materials, labour, HOM complete as per specifications. MORTH Specification No. 3003
PWD SoR for Roads & Bridges - 2023-24 ( Item No.VOL-III-10.3 / Page No. 91)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 51.54 | 51.54 | 641.55 | False | None | None | False | None | False | 33065.487 | 0 | 3015985 | 100793 | None | Item No.VOL-III-10.2 Page No. 91 | Maintenance of Earthen Shoulder (filling with fresh soil) - Making up loss of material I irregularities on shoulder to a minimum depth of 150mm to the design level by adding fresh approved soil and compacting it with appropriate equipment including cost of materials, labour, HOM complete as per specifications. MORTH Specification No.3003
PWD SoR for Roads & Bridges - 2023-24 ( Item No.VOL-III-10.2 / Page No. 91)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 128.2 | 128.2 | 2138.5 | False | None | None | False | None | False | 274155.7 | 0 | 3015986 | 100793 | None | Item No.VOL-III-10.4 Page No. 91 | Filling Pot-holes and Patch Repairs with Bituminous concrete, 40mm (using VG-30 Grade Bitumen) - Removal of all failed material, trimming of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 510 using HMP 40/60 TPH Capacity compacting, trimming and finishing the surface to form a smooth continuous surface, all as per clause 3004.2 - as per the direction of Engineer-in-charge.
(Item No. 10.5/ Page No.91/Vol.03/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 563.0 | 563.0 | 168.02 | False | None | None | False | None | False | 94595.26 | 0 | 3015987 | 100793 | None | Item No.VOL-III-16.22 Page No. 147 | Maintenance of Road Signs- Maintenance of road signs by way of cleaning and repainting of mandatory / requlatory / cautionary / informatory and place identifications sign board as perdrawings and technical specification Clause 1910
PWD SoR for Roads & Bridges - 2023-24 ( Item No.VOL-III-16.22 / Page No. 147)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Km | 2622.05 | 2622.05 | 6.11 | False | None | None | False | None | False | 16020.7255 | 0 | 3015988 | 100793 | None | Item No.OL-III-16.24 i Page No. 148 | Maintenance of 200 m and km stones - Maintenance of 200 metre and km stones-Maintenance of 200 metre km stone by way of refiting of tilted stones repairing with cement mortar, cleaning, repairing and lettering on 200 metre km stone and 5th km stone as per drawing and technical specification Clause 1912 Painting two coats with synthetic enamel paint
PWD SoR for Roads & Bridges - 2023-24 ( Item No.VOL-III-16.24 i / Page No. 148)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Km | 272.25 | 272.25 | 6.11 | False | None | None | False | None | False | 1663.4475 | 0 | 3015989 | 100793 | None | V 1 Page No.8. Item No.1.12 | Nala Training: Earth work in surface excavation by mechanical means for lowering & leveling the ground for all works other than foundation in all kinds of soils & upto depth not exceeding 300mm as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenances required to complete the work. PWD, Bangalore, SR:2023-24 V 1 Page No.8. Item No.1.12) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 125.55 | 125.55 | 1080.0 | False | None | None | False | None | False | 135594.0 | 0 | 3015990 | 100793 | None | tem No.VOL-III-8.10 Page No. 66 | Painting of Parapet walls of CD work. KSRRB M800-6. Painting two coats on New Concrete Surface : Painting two coats after filling the surface with synthetic enamel paint in all shades on new plastered concrete surfaces complete as per specifications. MORTH Specification No. 803
PWD SoR for Roads & Bridges - 2023-24 ( Item No.VOL-III-8.10/ Page No. 66)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 144.05 | 144.05 | 69.12 | False | None | None | False | None | False | 9956.736 | 0 |
| 1710251640000 | 0 | None | None | Roads | 4th Year Maintanance | 636164.16 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3015991 | 100794 | None | Item No.VOL-III-2.6 Page No. 9) | Clearing & grubbing road land including vegetation, bushes, shrubs, saplings by using weed cutter / minor equipment.
PWD SoR for Roads & Bridges - 2023-24 ( Item No.VOL-III-2.6 / Page No. 9)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | 100 Sqm | 537.94 | 537.94 | 73.32 | False | None | None | False | None | False | 39441.7608 | 0 | 3015992 | 100794 | None | Item No.VOL-III-16.19 Page No. 147 | Maintenance of Drains - The maintenance of drains include erosion, repair, clearing, cleaning, reshaping, regrading, deepening of side drains as well as catch water drains as per technical specification Clause 1908.
PWD SoR for Roads & Bridges - 2023-24 ( Item No.VOL-III-16.19 / Page No. 147)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Rmtr | 8.21 | 8.21 | 4888.0 | False | None | None | False | None | False | 40130.48 | 0 | 3015993 | 100794 | None | tem No.VOL-III-10.3 Page No. 91 | Maintenance of Earth Shoulder (stripping excess soil) - Stripping excess soil from the shoulder surface to a minimum depth of 150mm to achieve the approved level and compacting with plate compactor including cost of materials, labour, HOM complete as per specifications. MORTH Specification No. 3003
PWD SoR for Roads & Bridges - 2023-24 ( Item No.VOL-III-10.3 / Page No. 91)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 53.38 | 53.38 | 641.55 | False | None | None | False | None | False | 34245.939 | 0 | 3015994 | 100794 | None | Item No.VOL-III-10.2 Page No. 91 | Maintenance of Earthen Shoulder (filling with fresh soil) - Making up loss of material I irregularities on shoulder to a minimum depth of 150mm to the design level by adding fresh approved soil and compacting it with appropriate equipment including cost of materials, labour, HOM complete as per specifications. MORTH Specification No.3003
PWD SoR for Roads & Bridges - 2023-24 ( Item No.VOL-III-10.2 / Page No. 91)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 132.77 | 132.77 | 2138.5 | False | None | None | False | None | False | 283928.645 | 0 | 3015995 | 100794 | None | Item No.VOL-III-10.5 Page No. 91 | Filling Pot-holes and Patch Repairs with Bituminous concrete, 40mm (using VG-30 Grade Bitumen) - Removal of all failed material, trimming of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 510 using HMP 40/60 TPH Capacity compacting, trimming and finishing the surface to form a smooth continuous surface, all as per clause 3004.2 - as per the direction of Engineer-in-charge.
(Item No. 10.5/ Page No.91/Vol.03/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 583.11 | 583.11 | 168.02 | False | None | None | False | None | False | 97974.1422 | 0 | 3015996 | 100794 | None | V 1 Page No.8. Item No.1.12 | Nala Training: Earth work in surface excavation by mechanical means for lowering & leveling the ground for all works other than foundation in all kinds of soils & upto depth not exceeding 300mm as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenances required to complete the work. PWD, Bangalore, SR:2023-24 V 1 Page No.8. Item No.1.12) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 130.04 | 130.04 | 1080.0 | False | None | None | False | None | False | 140443.2 | 0 |
| 1710251641000 | 0 | None | None | Roads | 5th year Maintenance | 759492.9 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3015997 | 100795 | None | Item No.VOL-III-2.6 Page No. 9 | Clearing & grubbing road land including vegetation, bushes, shrubs, saplings by using weed cutter / minor equipment.
PWD SoR for Roads & Bridges - 2023-24 ( Item No.VOL-III-2.6 / Page No. 9)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | 100 Sqm | 556.49 | 556.49 | 73.32 | False | None | None | False | None | False | 40801.8468 | 0 | 3015998 | 100795 | None | VOL-III-16.19 Page No. 14 | Maintenance of Drains - The maintenance of drains include erosion, repair, clearing, cleaning, reshaping, regrading, deepening of side drains as well as catch water drains as per technical specification Clause 1908.
PWD SoR for Roads & Bridges - 2023-24 ( Item No.VOL-III-16.19 / Page No. 147)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Rmtr | 8.5 | 8.5 | 4888.0 | False | None | None | False | None | False | 41548.0 | 0 | 3015999 | 100795 | None | VOL-III-10.3 Page No. 91 | Maintenance of Earth Shoulder (stripping excess soil) - Stripping excess soil from the shoulder surface to a minimum depth of 150mm to achieve the approved level and compacting with plate compactor including cost of materials, labour, HOM complete as per specifications. MORTH Specification No. 3003
PWD SoR for Roads & Bridges - 2023-24 ( Item No.VOL-III-10.3 / Page No. 91)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 55.22 | 55.22 | 641.55 | False | None | None | False | None | False | 35426.391 | 0 | 3016000 | 100795 | None | VOL-III-10.2 Page No. 91 | Maintenance of Earthen Shoulder (filling with fresh soil) - Making up loss of material I irregularities on shoulder to a minimum depth of 150mm to the design level by adding fresh approved soil and compacting it with appropriate equipment including cost of materials, labour, HOM complete as per specifications. MORTH Specification No.3003
PWD SoR for Roads & Bridges - 2023-24 ( Item No.VOL-III-10.2 / Page No. 91)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 137.35 | 137.35 | 2138.5 | False | None | None | False | None | False | 293722.975 | 0 | 3016001 | 100795 | None | VOL-III-10.4 Page No. 91 | Filling Pot-holes and Patch Repairs with Bituminous concrete, 40mm (using VG-30 Grade Bitumen) - Removal of all failed material, trimming of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 510 using HMP 40/60 TPH Capacity compacting, trimming and finishing the surface to form a smooth continuous surface, all as per clause 3004.2 - as per the direction of Engineer-in-charge.
(Item No. 10.5/ Page No.91/Vol.03/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 603.22 | 603.22 | 336.05 | False | None | None | False | None | False | 202712.081 | 0 | 3016002 | 100795 | None | V 1 Page No.8. Item No.1.12 | Nala Training: Earth work in surface excavation by mechanical means for lowering & leveling the ground for all works other than foundation in all kinds of soils & upto depth not exceeding 300mm as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenances required to complete the work. PWD, Bangalore, SR:2023-24 V 1 Page No.8. Item No.1.12) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 134.52 | 134.52 | 1080.0 | False | None | None | False | None | False | 145281.6 | 0 |
| 1710251641000 | 0 | None | None | Roads | 6th Year Renewal after Maintanance | 19686151.87 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3016003 | 100796 | None | Item No 16.22, Page no 147, Vol 3, PWD Common SR | Maintenance of Road Signs- Maintenance of road signs by way of cleaning and repainting of mandatory / requlatory / cautionary / informatory and place identifications sign board as perdrawings and technical specification Clause 1910
Add Adhoc increase in SR @ the rate of 24% however even if the executed maintainence quantity exceeds the quantity considered in estimate no additional payment shall be made
2341.12+561.87 = 2902.99
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Km | 2902.99 | 2902.99 | 5.01 | False | None | None | False | None | False | 14543.9799 | 0 | 3016004 | 100796 | None | Item No 16.24 i, Page no 148, Vol 3, PWD Common S | Maintenance of 200 m and km stones - Maintenance of 200 metre and km stones- Maintenance of 200 metre km stone by way of refiting of tilted stones repairing with cement mortar, cleaning, repairing and lettering on 200 metre km stone and 5th km stone as per drawing and technical specification Clause 1912 Painting two coats withsynthetic enamel paint
Add Adhoc increase in SR @ the rate of 24% however even if the executed maintainence quantity exceeds the quantity considered in estimate no additional payment shall be made
243.08+58.34 = 301.42 ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 301.42 | 301.42 | 5.01 | False | None | None | False | None | False | 1510.1142 | 0 | 3016005 | 100796 | None | Item No 8.1, Page no 66, Vol 3, PWD Common SR 202 | Painting two coats on New Concrete Surface : Painting two coats after filling the surface with synthetic enamel paint in all shades on new plastered concrete surfaces complete as per specifications. MORTH Specification No. 803
Add Adhoc increase in SR @ the rate of 24% however even if the executed maintainence quantity exceeds the quantity considered in estimate no additional payment shall be made
128.62+30.87 = 159.49 ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 159.49 | 159.49 | 86.4 | False | None | None | False | None | False | 13779.936 | 0 | 3016006 | 100796 | None | Item No 5.3i, Page no 31, Vol 3, PWD Common SR 20 | Providing and applying tack coat with RS1 Bituminous Emulsion using emulsion pressure distributor at the rate of 0.20 kg/m2 on the prepared bituminous surface cleaned with mechanical broom
Add Adhoc increase in SR @ the rate of 24% however even if the executed maintainence quantity exceeds the quantity considered in estimate no additional payment shall be made
14.16+3.40 = 17.56 ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 17.56 | 17.56 | 36754.11 | False | None | None | False | None | False | 645402.1716 | 0 | 3016007 | 100796 | None | Item No 5.16 C (ii), Page no 40, Vol 3, PWD Comm | Bituminous Concrete Grading II for traffic 20 MSAProviding and laying Bituminous Concrete with 40/60 TPH capacity hot mix plant using crushed aggregates of specifiedgrading, premixed with bituminous binder VG-30, @ 5.4 percent of mix and filler, transporting the hot mix to work site,laying with mechanical paver finisher to the required grade,level and alignment, rolling with smooth wheeled, vibratory andtandem rollers to achieve the desired compaction as per MORTHspecification clause No. 507 complete in all respects
12925.72 + 3102.17 = 16027.89 ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 16027.89 | 16027.89 | 1102.62 | False | None | None | False | None | False | 17672672.0718 | 0 | 3016008 | 100796 | None | Item No 8.15, Page no 67, Vol 3, PWD Common SR 20 | Providing and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 g/m2 area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35:2015.The finished surface to be level, uniform and free from streaks and holes.
Add Adhoc increase in SR @ the rate of 24% however even if the executed maintainence quantity exceeds the quantity considered in estimate no additional payment shall be made
625.40 + 150.10 = 775.50 ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 775.5 | 775.5 | 1220.0 | False | None | None | False | None | False | 946110.0 | 0 | 3016009 | 100796 | None | Item No 8.43, Page no 74, Vol 3, PWD Common SR 20 | Supplying and Fixing of Molded Shank Raised PavementMarkers / Cat's Eye made of polycarbonate and ABS mouldedbody and reflective panels with micro prismatic lens capable ofproviding total internal reflection of the light entering the lensface and shall support a load of 16000 kg tested in accordanceto ASTM D 4280 Type H and complying to Specifications ofCategory A of MORTH Circular No RW/NH/33023/10-97DO III Dt 11.06. 1997. The height, width and length shall notexceed 50 mm, 100 mm and 102 +/- 2 mm and with minimumreflective area of 13 cm2 on each side and the slope to thebase shall be 35 +/- 5 degree. The strength of detachment ofthe integrated cylindrical shanks, (of diameter not less than19 +/- 2 mm and height not less than 30+/- 2 mm) fromthe body is to be a minimum value of 500 Kg. Fixing will beby drilling holes on the road for the shanks to go inside,without nails and using epoxy resin based adhesive as permanufacturer's recommendation and complete as directed bythe engineer.The contractor shall submit a two year warrantyfor satisfactory field performance including stipulatedretro-reflectance of the reflecting panel, to the Engineer.
430.70 + 103.347 = 534.07
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 534.07 | 534.07 | 720.0 | False | None | None | False | None | False | 384530.4 | 0 | 3016010 | 100796 | None | Item No. 8.4 Page No. 64 Vol.03 | Printing New Letter
Printing New Letter and Figures of any Shade Printing new letter and figures of any shade with synthetic enamel paint black or any other approved colour to give an even shade-English and Roman (Item No. 8.4/ Page No. 64/Vol.03/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work."
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | cm | 1.32 | 1.32 | 5760.0 | False | None | None | False | None | False | 7603.2 | 0 |
| 1710251641000 | 0 | None | None | Roads | PKG-783 (B)Improvements to Road from Mandya Hadagalli to join Bevinakuppe-Shambuvinahalli via Shettihalli Anuvunahalli, Narahalli road PDP -56 at Ch0.00 KM to 9.60 KM In Selected reaches In Pandavapura Taluk of Mandya District. - Road Works | 34731061.6 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3016011 | 100797 | None | Item No 2.5, Page no 9, Vol 3, PWD Common SR 2023 | Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness. (ii) By Mechanical Means using Dozer (a) In area of light jungle
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | 100 Sqm | 463.74 | 463.74 | 54.72 | False | None | None | False | None | False | 25375.8528 | 0 | 3016012 | 100797 | None | Item No 3.5, Page no 17, Vol 3, PWD Common SR 202 | Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of scarified material by Mechanical Means using Hydraulic excavator with in all lifts and lead
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 7.08 | 7.08 | 4275.0 | False | None | None | False | None | False | 30267.0 | 0 | 3016013 | 100797 | None | Item No 1.12, Page no 8, Vol 1, PWD Common SR 202 | Earth work in surface excavation by mechanical means for lowering & leveling the ground for all works other than foundation in all kinds of soils & upto depth not exceeding 300mm as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenances required to complete the work.-In all kinds of soils upto 300 mm depth)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 112.1 | 112.1 | 1026.0 | False | None | None | False | None | False | 115014.6 | 0 | 3016014 | 100797 | None | Item No 1.7, Page no 7, Vol 1, PWD Common SR 2023 | Construction of Embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded with desired compaction.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 140.42 | 140.42 | 820.8 | False | None | None | False | None | False | 115256.736 | 0 | 3016015 | 100797 | None | Item No 1.8, Page no 7, Vol 1, PWD Common SR 2023 | Construction of Embankment by excavating the available approved Gravel/Murrum deposited at a place or borrow pits during or prior excavation with all lifts and lead, transportation to site, spreading, grading to required slope and compacting to meet the requirement complete as per specifications, including cost of labour,rolling,water,all materials,usage& all other appurtenaces required to complete the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 559.32 | 559.32 | 2938.31 | False | None | None | False | None | False | 1643455.5492 | 0 | 3016016 | 100797 | None | Item No 3.6, Page no 17, Vol 3, PWD Common SR 202 | Construction of sub-grade and earthen shoulders with approved material ( CBR min 10 %) obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 581.74 | 581.74 | 3032.4 | False | None | None | False | None | False | 1764068.376 | 0 | 3016017 | 100797 | None | Item No 4.2 (v), Page no 23, Vol 3, PWD Common SR | By Mix in Place Method
Construction of Granular Sub-Base of required grading as per design spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with front end loader at OMC and compacting with vibratory roller to achieve the desired density, complete as per clause 401 For Grading -V Material"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 2783.62 | 2783.62 | 2739.45 | False | None | None | False | None | False | 7625587.809 | 0 | 3016018 | 100797 | None | Item No. 4.17 Page No. 26 Vol.03 | Wet Mix Macadam (Plant Mix Method) Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver/grader in sub-base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. (Item No. 4.17/ Page No. 26/Vol.03/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 3019.62 | 3019.62 | 3381.29 | False | None | None | False | None | False | 10210210.9098 | 0 | 3016019 | 100797 | None | Item No 5.1 A (I), Page no 31, Vol 3, PWD Common | Providing and applying primer coat with SS1 grade Bitumen Emulsion on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70 kg per m2 using mechanical means.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 48.38 | 48.38 | 13069.15 | False | None | None | False | None | False | 632285.477 | 0 | 3016020 | 100797 | None | Item No 5.4, Page no 31, Vol 3, PWD Common SR 202 | Providing and applying tack coat with RS1 Bituminous Emulsion using emulsion pressure distributor at the rate of 0.25 kg/m2on Granular surface
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 16.52 | 16.52 | 13069.15 | False | None | None | False | None | False | 215902.358 | 0 | 3016021 | 100797 | None | Item No 5.12 (B ), Page no 35, Vol 3, PWD Common | Dense Graded Bituminous Macadam Grading - II for traffic20 MSA Providing and laying Dense Graded Bituminous Macadam with40/60 TPH capacity HMP using crushed aggregates of specifiedgrading, premixed with bituminous binder VG-30, @ 4.5 per centby weight of total mix and filler, transporting the hot mix to worksite, laying with mechanical paver finisher to the required grade,level and alignment, rolling with smooth wheeled, vibratory andtandem rollers to achieve the desired compaction as per MoRTHspecification clause No. 505 complete in all respects."
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 11149.82 | 11149.82 | 653.45 | False | None | None | False | None | False | 7285849.879 | 0 | 3016022 | 100797 | None | Item No 5.24 B (ii), Page no 40, Vol 3, PWD Commo | Bituminous Concrete Grading II for traffic 20 MSAProviding and laying Bituminous Concrete with 40/60 TPH capacity hot mix plant using crushed aggregates of specifiedgrading, premixed with bituminous binder VG-30, @ 5.4 percent of mix and filler, transporting the hot mix to work site,laying with mechanical paver finisher to the required grade,level and alignment, rolling with smooth wheeled, vibratory andtandem rollers to achieve the desired compaction as per MORTHspecification clause No. 507 complete in all respects
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 12925.72 | 12925.72 | 392.07 | False | None | None | False | None | False | 5067787.0404 | 0 |
| 1710251641000 | 0 | None | None | Roads | Road Furnitures | 837267.82 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3016023 | 100798 | None | Item No 8.15, Page no 67, Vol 3, PWD Common SR 20 | Road Marking with Hot Applied Thermoplastic Compound with Reflectorising Glass Beads on Bituminous SurfaceProviding and laying of hot applied thermoplastic compound2.5 mm thick including reflectorising glass beads @ 250 g/m2area, thickness of 2.5 mm is exclusive of surface applied glassbeads as per IRC:35:2015.The finished surface to be level,uniform and free from streaks and holes.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 625.4 | 625.4 | 474.0 | False | None | None | False | None | False | 296439.6 | 0 | 3016024 | 100798 | None | Item No 16.29, Page no 150, Vol 3, PWD Common SR | Project Display Board
i) The board will be a composite unit consisting of three plates of Aluminium Composite Materials (ACM), material specifications as per Clause 1701.3.7. The top most platewill be in Rectangular shape of 600mm x 600 mm size, riveted over welded M.S. angle iron frame of 25 mm x 25mm x 5 mm size on back on edges. The middle plate will be 1200 mm x 150 mm size riveted over welded M.S. angle iron frame of 25mm x 25mmx 5 mm size on back on edges. The main lower most plate will be 1500 mm x 600 mm size, riveted over welded M.S. angle iron frame of 25 mm x 25 mm x 5 mm size. Welding of all the sheets over angle iron frame will be done neatly to have plain surface on one side. The angle iron frames of the lower most plate and the middle plate will be welded to two nos. 75 mm x 75 mm (12 SWG) sheet tubes posts placed at 1125 mm apart centre to centre. The top of the middle plate will be flushed with the top of 75 mm dia medium steel tube posts and these posts will be embedded in cement concrete M15 grade blocks of 450 mm x 450 mm x 600 mm below ground level. The height of bottom of the lower most plate will be 1200 mm from normal ground level and the bottom of middle plate will be 100 mm above the top level of the lower most plate. The Rectangular shaped plate mounted over angle iron frame will be connected to middle plate by square medium steel section of 47 mm x 47 mm thickness 12 SWG having a spacing of 100 mm between the Rectangular shaped plate and middle plate and this square section will be welded to the bottom point of the Rectangular shaped plate. (ii) The lettering and borders, etc. of middle and bottom plate, SHDP logo on top plate shall be as per clause 1701.4.6 essages/Borders. All the sections of frame and posts will be painted with primer and two coats of Epoxy paint. The steel tube below ground level will be painted with three coats of Epoxy paint. The design, painting and lettering shall be done as per approved drawing. (iii) For warranty and durability the clause 1701.5 and for maintenance the clause 1911 shall be applicable. (iv) A reference number along with the month and year of installation should be placed on the back of a sign in
a contrasting colour or by stamping in characters not exceeding 50 mm in height.485777/2019/Dir(Tech) 7Retro Reflective Trafic Sign As per IRC 67 Clause 1701.3.8.1 Class A Type 1 (Item No. 16.29/ Page No. 149/Vol.03/Common SR-2023-24) - as per the direction of Engineer-in-charge. - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work."
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Each | 18115.36 | 18115.36 | 2.0 | False | None | None | False | None | False | 36230.72 | 0 | 3016025 | 100798 | None | Item No 8.7, Page no 65, Vol 3, PWD Common SR 202 | Direction and Place Identification Signs upto 0.9 m2 SizeBoard.Providing and erecting direction and place identification retroreflectorisedsign as per IRC:67:2022 made of high intensitygrade sheeting vide clause 801.3, fixed over aluminiumsheeting, 2 mm thick or Aluminium composite material sheetwith overall thickness of 4mm with area not exceeding 0.9m2 fixed over back support frame of min 35 x 35 x 3mm anglemounted on a mild steel circular pipe 65 NB, firmly fixed to theground by means of properly designed foundation with M25grade cement concrete 45 x 45 x 60 cm, 60 cm below ground
level as per approved drawing"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 10631.8 | 10631.8 | 1.8 | False | None | None | False | None | False | 19137.24 | 0 | 3016026 | 100798 | None | Item No 8.5 ii, Page no 64, Vol 3, PWD Common SR | Retro-Reflectorised Traffic SignsProviding and fixing of retro- reflectorised cautionary,mandatory and informatory sign as per IRC:67:2022 madeof Class B Type XI retro reflective sheeting fixed over 2 mmthick aluminium sheeting vide clause 801.3, 3mm/4mm thickAluminium composite material sheet depending on the size ofthe sign fixed over the back support frame of min 25 x 25 x3mm angle mounted on a mild steel circular pipe 65 NB, 3.2mm thickness firmly fixed to the ground by means of properlydesigned foundation with M25 grade cement concrete 45 cmx 45 cm x 60 cm, 60 cm below ground level as per approveddrawing.The sign shall be maintained as per section 12 ofIRC:67:2022. (ii) 90 cm equilateral triangle
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Each | 5527.12 | 5527.12 | 18.0 | False | None | None | False | None | False | 99488.16 | 0 | 3016027 | 100798 | None | Item No 8.5 viii, Page no 64, Vol 3, PWD Common S | Retro-Reflectorised Traffic SignsProviding and fixing of retro- reflectorised cautionary,mandatory and informatory sign as per IRC:67:2022 made
of Class B Type XI retro reflective sheeting fixed over 2 mmthick aluminium sheeting vide clause 801.3, 3mm/4mm thickAluminium composite material sheet depending on the size ofthe sign fixed over the back support frame of min 25 x 25 x3mm angle mounted on a mild steel circular pipe 65 NB, 3.2mm thickness firmly fixed to the ground by means of properlydesigned foundation with M25 grade cement concrete 45 cmx 45 cm x 60 cm, 60 cm below ground level as perapproveddrawing.The sign shall be maintained as per section 12 ofIRC:67:2022. (viii) 60 cm circular"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Each | 5070.46 | 5070.46 | 2.0 | False | None | None | False | None | False | 10140.92 | 0 | 3016028 | 100798 | None | Item No 8.43, Page no 74, Vol 3, PWD Common SR 20 | Supplying and Fixing of Molded Shank Raised PavementMarkers / Cat's Eye made of polycarbonate and ABS mouldedbody and reflective panels with micro prismatic lens capable ofproviding total internal reflection of the light entering the lensface and shall support a load of 16000 kg tested in accordanceto ASTM D 4280 Type H and complying to Specifications ofCategory A of MORTH Circular No RW/NH/33023/10-97DO III Dt 11.06. 1997. The height, width and length shall notexceed 50 mm, 100 mm and 102 +/- 2 mm and with minimumreflective area of 13 cm2 on each side and the slope to thebase shall be 35 +/- 5 degree. The strength of detachment ofthe integrated cylindrical shanks, (of diameter not less than19 +/- 2 mm and height not less than 30+/- 2 mm) fromthe body is to be a minimum value of 500 Kg. Fixing will beby drilling holes on the road for the shanks to go inside,without nails and using epoxy resin based adhesive as permanufacturer's recommendation and complete as directed bythe engineer.The contractor shall submit a two year warrantyfor satisfactory field performance including stipulatedretro-reflectance of the reflecting panel, to the Engineer.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 430.7 | 430.7 | 380.0 | False | None | None | False | None | False | 163666.0 | 0 | 3016029 | 100798 | None | Item No 8.16 (ii), Page no 67, Vol 3, PWD Common | Kilometre Stone Reinforced cement concrete M15grade kilometre stone oftandard design as per IRC:8-1980, fixing in position including painting and printing etc- (ii) Ordinary kilometer stone (precast)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Each | 3453.86 | 3453.86 | 2.0 | False | None | None | False | None | False | 6907.72 | 0 | 3016030 | 100798 | None | Item No 8.16 (iii), Page no 67, Vol 3, PWD Commo | Kilometre Stone Reinforced cement concrete M15grade kilometre stone ofstandard design as per IRC:8-1980, fixing in position includingpainting and printing etc- (iii) 200 m stone (precast)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Each | 993.56 | 993.56 | 9.0 | False | None | None | False | None | False | 8942.04 | 0 | 3016031 | 100798 | None | Item No. 8.60.2 (ii) Page No. 80 Vol.03 | Providing Speed Breakers/Raised pedestrian crossings in Trapezoidal section with 2.5 m Top width and transition length of 0.8 m length and height of 0.1 m as per IRC 99:2018 using Dense Bituminous Macadam (DBM) Gr II and Bituminous Concrete (BC) Gr II for entire formation width & WBM Gr II for Shoulder hump portion only (150 mm thick), completing with road marking paint with applied thermoplastic compound with reflecting glass beeds on bituminous surface and providing 2 Nos. retro reflective traffic signs as per IRC 67 -2022 Intermediate lane with formation width of 7.50 m (Item No. 8.60.2 (ii) / Page No. 80/Vol.03/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 53635.72 | 53635.72 | 2.0 | False | None | None | False | None | False | 107271.44 | 0 | 3016032 | 100798 | None | Item No. 8.5 A xv) Page No. 65 Vol.03 | Retro-Reflectorised Traffic Signs Providing and fixing of retro- reflectorised cautionary, mandatory and informatory sign as per IRC:67:2022 made of Class B Type XI retro reflective sheeting fixed over 2 mm thick aluminium sheeting vide clause 801.3, 3mm/4mm thick Aluminium composite material sheet depending on the size of the sign fixed over the back support frame of min 25 x 25 x 3mm angle mounted on a mild steel circular pipe 65 NB, 3.2 mm thickness firmly fixed to the ground by means of properly designed foundation with M25 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing.The sign shall be maintained as per section 12 of IRC:67:2022. (xv) 90 cm high octagon (Item No. 8.5 A (xv)/ Page No. 65/Vol.03/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Each | 7672.36 | 7672.36 | 2.0 | False | None | None | False | None | False | 15344.72 | 0 | 3016033 | 100798 | None | Item No. 8.48 Page No. 76Vol.03 | Chevron Boards Supply and installation of retro- reflective Chevron signboards of 600x450mm made out of cube corner micro prismatic grade sheeting confirming to Type XI standards of IRC:67:2022 & ASTM D 4956-09 specification & fixed over 3 mm thick Aluminium Composite Panel sheet having minimum 0.30 mm thick aluminum skin on both sides & fixed over back support frame of 25x25x3mm MS angle frame. Supported on 75 mm dia OR 75x75x6mm Mild steel with clear height of not less than 2.1 m from the ground level to the bottom of the Sign board & 60 cm below ground level. The sign post should be painted with one coat of red oxide paint and two coats of synthetic enamel paint of black and white colour with bands of 30 cm height, firmly fixed to the ground by means of foundation with M 20 grade cement, concrete foundation size of 45cm x 45 cm x 60 cm including cost & conveyance of all materials, equipment,machinery & Labour with all leads and lifts for satisfactory completion of the work as directed by Engineer incharge. (Item No. 8.48/ Page No. 76/Vol.03/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 4231.48 | 4231.48 | 16.0 | False | None | None | False | None | False | 67703.68 | 0 | 3016034 | 100798 | None | Item No. 8.16 (i) Page No. 67 Vol.03 | Reinforced cement concrete M15grade kilometre stone of standard design as per IRC:8-1980, fixing in position including painting and printing etc 5th kilometre stone (precast) (Item No. 8.16 (i)/ Page No. 67/Vol.03/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Each | 5995.58 | 5995.58 | 1.0 | False | None | None | False | None | False | 5995.58 | 0 |
| 1710251641000 | 0 | None | None | Roads | RCC Drain | 1969800.82 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3016035 | 100799 | None | Item No 1.14.1, Page no 8, Vol 1, PWD Common SR 2 | Earth work excavation for Foundationdepth upto 3 m, as per drawing and technicalout, shoring, strutting, barricading,excavated surfaces, disposing off or & stacking the selected earth for reusem including cost of labour, tools, usagerequired to complete the workIn all kinds of soils Depth upto 3 m
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 120.36 | 120.36 | 462.2 | False | None | None | False | None | False | 55630.392 | 0 | 3016036 | 100799 | None | Item No 2.1.3, Page no 15, Vol 1, PWD Common SR 2 | Providing and laying in position Cement Concrete for levelling course forall works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators,including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the otherappurtenances required to complete the work as per technical specifications.- Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 7067.02 | 7067.02 | 36.8 | False | None | None | False | None | False | 260066.336 | 0 | 3016037 | 100799 | None | Item No. 2.4.2 Page No. 16 Vol.01 | Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates (Item No. 2.4.2/ Page No. 16/Vol.01/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 7461.14 | 7461.14 | 29.6 | False | None | None | False | None | False | 220849.744 | 0 | 3016038 | 100799 | None | Item No 2.4.2, Page no 15, Vol 1, PWD Common SR 2 | Providing and laying in position Cement Concrete for all Sub structures ofbuilding, Irrigation works, Sub structure works of bridges, Drain works &other parallel works from 0.50m to 3.50 m height. The granite/trap/basaltcrushed graded coarse aggregates and fine aggregates as per relevant ISCodes machine mixed with super plasticisers, laid in layers, well compactedusing needle vibrators, providing weep holes wherever necessary, includingall lead & lifts, cost of all materials of quality, confirming to the requirementsof relevant IS codes, labour, Usage charges of machinery, curing and all otherappurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 10072.54 | 10072.54 | 48.0 | False | None | None | False | None | False | 483481.92 | 0 | 3016039 | 100799 | None | Item No 2.5.1, Page no 16, Vol 1, PWD Common SR 2 | Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 9388.08 | 9388.08 | 25.6 | False | None | None | False | None | False | 240334.848 | 0 | 3016040 | 100799 | None | Item No 2.11 h, Page no 18, Vol 1, PWD Common SR | Steel FabricationSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification.All other type of structures
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | MT | 93232.98 | 93232.98 | 6.57 | False | None | None | False | None | False | 612540.6786 | 0 | 3016041 | 100799 | None | Item No. 2.5.2 Page No. 16 Vol.01 | Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates (Item No. 2.5.2/ Page No. 16/Vol.01/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 9689.69 | 9689.69 | 10.0 | False | None | None | False | None | False | 96896.9 | 0 |
| 1710251641000 | 0 | None | None | Roads | Water Supply | 147889.4 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3016042 | 100800 | None | Item No 1.17.1, Page no 10, Vol 1, PWD Common SR | Earth work excavation for pipeline trenches in all kinds of soils by mechanical means as per drawing and technical specifications, including setting out, construction of shoring, strutting, barricading, caution lights, bracing, using sight rails & bonding rods at every 100 mm wherever necessary as directed, removal of stumps and other deleterious matter, dressing of sides and levelling the bottom of trench to the extent required , utilising the available excavated earth locally for the work etc., and all other appurtenances complete in the followingstrata
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 309.16 | 309.16 | 90.0 | False | None | None | False | None | False | 27824.4 | 0 | 3016043 | 100800 | None | Item No 9.2.1, Page no 96, Vol 5, PWD Common SR 2 | Providing, laying and jointing HDPE pipes of specified grade and conforming to IS 4984-2016 with latest ammendments and conveying to work site including loading and unloading at both destinations and rolli g and lowering into trenches, laying true to line and jointing of pipes and specials with electrofusion welding, giving hydraulic test as per relevant ISS with all lead and lifts including encasing the pipe alround to a depth of not less than 15 cms. with soft gravel or selected earth available from the excation, testing and commissioning. The rate is exclusive of required specials and fittings wherever necessary like saddle Tee, stub ends, flanged sets, bedns, reducers etc. complete (Contractor will make his own arrangements for procuring water for t e s t i n g ) e t c . c o m p l e t e HDPE Grade PE80-PN8.0, 63mm dia
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Rmtr | 258.42 | 258.42 | 50.0 | False | None | None | False | None | False | 12921.0 | 0 | 3016044 | 100800 | None | Item No 1.1, Page no 7, Vol 1, PWD Common SR 2023 | Refilling available earth around trenches/pipelines, cables in layers not exceeding 20 cms in depth, compacting each deposited layer by ramming after watering with a lead upto 50 m, and lift upto 1.5 m. Including cost of alllabour complete as per specifications
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 188.8 | 188.8 | 90.0 | False | None | None | False | None | False | 16992.0 | 0 | 3016045 | 100800 | None | Item No. 19.2.3 Page No. 96 Vol.05 | Providing, laying and jointing HDPE pipes of specified grade and conforming to IS 4984-2016 with latest ammendments and conveying to work site including loading and nloading at both destinations and rolling and lowering into trenches, laying true to line and jointing of pipes and specials with electrofusion welding, giving hydraulic test as per relevant ISS with all lead and lifts including encasing the pipe alround to a depth of not less than 15 cms. with soft gravel or selected earth available from the excation, testing and commissioning. The rate is exclusive of required specials and fittings wherever necessary like saddle Tee, stub ends, flanged sets, bedns, reducers etc. complete (Contractor will make his own arrangements for procuring water for testing) etc. complete. NOTE: Upto 110mm dia Coil shall be used. For: HDPE Grade PE80-PN8.0,90mm dia (Item No. 19.2.3/ Page No. 96/Vol.05/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | m | 450.76 | 450.76 | 200.0 | False | None | None | False | None | False | 90152.0 | 0 |
| 1710251641000 | 0 | None | None | Roads | Box Culvert (1.5 x 1.5) 1Vent | 2726355.92 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3016046 | 100801 | None | Item No 1.14.1, Page no 8, Vol 1, PWD Common SR 2 | Earth work excavation for Foundationdepth upto 3 m, as per drawing and technicalout, shoring, strutting, barricading,excavated surfaces, disposing off or& stacking the selected earth for reusem including cost of labour, tools, usagerequired to complete the workIn all kinds of soils Depth upto 3 m
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 120.36 | 120.36 | 210.0 | False | None | None | False | None | False | 25275.6 | 0 | 3016047 | 100801 | None | Item No 2.1.3, Page no 15, Vol 1, PWD Common SR 2 | Providing and laying in position Cement Concrete for levelling course forall works in foundation. The granite/trap/basalt crushed graded coarseaggregates and fine aggregates as per relevant IS Codes machine mixed, laid inlayers not exceeding 150 mm thickness, well compacted using plate vibrators,including all lead & lifts, cost of all materials of quality, labour, Usage charges ofmachinery, curing, and all the otheappurtenances required to complete thework as per technical specifications.-Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 7067.02 | 7067.02 | 27.0 | False | None | None | False | None | False | 190809.54 | 0 | 3016048 | 100801 | None | Item No 2.4.3, Page no 15, Vol 1, PWD Common SR 2 | Providing and laying in position Cement Concrete for all Sub structures ofbuilding, Irrigation works, Sub structure works of bridges, Drain works &other parallel works from 0.50m to 3.50 m height. The granite /trap/ basaltcrushed graded coarse aggregates and fine aggregates as per relevant ISCodes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, includingall lead & lifts, cost of all materials of quality, confirming to the requirementsof relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. .M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 8971.78 | 8971.78 | 107.1 | False | None | None | False | None | False | 960877.638 | 0 | 3016049 | 100801 | None | Item No 2.11 h, Page no 18, Vol 1, PWD Common SR | Steel FabricationSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification.All other type of structures
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | MT | 93232.98 | 93232.98 | 11.47 | False | None | None | False | None | False | 1069382.2806 | 0 | 3016050 | 100801 | None | Item No 8.1, Page no 66, Vol 3, PWD Common SR 202 | Painting Two Coats on New Concrete Surfaces Painting two coats after filling the surface with synthetic enamel paint in all shades on new plastered concrete surfaces
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 128.62 | 128.62 | 22.5 | False | None | None | False | None | False | 2893.95 | 0 | 3016051 | 100801 | None | Item No 8.4, Page no 15, Vol 1, PWD Common SR 202 | Printing New letter and Figures of any Shade
Printing new letter and figures of any shade with synthetic
enamel paint black or any other approved colour to give an
even shadeper cm height"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Per cm Height Per Letter | 1.06 | 1.06 | 1200.0 | False | None | None | False | None | False | 1272.0 | 0 | 3016052 | 100801 | None | Item No. 2.11 (ii) A Page No. 10 Vol.03 | Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead By Mechanical Means (A)Dismantling Brick / Tile work / rubble masonry / pitching / etc bymechanical means (Item No. 2.11 (ii) A/ Page No. 10/Vol.03/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 212.4 | 212.4 | 39.0 | False | None | None | False | None | False | 8283.6 | 0 | 3016053 | 100801 | None | Item No. 2.17 (ix) B Page No. 11 Vol.03 | Removing all type of Hume Pipes and Stacking including Earthwork and Dismantling of Masonry Works. Above 600 mm to 900 mm dia (Item No. 2.17 (ix) B/ Page No. 11/Vol.03/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | m | 1293.28 | 1293.28 | 50.0 | False | None | None | False | None | False | 64664.0 | 0 | 3016054 | 100801 | None | Item No. 2.5.2Page No. 16 Vol.01 | Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates (Item No. 2.5.2/ Page No. 16/Vol.01/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 9689.69 | 9689.69 | 41.58 | False | None | None | False | None | False | 402897.3102 | 0 |
| 1710251641000 | 0 | None | None | Roads | Shifting of Electrical Poles | 382874.04 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3016055 | 100802 | None | 1.02 | Line Supports (Pole)
RCC Pole - 9 Mtr Long, 150 Kg WL Sq Section (Dwg No. BESCOM/GM/QS&S/51 Dtd 24.11.2018) as per IS-785. ( Common SR - 2023-24, Item No 1.02 Page No 03/81 Material No -200106)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 9812.88 | 9812.88 | 7.0 | False | None | None | False | None | False | 68690.16 | 0 | 3016056 | 100802 | None | 2.02 | Erection of Poles
Erection of RCC/PSCC Pole of 9 to 10 Mtr long in a pit of 1.8 Mtr depth ( Common SR - 2023-24, Item No 2.02 Page No 44/81 Material No -)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 1313.34 | 1313.34 | 7.0 | False | None | None | False | None | False | 9193.38 | 0 | 3016057 | 100802 | None | 1.05 | Line Supports (Pole)
PSCC Pole - 8 Mtr Long, 200 Kg WL (Dwg No. BESCOM/GM/QS&S/49 Dtd 24.11.2018) as per REC Standards. ( Common SR - 2023-24, Item No 1.05 Page No 03/81 Material No -200004)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 4364.82 | 4364.82 | 2.0 | False | None | None | False | None | False | 8729.64 | 0 | 3016058 | 100802 | None | 2.01 | Erection of Poles
Erection of RCC/PSCC Pole of 7.5 to 8 Mtr long in a pit of 1.5 Mtr depth ( Common SR - 2023-24, Item No 2.01 Page No 44/81 Material No -)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 1087.96 | 1087.96 | 2.0 | False | None | None | False | None | False | 2175.92 | 0 | 3016059 | 100802 | None | 1.07 | Line Supports (Pole)
Pre-Stressed Tubular Spun Pole - 11 Mtr Long, 500 Kg WL (Dwg No. BESCOM/GM/QS&S/45 Dtd 24.11.2018) as per IS-13158: 1991 ( Common SR - 2023-24, Item No 1.07 Page No 03/81 Material No -200120)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 20888.36 | 20888.36 | 1.0 | False | None | None | False | None | False | 20888.36 | 0 | 3016060 | 100802 | None | 2.05 | Erection of Poles
Erection of 11 Mtr long Concrete Spun Pole in a pit of 2.5 Mtr depth (Mechnised Labour) ( Common SR - 2023-24, Item No 2.05 Page No 44/81 Material No -)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 3001.92 | 3001.92 | 1.0 | False | None | None | False | None | False | 3001.92 | 0 | 3016061 | 100802 | None | 2.01 | 1 kV, Horizontal Cross Arm - Mild Steel (MS) (Dwg No. BESCOM/GM/QS&S/04 Dtd 24.11.2018). ( Common SR - 2023-24, Item No 2.01 Page No 03/81 Material No -279020)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 438.96 | 438.96 | 8.0 | False | None | None | False | None | False | 3511.68 | 0 | 3016062 | 100802 | None | 2.11 | HT ST Support 50x6 mm Flat - MS (Dwg No. BESCOM/GM/QS&S/04 Dtd 24.11.2018). ( Common SR - 2023-24, Item No 2.11 Page No 04/81 Material No -279092)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 107.38 | 107.38 | 23.0 | False | None | None | False | None | False | 2469.74 | 0 | 3016063 | 100802 | None | 5.06 | Fixing of HT/LT Single Top Support ( Common SR - 2023-24, Item No 5.06 Page No 45/81 Material No -)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Each | 132.16 | 132.16 | 23.0 | False | None | None | False | None | False | 3039.68 | 0 | 3016064 | 100802 | None | 2.07 | LT 2 Pin Cross Arm - MS (Dwg No. BESCOM/GM/QS&S/32 Dtd 24.11.2018). ( Common SR - 2023-24, Item No 2.07 Page No 04/81 Material No -279012)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 155.76 | 155.76 | 5.0 | False | None | None | False | None | False | 778.8 | 0 | 3016065 | 100802 | None | 2.05 | LT 4 Pin Cross Arm - MS
(Dwg No. BESCOM/GM/QS&S/32 Dtd 24.11.2018) ( Common SR - 2023-24, Item No 2.05 Page No 04/81 Material No -279014)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 341.02 | 341.02 | 5.0 | False | None | None | False | None | False | 1705.1 | 0 | 3016066 | 100802 | None | 5.01 | Fixing of 2 Pin cross arm with Insulator and Braces fixing / Fixing of 4 Pin cross arm with Insulator and Braces fixing ( Common SR - 2023-24, Item No 5.01 & 5.02 Page No 45/81 Material No -)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 188.8 | 188.8 | 10.0 | False | None | None | False | None | False | 1888.0 | 0 | 3016067 | 100802 | None | 6.1 | 11 kV, 45 kN Polymeric Insulator . ( Common SR - 2023-24, Item No 6.1 Page No 05/81 Material No -283320)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 219.48 | 219.48 | 6.0 | False | None | None | False | None | False | 1316.88 | 0 | 3016068 | 100802 | None | 6.06 | 11 kV, 5 kN Composite/Polymeric Pin Insulator. ( Common SR - 2023-24, Item No 6.06 Page No 05/81 Material No -283008)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 241.9 | 241.9 | 9.0 | False | None | None | False | None | False | 2177.1 | 0 | 3016069 | 100802 | None | 7.02 | Rabbit ACSR conductor ( Common SR - 2023-24, Item No 7.02 Page No 05/81 Material No -284108)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Km | 60731.06 | 60731.06 | 1.0 | False | None | None | False | None | False | 60731.06 | 0 | 3016070 | 100802 | None | cost data | Erection of 3 Phase, 11kV/433V, 63 kVA BEE - 4/5 Star Rated Distribution Transformer Centre Using 9 Mtr RCC Pole DPTC ( WithOut Transformer) - Cost Data Sheet - 25 ( Common SR - 2023-24, )
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Set | 115431.14 | 115431.14 | 1.0 | False | None | None | False | None | False | 115431.14 | 0 | 3016071 | 100802 | None | 51.01 | GI Grounding pipe, B - Class, 42 mm dia, 2.5 Mtr long, 3.2 mm thick with bolt, nut, GI Strips and washer complete Minimum Weight of GI Pipe: 7.3 Kg ( Common SR - 2023-24, Item No 51.01 Page No 22/81 Material No -281674)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 880.28 | 880.28 | 2.0 | False | None | None | False | None | False | 1760.56 | 0 | 3016072 | 100802 | None | 51.02 | Good Quality well burnt Charcoal for grounding purposes packed in non returnable gunny bag of 30 Kg each ( Common SR - 2023-24, Item No 51.02 Page No 22/81 Material No -600095)" ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 797.68 | 797.68 | 2.0 | False | None | None | False | None | False | 1595.36 | 0 | 3016073 | 100802 | None | 51.03 | Good Quality Salt for grounding purposes packed in 50 Kg gunny bag ( Common SR - 2023-24, Item No 51.03 Page No 22/81 Material No -607054)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Bag | 365.8 | 365.8 | 2.0 | False | None | None | False | None | False | 731.6 | 0 | 3016074 | 100802 | None | 51.04 | Rod type of earthing using 40 mm Dia, 3 Mtr long MS rod as ground rod, in earth pit of 300 mm width and 3300 mm depth and using 50x6 mm flat welded to ground rod as terminal & connected to equipment ground terminal using PVC Al wire as specified ( Common SR - 2023-24, Item No 51.04 Page No 23/81 Material No -281685)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 2562.96 | 2562.96 | 2.0 | False | None | None | False | None | False | 5125.92 | 0 | 3016075 | 100802 | None | 1.2.2 | Digging of Pit - Digging of Pit 1.6 Mtr depth for erection of 7.5/8 Mtr Long Steel/RCC/PSCC supports as per approved Drawing. - Hard Soil ( Common SR - 2023-24, Item No 1.2.2 Page No 43/81 Material No -)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Per Pit | 1187.08 | 1187.08 | 15.0 | False | None | None | False | None | False | 17806.2 | 0 | 3016076 | 100802 | None | 9 mt | R&R of 9mt pole ( Common SR - 2023-24, Item No Page No Material No -)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 2495.35 | 2495.35 | 8.0 | False | None | None | False | None | False | 19962.8 | 0 | 3016077 | 100802 | None | arm | R&R of X-Arm ( Common SR - 2023-24, Item No Page No Material No -)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 358.72 | 358.72 | 8.0 | False | None | None | False | None | False | 2869.76 | 0 | 3016078 | 100802 | None | htst | R&R of HTST ( Common SR - 2023-24, Item No Page No Material No -)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos. | 251.1 | 251.1 | 30.0 | False | None | None | False | None | False | 7533.0 | 0 | 3016079 | 100802 | None | 7.02 | R&R of Rabbit ( Common SR - 2023-24, Item No 7.02 & 7.04 Page No 46/81 Material No -)
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Km | 9880.14 | 9880.14 | 2.0 | False | None | None | False | None | False | 19760.28 | 0 |
| 1710251641000 | 0 | None | None | Roads | 1st year Maintanance | 0.0 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3016080 | 100803 | None | 2.5(ii) a | Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness. By Mechanical Means using Dozer A) In area of light jungle Inclusive of all lift and leads and all complete as per direction of Engineer-in-charge.
UNI SR 2023-24, V-3, Page No. 9, Item No. 2.5(ii) a (Quantity to be executed 43.36) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | 100 Sqm | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3016081 | 100803 | None | 16.19 | Maintenance of Drains - The maintenance of drains include erosion, repair, clearing, cleaning, reshaping, regrading, deepening of side drains as well as catch water drains as per technical specification Clause 1908. Inclusive of all lift and leads and all complete as per direction of Engineer-in-charge.
UNI SR 2023-24, V-3, Page No. 147, Item No. 16.19 (Quantity to be executed 3252) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Rmtr | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3016082 | 100803 | None | 10.3 | Maintenance of Earth Shoulder (stripping excess soil)-Stripping excess soil from the shoulder surface to a minimum depth of 150mm to achieve the approved level and compacting with plate compactor including cost of materials, labour, HOM complete as per specifications. MORTH Specification No. 3003. Inclusive of all lift and leads and all complete as per direction of Engineer-in-charge.
UNI SR 2023-24, V-3, Page No. 91, Item No. 10.3(Quantity to be executed =2710) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3016083 | 100803 | None | 10.2 | Maintenance of Earthen Shoulder (filling with fresh soil) - Making up loss of material I irregularities on shoulder to a minimum depth of 150mm to the design level by adding fresh approved soil and compacting it with appropriate equipment including cost of materials, labour, HOM complete as per specifications etc. MORTH Specification No.3003. Inclusive of all lift and leads and all complete as per direction of Engineer-in-charge.
UNI SR 2023-24, V-3, Page No. 91, Item No. 10.2.(Quantity to be executed =2710) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3016084 | 100803 | None | 10.5 | Filling Pot-holes and Patch Repairs with BituminousRemoval of all failed material, trimming of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 504 using HMP 40/60 TPH Capacity compacting, trimming and finishing the surface to form a smooth continuous surface, all as per clause 3004.2
UNI SR 2023-24, V-3, Page No. 91, Item No. 10.5.(Quantity to be executed =298.10) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3016085 | 100803 | None | 1.12 | Nala Training: Earthwork in surface excavation by mechanical means for lowering & leveling the ground for all works other than foundation in all kinds of soils & upto depth not exceeding 300mm as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking thes elected earth for re use inaradius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenances required to complete the work.In all kinds of soils upto 300 mm depthUNI SR 2023-24, V-1, Page No. 8, Item No. 1.12(Quantity to be executed =225) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 |
| 1710251641000 | 0 | None | None | Roads | 2nd Year Maintanance | 0.0 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3016086 | 100804 | None | 2.5(ii) a | Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness. By Mechanical Means using Dozer A) In area of light jungle Inclusive of all lift and leads and all complete as per direction of Engineer-in-charge.
UNI SR 2023-24, V-3, Page No. 9, Item No. 2.5(ii) a(Quantity to be executed =65.04) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | 100 Sqm | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3016087 | 100804 | None | 16.19 | Maintenance of Drains - The maintenance of drains include erosion, repair, clearing, cleaning, reshaping, regrading, deepening of side drains as well as catch water drains as per technical specification Clause 1908. Inclusive of all lift and leads and all complete as per direction of Engineer-in-charge.
UNI SR 2023-24, V-3, Page No. 147, Item No. 16.19(Quantity to be executed =4336) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Rmtr | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3016088 | 100804 | None | 10.3 | Maintenance of Earth Shoulder (stripping excess soil) - Stripping excess soil from the shoulder surface to a minimum depth of 150mm to achieve the approved level and compacting with plate compactor including cost of materials, labour, HOM complete as per specifications. MORTH Specification No. 3003 . Inclusive of all lift and leads and all complete as per direction of Engineer-in-charge.
UNI SR 2023-24, V-2, Page No. 91, Item No. 10.3.(Quantity to be executed =813) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3016089 | 100804 | None | 10.2 | Maintenance of Earthen Shoulder (filling with fresh soil) - Making up loss of material I irregularities on shoulder to a minimum depth of 150mm to the design level by adding fresh approved soil and compacting it with appropriate equipment including cost of materials, labour, HOM complete as per specifications etc. MORTH Specification No.3003. Inclusive of all lift and leads and all complete as per direction of Engineer-in-charge.
UNI SR 2023-24, V-3, Page No. 91, Item No. 10.2.(Quantity to be executed =2710) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3016090 | 100804 | None | 10.5 | Filling Pot-holes and Patch Repairs with BituminousRemovalofallfailedmaterial,trimmingofcompletedexcavationtoprovidefirmverticalfaces,cleaningofsurface,paintingoftackcoatonthesidesandbaseofexcavationasperclause503,backfillingthepotholeswithhotbituminousmaterialasperclause504usingHMP40/60TPHCapacitycompacting,trimmingandfinishingthesurfacetoformasmoothcontinuoussurface,allasperclause 3004.2
UNI SR 2023-24, V-3, Page No. 91, Item No. 10.5(Quantity to be executed =379.40) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3016091 | 100804 | None | 1.12 | Nala Training : Earth work in surface excavation by mechanical means for lowering & leveling the ground for all works other than foundation in all kinds of soils & upto depth not exceeding 300mm as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenances required to complete the work.In all kinds of soils upto 300 mm depth
UNI SR 2023-24, V-1, Page No. 8, Item No. 1.12(Quantity to be executed =225) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 |
| 1710251641000 | 0 | None | None | Roads | 3rd Year Maintenance | 216187.5 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3016092 | 100805 | None | Item No.VOL-III-2.6 Page No. 9 | Clearing & grubbing road land including vegetation, bushes, shrubs, saplings by using weed cutter / minor equipment.
PWD SoR for Roads & Bridges - 2023-24 ( Item No.VOL-III-2.6 / Page No. 9)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | 100 Sqm | 519.39 | 519.39 | 27.36 | False | None | None | False | None | False | 14210.5104 | 0 | 3016093 | 100805 | None | tem No.VOL-III-16.19 Page No. 147 | Maintenance of Drains - The maintenance of drains include erosion, repair, clearing, cleaning, reshaping, regrading, deepening of side drains as well as catch water drains as per technical specification Clause 1908.
PWD SoR for Roads & Bridges - 2023-24 ( Item No.VOL-III-16.19 / Page No. 147)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Rmtr | 7.93 | 7.93 | 1824.0 | False | None | None | False | None | False | 14464.32 | 0 | 3016094 | 100805 | None | tem No.VOL-III-10.3 Page . 91 | Maintenance of Earth Shoulder (stripping excess soil) - Stripping excess soil from the shoulder surface to a minimum depth of 150mm to achieve the approved level and compacting with plate compactor including cost of materials, labour, HOM complete as per specifications. MORTH Specification No. 3003
PWD SoR for Roads & Bridges - 2023-24 ( Item No.VOL-III-10.3 / Page No. 91)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 51.54 | 51.54 | 239.4 | False | None | None | False | None | False | 12338.676 | 0 | 3016095 | 100805 | None | Item No.VOL-III-10.2 Page No. 91 | Maintenance of Earthen Shoulder (filling with fresh soil) - Making up loss of material I irregularities on shoulder to a minimum depth of 150mm to the design level by adding fresh approved soil and compacting it with appropriate equipment including cost of materials, labour, HOM complete as per specifications. MORTH Specification No.3003
PWD SoR for Roads & Bridges - 2023-24 ( Item No.VOL-III-10.2 / Page No. 91)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 128.2 | 128.2 | 798.0 | False | None | None | False | None | False | 102303.6 | 0 | 3016096 | 100805 | None | Item No.VOL-III-10.5 Page No. 91 | Filling Pot-holes and Patch Repairs with Bituminous concrete, 40mm (using VG-30 Grade Bitumen) - Removal of all failed material, trimming of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 510 using HMP 40/60 TPH Capacity compacting, trimming and finishing the surface to form a smooth continuous surface, all as per clause 3004.2 - as per the direction of Engineer-in-charge.
(Item No. 10.5/ Page No.91/Vol.03/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 563.0 | 563.0 | 62.7 | False | None | None | False | None | False | 35300.1 | 0 | 3016097 | 100805 | None | Item No.VOL-III-16.22 Page No. 147 | Maintenance of Road Signs- Maintenance of road signs by way of cleaning and repainting of mandatory / requlatory / cautionary / informatory and place identifications sign board as perdrawings and technical specification Clause 1910
PWD SoR for Roads & Bridges - 2023-24 ( Item No.VOL-III-16.22 / Page No. 147)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Km | 2622.05 | 2622.05 | 2.28 | False | None | None | False | None | False | 5978.274 | 0 | 3016098 | 100805 | None | Item No.OL-III-16.24 i Page No. 148 | Maintenance of 200 m and km stones - Maintenance of 200 metre and km stones-Maintenance of 200 metre km stone by way of refiting of tilted stones repairing with cement mortar, cleaning, repairing and lettering on 200 metre km stone and 5th km stone as per drawing and technical specification Clause 1912 Painting two coats with synthetic enamel paint
PWD SoR for Roads & Bridges - 2023-24 ( Item No.VOL-III-16.24 i / Page No. 148)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Km | 272.25 | 272.25 | 2.28 | False | None | None | False | None | False | 620.73 | 0 | 3016099 | 100805 | None | V 1 Page No.8. Item No.1.12 | Nala Training: Earth work in surface excavation by mechanical means for lowering & leveling the ground for all works other than foundation in all kinds of soils & upto depth not exceeding 300mm as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenances required to complete the work. PWD, Bangalore, SR:2023-24 V 1 Page No.8. Item No.1.12) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 125.55 | 125.55 | 225.0 | False | None | None | False | None | False | 28248.75 | 0 | 3016100 | 100805 | None | tem No.VOL-III-8.10 Page No. 66 | Painting of Parapet walls of CD work. KSRRB M800-6. Painting two coats on New Concrete Surface : Painting two coats after filling the surface with synthetic enamel paint in all shades on new plastered concrete surfaces complete as per specifications. MORTH Specification No. 803
PWD SoR for Roads & Bridges - 2023-24 ( Item No.VOL-III-8.10/ Page No. 66)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 144.05 | 144.05 | 18.9 | False | None | None | False | None | False | 2722.545 | 0 |
| 1710251641000 | 0 | None | None | Roads | 4th Year Maintenance | 214242.71 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3016101 | 100806 | None | Item No.VOL-III-2.6 Page No. 9) | Clearing & grubbing road land including vegetation, bushes, shrubs, saplings by using weed cutter / minor equipment.
PWD SoR for Roads & Bridges - 2023-24 ( Item No.VOL-III-2.6 / Page No. 9)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | 100 Sqm | 537.94 | 537.94 | 27.36 | False | None | None | False | None | False | 14718.0384 | 0 | 3016102 | 100806 | None | Item No.VOL-III-16.19 Page No. 147 | Maintenance of Drains - The maintenance of drains include erosion, repair, clearing, cleaning, reshaping, regrading, deepening of side drains as well as catch water drains as per technical specification Clause 1908.
PWD SoR for Roads & Bridges - 2023-24 ( Item No.VOL-III-16.19 / Page No. 147)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Rmtr | 8.21 | 8.21 | 1824.0 | False | None | None | False | None | False | 14975.04 | 0 | 3016103 | 100806 | None | tem No.VOL-III-10.3 Page No. 91 | Maintenance of Earth Shoulder (stripping excess soil) - Stripping excess soil from the shoulder surface to a minimum depth of 150mm to achieve the approved level and compacting with plate compactor including cost of materials, labour, HOM complete as per specifications. MORTH Specification No. 3003
PWD SoR for Roads & Bridges - 2023-24 ( Item No.VOL-III-10.3 / Page No. 91)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 53.38 | 53.38 | 239.4 | False | None | None | False | None | False | 12779.172 | 0 | 3016104 | 100806 | None | Item No.VOL-III-10.2 Page No. 91 | Maintenance of Earthen Shoulder (filling with fresh soil) - Making up loss of material I irregularities on shoulder to a minimum depth of 150mm to the design level by adding fresh approved soil and compacting it with appropriate equipment including cost of materials, labour, HOM complete as per specifications. MORTH Specification No.3003
PWD SoR for Roads & Bridges - 2023-24 ( Item No.VOL-III-10.2 / Page No. 91)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 132.77 | 132.77 | 798.0 | False | None | None | False | None | False | 105950.46 | 0 | 3016105 | 100806 | None | Item No.VOL-III-10.5 Page No. 91 | Filling Pot-holes and Patch Repairs with Bituminous concrete, 40mm (using VG-30 Grade Bitumen) - Removal of all failed material, trimming of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 510 using HMP 40/60 TPH Capacity compacting, trimming and finishing the surface to form a smooth continuous surface, all as per clause 3004.2 - as per the direction of Engineer-in-charge.
(Item No. 10.5/ Page No.91/Vol.03/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 583.11 | 583.11 | 62.7 | False | None | None | False | None | False | 36560.997 | 0 | 3016106 | 100806 | None | V 1 Page No.8. Item No.1.12) | Nala Training: Earth work in surface excavation by mechanical means for lowering & leveling the ground for all works other than foundation in all kinds of soils & upto depth not exceeding 300mm as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenances required to complete the work. PWD, Bangalore, SR:2023-24 V 1 Page No.8. Item No.1.12) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 130.04 | 130.04 | 225.0 | False | None | None | False | None | False | 29259.0 | 0 |
| 1710251641000 | 0 | None | None | Roads | 5th Year Maintenance | 259465.33 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3016107 | 100807 | None | Item No.VOL-III-2.6 Page No. 9 | Clearing & grubbing road land including vegetation, bushes, shrubs, saplings by using weed cutter / minor equipment.
PWD SoR for Roads & Bridges - 2023-24 ( Item No.VOL-III-2.6 / Page No. 9)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | 100 Sqm | 556.49 | 556.49 | 27.36 | False | None | None | False | None | False | 15225.5664 | 0 | 3016108 | 100807 | None | VOL-III-16.19 Page No. 14 | Maintenance of Drains - The maintenance of drains include erosion, repair, clearing, cleaning, reshaping, regrading, deepening of side drains as well as catch water drains as per technical specification Clause 1908.
PWD SoR for Roads & Bridges - 2023-24 ( Item No.VOL-III-16.19 / Page No. 147)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Rmtr | 8.5 | 8.5 | 1824.0 | False | None | None | False | None | False | 15504.0 | 0 | 3016109 | 100807 | None | VOL-III-10.3 Page No. 91 | Maintenance of Earth Shoulder (stripping excess soil) - Stripping excess soil from the shoulder surface to a minimum depth of 150mm to achieve the approved level and compacting with plate compactor including cost of materials, labour, HOM complete as per specifications. MORTH Specification No. 3003
PWD SoR for Roads & Bridges - 2023-24 ( Item No.VOL-III-10.3 / Page No. 91)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 55.22 | 55.22 | 239.4 | False | None | None | False | None | False | 13219.668 | 0 | 3016110 | 100807 | None | VOL-III-10.2 Page No. 91 | Maintenance of Earthen Shoulder (filling with fresh soil) - Making up loss of material I irregularities on shoulder to a minimum depth of 150mm to the design level by adding fresh approved soil and compacting it with appropriate equipment including cost of materials, labour, HOM complete as per specifications. MORTH Specification No.3003
PWD SoR for Roads & Bridges - 2023-24 ( Item No.VOL-III-10.2 / Page No. 91)"
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 137.35 | 137.35 | 798.0 | False | None | None | False | None | False | 109605.3 | 0 | 3016111 | 100807 | None | VOL-III-10.5 Page No. 91 | Filling Pot-holes and Patch Repairs with Bituminous concrete, 40mm (using VG-30 Grade Bitumen) - Removal of all failed material, trimming of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 510 using HMP 40/60 TPH Capacity compacting, trimming and finishing the surface to form a smooth continuous surface, all as per clause 3004.2 - as per the direction of Engineer-in-charge.
(Item No. 10.5/ Page No.91/Vol.03/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 603.22 | 603.22 | 125.4 | False | None | None | False | None | False | 75643.788 | 0 | 3016112 | 100807 | None | V 1 Page No.8. Item No.1.12 | Nala Training: Earth work in surface excavation by mechanical means for lowering & leveling the ground for all works other than foundation in all kinds of soils & upto depth not exceeding 300mm as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenances required to complete the work. PWD, Bangalore, SR:2023-24 V 1 Page No.8. Item No.1.12) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work.
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 134.52 | 134.52 | 225.0 | False | None | None | False | None | False | 30267.0 | 0 |
| 1710251641000 | 0 | None | None | Roads | 6th Year Renewal after Maintenance | 7273375.28 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3016113 | 100808 | None | Item No 16.22, Page no 147, Vol 3, PWD Common SR | Maintenance of Road Signs- Maintenance of road signs by way of cleaning and repainting of mandatory / requlatory / cautionary / informatory and place identifications sign board as perdrawings and technical specification Clause 1910
Add Adhoc increase in SR @ the rate of 24% however even if the executed maintainence quantity exceeds the quantity considered in estimate no additional payment shall be made
2341.12+561.87 = 2902.99
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Km | 2902.99 | 2902.99 | 2.28 | False | None | None | False | None | False | 6618.8172 | 0 | 3016114 | 100808 | None | Item No 16.24 i, Page no 148, Vol 3, PWD Common S | Maintenance of 200 m and km stones - Maintenance of 200 metre and km stones- Maintenance of 200 metre km stone by way of refiting of tilted stones repairing with cement mortar, cleaning, repairing and lettering on 200 metre km stone and 5th km stone as per drawing and technical specification Clause 1912 Painting two coats withsynthetic enamel paint
Add Adhoc increase in SR @ the rate of 24% however even if the executed maintainence quantity exceeds the quantity considered in estimate no additional payment shall be made
243.08+58.34 = 301.42 ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 301.42 | 301.42 | 2.28 | False | None | None | False | None | False | 687.2376 | 0 | 3016115 | 100808 | None | Item No 8.1, Page no 66, Vol 3, PWD Common SR 202 | Painting two coats on New Concrete Surface : Painting two coats after filling the surface with synthetic enamel paint in all shades on new plastered concrete surfaces complete as per specifications. MORTH Specification No. 803
Add Adhoc increase in SR @ the rate of 24% however even if the executed maintainence quantity exceeds the quantity considered in estimate no additional payment shall be made
128.62+30.87 = 159.49 ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 159.49 | 159.49 | 22.5 | False | None | None | False | None | False | 3588.525 | 0 | 3016116 | 100808 | None | Item No 5.3i, Page no 31, Vol 3, PWD Common SR 20 | Providing and applying tack coat with RS1 Bituminous Emulsion using emulsion pressure distributor at the rate of 0.20 kg/m2 on the prepared bituminous surface cleaned with mechanical broom
Add Adhoc increase in SR @ the rate of 24% however even if the executed maintainence quantity exceeds the quantity considered in estimate no additional payment shall be made
14.16+3.40 = 17.56 ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 17.56 | 17.56 | 13069.15 | False | None | None | False | None | False | 229494.274 | 0 | 3016117 | 100808 | None | Item No 5.16 C (ii), Page no 40, Vol 3, PWD Comm | Bituminous Concrete Grading II for traffic 20 MSAProviding and laying Bituminous Concrete with 40/60 TPH capacity hot mix plant using crushed aggregates of specifiedgrading, premixed with bituminous binder VG-30, @ 5.4 percent of mix and filler, transporting the hot mix to work site,laying with mechanical paver finisher to the required grade,level and alignment, rolling with smooth wheeled, vibratory andtandem rollers to achieve the desired compaction as per MORTHspecification clause No. 507 complete in all respects
12925.72 + 3102.17 = 16027.89 ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 16027.89 | 16027.89 | 392.07 | False | None | None | False | None | False | 6284054.8323 | 0 | 3016118 | 100808 | None | Item No 8.15, Page no 67, Vol 3, PWD Common SR 20 | Providing and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 g/m2 area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35:2015.The finished surface to be level, uniform and free from streaks and holes.
Add Adhoc increase in SR @ the rate of 24% however even if the executed maintainence quantity exceeds the quantity considered in estimate no additional payment shall be made
625.40 + 150.10 = 775.50 ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 775.5 | 775.5 | 702.0 | False | None | None | False | None | False | 544401.0 | 0 | 3016119 | 100808 | None | Item No 8.43, Page no 74, Vol 3, PWD Common SR 20 | Supplying and Fixing of Molded Shank Raised PavementMarkers / Cat's Eye made of polycarbonate and ABS mouldedbody and reflective panels with micro prismatic lens capable ofproviding total internal reflection of the light entering the lensface and shall support a load of 16000 kg tested in accordanceto ASTM D 4280 Type H and complying to Specifications ofCategory A of MORTH Circular No RW/NH/33023/10-97DO III Dt 11.06. 1997. The height, width and length shall notexceed 50 mm, 100 mm and 102 +/- 2 mm and with minimumreflective area of 13 cm2 on each side and the slope to thebase shall be 35 +/- 5 degree. The strength of detachment ofthe integrated cylindrical shanks, (of diameter not less than19 +/- 2 mm and height not less than 30+/- 2 mm) fromthe body is to be a minimum value of 500 Kg. Fixing will beby drilling holes on the road for the shanks to go inside,without nails and using epoxy resin based adhesive as permanufacturer's recommendation and complete as directed bythe engineer.The contractor shall submit a two year warrantyfor satisfactory field performance including stipulatedretro-reflectance of the reflecting panel, to the Engineer.
430.70 + 103.347 = 534.07
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 534.07 | 534.07 | 380.0 | False | None | None | False | None | False | 202946.6 | 0 | 3016120 | 100808 | None | Item No. 8.4 Page No. 64 Vol.03 | Printing New Letter
Printing New Letter and Figures of any Shade Printing new letter and figures of any shade with synthetic enamel paint black or any other approved colour to give an even shade-English and Roman (Item No. 8.4/ Page No. 64/Vol.03/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work."
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | cm | 1.32 | 1.32 | 1200.0 | False | None | None | False | None | False | 1584.0 | 0 |
|
|
---|