noticeInvitingTenderDTO
createdTs1716828369894
version3
createdDateNone
modifiedDateNone
tenderTypeRFQ
evaluationTypeTWO_COVER
evaluationTypeTextTwo Cover
invitingStrategyOPEN
invitingStrategyTextOpen
taxTypeINCLUSIVE_TAX
tenderFee2120.00
emd169000.00
bidValueTypeITEM_WISE
bidValueTypeTextItem wise
tenderReceiptClose05-06-2024 16:00:00
tenderQueryClose31-05-2024 17:30:00
technicalBidOpen06-06-2024 16:30:00
publishedDate29-05-2024 11:32:00
publishedByPostPWD_EE_DIV_KLB
publishedByUserKPE14204 - SUBHASH L SHIXNAKAR
bidValidityPeriod90
noOfCalls1
preBidMeetingDateNone
preBidMeetingYnFalse
preQualificationBidOpenNone
denominationTypeRUPEES
denominationTypeTextRupees
retenderedYnNone
percentageRateTypeTextNone
contactPersonSubhash L Shixnakar
splitEmdRequiredYnFalse
emdBankGuaranteeNone
emdCashNone
bgValidityPeriodNone
hideWeightageNone
multipleCurrencySelectionAllowedYnFalse
isTechWeightageAllowedFalse
highestBidderSelectionFalse
isVariableEmdAllowedNone
qcbsTenderYnNone
itemwiseEmdRequiredYnNone
sampleSubmissionDateNone
officeNumber08472224455
mobileNumber9448652632
tenderSupplierListNone
tenderSchedule
createdTs1716828369930
version4
createdDateNone
modifiedDateNone
tenderNumberPWD/2024-25/RD/WORK_INDENT10818
titleConstruction of Road & Drain and Footpath from KCT Engineering College to Al-Hilal School at Kalaburagi City. Under KKRDB Micro (KLB2312243166) for the year 2023-24
descriptionConstruction of Road & Drain and Footpath from KCT Engineering College to Al-Hilal School at Kalaburagi City. Under KKRDB Micro (KLB2312243166) for the year 2023-24
categoryWORKS
categoryTextWorks
ecv8468691.42
deptNamePublic Works Department
statusPUBLISHED
statusTextPublished
remarksNone
csrValueNone
ecvtenderYnTrue
location1689
locationNamePWD Division Office Kalaburagi
provisionalAmount10000000.0
groupOverheadTotal0.0
fileNumberPWD/SD/KLB/KKRDB/2024-25/24
tenderSubEstimateList
createdTsversioncreatedDatemodifiedDateworkCategoryNamesubEstimateNameestimateTotalitemList
17168283700000NoneNoneRoadsConstruction of Road & Drain and Footpath from KCT Engineering College to Al-Hilal School at Kalaburagi City. Under KKRDB Micro (KLB2312243166) for the year 2023-248468691.42
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3180390109462NonePWD 2023-24 S R Vol-I I No. 1.14.1 Page No. 8Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work In all kinds of soils Depth upto 3 mCum107.1107.1851.75FalseNoneNoneFalseNoneFalse91222.4250
3180391109462NonePWD 2023-24 S R Vol-III I No. 2.19 Page No. 12Dismantling of cement concrete pavement by mechanical means using pneumatic tools, breaking to pieces not exceeding 0.02 m3 in volume and stock piling at designated locations and disposal of dismantled materials and stacking serviceable and unserviceable materials separatelyCum591.15591.1516.2FalseNoneNoneFalseNoneFalse9576.630
3180392109462NonePWD 2023-24 S R Vol-I I no. 2.1.4 page No. 15Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregatesCum6527.856527.8578.43FalseNoneNoneFalseNoneFalse511979.27550
3180393109462NonePWD 2023-24 S R Vol-I I No. 2.4.2 Page No. 16Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates including Addendum I-Percentage Additionalities for Formwork, Centering & Scaffolding for Cement Concrete Drain Walls add 35% to Finished Final Rate of ConcreteCum8962.858962.85331.56FalseNoneNoneFalseNoneFalse2971722.5460
3180394109462NonePWD 2023-24 S R Vol-I I No. 2.11 (d) Page No. 18Supplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Super structure of Bridgest90990.990990.916.58FalseNoneNoneFalseNoneFalse1508629.1220
3180395109462NonePWD 2023-24 S R Vol-I I No. 1.14.1 Page No. 8Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work In all kinds of soils Depth upto 3 mCum107.1107.1573.0FalseNoneNoneFalseNoneFalse61368.30
3180396109462NonePWD 2023-24 S R Vol-III I No. 3.6 Page No. 17Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2Cum517.65517.65229.2FalseNoneNoneFalseNoneFalse118645.380
3180397109462NonePWD 2023-24 S R Vol-III I No. 4.17 Page No. 26Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver/grader in sub-base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density.Cum2686.952686.95229.2FalseNoneNoneFalseNoneFalse615848.940
3180398109462NonePWD 2023-24 S R Vo-III I No. 6.8.1 Page No. 51Providing and laying 60mm thick factory made precast M -30 grade Cement Concrete Paver Block as per IRC SP 63:2018 & IS 15658 for Cycle Tracks & Pedestrian Footpaths of approved shape and colour, laid in required pattern and including over 30mm thick compacted bed of coarse sand, filling the joints with fine sand etc. all complete as per the direction of Engineer-in-charge. (WMM/WBM Base to be paid separately if necessary as per relevant technical specification)Sqm1121.41121.42292.0FalseNoneNoneFalseNoneFalse2570248.80
3180399109462NonePWD 2023-24 S R Vol-III I No. 8.54 Page No. 78Providing and fixing board displaying information, such as 'Name of work, Tender cost, Name of Contractor, Work completion and liability period etc', having rectangular shape of 1.20m x 0.90m size made out 18 gauge (1.25mm) thick mild steel sheet painted with one coat of Zinc chromate stoving primer and two coats of enamel paint on front side and grey stove enamel on back side and border / messages / symbols etc. with approved colour shade paint complete, on M.S.angle of size 35 x 35 x 3 mm frame with properly cross braced M.S. angles of size 35mmx35mmx3mm duly painted including Two M.S. angle iron posts of size 65 mm x 65 mm x 6 mm, 3.65 m long painted with alternate black and white bands of 25 cm width including all fixtures etc.and fixing the boards in 1:4:8 concrete block of size 60 cm x 60 cm x 75 cm including, excavation, refilling, transportation, and labour etc complete. Spec. No. As directed by Engineer in Charge & MoRTH specification 804No9450.09450.01.0FalseNoneNoneFalseNoneFalse9450.00
generalCriterionList
createdTsversioncreatedDatemodifiedDatecriterionTypedescriptiontenderEligibilityCriterionDocumentList
17168283730000NoneNoneELIGIBILITYTenders from Joint ventures are not acceptable.None
17168283730001NoneNoneELIGIBILITYBidders shall not be under a declaration of ineligibility for corrupt and fraudulent practices issued by any State Government / Government of India /Union Territory.None
17168283730001NoneNoneELIGIBILITYIt shall be the responsibility of the Bidder to ensure credit of Tender Processing Fee and EMD into the respective receiving bank accounts of kppp portal on or before the last date and time of bid submission.None
17168283730000NoneNoneELIGIBILITYIt shall be the responsibility of the Bidder to ensure credit of Tender Processing Fee and EMD into the respective receiving bank accounts of e-Procurement on or before the last date and time of bid submission.None
17168283730000NoneNoneELIGIBILITYEMD Payments through e-Payment mode shall be made as one single transaction and payments made in part are liable for rejection.None
17169074200000NoneNoneELIGIBILITYBidder shall pay Contract Management Module processing fees of 0.025% of the contact value (Min Rs.500/- & Max Rs.7500/-) soon after contract has been issued to bidder.None
17169074270000NoneNoneELIGIBILITYAs per Karnataka State Government order No.LD/300/LET/2006 Bangalore Dated 01.01.2007 and Government Letter No.PW/134/BMS/2007 Dated 27.7.2007, a sum amounting to 1%of the bill amount will be deducted towards Construction Labour Welfare fund.None
17169074330000NoneNoneELIGIBILITYThe Item Rate quoted shall include the Royalty Charges on construction materials and other taxes as per prevailing Government Orders.None
17169074530000NoneNoneELIGIBILITYConditional tenders will not be accepted.None
17169074620000NoneNoneELIGIBILITYThe Tenderer shall obtain the workdone certificate in the prescribed format from the Competent Authority not below the rank of Executive Engineer (District Level Officer) and scan the Original Certificate and attach the scanned file to the Bid. The Original Certificate/Certificates shall be produced at the time of opening of technical Bids for physical verification.None
17169074680000NoneNoneELIGIBILITYFinancial Year will be reckoned as the period between first day of April and Thirty first day of March of succeeding year(both days inclusive).None
17169074750000NoneNoneELIGIBILITYThe Tenderer shall scan the Original Ownership Documents/ Lease/ Hire commitment Agreement for the Machinery and attach the scanned file to the Bid. The Original Documents shall be produced at the time of opening of technical Bids for physical verification.None
17169074830000NoneNoneELIGIBILITYThe tenderer shall note that the scanned Documents can also be uploaded in the tasks created under Document/Evidence Required from the BidderNone
17169074910000NoneNoneELIGIBILITYThe Employer reserves the right to Reject any or all Tenders without assigning any reason.None
17169074980000NoneNoneELIGIBILITYThe defect liability period for this work is 365 daysNone
17169075050000NoneNoneELIGIBILITYThe Department is not responsible for any delay in accessing kppp portal.None
17169075130000NoneNoneELIGIBILITYThe rates of all the items appeared in Bill of Quantities are inclusive of all leads and liftsNone
17169075200000NoneNoneELIGIBILITYThe contractor shall bound to comply the prevailing rules and regulations with regard to the EPF rules and any modifications before and after execution of agreementNone
17169075280000NoneNoneELIGIBILITYAfter the award of the contract, the contractor has to furnish the details in respect of labour employed and the EPF details for this work in every RA bill.None
17169075370000NoneNoneELIGIBILITYBidders are advised to note that , 18% GST will be added to the contract amount.None
17169075450000NoneNoneELIGIBILITYFinancial turnover of previous years shall be given a weight of 10% per year to bring them to the price level of the 2024-25 in the Technical Qualification Criteria mentioned in the next section.None
17169075540000NoneNoneELIGIBILITYThe bidder should mention the UDIN No on the turnover certificate, failing which bid is rejected.None
17169075630000NoneNoneELIGIBILITYIf the bidder uploaded the false document while participating in the tender, the bidder will be responsible and action will be initiated as per the tender clause.None
17169075740000NoneNoneELIGIBILITYThe work should be completed in 06 (Six) Months ( including monsoon)None
17169075860000NoneNoneELIGIBILITYThe star rates inrespect of specified materials ( Cement, Steel and Bitumen) shall be payable as per CIRCULAR NO.PWD 159 CRM 2009 Bangalore Dated 30.09.2010None
17169075960000NoneNoneELIGIBILITYIn respect of work costing more than Rs. 1.00 crore, the contractor shall establish field laboratory at his cost with requisite equipment or as stipulated in the AgreemenNone
preQualCriterionListNone
technicalCriterionList
createdTsversioncreatedDatemodifiedDatedescriptioncriterionCategoryTextcriterionTypeOthersValuetenderTechnicalCriterionDocumentList
NoneNoneNoneNoneTo qualify for award of this contract, each Tenderer in his name should have in the last five years i.e., 2019-20, 2020-21, 2021-22 ,2022-23 & 2023-24a) a) Achieved in at least two financial years an average financial turnover (in all classes of civil engineering construction works only) of Rs. 84.69 lakhsPast ExperienceNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneAudited CA Certificate of Annual Turnover
NoneNoneNoneNoneTo qualify for award of this contract, each Tenderer in his name should have in the last five years i.e., 2019-20, 2020-21, 2021-22 ,2022-23 & 2023-24 b) Satisfactorily completed, as prime contractor, at least one similar work such as ROAD Work of value not less than Rs. 42.34LakhsPast ExperienceNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneWork Done Certificate
NoneNoneNoneNoneTo qualify for award of this contract, each Tenderer in his name should have in the last five years i.e., 2019-20, 2020-21, 2021-22 ,2022-23 & 2023-24 c) Executed in any one year, the following minimum quantities of work: 1) Earth wrok/Emb/Subgrade.1323.00Cum, 2) PCC/RCC 511.00Cum 3) TMT 13.00 MTPast ExperienceNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneWork Done Certificate
NoneNoneNoneNoneLiquid Assets and /or availability of credit facilities of no less than Rs. 25.41lakhs (Credit Lines/letter of credit/ certificates from the banks for meeting the fund requirement etcPast ExperienceNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneLine of Credit
NoneNoneNoneNoneAs per the Govt Order No: FD 263 EXP-12/2022 Bangelore Dated: 11.05.2022 as per condition no 3 relaxation of machinery upto Rs. 300.00 Lakhs i.e. KW-3 & KW-4Capabilities of VendorNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneOthers -- Information in Format-8 and scanned copies of the owership Documents & Hire commitment Agreements
NoneNoneNoneNoneQualification and experience of the key technical and Management personnel in permanent employment with the Tenderer and those that are proposed to be deployed on this work, if work is awarded.Capabilities of VendorNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneOthers -- Biodata of the personnel
NoneNoneNoneNoneReport on the financial standing of the Tenderer, such as profit and loss statements and auditors report for the last five years.Financial StatusNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneOthers -- Scanned Copy of ITC Certificate
NoneNoneNoneNoneLatest Income Tax Clearance CertificateFinancial StatusNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneOthers -- Scanned Copy of ITC Certificate
NoneNoneNoneNoneAssessed Tender Capacity shall be more than the Tendered AmountOthersAssessed Tender Capacity
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneOthers -- Assessement on the Letter Head of the Tenderer
NoneNoneNoneNoneConstitutional or Legal Status of the TendererOthersLegal Status
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneOthers -- Attach copy of registration
NoneNoneNoneNoneInformation of the works for which Tender acceptance letters are received.OthersNew Works
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneOthers -- Information in Format-6 and Letter of Acceptance
NoneNoneNoneNoneInformation on works which are yet to be completedOthersPending work
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneOthers -- Information in Format-5 and Certificates in Format-3
NoneNoneNoneNoneInformation of the works for which Tenderer has submitted Tender.OthersTenderer Works
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneOthers -- Information in Format-7
NoneNoneNoneNoneThe proposed methodology and program of construction, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability of execution and completion of the work as per technical specifications within the stipulated period of completion.OthersCPM/PERT
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneOthers -- CPM/PERT Chart
NoneNoneNoneNoneValue at 2024-25 price level, of existing commitments and on-going works to be executed during the next 06 months(Financial commitment of previous years shall be given a weight of 10% per year to bring them to the price level of the 2024-25), (Monthwise commitment shall be furnished).OthersCommitted Works
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneOthers -- Statement on the Letter head of the tenderer
tenderCriterionDocumentList
documentNameoptionaldocumentTypeText
Contractor Registration CertificateTrueTechnical Bid
Annual Turnover Certificate with UDINTrueTechnical Bid
single similar Nature of Work Done Certificate 50percent of APTTrueTechnical Bid