tenderSubEstimateList | createdTs | version | createdDate | modifiedDate | workCategoryName | subEstimateName | estimateTotal | itemList |
---|
1718102322000 | 0 | None | None | Buildings | Construction of Toilet Room for Government Primary School at Ward No. 07 in C.M. Street (ST Colony), Kamela Road in Ballari City, Under 2515 KKRDB (Micro) for the year 2023-24. | 895151.32 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3269869 | 113271 | None | I.No. 1 | Demolishing R.C.C. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material to the appropriate disposal area as per direction of Engineer-in-charge ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 2547.3 | 2547.3 | 0.28 | False | None | None | False | None | False | 713.244 | 0 | 3269870 | 113271 | None | I.No. 19.7.3 | Demolishing brick work manually/ by mechanical means including stack ing of serviceable material and disposal of unserviceable material to the appropriate disposal area as per direction of Engineer-in-charge. (PWD CSR For 2023-24 Vol 2 pag No:187 Item No. 19.7.3) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 1080.45 | 1080.45 | 16.02 | False | None | None | False | None | False | 17308.809 | 0 | 3269871 | 113271 | None | I.No. 1.14.1 | Earth work in surface excavation by mechanical means for lowering & leveling the ground for all works other than foundation in all kinds of soils & upto depth not exceeding 300mm as per drawing and technical specifications, includingsetting out, shoring, strutting, barricading, caution lights, removal of stumpsand other deleterious matter including dressing of excavated surfaces, posing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenances required to complete the work. In all kinds of soils upto 3 m depth (PWD CSR For 2023-24 Vol 1 Pag No:8 Item No. 1.14.1) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 107.1 | 107.1 | 25.53 | False | None | None | False | None | False | 2734.263 | 0 | 3269872 | 113271 | None | I.No. 2.1.3 | Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. (PWD SR 2021-22 Volume-1 Page No. 15 I.No.2.1.3) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 6288.45 | 6288.45 | 3.71 | False | None | None | False | None | False | 23330.1495 | 0 | 3269873 | 113271 | None | I.No. 2.2.1 | Providing and laying in position Cement Concrete for all Foundation works.The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all aterials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. ( For footing) (PWD SR 2021-22 Volume-1 Page No. 15 I.No.2.2.1) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 6601.35 | 6601.35 | 2.59 | False | None | None | False | None | False | 17097.4965 | 0 | 3269874 | 113271 | None | I.No. 2.2.1 | Form work for Footing at 8% ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 528.11 | 528.11 | 2.59 | False | None | None | False | None | False | 1367.8049 | 0 | 3269875 | 113271 | None | I.No. 2.4.2 | Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications (For coloumn) and shear wall (PWD SR 2021-22 Volume-1 Page No. 16 I.No.2.4.2) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 6639.15 | 6639.15 | 7.4 | False | None | None | False | None | False | 49129.71 | 0 | 3269876 | 113271 | None | I.No. 2.4.2 | Form work for Shear Wall at 8% ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 531.13 | 531.13 | 7.4 | False | None | None | False | None | False | 3930.362 | 0 | 3269877 | 113271 | None | I.No. 1.9 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of
foundations and other similar works etc. in layers not exceeding 20cm in depth,
consolidating each deposited layer by ramming and watering, lead up to 50 m
and lift upto 1.5 m (PWD SR 2021-22 Volume-1 Page No. 7 I.No.1.9) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 279.3 | 279.3 | 21.82 | False | None | None | False | None | False | 6094.326 | 0 | 3269878 | 113271 | None | I.No. 2.5.1 | Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse
aggregates and fine aggregates as per relevant IS Codes machine mixed with
super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical
specifications. (For plinth Beam ) (PWD SR 2021-22 Volume-1 Page No. 16 I.No.2.5.1) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 6961.5 | 6961.5 | 2.36 | False | None | None | False | None | False | 16429.14 | 0 | 3269879 | 113271 | None | I.No. 2.5.1 | Form work for Plinth Beam at 50% ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 3480.75 | 3480.75 | 2.4 | False | None | None | False | None | False | 8353.8 | 0 | 3269880 | 113271 | None | I.No. 1.11 | Filling approved earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. (PWD CSR For 2023-24 Vol 1 Pag No:7 Item No.1.11) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 454.65 | 454.65 | 19.58 | False | None | None | False | None | False | 8902.047 | 0 | 3269881 | 113271 | None | I.No. 2.5.1 | Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with
super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. (For coloumns above plinth Beam ) (PWD SR 2021-22 Volume-1 Page No. 16 I.No.2.5.1) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 6961.5 | 6961.5 | 0.95 | False | None | None | False | None | False | 6613.425 | 0 | 3269882 | 113271 | None | I.No. 2.5.1 | Form work for Culmns at 70% ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 4873.05 | 4873.05 | 3.57 | False | None | None | False | None | False | 17396.7885 | 0 | 3269883 | 113271 | None | I.No. 2.5.1 | Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with
super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. (For Beams and lintle of Buildings) (PWD SR 2021-22 Volume-1 Page No. 16 I.No.2.5.1) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 6961.5 | 6961.5 | 2.62 | False | None | None | False | None | False | 18239.13 | 0 | 3269884 | 113271 | None | I.No. 2.5.1 | Form work for Lintel & Roof Beam at 60% ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 4176.9 | 4176.9 | 2.62 | False | None | None | False | None | False | 10943.478 | 0 | 3269885 | 113271 | None | I.No. 2.5.1 | Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fineaggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers,wellcompacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per techncal specifications. (For chejja, staricase of Buildingsl) (PWD SR 2021-22 Volume-1 Page No. 16 I.No.2.5.1) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 6961.5 | 6961.5 | 0.1 | False | None | None | False | None | False | 696.15 | 0 | 3269886 | 113271 | None | I.No. 2.5.1 | Form work for Chejja at 45% ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 3132.68 | 3132.68 | 0.1 | False | None | None | False | None | False | 313.268 | 0 | 3269887 | 113271 | None | I.No. 2.5.1 | Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. (For Roof slabs of Buildingsl) (PWD SR 2021-22 Volume-1 Page No. 16 I.No.2.5.1) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 6961.5 | 6961.5 | 3.0 | False | None | None | False | None | False | 20884.5 | 0 | 3269888 | 113271 | None | I.No. 2.5.1 | Form work for Roof Slab at 50% ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 3480.75 | 3480.75 | 3.0 | False | None | None | False | None | False | 10442.25 | 0 | 3269889 | 113271 | None | I.No. 2.11.a | Supplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and
technical specification for buildings (PWD CSR For 2023-24 Vol 1 Pag No:18 Item No. 2.11(a)) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 93929.85 | 93929.85 | 0.91 | False | None | None | False | None | False | 85476.1635 | 0 | 3269890 | 113271 | None | I.No. 6.32 | Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications (PWD CSR For 2023-24 Vol 2 Pag No:17 Item No. 6.32) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 1375.5 | 1375.5 | 122.42 | False | None | None | False | None | False | 168388.71 | 0 | 3269891 | 113271 | None | I.No. 8.5.2 | Providing 15 mm cement plaster on rough side of single or half brick wall finished with a floating coat of neat cement of mix: 1:4 (1 cement: 4 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge (PWD CSR For 2023-24 Vol 2 Pag No:42 Item No. 8.5.2) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Sqm | 366.45 | 366.45 | 55.8 | False | None | None | False | None | False | 20447.91 | 0 | 3269892 | 113271 | None | I.No. 8.4.2 | Providing 12 mm cement plaster finished with a floating coat of neat cement of mix :1:4 (1 cement: 4 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete
as per specifications and as per directions of Engineer-in-charge. (PWD CSR For 2023-24 Vol 2 Pag No:41 Item No. 8.4.2) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Sqm | 327.6 | 327.6 | 230.4 | False | None | None | False | None | False | 75479.04 | 0 | 3269893 | 113271 | None | I.No. 8.39 | Wall painting with acrylic emulsion paint of approved brand and manufacture to give an even shade :Two coats on new work after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in (PWD CSR For 2023-24 Vol 2 Pag No:48 Item No. 8.39) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Sqm | 133.35 | 133.35 | 186.59 | False | None | None | False | None | False | 24881.7765 | 0 | 3269894 | 113271 | None | I.No. 8.31 | Finishing walls with Premium Acrylic Smooth exterior paint with Silicone additives with pure Acrylic Resin, UV resistant, dirt & pick up resistant, Alkali & Water resistant of required shade: New work (Two coats applied @ 1.43 L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per
specifications and as per directions of Engine (PWD CSR For 2023-24 Vol 2 Pag No:46 Item No. 8.31) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Sqm | 186.9 | 186.9 | 54.46 | False | None | None | False | None | False | 10178.574 | 0 | 3269895 | 113271 | None | I.No. 11.34B | Providing and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. (PWD CSR For 2023-24 Vol 2 Pag No:86 Item No. 11.34.B) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Kgs | 192.15 | 192.15 | 25.52 | False | None | None | False | None | False | 4903.668 | 0 | 3269896 | 113271 | None | I.No. 8.41 | Painting with synthetic enamel paint of approved brand and manufacture of required colour to give an even shade :Two coats on new work over an under coat of suitable shade with ordinary paint of pproved brand and manufacture after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. (PWD CSR For 2023-24 Vol 2 Pag No:48 Item No. 8.41) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Sqm | 175.35 | 175.35 | 2.73 | False | None | None | False | None | False | 478.7055 | 0 | 3269897 | 113271 | None | I.No. 11.51 | Providing and fixing 1mm thick M.S. sheet door with frame of 40x40x6 mm angle iron and 3 mm M.S. gusset plates at the junctions and corners, all necessary fittings complete, including applying a priming coat of approved steel primer. Using M.S. angels 40x40x6 mm for diagonal braces including cost of materials, labour, usage charges of machinery (PWD CSR For 2023-24 Vol 2 Pag No:77 Item No. 11.5.1) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Sqm | 4701.9 | 4701.9 | 4.2 | False | None | None | False | None | False | 19747.98 | 0 | 3269898 | 113271 | None | I.No. 12.54 | Providing & fixing factory made PVC Door frame of size 50x47mm with a wall thickness of 5mm, made out of extruded 5mm rigid PVC foam sheet metered cut at corners & jointed 2 No.s of 150mm long brackets of 15x15mm M.S Square tube, the entire door frame to be reinforced with 19x19mm M.S Square tube of 19 gauge. The door frame to be fixed to the wall using M.S. Screws of 65/80mm size complete as per manufacturers
specification & direction of Engineer-in-charge. (PWD SR 2023-24 Volume-II Iteam Code-12.54 p-104) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 333.9 | 333.9 | 7.0 | False | None | None | False | None | False | 2337.3 | 0 | 3269899 | 113271 | None | I.No. 12.55 | Providing & fixing 30mm thick factory made rigid foam Prelam Panelled Door Shutters made from M.S. tube of 19x19mm, 19 gauge for stiles and 15x15mm for top & bottom rails, covered with heat moulded Prelaminated PVC C Channel of 5mm thick sheet & 30x50mm wide to form stiles & 5mm thick & 75mm wide Prelaminated PVC Sheets for top rail, lock rail & bottom rail on either side & 5mm thick, 20mm wide cross PVC sheet as gap insert for top rail & bottom rail, Panelling of 5mm thick PVC sheet Prelaminated on either side fitted in the M.S. frame, Sealed to the stiles & rails with PVC Designer beading on either side & joined together with solvent cement adhesive etc., Complete as per manufacturers specification & direction of Engineer-in-charge fixed to frames with 3 nos of 75mm Aluminium hinges. (PWD SR 2023-24 Volume-II Iteam Code-12.55.1 p-104) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Sqm | 2484.3 | 2484.3 | 6.0 | False | None | None | False | None | False | 14905.8 | 0 | 3269900 | 113271 | None | I.No. 9.9 | Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be specified by the manufacturer) of 1st quality conforming to IS : 15622 of approved make in colours such as White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick cement mortar 1:4 (1 Cement : 4 Coarse sand), Jointing with grey cement slurry @ 3.3 kg/m2 including pointing the joints with white cement and matching pigment etc., complete. (CSR 2023-24 Volume-II Iteam Code-9.9 P-60) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Sqm | 1129.8 | 1129.8 | 19.2 | False | None | None | False | None | False | 21692.16 | 0 | 3269901 | 113271 | None | I.No. 22.15.2 | Providing and fixing stainless steel fixtures conforming to 304 graded steel as per direction of engineer in charge SSHandles 300 mm (PWD CSR For 2023-24 Vol 2 Pag No:218 Sl No.22.15.2) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Nos | 577.5 | 577.5 | 6.0 | False | None | None | False | None | False | 3465.0 | 0 | 3269902 | 113271 | None | I.No. 22.15.4 | Providing and fixing stainless steel fixtures conforming to 304 graded steel as per direction of engineer in charge SS Aldrop 16 mm dia 300 mm (PWD CSR For 2023-24 Vol 2 Pag No:218 Sl No.22.15.4) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | No | 393.75 | 393.75 | 6.0 | False | None | None | False | None | False | 2362.5 | 0 | 3269903 | 113271 | None | I.No. 22.15.6 | Providing and fixing stainless steel fixtures conforming to 304 graded steel as per direction of engineer in charge SS Tower Bolt 200x 10mm (PWD CSR For 2023-24 Vol 2 Pag No:218 Sl No.22.15.6) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | No | 157.5 | 157.5 | 6.0 | False | None | None | False | None | False | 945.0 | 0 | 3269904 | 113271 | None | I.No. 22.15.8 | Providing and fixing stainless steel fixtures conforming to 304 graded steel as per direction of engineer in charge SS hinges 125 mm (PWD CSR For 2023-24 Vol 2 Pag No:218 Sl No.22.15.8) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | No | 52.5 | 52.5 | 6.0 | False | None | None | False | None | False | 315.0 | 0 | 3269905 | 113271 | None | I.No. 14.1.1 | Providing and fixing water closet squatting pan (Indian type W.C. pan ) with 100 mm sand cast Iron P or S trap, 10 litre low level white P.V.C. flushing cistern, including flush pipe, with manually controlled device (handle lever) conforming to IS : 7231, with all fittings and fixtures complete, including cutting and making good the walls and floors wherever required: White Vitreous china Orissa pattern W.C. pan of size 580x440 mm with integral type foot rests ( PWD SR. 2023-24 Vol-2 Pg- 131 I No.14.1.1) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | No | 5128.2 | 5128.2 | 6.0 | False | None | None | False | None | False | 30769.2 | 0 | 3269906 | 113271 | None | I.No. 13.34 | Providing and placing on terrace (at all floor levels) polyethylenewater storage tank, IS : 12701 marked, with cover and suitable lockingarrangement and making necessary holes for inlet, outlet and overflowpipes but without fittings and the base support for tank. (PWD SR. 2023-24/ Pg- 123 I No.13.34) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Ltr | 9.45 | 9.45 | 2.0 | False | None | None | False | None | False | 18.9 | 0 | 3269907 | 113271 | None | I.No. 13.23.3 | Providing PVC ringtite pipes conforming to IS 4985:2000 with latest amendments and conveying to worksite, rolling and lowering into trenches, laying true to line and level and perfect linking at joints, testing and commissioning, including loading unloading at both destinations and cuts of pipes wherever necessary including jointing of PVC pipes and specials (excluding cost of specials) with jointing of approved type, with all labour with all lead & lift including encasing the pipe alround to a depth of not less than 15 cms. with soft gravel or selected earth available from the excavation etc. complete and giving necessary hydraulic test to the required pressure as per ISS (Contractor will make his own arrangements for procuring water for testing) etc. complete for: PVC pipes 32mm dia., 10 kg/sqcm & class 5 (PWD SR. 2023-24/ Pg- 122 I No.13.32.3) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Mtr | 70.35 | 70.35 | 50.0 | False | None | None | False | None | False | 3517.5 | 0 | 3269908 | 113271 | None | I.No. 10.1.1 | Providing PVC ringtite pipes conforming to IS 4985:2000 with latest amendments and conveying to worksite, rolling and lowering into trenches, laying true to line and level and perfect linking at joints, testing and commissioning, including loading unloading at both destinations and cuts of pipes wherever necessary including jointing of PVC pipes and specials (excluding cost of specials) with jointing of approved type, with all labour with all lead & lift including encasing the pipe alround to a depth of not less than 15 cms. with soft gravel or selected earth available from the excavation etc. complete and giving necessary hydraulic test to the required pressure as per ISS (Contractor will make his own arrangements for procuring water for testing) etc. complete for:PVC pipes 25mm dia, 10 kg/sqcm & class 5 (CSR2023-24 Volume-V Iteam Code-10.1.1 P-113) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Mtr | 50.4 | 50.4 | 50.0 | False | None | None | False | None | False | 2520.0 | 0 | 3269909 | 113271 | None | I.No. 7.3 | Providing and fixing MS inspection door of size 60 cms x 60 cms, including MS frame made of 50x50x6mm angle, shutters made of 3mm thick MS sheets, with hinges, locking arrangements at top etc. including painting with anticorrosive approved paint etc. complete including all lead and lifts etc PWD SR. 2023-24/ Pg- 85 I No.7.3 Rs. 2140.00/mtr (CSR2023-24 Volume-II Iteam Code-7.3 P-85) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 1461.6 | 1461.6 | 2.0 | False | None | None | False | None | False | 2923.2 | 0 | 3269910 | 113271 | None | I.No. 14.8.2 | Providing and fixing P.V.C. low level flushing cistern with manually controlled device (handle lever) conforming to IS : 7231, with all fittings and fixtures complete.10 litre capacity - White (CSR2023-24 Volume-II Iteam Code-14.8.2 P-135) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 989.1 | 989.1 | 2.0 | False | None | None | False | None | False | 1978.2 | 0 | 3269911 | 113271 | None | I.No. 14.23 | Providing and fixing white vitreous china flat back or wall corner type lipped front urinal basin of 430x260x350 mm or 340x410x265 mm sizes respectively. (CSR2023-24 Volume-II Iteam Code-14.23 P-135) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 1211.7 | 1211.7 | 4.0 | False | None | None | False | None | False | 4846.8 | 0 | 3269912 | 113271 | None | I.No. 14.25 | Providing and fixing white vitreous china wash basin including making all connections but including the cost of fittings :Flat back wash basin of size 550x400 mm (CSR2023-24 Volume-II Iteam Code-14.25.2 P-135) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 808.5 | 808.5 | 2.0 | False | None | None | False | None | False | 1617.0 | 0 | 3269913 | 113271 | None | I.No. 14.28 | Providing and fixing P.V.C. waste pipe for sink or wash basin including P.V.C. waste fittings complet. 40 mm dia (CSR2023-24 Volume-II Iteam Code-14.28.1.2 P-135) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 92.4 | 92.4 | 2.0 | False | None | None | False | None | False | 184.8 | 0 | 3269914 | 113271 | None | I.No. 14.32.3 | Providing and fixing mirror of superior glass (of approved quality) and of required shape and size with plastic moulded frame of approved make and shade with 6 mm thick hard board backing. Rectangular shape 453x357 mm (CSR2023-24 Volume-II Iteam Code-14.32.3 P-136) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 1068.9 | 1068.9 | 2.0 | False | None | None | False | None | False | 2137.8 | 0 | 3269915 | 113271 | None | I.No. 14.51A | Providing and fixing Pillar cock with high neck with 265mm Extended body made of Stainless steel with all concealed fitting arrangements & all necessary accesories complete - Class- Economy (CSR2023-24 Volume-II Iteam Code-14.51A P-139) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 2627.1 | 2627.1 | 2.0 | False | None | None | False | None | False | 5254.2 | 0 | 3269916 | 113271 | None | I.No. 10.2.4 | Providing UNPLASTICISED PVC pipes conforming to IS 16098:2013 with latest amendments ended with integral sockets with ISI mark and conveying to worksite, rolling and lowering into trenches, laying true to line and level and perfect linking at joints, testing and commissioning, including loading and unloading at both destinations and cuts of pipes wherever necessary including jointing of UPVC pipes (with cost of elastomeric sealing rings) and specials (excluding cost of specials) with jointing of approved type, with all labour, lead & lifts, including encasing the pipes alround to a depth of not less than 15 cms. with soft gravel or selected earth available from the excavation etc. complete and giving necessary hydraulic test to the required pressure as per ISS (contractor will make his own arrangements for procuring water for testing) etc. complete for: Pipes of SN4, 160mm dia. (CSR2023-24 Volume-V Iteam Code-10.2.4 P-114) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 604.8 | 604.8 | 50.0 | False | None | None | False | None | False | 30240.0 | 0 | 3269917 | 113271 | None | I.No. 16.40 | Providing and constructing of Machinehole chambers conical in shape at top with CC 1:3:6 foundation using 40mm and down size graded metal of approved quality and with an offset of 0.15m alround the chamber and brick masonry in C.M 1:4 plaster with bricks of approved quality and CM plaster 1:3 proportion 12mm thick inside and outside except for the conical surface outside where the thickness of plaster shall be 20 mm thick, with 1 to 6 slope in the concrete towards the central drain, finished smooth and fixing of pipes in CC 1:2:4 with graded metal of 20 mm and down size including Providing and fixing SFRC Machinehole frame and cover confoming to IS 12592(Part-I): 1988 & IS 12592(Part-II) :1991 with latest amendments in CC 1:2:4, Providing and fixing of plastic foot steps staggered at 30cms apart as directed, watering, curing,barricading, danger lighting, pouring tar over M.H. frame and cover, cost of tar, shoring, strutting, dewatering, engraving Machinehole No. on the inner and outer conical surface etc. as per the drawing with all lead and lift for various diameters and depths noted below. With Table Moulded Bricks & Medium Duty cover and frame.For 1.2m dia Constructing Table Moulded Bricks Machinehole 1.2 m internal dia. , 1.0
M depth & Medium duty SFRC cover & frame (CSR2023-24 Volume-V Iteam Code-16.40.1 P-201) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 25566.45 | 25566.45 | 1.0 | False | None | None | False | None | False | 25566.45 | 0 | 3269918 | 113271 | None | I.No. 16.8.1 | Constructing brick masonry chamber of internal dimension 600x450mm and depth of 600mm (inner dimensions) with modular bricks of CD 75 in cement mortar 1:6, bed concrete 150mm thick with 1:3:6, plastering 12 mm thick with cement mortar 1:4, CC 1:2:4 coping 75mm thk for fixing CI cover & frame etc. excluding the cost of CI frame and cover. (CSR2023-24 Volume-V Iteam Code-16.8.1 P-190) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 5030.55 | 5030.55 | 2.0 | False | None | None | False | None | False | 10061.1 | 0 | 3269919 | 113271 | None | I.No. 9.38 | Providing skirting, dadooing, rises of steps with white glazed tiles 6mm thick on 10mm thick cement plaster 1:3 and jointed with white cement slurry over existing rough plaster surface using glazed tiles of approved make and size including cost of materials, labour, complete as per specifications. (CSR2023-24 Volume-II Iteam Code-9.38 P-64) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Sqm | 1461.6 | 1461.6 | 31.68 | False | None | None | False | None | False | 46303.488 | 0 | 3269920 | 113271 | None | I.No. 11.19.3 | Providing GM gland cocks tested against hydraulic pressure of 20 Kg/ m² with ISI mark- For 25 mm dia GM gland cocks (CSR2023-24 Volume-V Iteam Code-11.19.3 P-134) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 538.65 | 538.65 | 17.0 | False | None | None | False | None | False | 9157.05 | 0 | 3269921 | 113271 | None | I.No. 8.54 | Providing and fixing board displaying information, such as 'Name of work, Tender cost, Name of Contractor, Work completion and liability period etc', having rectangular shape of 1.20m x 0.90m size made out 18 gauge (1.25mm) thick mild steel sheet painted with one coat of Zinc chromate stoving primer and two coats of enamel paint on front side and grey stove enamel on back side and border / messages / symbols etc. with approved colour shade paint complete, on M.S.angle of size 35 x 35 x 3 mm frame with properly cross braced M.S. angles of size 35mmx35mmx3mm duly painted including Two M.S. angle iron posts of size 65 mm x 65 mm x 6 mm, 3.65 m long painted with alternate black and white bands of 25 cm width including all fixtures etc.and fixing the boards in 1:4:8 concrete block of size 60 cm x 60 cm x 75 cm including, excavation, refilling, transportation, and labour etc complete. Spec. No. As directed by Engineer in Charge & MoRTH specification 804 (CSR2023-24 Volume-III Iteam Code-8.54 P-78) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 9450.0 | 9450.0 | 1.0 | False | None | None | False | None | False | 9450.0 | 0 | 3269922 | 113271 | None | I.No. 9.34 | Flooring with 25mm thick polished tandur blue stone slabs using cement mortar 1:6, 25mm thick over existing cement concrete bed or top of roof laid to line and level and jointed with cement slurry mixed with pigment to match the shade of the slab, , including cost of materials, labour, curing, polishing complete as per specifications. (CSR2023-24 Volume-II Iteam Code-9.34 P-64) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Sqm | 1622.25 | 1622.25 | 7.2 | False | None | None | False | None | False | 11680.2 | 0 |
| 1718102322000 | 0 | None | None | Buildings | Electrical work | 41780.22 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3269923 | 113272 | None | I.No. 1.2.1 | Concealed Conduit SystemSupplying heavy gauge PVC conduit pipe ...... mm dia..........mm thick confirming to IS 2509 with suitable size bends, metal/PVC Junction boxes, adhesive paste etc., and running before concreting the slab. The conduit should be tie ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Mtr | 69.3 | 69.3 | 24.0 | False | None | None | False | None | False | 1663.2 | 0 | 3269924 | 113272 | None | I.No. 1.3.2 | Supplying heavy gauge PVC Conduit Pipe .... dia ....... mm thick
with suitable size bends, metal junction boxes adhesive paste etc., by groove cutting in the wall and fixing by bracing U or J hooks and cement plastering upto the wall surface and run with ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Mtr | 82.95 | 82.95 | 7.0 | False | None | None | False | None | False | 580.65 | 0 | 3269925 | 113272 | None | I.No. 1.3.2 | Supplying and wiring adopting loop system in existing PVC Conduit/casing capping casing capping using 2x1.5Sqmm (Phase & Neutral)& 1x1.0 sqmm (Earth wire) FRLS multi strand PVC insulatedcopper wire (confirming to IS-694: and latest amendments) without con ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Mtr | 282.45 | 282.45 | 2.0 | False | None | None | False | None | False | 564.9 | 0 | 3269926 | 113272 | None | I.No. 2.2.1 | Medium point above 3Mtr upto 6Mtr from tapping point to out let via switch. Common Sr 2023-24 vol-6,pg no-5 ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Point | 397.95 | 397.95 | 2.0 | False | None | None | False | None | False | 795.9 | 0 | 3269927 | 113272 | None | I.No. 2.2.2 | Long point above 6Mtr upto 10Mtr from tapping point to out let via switch box.Common Sr 2023-24 vol-6,pg no-5 ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Point | 582.75 | 582.75 | 2.0 | False | None | None | False | None | False | 1165.5 | 0 | 3269928 | 113272 | None | I.No. 2.2.3 | Wiring for lighting/power circuit using one of FRLS PVC insulated 1100V grade, multistrand copper wire with low conductor resistance single core in open or concealed system of wiring with specified IS 694:2010.1.5 mm2 Common SR 2023- ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Point | 27.3 | 27.3 | 4.0 | False | None | None | False | None | False | 109.2 | 0 | 3269929 | 113272 | None | I.No. 2.3.2 | Wiring for lighting/power circuit using one of FRLS PVC insulated 1100V grade, multistrand copper wire with low conductor resistance single core in open or concealed system of wiring with specified IS 694:2010.2.5 mm2 Common SR 2023- ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Mtr | 44.1 | 44.1 | 4.0 | False | None | None | False | None | False | 176.4 | 0 | 3269930 | 113272 | None | I.No. 2.3.3 | Supplying and fixing surface/flush mounting unbreakable PVC modular box suitable for mounting modular switch plates with due groove cutting in Brick/C.C wall, including necessary rawl plugs, Machine/NF screws etc., complete.10-12 Way.Common SR 2023-24 vol ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Mtr | 274.05 | 274.05 | 1.0 | False | None | None | False | None | False | 274.05 | 0 | 3269931 | 113272 | None | I.No. 3.3.6 | Supplying and fixing surface/flush mounting unbreakable PVC modular box suitable for mounting modular switch plates with due groove cutting in Brick/C.C wall, including necessary rawl plugs, Machine/NF screws etc., complete.16 Way.Common SR 2023-24 vol-6, ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 308.7 | 308.7 | 1.0 | False | None | None | False | None | False | 308.7 | 0 | 3269932 | 113272 | None | I.No. 3.3.7 | Supplying and fixing superior quality modular switch mounting polycarbonate plate with necessary supporting back plate with required nos. of machine screws, bolts nuts etc., complete on the existing metal/PVC box.10-12 Module .Common SR 2023-24 vol-6,pg n ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 361.2 | 361.2 | 1.0 | False | None | None | False | None | False | 361.2 | 0 | 3269933 | 113272 | None | I.No. 3.5.6 | Supplying and fixing superior quality modular switch mounting polycarbonate plate with necessary supporting back plate with required nos. of machine screws, bolts nuts etc., complete on the existing metal/PVC box.16 Module .Common SR 2023-24 vol-6,pg no-8 ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 416.85 | 416.85 | 1.0 | False | None | None | False | None | False | 416.85 | 0 | 3269934 | 113272 | None | I.No. 3.5.7 | Supplying and fixing of modular switch & connected accessories on existing modular switch plate as per IS 3854 and IS 1293.6A One Way Switch Common SR 2023-24 vol-6,pg no-9 ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 107.1 | 107.1 | 4.0 | False | None | None | False | None | False | 428.4 | 0 | 3269935 | 113272 | None | I.No. 3.6.1 | Supplying and fixing of modular switch & connected accessories on existing modular switch plate as per IS 3854 and IS 1293. 6A Three Way socket Common SR 2023-24 vol-6,pg no-9 ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 179.55 | 179.55 | 1.0 | False | None | None | False | None | False | 179.55 | 0 | 3269936 | 113272 | None | I.No. 3.6.3 | Supplying and fixing of modular switch & connected accessories on existing modular switch plate as per IS 3854 and IS 1293Stepped Fan Regulator Two Module Common SR 2023-24 vol-6,pg no-9 Stepped Fan Regulator Two Module ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 328.65 | 328.65 | 2.0 | False | None | None | False | None | False | 657.3 | 0 | 3269937 | 113272 | None | I.No. 3.6.4 | Supplying and fixing of modular switch & connected accessories on existing modular switch plate as per IS 3854 and IS 1293. 6/16A Universal Socket Common SR 2023-24 vol-6,pg no-9 . ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 247.8 | 247.8 | 1.0 | False | None | None | False | None | False | 247.8 | 0 | 3269938 | 113272 | None | I.No. 3.6.10 | Supplying and fixing of modular switch & connected accessories on existing modular switch plate as per IS 3854 and IS 1293. TV/Telephone Socke Common SR 2023-24 vol-6,pg no-9 . ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 163.8 | 163.8 | 1.0 | False | None | None | False | None | False | 163.8 | 0 | 3269939 | 113272 | None | I.No. 3.6.11 | Supplying And fixing/replacing of 6/16/32A electrical
accessories on existing switch board.6A Bakelite Ceiling Rose.Common SR 2023-24 Vol-6 page no-10 ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 81.9 | 81.9 | 2.0 | False | None | None | False | None | False | 163.8 | 0 | 3269940 | 113272 | None | I.No. 3.14.5 | Supplying And fixing/replacing of 6/16/32A electrical
accessories on existing switch board.6A Pendant Holder.Common SR 2023-24 Vol-6 page no-10 ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 74.55 | 74.55 | 2.0 | False | None | None | False | None | False | 149.1 | 0 | 3269941 | 113272 | None | I.No. 3.14.6 | Supplying and fixing regular 4 Way MCCB distribution Panel confirming to IS/IEC 61439 - 3 and IK09 tested as per IS/IEC 62262 with minimum IP43 protection provided with Polyurethane (PUR) gasket, with suitable earthing system, on wall/wood board/flush mo ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 549.15 | 549.15 | 1.0 | False | None | None | False | None | False | 549.15 | 0 | 3269942 | 113272 | None | I.No. 5.17.4 | Supplying and fixing regular MCB distribution boards on wall/ood board / flush mounting using required clamps, bolts, nuts etc., with provision for fixing suitable type capacity MCB's single phase/3 phase/single door with powder coated painting Made out o ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 10329.0 | 10329.0 | 1.0 | False | None | None | False | None | False | 10329.0 | 0 | 3269943 | 113272 | None | I.No. 5.19.1 | Supplying, fixing and wiring Electronic Trivector Meter (ETV) 5 to 20A single phase Class-1 Accuracy with Temper Proof Energy Meter.Common SR 2023-24 Vol-6 page no-19 ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 1449.0 | 1449.0 | 1.0 | False | None | None | False | None | False | 1449.0 | 0 | 3269944 | 113272 | None | I.No. 6.3.1 | Supplying of .....feet -PVC Batten with integrated LED tube .... W with high quality diffuser with Life of 25000 burning hours & 70% lumen maintenance with CRI 80. Power Input: 220-240V@ 50/60Hz & Power factor 0.9 along with CE approved. 2 years Warran ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 724.5 | 724.5 | 2.0 | False | None | None | False | None | False | 1449.0 | 0 | 3269945 | 113272 | None | I.No. 11.3.2 | Supplying & fixing of retrofit type - LED bulb ...... W with OPAL acrylic diffuser comprising of LED source with CCT 6500 degree K, CRI 70%. efficacy 80 lumen per W, life 25000 burning hours and Compliance to IS 10322/IEC 60598, LM 79 & LM 80. The LED ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 168.0 | 168.0 | 3.0 | False | None | None | False | None | False | 504.0 | 0 | 3269946 | 113272 | None | I.No. 22.49 | Providing & fixing upvc ventilator with Exhaust Turbo speed fan with 5 blades (300mm x 300 mm & above sized fan) with copper motor having mounting rrangements as per direction of Engineer in charge
of work.Common SR 2023-24,Vol-2 I no 22.49 page no-221 ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 2047.5 | 2047.5 | 4.0 | False | None | None | False | None | False | 8190.0 | 0 | 3269947 | 113272 | None | I.No. 13.11 | GI Grounding pipe, B - Class, 42 mm dia, 2.5 Mtr long, 3.2 mm thick with bolt, nut, GI Strips and washer complete Minimum Weight of GI Pipe: 7.3 Kg.Common SR 2023-24,Vol-6 ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 780.15 | 780.15 | 1.0 | False | None | None | False | None | False | 780.15 | 0 | 3269948 | 113272 | None | I.No. 51.01 | Good Quality well burnt Charcoal for grounding purposes packed in non returnable gunny bag of 30 Kg each ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | No | 709.8 | 709.8 | 1.0 | False | None | None | False | None | False | 709.8 | 0 | 3269949 | 113272 | None | I.No. 54.02 | Good Quality Salt for grounding purposes packed in 50 Kg gunny bag ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | No | 325.5 | 325.5 | 1.0 | False | None | None | False | None | False | 325.5 | 0 | 3269950 | 113272 | None | I.No. 54.03 | Digging of Pit for providing GI Pipe type Earthing for Haed Soil ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Bag | 3139.5 | 3139.5 | 1.0 | False | None | None | False | None | False | 3139.5 | 0 | 3269951 | 113272 | None | I.No. 1.6.2 | 1.1 kV, XLPE or Heat resistant PVC
insulated, PVC exutruted Inner Seath
Armoured LTUG Cable as per IS-1554 (Part1) or IS-7098 Part-1, Armouring strip
thickness and resistivity as per IS-3975 10 Sqmm, 2 Core, (9 GI Strips - 4 x 0.8 mm) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Pit | 83193.6 | 83193.6 | 0.03 | False | None | None | False | None | False | 2495.808 | 0 | 3269952 | 113272 | None | I.No. 32.01 | Earth work excavation for cable trench of 0.5 to 0.75 Mtr. Width and Depth upto 1 Mtr including trial pits, depositing on bank upto a lead of 50 Mtr, Supplying and Displaying necessary Danger Boards and Lighting, Using sight Rails and Sign Boards at every ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Km | 273.0 | 273.0 | 6.5 | False | None | None | False | None | False | 1774.5 | 0 | 3269953 | 113272 | None | I.No. 29.02 | Laying of cable in Existing Trench/GI pipe/Stone Ware/RCC Hume pipe using Wooden/Aluminum Rollers as directed by the departmental staff. 2.5 to 25 Sqmm (Single/3.5/4 Core) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | cm | 21930.3 | 21930.3 | 0.03 | False | None | None | False | None | False | 657.909 | 0 | 3269954 | 113272 | None | I.No. 21.05 | Supplying heavy gauge PVC conduit pipe 25mm dia 2 mm thick confirming to IS 2509 with suitable size bends, junction boxes, adhesive paste etc , and fixing using inverted wood plugs in case of RCC ceiling and RCC wall/ stone structure or rawl plugs in case ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Km | 85.05 | 85.05 | 12.0 | False | None | None | False | None | False | 1020.6 | 0 |
|
|
---|