tenderSubEstimateList | createdTs | version | createdDate | modifiedDate | workCategoryName | subEstimateName | estimateTotal | itemList |
---|
1719647716000 | 0 | None | None | Roads | PKG-785 (A)Improvements to Road from Maddur -T M road to Nidagatta connecting Road From Ch0.00 KM to 5.40 KM road (SH-33 to NH 275 connecting road ) In Selected reaches in Maddur Taluk of Mandya District.Road Estimate | 96962865.14 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3409645 | 120473 | None | Item No 5 (ii) a Page No 9 Vol 03 Common SR2023-24 | Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness. (ii) By Mechanical Means using Dozer (a) In area of light jungle (Item No. 2.5 (ii) a/ Page No. 9/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | 100 Sqm | 463.74 | 463.74 | 96.0 | False | None | None | False | None | False | 44519.04 | 0 | 3409646 | 120473 | None | Item No 3.5 Page No 17Vol03 Common SR-2023-24 | Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of scarified material by Mechanical Means using Hydraulic excavator with in all lifts and lead (Item No. 3.5 / Page No. 17/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 7.08 | 7.08 | 18976.0 | False | None | None | False | None | False | 134350.08 | 0 | 3409647 | 120473 | None | Item No 1.12 Page No 8Vol 01 Common SR-2023-24 | Earth work in surface excavation by mechanical means for lowering & leveling the ground for all works other than foundation in all kinds of soils & upto depth not exceeding 300mm as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenances required to complete the work. In all kinds of soils upto 300 mm depth (Item No. 1.12/ Page No. 8/Vol.01/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 112.1 | 112.1 | 7699.81 | False | None | None | False | None | False | 863148.701 | 0 | 3409648 | 120473 | None | Item No. 1.7 Page No. 7 Vol.01 Common SR-2023-24 | Construction of Embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded with desired compaction. (Royalty shall be recovered @ Rs. 60.00/m3) (Item No. 1.7/ Page No. 7/Vol.01/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 140.42 | 140.42 | 6722.83 | False | None | None | False | None | False | 944019.7886 | 0 | 3409649 | 120473 | None | Item No. 1.8 Page No. 7 Vol.01 Common SR-2023-24 | Construction of Embankment by excavating the available approved Gravel/ Murrum deposited at a place or borrow pits during or prior excavation with all lifts and lead, transportation to site, spreading, grading to required slope and compacting to meet the requirement complete as per specifications, including cost of labour,rolling,water,all materials,usage& all other appurtenaces required to complete the work. (Item No. 1.8/ Page No. 7/Vol.01/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 559.32 | 559.32 | 10054.23 | False | None | None | False | None | False | 5623531.9236 | 0 | 3409650 | 120473 | None | Item No. 3.6 Page No. 17 Vol.03 Common SR-2023-24 | Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2 (Item No. 3.6/ Page No. 17/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 581.74 | 581.74 | 3686.0 | False | None | None | False | None | False | 2144293.64 | 0 | 3409651 | 120473 | None | Item No 4.2 B (v) Page No 23 Vol3Common SR 2023-24 | Construction of Granular Sub-Base of required grading as per design spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with front end loader at OMC and compacting with vibratory roller to achieve the desired density, complete as per clause 401 By Mix in Place Method (v) For Grading -V Material (Item No. 4.2 B (v)/ Page No. 23/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 2783.62 | 2783.62 | 6715.48 | False | None | None | False | None | False | 18693344.4376 | 0 | 3409652 | 120473 | None | Item No. 4.17 Page No. 26 Vol.03 Common SR-2023-24 | Wet Mix Macadam (Plant Mix Method) Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver/grader in sub-base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. (Item No. 4.17/ Page No. 26/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 3019.62 | 3019.62 | 9825.89 | False | None | None | False | None | False | 29670453.9618 | 0 | 3409653 | 120473 | None | Item No. 5.1 A i Page No. 31 Vol3 CommonSR2023-24 | Prime Coat over WMM/WBM Providing and applying primer coat with SS1 grade Bitumen Emulsion on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70 kg/m2 using mechanical means. (Item No. 5.1 A (i)/ Page No. 31/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 48.38 | 48.38 | 38310.86 | False | None | None | False | None | False | 1853479.4068 | 0 | 3409654 | 120473 | None | Item No. 5.4 Page No. 31Vol.03Common SR-2023-24 | Tack coat on Granular surface treated with primer Providing and applying tack coat with RS1 Bituminous Emulsion using emulsion pressure distributor at the rate of 0.25 kg/m2 on Granular surface (Item No. 5.4/ Page No. 31/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 16.52 | 16.52 | 38461.64 | False | None | None | False | None | False | 635386.2928 | 0 | 3409655 | 120473 | None | Item No. 5.12 C Page No 35Vol03Common SR2023-24 | Dense Graded Bituminous Macadam Grading - II for traffic 20 MSA Providing and laying Dense Graded Bituminous Macadam with 40/60 TPH capacity HMP using crushed aggregates of specified grading, premixed with bituminous binder VG-30, @ 4.5 per cent by weight of total mix and filler, transporting the hot mix to work site, laying with mechanical paver finisher to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 505 complete in all respects. (Item No. 5.12 C/ Page No. 35/Vol.03/Common SR-2023-24)--- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 11149.82 | 11149.82 | 1923.08 | False | None | None | False | None | False | 21441995.8456 | 0 | 3409656 | 120473 | None | Item No. 5.16 C Page No. 38 Vol 3 Common SR2023-24 | Bituminous Concrete Grading II for traffic 20 MSA Providing and laying Bituminous Concrete with 40/60 TPH capacity hot mix plant using crushed aggregates of specified grading, premixed with bituminous binder VG-30, @ 5.4 per cent of mix and filler, transporting the hot mix to work site, laying with mechanical paver finisher to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respects (Item No. 5.16 C/ Page No. 38/Vol.03/Common SR-2023-24 --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 12925.72 | 12925.72 | 1153.85 | False | None | None | False | None | False | 14914342.022 | 0 |
| 1719647716000 | 0 | None | None | Roads | ROAD SAFETY FURNITURES | 2512488.8 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3409657 | 120474 | None | Item No. 8.5 A (ii) Page No. 64 Vol3 CSR2023-24 | Retro-Reflectorised Traffic Signs Providing and fixing of retro- reflectorised cautionary, mandatory and informatory sign as per IRC:67:2022 made of Class B Type XI retro reflective sheeting fixed over 2 mm thick aluminium sheeting vide clause 801.3, 3mm/4mm thick Aluminium composite material sheet depending on the size of the sign fixed over the back support frame of min 25 x 25 x 3mm angle mounted on a mild steel circular pipe 65 NB, 3.2 mm thickness firmly fixed to the ground by means of properly designed foundation with M25 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing.The sign shall be maintained as per section 12 of IRC:67:2022. (ii) 90 cm equilateral triangle (Item No. 8.5 A (ii)/ Page No. 64/Vol.03/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Each | 5527.12 | 5527.12 | 34.0 | False | None | None | False | None | False | 187922.08 | 0 | 3409658 | 120474 | None | Item No. 8.5 A (x) Page No65 Vol3 Common SR2023-24 | Retro-Reflectorised Traffic Signs Providing and fixing of retro- reflectorised cautionary, mandatory and informatory sign as per IRC:67:2022 made of Class B Type XI retro reflective sheeting fixed over 2 mm thick aluminium sheeting vide clause 801.3, 3mm/4mm thick Aluminium composite material sheet depending on the size of the sign fixed over the back support frame of min 25 x 25 x 3mm angle mounted on a mild steel circular pipe 65 NB, 3.2 mm thickness firmly fixed to the ground by means of properly designed foundation with M25 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing.The sign shall be maintained as per section 12 of IRC:67:2022. 80 mm x 60 mm rectangular (Item No. 8.5 A (x)/ Page No. 65/Vol.03/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Each | 6392.06 | 6392.06 | 14.0 | False | None | None | False | None | False | 89488.84 | 0 | 3409659 | 120474 | None | Item No 8.5 A(ii) Page No64 Vool3 Common SR2023-24 | Retro-Reflectorised Traffic Signs Providing and fixing of retro- reflectorised cautionary, mandatory and informatory sign as per IRC:67:2022 made of ClassB Type XI retro reflective sheeting fixed over 2 mm thick aluminium sheeting vide clause 801.3, 3mm/4mm thick Aluminium composite material sheet depending on the size of the sign fixed over the back support frame of min 25 x 25 x 3mm angle mounted on a mild steel circular pipe 65 NB, 3.2 mm thickness firmly fixed to the ground by means of properly designed foundation with M25 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing.The sign shall be maintained as per section 12 of IRC:67:2022. (iv) 60 cm Circular (Item No. 8.5 A (ii)/ Page No. 64/Vol.03/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Each | 5070.46 | 5070.46 | 8.0 | False | None | None | False | None | False | 40563.68 | 0 | 3409660 | 120474 | None | Item No 8.5A(xv) Page No. 65 Vol3 Common SR2023-24 | Retro-Reflectorised Traffic Signs Providing and fixing of retro- reflectorised cautionary, mandatory and informatory sign as per IRC:67:2022 made of Class B Type XI retro reflective sheeting fixed over 2 mm thick aluminium sheeting vide clause 801.3, 3mm/4mm thick Aluminium composite material sheet depending on the size of the sign fixed over the back support frame of min 25 x 25 x 3mm angle mounted on a mild steel circular pipe 65 NB, 3.2 mm thickness firmly fixed to the ground by means of properly designed foundation with M25 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing.The sign shall be maintained as per section 12 of IRC:67:2022. (xv) 90 cm high octagon (Item No. 8.5 A (xv)/ Page No. 65/Vol.03/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Each | 7672.36 | 7672.36 | 10.0 | False | None | None | False | None | False | 76723.6 | 0 | 3409661 | 120474 | None | Item No 8.48 Page No. 76 Vol.03 Common SR-2023-24 | Chevron Boards Supply and installation of retro- reflective Chevron signboards of 600x450mm made out of cube corner micro prismatic grade sheeting confirming to Type XI standards of IRC:67:2022 & ASTM D 4956-09 specification & fixed over 3 mm thick Aluminium Composite Panel sheet having minimum 0.30 mm thick aluminum skin on both sides & fixed over back support frame of 25x25x3mm MS angle frame. Supported on 75 mm dia OR 75x75x6mm Mild steel with clear height of not less than 2.1 m from the ground level to the bottom of the Sign board & 60 cm below ground level. The sign post should be painted with one coat of red oxide paint and two coats of synthetic enamel paint of black and white colour with bands of 30 cm height, firmly fixed to the ground by means of foundation with M 20 grade cement, concrete foundation size of 45cm x 45 cm x 60 cm including cost & conveyance of all materials, equipment,machinery & Labour with all leads and lifts for satisfactory completion of the work as directed by Engineer incharge. (Item No. 8.48/ Page No. 76/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | No. | 4231.48 | 4231.48 | 22.0 | False | None | None | False | None | False | 93092.56 | 0 | 3409662 | 120474 | None | Item No. 8.7 Page No. 65 Vol.03 Common SR-2023-24 | Direction and Place Identification Signs upto 0.9 m2 Size Board. Providing and erecting direction and place identification retroreflectorised sign as per IRC:67:2022 made of high intensity grade sheeting vide clause 801.3, fixed over aluminium sheeting, 2 mm thick or Aluminium composite material sheet with overall thickness of 4mm with area not exceeding 0.9 m2 fixed over back support frame of min 35 x 35 x 3mm angle mounted on a mild steel circular pipe 65 NB, firmly fixed to the ground by means of properly designed foundation with M25 grade cement concrete 45 x 45 x 60 cm, 60 cm below ground level as per approved drawing (Item No. 8.7/ Page No. 65/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 10631.8 | 10631.8 | 6.48 | False | None | None | False | None | False | 68894.064 | 0 | 3409663 | 120474 | None | Item No 16.29 Page No. 149 Vol.3 Common SR2023-24 | Project Display Board i) The board will be a composite unit consisting of three plates of Aluminium Composite Materials (ACM), material specifications as per Clause 1701.3.7. The top most platewill be in rectangular shape of 600mm x 600 mm size, riveted over welded M.S. angle iron frame of 25 mm x 25mm x 5 mm size on back on edges. The middle plate will be 1200 mm x 150 mm size riveted over welded M.S. angle iron frame of 25mm x 25mmx 5 mm size on back on edges. The main lower most plate will be 1500 mm x 600 mm size, riveted over welded M.S. angle iron frame of 25 mm x 25 mm x 5 mm size. Welding of all the sheets over angle iron frame will be done neatly to have plain surface on one side. The angle iron frames of the lower most plate and the middle plate will be welded to two nos. 75 mm x 75 mm (12 SWG) sheet tubes posts placed at 1125 mm apart centre to centre. The top of the middle plate will be flushed with the top of 75 mm dia medium steel tube posts and these posts will be embedded in cement concrete M15 grade blocks of 450 mm x 450 mm x 600 mm below ground level. The height of bottom of the lower most plate will be 1200 mm from normal ground level and the bottom of middle plate will be 100 mm above the top level of the lower most plate. The rectangular shaped plate mounted over angle iron frame will be connected to middle plate by square medium steel section of 47 mm x 47 mm thickness 12 SWG having a spacing of 100 mm between the rectangular shaped plate and middle plate and this square section will be welded to the bottom point of the rectangular shaped plate. (ii) The lettering and borders, etc. of middle and bottom plate, SHDP logo on top plate shall be as per clause 1701.4.6 essages/Borders. All the sections of frame and posts will be painted with primer and two coats of Epoxy paint. The steel tube below ground level will be painted with three coats of Epoxy paint. The design, painting and lettering shall be done as per approved drawing. (iii) For warranty and durability the clause 1701.5 and for maintenance the clause 1911 shall be applicable. (iv) A reference number along with the month and year of installation should be placed on the back of a sign in a contrasting colour or by stamping in characters not exceeding 50 mm in height.485777/2019/Dir(Tech) 7Retro Reflective Trafic Sign As per IRC 67 Clause 1701.3.8.1 Class A Type 1 (Item No. 16.29/ Page No. 149/Vol.03/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 18115.36 | 18115.36 | 2.0 | False | None | None | False | None | False | 36230.72 | 0 | 3409664 | 120474 | None | Item No 8.15 Page No. 67 Vol.03 Common SR-2023-24 | Road Marking with Hot Applied Thermoplastic Compound with Reflectorising Glass Beads on Bituminous Surface Providing and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 g/m2 area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35:2015.The finished surface to be level, uniform and free from streaks and holes. (Item No. 8.15/ Page No. 67/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 625.4 | 625.4 | 1299.7 | False | None | None | False | None | False | 812832.38 | 0 | 3409665 | 120474 | None | Item No 8.43 Page No. 74 Vol.03 Common SR-2023-24 | Supplying and Fixing of Molded Shank Raised Pavement Markers / Cat's Eye made of polycarbonate and ABS moulded body and reflective panels with micro prismatic lens capable of providing total internal reflection of the light entering the lens face and shall support a load of 16000 kg tested in accordance to ASTM D 4280 Type H and complying to Specifications of Category A of MORTH Circular No RW/NH/33023/10-97 DO III Dt 11.06. 1997. The height, width and length shall not exceed 50 mm, 100 mm and 102 +/- 2 mm and with minimum reflective area of 13 cm2 on each side and the slope to the base shall be 35 +/- 5 degree. The strength of detachment of the integrated cylindrical shanks, (of diameter not less than 19 +/- 2 mm and height not less than 30+/- 2 mm) from the body is to be a minimum value of 500 Kg. Fixing will be by drilling holes on the road for the shanks to go inside, without nails and using epoxy resin based adhesive as per manufacturer's recommendation and complete as directed by the engineer.The contractor shall submit a two year warranty for satisfactory field performance including stipulated retro-reflectance of the reflecting panel, to the Engineer. (Item No. 8.43/ Page No. 74/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | No | 430.7 | 430.7 | 510.0 | False | None | None | False | None | False | 219657.0 | 0 | 3409666 | 120474 | None | Item No 8.17 Page No. 8.17 Vol.03 Common SR2023-24 | Road DelineatorsSupplying and installation of delineators (road way indicators, hazard markers, object markers), 80-100 cm high above ground level, painted black and white in 15 cm wide strips, fitted with 80 x 100 mm rectangular or 75 mm dia circular reflectorised panels at the top, buried or pressed into the ground and conforming to IRC-79-2019 and the drawings./ (Item No. 8.17 Page No. 8.17/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Each | 2384.78 | 2384.78 | 198.0 | False | None | None | False | None | False | 472186.44 | 0 | 3409667 | 120474 | None | Item No 8.16(i) Page No. 67 Vol3 Common SR2023-24 | Reinforced cement concrete M15grade kilometre stone of standard design as per IRC:8-1980, fixing in position including painting and printing etc 5th kilometre stone (precast) (Item No. 8.16 (i)/ Page No. 67/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Each | 5995.58 | 5995.58 | 2.0 | False | None | None | False | None | False | 11991.16 | 0 | 3409668 | 120474 | None | Item No 8.16(ii) Page No 67 Vol3 Common SR2023-24 | Reinforced cement concrete M15grade kilometre stone of standard design as per IRC:8-1980, fixing in position including painting and printing etc Ordinary kilometer stone (precast) (Item No. 8.16 (ii)/ Page No. 67/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Each | 3453.86 | 3453.86 | 4.0 | False | None | None | False | None | False | 13815.44 | 0 | 3409669 | 120474 | None | Item No8.16(iii) Page No67 Vol3 Common SR2023-24 | Reinforced cement concrete M15grade kilometre stone of standard design as per IRC:8-1980, fixing in position including painting and printing etc 200 m stone (precast) (Item No. 8.16 (iii)/ Page No. 67/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Each | 993.56 | 993.56 | 22.0 | False | None | None | False | None | False | 21858.32 | 0 | 3409670 | 120474 | None | ItemNo 8.60.2(iii) Page No 80 Vol3 CommonSR2023-24 | Providing Speed Breakers/Raised pedestrian crossings in Trapezoidal section with 2.5 m Top width and transition length of 0.8 m length and height of 0.1 m as per IRC 99:2018 using Dense Bituminous Macadam (DBM) Gr II and Bituminous Concrete (BC) Gr II for entire formation width & WBM Gr II for Shoulder hump portion only (150 mm thick), completing with road marking paint with applied thermoplastic compound with reflecting glass beeds on bituminous surface and providing 2 Nos. retro reflective traffic signs as per IRC 67 -2022 Two lane with formation width of 9.00 m (Item No. 8.60.2 (iii) / Page No. 80/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | No | 61205.42 | 61205.42 | 6.0 | False | None | None | False | None | False | 367232.52 | 0 |
| 1719647716000 | 0 | None | None | Roads | RCC DRAIN | 12581489.36 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3409671 | 120475 | None | Item No 1.14 Pg No 8 Vol 1 Common SR2023-24 | Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete (Item No. 1.14/ Page No. 8/Vol.01/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 120.36 | 120.36 | 2914.5 | False | None | None | False | None | False | 350789.22 | 0 | 3409672 | 120475 | None | Item No 2.1.3 Pg No. 15 Vol1 Common SR2023-24 | Providing and laying in Position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates (Item No. 2.1.3/ Page No. 15/Vol.01/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 7067.02 | 7067.02 | 230.0 | False | None | None | False | None | False | 1625414.6 | 0 | 3409673 | 120475 | None | Item No 2.4.2 Pg No 16 Vol 1 Common SR 2023-24 | Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates (Item No. 2.4.2/ Page No. 16/Vol.01/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 7461.14 | 7461.14 | 185.2 | False | None | None | False | None | False | 1381803.128 | 0 | 3409674 | 120475 | None | Item No 2.4.2 Pg No 16 Vol 1 Common SR2023-24 | Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates (Item No. 2.4.2/ Page No. 16/Vol.01/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 10072.54 | 10072.54 | 304.8 | False | None | None | False | None | False | 3070110.192 | 0 | 3409675 | 120475 | None | Item No. 2.5.1 Pg No 16 Vol 1 Common SR2023-24 | Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates (Item No. 2.5.1/ Page No. 16/Vol.01/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 9388.08 | 9388.08 | 230.2 | False | None | None | False | None | False | 2161136.016 | 0 | 3409676 | 120475 | None | Item No 2.11 h Pg No 18 Vol1 Common SR2023-24 | Supplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. All other type of structures (Item No. 2.11 h/ Page No. 18/Vol.01/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | MT | 93232.98 | 93232.98 | 42.82 | False | None | None | False | None | False | 3992236.2036 | 0 |
| 1719647716000 | 0 | None | None | Roads | Water Supply Line Shifting. (Slice-1) | 897415.25 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3409677 | 120476 | None | Item No. 1.17.1 pg No.10 Vol 1 Common SR 2023-24 | Earth work excavation for pipeline trenches in all kinds of soils by mechanical means as per drawing and technical specifications, including setting out, construction of shoring, strutting, barricading, caution lights, bracing, using sight rails & bonding rods at every 100 mm wherever necessary as directed, removal of stumps and other deleterious matter, dressing of sides and levelling the bottom of trench to the extent required , utilising the available excavated earth locally for the work etc., and all other appurtenances complete in the following strata.(Item No. 1.17.1/ Page No. 10/Vol.01/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 309.16 | 309.16 | 556.2 | False | None | None | False | None | False | 171954.792 | 0 | 3409678 | 120476 | None | Item No.9.2.1 pg No. 96 Vol 05 Common SR 2023-24 | Providing, laying and jointing HDPE pipes of specified grade and conforming to IS 4984-2016 with latest ammendments and conveying to work site including loading and nloading at both destinations and rolling and lowering into trenches, laying true to line and jointing of pipes and specials with electrofusion welding, giving hydraulic test as per relevant ISS with all lead and lifts including encasing the pipe alround to a depth of not less than 15 cms. with soft gravel or selected earth available from the excation, testing and commissioning. The rate is exclusive of required specials and fittings wherever necessary like saddle Tee, stub ends, flanged sets, bedns, reducers etc. complete (Contractor will make his own arrangements for procuring water for testing) etc. complete. NOTE: Upto 110mm dia Coil shall be used. For: HDPE Grade PE80-PN8.0,63mm dia (Item No. 9.2.1/ Page No. 96/Vol.05/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 258.42 | 258.42 | 395.0 | False | None | None | False | None | False | 102075.9 | 0 | 3409679 | 120476 | None | Item No.19.2.3 pg No. 96 Vol 05 Common SR 2023-24 | Providing, laying and jointing HDPE pipes of specified grade and conforming to IS 4984-2016 with latest ammendments and conveying to work site including loading and nloading at both destinations and rolling and lowering into trenches, laying true to line and jointing of pipes and specials with electrofusion welding, giving hydraulic test as per relevant ISS with all lead and lifts including encasing the pipe alround to a depth of not less than 15 cms. with soft gravel or selected earth available from the excation, testing and commissioning. The rate is exclusive of required specials and fittings wherever necessary like saddle Tee, stub ends, flanged sets, bedns, reducers etc. complete (Contractor will make his own arrangements for procuring water for testing) etc. complete. NOTE: Upto 110mm dia Coil shall be used. For: HDPE Grade PE80-PN8.0,90mm dia (Item No. 19.2.3/ Page No. 96/Vol.05/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 450.76 | 450.76 | 1150.0 | False | None | None | False | None | False | 518374.0 | 0 | 3409680 | 120476 | None | Item No. 1.10 pg No. 7 Vol 01 Common SR 2023-24 | Refilling available earth around trenches/pipelines, cables in layers not exceeding 20 cms in depth, compacting each deposited layer by ramming after watering with a lead upto 50 m, and lift upto 1.5 m. Including cost of all labour complete as per specifications(Item No. 1.10/ Page No. 7/Vol.01/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 188.8 | 188.8 | 556.2 | False | None | None | False | None | False | 105010.56 | 0 |
| 1719647716000 | 0 | None | None | Roads | Box Culvert (1.0 x 1.0) 1Vent at Ch 345 Mts, Ch 1550 Mts, Ch 1700 Mts, Ch 2530 Mts, Ch 2990 Mts, Ch 4990 Mts | 2508406.94 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3409681 | 120477 | None | Item No.2.8(ii)a Pg No10 Vol.03 Common SR 2023-24 | Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead By Mechanical Means (a)Cement Concrete Grade M-15 & M-20 (Item No. 2.8 (ii) a/ Page No. 10/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 848.42 | 848.42 | 40.5 | False | None | None | False | None | False | 34361.01 | 0 | 3409682 | 120477 | None | Item No 2.11(ii)A Pg No.10 Vol3 Common SR 2023-24 | Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead By Mechanical Means (A)Dismantling Brick / Tile work / rubble masonry / pitching / etc bymechanical means (Item No. 2.11 (ii) A/ Page No. 10/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 212.4 | 212.4 | 37.2 | False | None | None | False | None | False | 7901.28 | 0 | 3409683 | 120477 | None | Item No 2.17(ix)B Pg No.11 Vol3 Common SR 2023-24 | Removing all type of Hume Pipes and Stacking including Earthwork and Dismantling of Masonry Works. Above 600 mm to 900 mm dia (Item No. 2.17 (ix) B/ Page No. 11/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | m | 1293.28 | 1293.28 | 7.5 | False | None | None | False | None | False | 9699.6 | 0 | 3409684 | 120477 | None | Item No 1.14 Pg No. 8 Vol.01 Common SR 2023-24 | Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete (Item No. 1.14/ Page No. 8/Vol.01/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 120.36 | 120.36 | 149.76 | False | None | None | False | None | False | 18025.1136 | 0 | 3409685 | 120477 | None | Item No 2.1.3 Pg No. 15 Vol.01 Common SR 2023-24 | Providing and laying in Position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates (Item No. 2.1.3/ Page No. 15/Vol.01/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 7067.02 | 7067.02 | 25.92 | False | None | None | False | None | False | 183177.1584 | 0 | 3409686 | 120477 | None | Item No 2.4.3 Pg No. 16 Vol.01 Common SR 2023-24 | Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates(Item No. 2.4.3/ Page No. 16/Vol.01/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 8971.78 | 8971.78 | 93.96 | False | None | None | False | None | False | 842988.4488 | 0 | 3409687 | 120477 | None | Item No 2.5.2 Pg No. 16 Vol.01 Common SR 2023-24 | Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates (Item No. 2.5.2/ Page No. 16/Vol.01/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 9689.69 | 9689.69 | 38.02 | False | None | None | False | None | False | 368402.0138 | 0 | 3409688 | 120477 | None | Item No 2.11h Pg No. 18 Vol.01 Common SR 2023-24 | Supplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. All other type of structures (Item No. 2.11 h/ Page No. 18/Vol.01/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | MT | 93232.98 | 93232.98 | 11.15 | False | None | None | False | None | False | 1039547.727 | 0 | 3409689 | 120477 | None | Item No 8.10 Pg No. 66 Vol.03 Common SR 2023-24 | Painting Two Coats on New Concrete Surfaces Painting two coats after filling the surface with synthetic enamel paint in all shades on new plastered concrete surfaces (Item No. 8.10/ Page No. 66/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 128.62 | 128.62 | 21.6 | False | None | None | False | None | False | 2778.192 | 0 | 3409690 | 120477 | None | Item No 8.4 Pg No. 64 Vol.03 Common SR 2023-24 | Printing New Letter Printing New Letter and Figures of any Shade Printing new letter and figures of any shade with synthetic enamel paint black or any other approved colour to give an even shade-English and Roman (Item No. 8.4/ Page No. 64/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | cm | 1.06 | 1.06 | 1440.0 | False | None | None | False | None | False | 1526.4 | 0 |
| 1719647716000 | 0 | None | None | Roads | Box Culvert (3.0x3.0) 3Vent at Ch 2280 mts | 7444964.14 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3409691 | 120478 | None | Item No 2.8(ii)a Pg No10 Vol 3 Common SR 2023-24 | Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead By Mechanical Means (a)Cement Concrete Grade M-15 & M-20 (Item No. 2.8 (ii) a/ Page No. 10/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 848.42 | 848.42 | 52.62 | False | None | None | False | None | False | 44643.8604 | 0 | 3409692 | 120478 | None | Item No 1.14 Pg No 8 Vol.01 Common SR 2023-24 | Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete (Item No. 1.14/ Page No. 8/Vol.01/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 120.36 | 120.36 | 432.0 | False | None | None | False | None | False | 51995.52 | 0 | 3409693 | 120478 | None | Item No 2.1.3 Pg No 15 Vol.01 Common SR 2023-24 | Providing and laying in Position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates (Item No. 2.1.3/ Page No. 15/Vol.01/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 7067.02 | 7067.02 | 33.3 | False | None | None | False | None | False | 235331.766 | 0 | 3409694 | 120478 | None | Item No 2.4.3 Pg No 16 Vol.01 Common SR 2023-24 | Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates(Item No. 2.4.3/ Page No. 16/Vol.01/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 8971.78 | 8971.78 | 146.34 | False | None | None | False | None | False | 1312930.2852 | 0 | 3409695 | 120478 | None | Item No 2.4.3 Pg No 16 Vol.01 Common SR 2023-24 | Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates(Item No. 2.4.3/ Page No. 16/Vol.01/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 8074.6 | 8074.6 | 192.0 | False | None | None | False | None | False | 1550323.2 | 0 | 3409696 | 120478 | None | Item No 2.5.2 Pg No 16 Vol.01 Common SR 2023-24 | Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates (Item No. 2.5.2/ Page No. 16/Vol.01/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 9689.69 | 9689.69 | 64.03 | False | None | None | False | None | False | 620430.8507 | 0 | 3409697 | 120478 | None | Item No 2.11 h Pg No 18 Vol.01 Common SR 2023-24 | Supplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. All other type of structures (Item No. 2.11 h/ Page No. 18/Vol.01/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | MT | 93232.98 | 93232.98 | 25.63 | False | None | None | False | None | False | 2389561.2774 | 0 | 3409698 | 120478 | None | Item No 13.2A Pg No 121 Vol.03 Common SR 2023-24 | Providing and laying Cement concrete wearing coat M-30 grade including reinforcement complete as per drawing and Technical Specifications. (Batching Plant)(Item No. 13.2 A/ Page No. 121/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 16485.78 | 16485.78 | 9.67 | False | None | None | False | None | False | 159417.4926 | 0 | 3409699 | 120478 | None | Item No 13.8 Pg No 121 Vol.03 Common SR 2023-24 | PCC M15 Grade leveling course below approach slab complete as per drawing and Technical specification (Item No. 13.8/ Page No. 121/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 8036.98 | 8036.98 | 10.8 | False | None | None | False | None | False | 86799.384 | 0 | 3409700 | 120478 | None | Item No 13.9 Pg No 122 Vol.03 Common SR 2023-24 | Reinforced cement concrete M30 grade for approach slab including reinforcement and formwork complete as per drawing and Technical specification (Batching Plant)(Item No. 13.9/ Page No. 122/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 13965.3 | 13965.3 | 21.6 | False | None | None | False | None | False | 301650.48 | 0 | 3409701 | 120478 | None | Item No 12.3 Pg No117 Vol.03 Common SR 2023-24 | Providing and laying of Filter media with granular materials/stone crushed aggregates satisfying the requirements laid down in clause 2504.2.2. of MoRTH specifications to a thickness of not less than 600 mm with smaller size towards the soil and bigger size towards the wall and provided over the entire surface behind abutment, wing wall and return wall to the full height compacted to a firm condition complete as per drawing and Technical Specification. (Item No. 12.3/ Page No.117/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 3158.86 | 3158.86 | 43.2 | False | None | None | False | None | False | 136462.752 | 0 | 3409702 | 120478 | None | Item No 14.4A Pg No 129 Vol.03 Common SR 2023-24 | Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in front of toe of embankment complete as per drawing and Technical specifications Stone/Boulder (Item No. 14.4 A/ Page No. 129/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 2256.16 | 2256.16 | 48.32 | False | None | None | False | None | False | 109017.6512 | 0 | 3409703 | 120478 | None | Item No 8.10 Pg No 66 Vol.03 Common SR 2023-24 | Painting Two Coats on New Concrete Surfaces Painting two coats after filling the surface with synthetic enamel paint in all shades on new plastered concrete surfaces (Item No. 8.10/ Page No. 66/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 128.62 | 128.62 | 30.13 | False | None | None | False | None | False | 3875.3206 | 0 | 3409704 | 120478 | None | Item No 8.4 Pg No 64 Vol.03 Common SR 2023-24 | Printing New Letter Printing New Letter and Figures of any Shade Printing new letter and figures of any shade with synthetic enamel paint black or any other approved colour to give an even shade-English and Roman (Item No. 8.4/ Page No. 64/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | cm | 1.06 | 1.06 | 240.0 | False | None | None | False | None | False | 254.4 | 0 | 3409705 | 120478 | None | Item No 1.8 Pg No 7 Vol.01 Common SR 2023-24 | Construction of Embankment by excavating the available approved Gravel/ Murrum deposited at a place or borrow pits during or prior excavation with all lifts and lead, transportation to site, spreading, grading to required slope and compacting to meet the requirement complete as per specifications, including cost of labour,rolling,water,all materials,usage& all other appurtenaces required to complete the work. (Item No. 1.8/ Page No. 7/Vol.01/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 559.32 | 559.32 | 450.0 | False | None | None | False | None | False | 251694.0 | 0 | 3409706 | 120478 | None | Item No 9.1(i) Pg No 87 Vol.03 Common SR 2023-24 | Laying Reinforced cement concrete pipe NP4/prestressed concrete pipe for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls and parapets. 1000 mm dia (Item No. 9.1 (i)/ Page No. 87/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Rmtr | 12705.06 | 12705.06 | 15.0 | False | None | None | False | None | False | 190575.9 | 0 |
| 1719647716000 | 0 | None | None | Roads | ELECTRICAL POLE SHIFTING | 1904177.28 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3409707 | 120479 | None | CSR2023-24 Item No 1.02 PgNo 03 81Mat No -200106 | Line Supports (Pole)RCC Pole - 9 Mtr Long, 150 Kg WL Sq Section (Dwg No. BESCOM/GM/QS&S/51 Dtd 24.11.2018) as per IS-785. ( Common SR - 2023-24, Item No 1.02 Page No 03/81 Material No -200106) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 9812.88 | 9812.88 | 30.0 | False | None | None | False | None | False | 294386.4 | 0 | 3409708 | 120479 | None | CSR 2023-24 Item No 2.02 PgNo 44 81Mat No -) | Erection of PolesErection of RCC/PSCC Pole of 9 to 10 Mtr long in a pit of 1.8 Mtr depth ( Common SR - 2023-24, Item No 2.02 Page No 44/81 Material No -) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 1313.34 | 1313.34 | 30.0 | False | None | None | False | None | False | 39400.2 | 0 | 3409709 | 120479 | None | CSR2023-24 Item No 1.05 PgNo 03 81Mat No -200004 | Line Supports (Pole)PSCC Pole - 8 Mtr Long, 200 Kg WL (Dwg No. BESCOM/GM/QS&S/49 Dtd 24.11.2018) as per REC Standards. ( Common SR - 2023-24, Item No 1.05 Page No 03/81 Material No -200004) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 4364.82 | 4364.82 | 10.0 | False | None | None | False | None | False | 43648.2 | 0 | 3409710 | 120479 | None | CSR 2023-24 Item No 2.01 PgNo 44 81Mat No - | Erection of PolesErection of RCC/PSCC Pole of 7.5 to 8 Mtr long in a pit of 1.5 Mtr depth ( Common SR - 2023-24, Item No 2.01 Page No 44/81 Material No -) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 1087.96 | 1087.96 | 10.0 | False | None | None | False | None | False | 10879.6 | 0 | 3409711 | 120479 | None | CSR2023-24 Item No 1.07 PgNo 03 81Mat No -200120 | Line Supports (Pole)Pre-Stressed Tubular Spun Pole - 11 Mtr Long, 500 Kg WL (Dwg No. BESCOM/GM/QS&S/45 Dtd 24.11.2018) as per IS-13158: 1991 ( Common SR - 2023-24, Item No 1.07 Page No 03/81 Material No -200120) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 20888.36 | 20888.36 | 6.0 | False | None | None | False | None | False | 125330.16 | 0 | 3409712 | 120479 | None | CSR 2023-24 Item No 2.05 PgNo 44 81Mat No - | Erection of PolesErection of 11 Mtr long Concrete Spun Pole in a pit of 2.5 Mtr depth (Mechnised Labour) ( Common SR - 2023-24, Item No 2.05 Page No 44/81 Material No -) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 3001.92 | 3001.92 | 6.0 | False | None | None | False | None | False | 18011.52 | 0 | 3409713 | 120479 | None | CSR2023-24 Item No 2.01 PgNo 03 81Mat No -279020 | 11 kV, Horizontal Cross Arm - Mild Steel (MS) (Dwg No. BESCOM/GM/QS&S/04 Dtd 24.11.2018). ( Common SR - 2023-24, Item No 2.01 Page No 03/81 Material No -279020) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 438.96 | 438.96 | 50.0 | False | None | None | False | None | False | 21948.0 | 0 | 3409714 | 120479 | None | CSR2023-24 Item No 2.11 PgNo 04 81Mat No -279092 | HT ST Support 50x6 mm Flat - MS (Dwg No. BESCOM/GM/QS&S/04 Dtd 24.11.2018). ( Common SR - 2023-24, Item No 2.11 Page No 04/81 Material No -279092) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 107.38 | 107.38 | 150.0 | False | None | None | False | None | False | 16107.0 | 0 | 3409715 | 120479 | None | CSR 2023-24 Item No 5.06 PgNo 45 81Mat No - | Fixing of HT/LT Single Top Support ( Common SR - 2023-24, Item No 5.06 Page No 45/81 Material No -) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Each | 132.16 | 132.16 | 150.0 | False | None | None | False | None | False | 19824.0 | 0 | 3409716 | 120479 | None | CSR2023-24 Item No 2.07 PgNo 04 81Mat No -279012 | LT 2 Pin Cross Arm - MS (Dwg No. BESCOM/GM/QS&S/32 Dtd 24.11.2018). ( Common SR - 2023-24, Item No 2.07 Page No 04/81 Material No -279012) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 155.76 | 155.76 | 30.0 | False | None | None | False | None | False | 4672.8 | 0 | 3409717 | 120479 | None | CSR2023-24 Item No 2.05 PgNo 04 81Mat No -279014 | LT 4 Pin Cross Arm - MS(Dwg No. BESCOM/GM/QS&S/32 Dtd 24.11.2018) ( Common SR - 2023-24, Item No 2.05 Page No 04/81 Material No -279014) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 341.02 | 341.02 | 30.0 | False | None | None | False | None | False | 10230.6 | 0 | 3409718 | 120479 | None | CSR2023-24 Item No 5.01 & 5.02 PgNo 45 81Mat No - | Fixing of 2 Pin cross arm with Insulator and Braces fixing / Fixing of 4 Pin cross arm with Insulator and Braces fixing ( Common SR - 2023-24, Item No 5.01 & 5.02 Page No 45/81 Material No -) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 188.8 | 188.8 | 110.0 | False | None | None | False | None | False | 20768.0 | 0 | 3409719 | 120479 | None | CSR 2023-24 Item No 6.1 PgNo 05 81Mat No -283320 | 11 kV, 45 kN Polymeric Insulator . ( Common SR - 2023-24, Item No 6.1 Page No 05/81 Material No -283320) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 219.48 | 219.48 | 48.0 | False | None | None | False | None | False | 10535.04 | 0 | 3409720 | 120479 | None | CSR2023-24 Item No 6.06 PgNo 05 81Mat No -283008 | 11 kV, 5 kN Composite/Polymeric Pin Insulator. ( Common SR - 2023-24, Item No 6.06 Page No 05/81 Material No -283008) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 241.9 | 241.9 | 60.0 | False | None | None | False | None | False | 14514.0 | 0 | 3409721 | 120479 | None | CSR2023-24 Item No 7.02 PgNo 05 81Mat No -284108 | Rabbit ACSR conductor ( Common SR - 2023-24, Item No 7.02 Page No 05/81 Material No -284108) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Km | 60731.06 | 60731.06 | 3.0 | False | None | None | False | None | False | 182193.18 | 0 | 3409722 | 120479 | None | CSR 2023-24 | Erection of 3 Phase, 11kV/433V, 63 kVA BEE - 4/5 Star Rated Distribution Transformer Centre Using 9 Mtr RCC Pole DPTC ( WithOut Transformer) - Cost Data Sheet - 25 ( Common SR - 2023-24, ) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Set | 115431.14 | 115431.14 | 5.0 | False | None | None | False | None | False | 577155.7 | 0 | 3409723 | 120479 | None | CSR2023-24 Item No 51.01 PgNo 22 81Mat No -281674 | GI Grounding pipe, B - Class, 42 mm dia, 2.5 Mtr long, 3.2 mm thick with bolt, nut, GI Strips and washer complete Minimum Weight of GI Pipe: 7.3 Kg ( Common SR - 2023-24, Item No 51.01 Page No 22/81 Material No -281674) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 880.28 | 880.28 | 10.0 | False | None | None | False | None | False | 8802.8 | 0 | 3409724 | 120479 | None | CSR2023-24 Item No 51.02 PgNo 22 81Mat No -600095 | Good Quality well burnt Charcoal for grounding purposes packed in non returnable gunny bag of 30 Kg each ( Common SR - 2023-24, Item No 51.02 Page No 22/81 Material No -600095) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 797.68 | 797.68 | 10.0 | False | None | None | False | None | False | 7976.8 | 0 | 3409725 | 120479 | None | CSR2023-24 Item No 51.03 PgNo 22 81Mat No -607054 | Good Quality Salt for grounding purposes packed in 50 Kg gunny bag ( Common SR - 2023-24, Item No 51.03 Page No 22/81 Material No -607054) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Bag | 365.8 | 365.8 | 10.0 | False | None | None | False | None | False | 3658.0 | 0 | 3409726 | 120479 | None | CSR2023-24 Item No 51.04 PgNo 23 81Mat No -281685 | Rod type of earthing using 40 mm Dia, 3 Mtr long MS rod as ground rod, in earth pit of 300 mm width and 3300 mm depth and using 50x6 mm flat welded to ground rod as terminal & connected to equipment ground terminal using PVC Al wire as specified ( Common SR - 2023-24, Item No 51.04 Page No 23/81 Material No -281685) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 2562.96 | 2562.96 | 10.0 | False | None | None | False | None | False | 25629.6 | 0 | 3409727 | 120479 | None | CSR 2023-24 Item No 1.2.2 PgNo 43 81Mat No | Digging of Pit - Digging of Pit 1.6 Mtr depth for erection of 7.5/8 Mtr Long Steel/RCC/PSCC supports as per approved Drawing. - Hard Soil ( Common SR - 2023-24, Item No 1.2.2 Page No 43/81 Material No -) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Per Pit | 1187.08 | 1187.08 | 115.0 | False | None | None | False | None | False | 136514.2 | 0 | 3409728 | 120479 | None | CSR 2023-24 Item No PgNo Mat No | R&R of 9mt pole ( Common SR - 2023-24, Item No Page No Material No -) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 2495.35 | 2495.35 | 70.0 | False | None | None | False | None | False | 174674.5 | 0 | 3409729 | 120479 | None | CSR 2023-24 Item No PgNo Mat No | R&R of X-Arm ( Common SR - 2023-24, Item No Page No Material No -) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 358.72 | 358.72 | 50.0 | False | None | None | False | None | False | 17936.0 | 0 | 3409730 | 120479 | None | CSR 2023-24 Item No PgNo Mat No | R&R of HTST ( Common SR - 2023-24, Item No Page No Material No -) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 251.1 | 251.1 | 200.0 | False | None | None | False | None | False | 50220.0 | 0 | 3409731 | 120479 | None | CSR 2023-24 Item No 7.02 & 7.04 PgNo 46 81Mat No | R&R of Rabbit ( Common SR - 2023-24, Item No 7.02 & 7.04 Page No 46/81 Material No -) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Km | 9880.14 | 9880.14 | 7.0 | False | None | None | False | None | False | 69160.98 | 0 |
| 1719647716000 | 0 | None | None | Roads | Maintenance of first year | 0.0 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3409732 | 120480 | None | Item No. 2.5 (ii) a Pg No. 9 Vol.03 Cmn SR 23-24 | Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness. (ii) By Mechanical Means using Dozer (a) In area of light jungle (Item No. 2.5 (ii) a/ Page No. 9/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3409733 | 120480 | None | Item No.16.19 Pg No. Vol.03 Cmn SR 23-24 | Maintenance of Drains - The maintenance of drains include erosion, repair, clearing, cleaning, reshaping, regrading, deepening of side drains as well as catch water drains as per technical specification Clause 1908. --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3409734 | 120480 | None | Item No.10.3 Pg No. Vol.03 Cmn SR 23-24 | Maintenance of Earth Shoulder (stripping excess soil) - Stripping excess soil from the shoulder surface to a minimum depth of 150mm to achieve the approved level and compacting with plate compactor including cost of materials, labour, HOM complete as per specifications. MORTH Specification No. 3003 --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3409735 | 120480 | None | Item No.10.2 Pg No. Vol.03 Cmn SR 23-24 | Maintenance of Earthen Shoulder (filling with fresh soil) - Making up loss of material I irregularities on shoulder to a minimum depth of 150mm to the design level by adding fresh approved soil and compacting it with appropriate equipment including cost of materials, labour, HOM complete as per specifications. MORTH Specification No.3003 --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3409736 | 120480 | None | Item No. 10.5 Pg No.91 Vol.03 Cmn SR 23-24 | Filling Pot-holes and Patch Repairs with Bituminous concrete, 40mm (using VG-30 Grade Bitumen) - Removal of all failed material, trimming of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 510 using HMP 40/60 TPH Capacity compacting, trimming and finishing the surface to form a smooth continuous surface, all as per clause 3004.2 - as per the direction of Engineer-in-charge.(Item No. 10.5/ Page No.91/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3409737 | 120480 | None | Cmn SR 23-24 V 1 Pg No.8. Item No.1.12 | Nala Training: Earth work in surface excavation by mechanical means for lowering & leveling the ground for all works other than foundation in all kinds of soils & upto depth not exceeding 300mm as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenances required to complete the work.. PWD, Bangalore, SR:2023-24 V 1 Page No.8. Item No.1.12) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 |
| 1719647716000 | 0 | None | None | Roads | Maintenance of second year | 0.0 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3409738 | 120481 | None | Item No. 2.5 (ii) a Pg No. 9 Vol.03 Cmn SR 23-24 | Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness. (ii) By Mechanical Means using Dozer (a) In area of light jungle (Item No. 2.5 (ii) a/ Page No. 9/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3409739 | 120481 | None | Item No.16.19 Pg No. Vol.03 Cmn SR 23-24 | Maintenance of Drains - The maintenance of drains include erosion, repair, clearing, cleaning, reshaping, regrading, deepening of side drains as well as catch water drains as per technical specification Clause 1908. --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3409740 | 120481 | None | Item No.10.3 Pg No. Vol.03 Cmn SR 23-24 | Maintenance of Earth Shoulder (stripping excess soil) - Stripping excess soil from the shoulder surface to a minimum depth of 150mm to achieve the approved level and compacting with plate compactor including cost of materials, labour, HOM complete as per specifications. MORTH Specification No. 3003 --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3409741 | 120481 | None | Item No.10.2 Pg No. Vol.03 Cmn SR 23-24 | Maintenance of Earthen Shoulder (filling with fresh soil) - Making up loss of material I irregularities on shoulder to a minimum depth of 150mm to the design level by adding fresh approved soil and compacting it with appropriate equipment including cost of materials, labour, HOM complete as per specifications. MORTH Specification No.3003 --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3409742 | 120481 | None | Item No. 10.5 Pg No.91 Vol.03 Cmn SR 23-24 | Filling Pot-holes and Patch Repairs with Bituminous concrete, 40mm (using VG-30 Grade Bitumen) - Removal of all failed material, trimming of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 510 using HMP 40/60 TPH Capacity compacting, trimming and finishing the surface to form a smooth continuous surface, all as per clause 3004.2 - as per the direction of Engineer-in-charge.(Item No. 10.5/ Page No.91/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3409743 | 120481 | None | Cmn SR 23-24 V 1 Pg No.8. Item No.1.12 | Nala Training: Earth work in surface excavation by mechanical means for lowering & leveling the ground for all works other than foundation in all kinds of soils & upto depth not exceeding 300mm as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenances required to complete the work.. PWD, Bangalore, SR:2023-24 V 1 Page No.8. Item No.1.12) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 |
| 1719647716000 | 1 | None | None | Roads | Maintenance of third year | 362060.51 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3409744 | 120482 | None | Item No. 2.5 (ii) a Pg No. 9 Vol.03 CSR 23-24 | Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness. (ii) By Mechanical Means using Dozer (a) In area of light jungle (Item No. 2.5 (ii) a/ Page No. 9/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 519.39 | 519.39 | 63.6 | False | None | None | False | None | False | 33033.204 | 0 | 3409745 | 120482 | None | Item No.16.19 Pg No. Vol.03 CSR 23-24 | Maintenance of Drains - The maintenance of drains include erosion, repair, clearing, cleaning, reshaping, regrading, deepening of side drains as well as catch water drains as per technical specification Clause 1908. --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | m | 7.93 | 7.93 | 4240.0 | False | None | None | False | None | False | 33623.2 | 0 | 3409746 | 120482 | None | Item No.10.3 Pg No. Vol.03 CSR 23-24 | Maintenance of Earth Shoulder (stripping excess soil) - Stripping excess soil from the shoulder surface to a minimum depth of 150mm to achieve the approved level and compacting with plate compactor including cost of materials, labour, HOM complete as per specifications. MORTH Specification No. 3003 --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 51.54 | 51.54 | 291.0 | False | None | None | False | None | False | 14998.14 | 0 | 3409747 | 120482 | None | Item No.10.2 Pg No. Vol.03 CSR 23-24 | Maintenance of Earthen Shoulder (filling with fresh soil) - Making up loss of material I irregularities on shoulder to a minimum depth of 150mm to the design level by adding fresh approved soil and compacting it with appropriate equipment including cost of materials, labour, HOM complete as per specifications. MORTH Specification No.3003 --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 128.2 | 128.2 | 970.0 | False | None | None | False | None | False | 124354.0 | 0 | 3409748 | 120482 | None | Item No. 10.5 Pg No.91 Vol.03 CSR 23-24 | Filling Pot-holes and Patch Repairs with Bituminous concrete, 40mm (using VG-30 Grade Bitumen) - Removal of all failed material, trimming of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 510 using HMP 40/60 TPH Capacity compacting, trimming and finishing the surface to form a smooth continuous surface, all as per clause 3004.2 - as per the direction of Engineer-in-charge.(Item No. 10.5/ Page No.91/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 563.0 | 563.0 | 169.75 | False | None | None | False | None | False | 95569.25 | 0 | 3409749 | 120482 | None | Item No. 16.22 Pg No. Vol.03 CSR 23-24 | Maintenance of Road Signs- Maintenance of road signs by way of cleaning and repainting of mandatory / requlatory / cautionary / informatory and place identifications sign board as perdrawings and technical specification Clause 1910 --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Km | 2622.05 | 2622.05 | 4.85 | False | None | None | False | None | False | 12716.9425 | 0 | 3409750 | 120482 | None | Item No. 16.24 i Pg No. Vol.03 CSR 23-24 | Maintenance of 200 m and km stones - Maintenance of 200 metre and km stones-Maintenance of 200 metre km stone by way of refiting of tilted stones repairing with cement mortar, cleaning, repairing and lettering on 200 metre km stone and 5th km stone as per drawing and technical specification Clause 1912 Painting two coats with synthetic enamel paint --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Km | 272.25 | 272.25 | 4.85 | False | None | None | False | None | False | 1320.4125 | 0 | 3409751 | 120482 | None | CSR 23-24 V 1 Pg No.8. Item No.1.12 | Nala Training: Earth work in surface excavation by mechanical means for lowering & leveling the ground for all works other than foundation in all kinds of soils & upto depth not exceeding 300mm as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenances required to complete the work.. PWD, Bangalore, SR:2023-24 V 1 Page No.8. Item No.1.12) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 125.55 | 125.55 | 315.0 | False | None | None | False | None | False | 39548.25 | 0 | 3409752 | 120482 | None | Item No. 8.1 Pg No. 64 Vol.03 CSR 23-24 | Painting two coats on New Concrete Surface : Painting two coats after filling the surface with synthetic enamel paint in all shades on new plastered concrete surfaces complete as per specifications. MORTH Specification No. 803 --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 144.05 | 144.05 | 47.88 | False | None | None | False | None | False | 6897.114 | 0 |
| 1719647716000 | 1 | None | None | Roads | Maintenance of forth year | 353289.39 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3409753 | 120483 | None | Item No. 2.5 (ii) a Pg No. 9 Vol.03 Cmn SR 23-24 | Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness. (ii) By Mechanical Means using Dozer (a) In area of light jungle (Item No. 2.5 (ii) a/ Page No. 9/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 537.94 | 537.94 | 63.6 | False | None | None | False | None | False | 34212.984 | 0 | 3409754 | 120483 | None | Item No.16.19 Pg No. Vol.03 Cmn SR 23-24 | Maintenance of Drains - The maintenance of drains include erosion, repair, clearing, cleaning, reshaping, regrading, deepening of side drains as well as catch water drains as per technical specification Clause 1908. --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | m | 8.21 | 8.21 | 4240.0 | False | None | None | False | None | False | 34810.4 | 0 | 3409755 | 120483 | None | Item No.10.3 Pg No. Vol.03 Cmn SR 23-24 | Maintenance of Earth Shoulder (stripping excess soil) - Stripping excess soil from the shoulder surface to a minimum depth of 150mm to achieve the approved level and compacting with plate compactor including cost of materials, labour, HOM complete as per specifications. MORTH Specification No. 3003 --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 53.38 | 53.38 | 291.0 | False | None | None | False | None | False | 15533.58 | 0 | 3409756 | 120483 | None | Item No.10.2 Pg No. Vol.03 Cmn SR 23-24 | Maintenance of Earthen Shoulder (filling with fresh soil) - Making up loss of material I irregularities on shoulder to a minimum depth of 150mm to the design level by adding fresh approved soil and compacting it with appropriate equipment including cost of materials, labour, HOM complete as per specifications. MORTH Specification No.3003 --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 132.77 | 132.77 | 970.0 | False | None | None | False | None | False | 128786.9 | 0 | 3409757 | 120483 | None | Item No. 10.5 Pg No.91 Vol.03 Cmn SR 23-24 | Filling Pot-holes and Patch Repairs with Bituminous concrete, 40mm (using VG-30 Grade Bitumen) - Removal of all failed material, trimming of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 510 using HMP 40/60 TPH Capacity compacting, trimming and finishing the surface to form a smooth continuous surface, all as per clause 3004.2 - as per the direction of Engineer-in-charge.(Item No. 10.5/ Page No.91/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 583.11 | 583.11 | 169.75 | False | None | None | False | None | False | 98982.9225 | 0 | 3409758 | 120483 | None | Cmn SR 23-24 V 1 Pg No.8. Item No.1.12 | Nala Training: Earth work in surface excavation by mechanical means for lowering & leveling the ground for all works other than foundation in all kinds of soils & upto depth not exceeding 300mm as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenances required to complete the work.. PWD, Bangalore, SR:2023-24 V 1 Page No.8. Item No.1.12) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 130.04 | 130.04 | 315.0 | False | None | None | False | None | False | 40962.6 | 0 |
| 1719647716000 | 0 | None | None | Roads | Maintenance of fifth year | 467898.27 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3409759 | 120484 | None | Item No. 2.5 (ii) a Pg No. 9 Vol.03 Cmn SR 23-24 | Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness. (ii) By Mechanical Means using Dozer (a) In area of light jungle (Item No. 2.5 (ii) a/ Page No. 9/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 556.49 | 556.49 | 63.6 | False | None | None | False | None | False | 35392.764 | 0 | 3409760 | 120484 | None | Item No.16.19 Pg No. Vol.03 Cmn SR 23-24 | Maintenance of Drains - The maintenance of drains include erosion, repair, clearing, cleaning, reshaping, regrading, deepening of side drains as well as catch water drains as per technical specification Clause 1908. --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | m | 8.5 | 8.5 | 4240.0 | False | None | None | False | None | False | 36040.0 | 0 | 3409761 | 120484 | None | Item No.10.3 Pg No. Vol.03 Cmn SR 23-24 | Maintenance of Earth Shoulder (stripping excess soil) - Stripping excess soil from the shoulder surface to a minimum depth of 150mm to achieve the approved level and compacting with plate compactor including cost of materials, labour, HOM complete as per specifications. MORTH Specification No. 3003 --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 55.22 | 55.22 | 291.0 | False | None | None | False | None | False | 16069.02 | 0 | 3409762 | 120484 | None | Item No.10.2 Pg No. Vol.03 Cmn SR 23-24 | Maintenance of Earthen Shoulder (filling with fresh soil) - Making up loss of material I irregularities on shoulder to a minimum depth of 150mm to the design level by adding fresh approved soil and compacting it with appropriate equipment including cost of materials, labour, HOM complete as per specifications. MORTH Specification No.3003 --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 137.35 | 137.35 | 970.0 | False | None | None | False | None | False | 133229.5 | 0 | 3409763 | 120484 | None | Item No. 10.5 Pg No.91 Vol.03 Cmn SR 23-24 | Filling Pot-holes and Patch Repairs with Bituminous concrete, 40mm (using VG-30 Grade Bitumen) - Removal of all failed material, trimming of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 510 using HMP 40/60 TPH Capacity compacting, trimming and finishing the surface to form a smooth continuous surface, all as per clause 3004.2 - as per the direction of Engineer-in-charge.(Item No. 10.5/ Page No.91/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 603.22 | 603.22 | 339.5 | False | None | None | False | None | False | 204793.19 | 0 | 3409764 | 120484 | None | Cmn SR 23-24 V 1 Pg No.8. Item No.1.12 | Nala Training: Earth work in surface excavation by mechanical means for lowering & leveling the ground for all works other than foundation in all kinds of soils & upto depth not exceeding 300mm as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenances required to complete the work.. PWD, Bangalore, SR:2023-24 V 1 Page No.8. Item No.1.12) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 134.52 | 134.52 | 315.0 | False | None | None | False | None | False | 42373.8 | 0 |
| 1719647716000 | 1 | None | None | Roads | Maintenance of sixth year | 20406098.82 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3409765 | 120485 | None | Item No 16.22 Pg No Vol03 CSR 23-24 | Maintenance of Road Signs- Maintenance of road signs by way of cleaning and repainting of mandatory / requlatory / cautionary / informatory and place identifications sign board as perdrawings and technical specification Clause 1910 --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Km | 2902.99 | 2902.99 | 5.3 | False | None | None | False | None | False | 15385.847 | 0 | 3409766 | 120485 | None | Item No 16.24 i Pg No Vol03 CSR 23-24 | Maintenance of 200 m and km stones - Maintenance of 200 metre and km stones-Maintenance of 200 metre km stone by way of refiting of tilted stones repairing with cement mortar, cleaning, repairing and lettering on 200 metre km stone and 5th km stone as per drawing and technical specification Clause 1912 Painting two coats with synthetic enamel paint --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Km | 301.42 | 301.42 | 5.3 | False | None | None | False | None | False | 1597.526 | 0 | 3409767 | 120485 | None | Item No 8.1 Pg No 64 Vol03 CSR 23-24 | Painting two coats on New Concrete Surface : Painting two coats after filling the surface with synthetic enamel paint in all shades on new plastered concrete surfaces complete as per specifications. MORTH Specification No. 803 --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 159.49 | 159.49 | 47.41 | False | None | None | False | None | False | 7561.4209 | 0 | 3409768 | 120485 | None | Item No 8.4 Pg No 64 Vol03 CSR 23-24 | Printing New Letter Printing New Letter and Figures of any Shade Printing new letter and figures of any shade with synthetic enamel paint black or any other approved colour to give an even shade-English and Roman (Item No. 8.4/ Page No. 64/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | cm | 1.32 | 1.32 | 1440.0 | False | None | None | False | None | False | 1900.8 | 0 | 3409769 | 120485 | None | Item No 5.3i Pg No Vol03 CSR 23-24 | Providing and applying tack coat with RS1 Bituminous Emulsion using emulsion pressure distributor at the rate of 0.20 kg/m2 on the prepared bituminous surface cleaned with mechanical broom --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 17.56 | 17.56 | 38461.64 | False | None | None | False | None | False | 675386.3984 | 0 | 3409770 | 120485 | None | Item No 5.17B Pg No Vol03 CSR 23-24 | Bituminous Concrete Grading II for traffic 20 MSA Providing and laying Bituminous Concrete with 40/60 TPH capacity hot mix plant using crushed aggregates of specified grading, premixed with bituminous binder VG-30, @ 5.4 per cent of mix and filler, transporting the hot mix to work site, laying with mechanical paver finisher to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respects (Item No. 5.16 C/ Page No. 38/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 16027.89 | 16027.89 | 1153.85 | False | None | None | False | None | False | 18493780.8765 | 0 | 3409771 | 120485 | None | Item No 8.15 Pg No Vol03 CSR 23-24 | Providing and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 g/m2 area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35:2015.The finished surface to be level, uniform and free from streaks and holes. --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 775.49 | 775.49 | 1209.7 | False | None | None | False | None | False | 938110.253 | 0 | 3409772 | 120485 | None | Item No 8.43 Pg No 74 Vol03 CSR 23-24 | Supplying and Fixing of Molded Shank Raised Pavement Markers / Cat's Eye made of polycarbonate and ABS moulded body and reflective panels with micro prismatic lens capable of providing total internal reflection of the light entering the lens face and shall support a load of 16000 kg tested in accordance to ASTM D 4280 Type H and complying to Specifications of Category A of MORTH Circular No RW/NH/33023/10-97 DO III Dt 11.06. 1997. The height, width and length shall not exceed 50 mm, 100 mm and 102 +/- 2 mm and with minimum reflective area of 13 cm2 on each side and the slope to the base shall be 35 +/- 5 degree. The strength of detachment of the integrated cylindrical shanks, (of diameter not less than 19 +/- 2 mm and height not less than 30+/- 2 mm) from the body is to be a minimum value of 500 Kg. Fixing will be by drilling holes on the road for the shanks to go inside, without nails and using epoxy resin based adhesive as per manufacturer's recommendation and complete as directed by the engineer.The contractor shall submit a two year warranty for satisfactory field performance including stipulated retro-reflectance of the reflecting panel, to the Engineer. (Item No. 8.43/ Page No. 74/Vol.03/Common SR-2023-24) --- Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | No | 534.07 | 534.07 | 510.0 | False | None | None | False | None | False | 272375.7 | 0 |
| 1719647716000 | 0 | None | None | Roads | PKG-785 (B)Improvements to road connecting from Maddur Taluk Satanooru - Muthathi - Halaguru to Mandya Ch60.5 KM to 66.00 KM road (K M Dhoddi sugar factory to Thittamelanahalli) in Selected reaches in Maddur Taluk of Mandya District. Road Estimate | 33597930.26 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3409773 | 120486 | None | Item No. 2.5 (ii) b Page No. 9 Vol.03 | Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness. (ii) By Mechanical Means using Dozer (a) In area of light jungle ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | 100 Sqm | 463.74 | 463.74 | 61.2 | False | None | None | False | None | False | 28380.888 | 0 | 3409774 | 120486 | None | Item No. 1.12 Page No. 8 Vol.01 | Earth work in surface excavation by mechanical means for lowering & leveling the ground for all works other than foundation in all kinds of soils & upto depth not exceeding 300mm as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenances required to complete the work. In all kinds of soils upto 300 mm depth ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 112.1 | 112.1 | 5628.61 | False | None | None | False | None | False | 630967.181 | 0 | 3409775 | 120486 | None | Item No. 10.15 (ii) Page No. 93 Vol.03 | Patching of Deep Potholes using WBM Gr l & SDBC Gr lI 25 mm thick: Patching of Deep Potholes 75mm thick by restoring the Granular Base course using material confirming to WBM Grade -I with 1ype Sereenings standards wherever necessary by manual means including trimming the pothole to the required shape and size, cleaning the pothole, applying Prime Coat (SS1) at 0.70 kg per m2 over the WBM surface and covering the surface with SDBC 25mm thick including lead, loading unloading, rolling and finishing etc., complete as per specification ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 586.46 | 586.46 | 146.25 | False | None | None | False | None | False | 85769.775 | 0 | 3409776 | 120486 | None | Item No. 1.7 Page No. 7 Vol.01 | Construction of Embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded with desired compaction. (Royalty shall be recovered at Rs. 60.00/m3 ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 140.42 | 140.42 | 4835.91 | False | None | None | False | None | False | 679058.4822 | 0 | 3409777 | 120486 | None | Item No. 1.8 Page No. 7 Vol.01 | Construction of Embankment by excavating the available approved Gravel/ Murrum deposited at a place or borrow pits during or prior excavation with all lifts and lead, transportation to site, spreading, grading to required slope and compacting to meet the requirement complete as per specifications, including cost of labour,rolling,water,all materials,usage& all other appurtenaces required to complete the work. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 559.32 | 559.32 | 1760.78 | False | None | None | False | None | False | 984839.4696 | 0 | 3409778 | 120486 | None | Item No. 3.6 Page No. 17 Vol.03 | Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2 ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 581.74 | 581.74 | 3397.55 | False | None | None | False | None | False | 1976490.737 | 0 | 3409779 | 120486 | None | Item No. 4.2 B (iii) Page No. 23 Vol.03 | Construction of Granular Sub-Base of required grading as per design spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with front end loader at OMC and compacting with vibratory roller to achieve the desired density, complete as per clause 401 By Mix in Place Method (v) For Grading -III Material ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 2813.12 | 2813.12 | 1077.75 | False | None | None | False | None | False | 3031840.08 | 0 | 3409780 | 120486 | None | Item No. 4.2 B (v) Page No. 23 Vol.03 | Construction of Granular Sub-Base of required grading as per design spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with front end loader at OMC and compacting with vibratory roller to achieve the desired density, complete as per clause 401 By Mix in Place Method (v) For Grading -V Material ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 2783.62 | 2783.62 | 775.26 | False | None | None | False | None | False | 2158029.2412 | 0 | 3409781 | 120486 | None | Item No. 4.17 Page No. 26 Vol.03 | Wet Mix Macadam (Plant Mix Method) Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver/grader in sub-base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 3019.62 | 3019.62 | 1583.01 | False | None | None | False | None | False | 4780088.6562 | 0 | 3409782 | 120486 | None | Item No. 5.1 A (i) Page No. 31 Vol.03 | Prime Coat over WMM/WBM Providing and applying primer coat with SS1 grade Bitumen Emulsion on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70 kg/m2 using mechanical means. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 48.38 | 48.38 | 5138.03 | False | None | None | False | None | False | 248577.8914 | 0 | 3409783 | 120486 | None | Item No. 5.4 Page No. 31 Vol.03 | Tack coat on Granular surface treated with primer Providing and applying tack coat with RS1 Bituminous Emulsion using emulsion pressure distributor at the rate of 0.25 kg/m2 on Granular surface ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 16.52 | 16.52 | 19748.73 | False | None | None | False | None | False | 326249.0196 | 0 | 3409784 | 120486 | None | Item No. 5.12 C Page No. 35 Vol.03 | Dense Graded Bituminous Macadam Grading - II for traffic 20 MSA Providing and laying Dense Graded Bituminous Macadam with 40/60 TPH capacity HMP using crushed aggregates of specified grading, premixed with bituminous binder VG-30, at 4.5 per cent by weight of total mix and filler, transporting the hot mix to work site, laying with mechanical paver finisher to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 505 complete in all respects. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 11149.82 | 11149.82 | 987.43 | False | None | None | False | None | False | 11009666.7626 | 0 | 3409785 | 120486 | None | Item No. 5.16 C Page No. 38 Vol.03 | Bituminous Concrete Grading II for traffic 20 MSA Providing and laying Bituminous Concrete with 40/60 TPH capacity hot mix plant using crushed aggregates of specified grading, premixed with bituminous binder VG-30, at 5.4 per cent of mix and filler, transporting the hot mix to work site, laying with mechanical paver finisher to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respects ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 12925.72 | 12925.72 | 592.46 | False | None | None | False | None | False | 7657972.0712 | 0 |
| 1719647716000 | 0 | None | None | Roads | ROAD SAFETY FURNITURES | 1275317.57 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3409786 | 120487 | None | Item No. 8.5 A (ii) Page No. 64 Vol.03 | Retro-Reflectorised Traffic Signs Providing and fixing of retro- reflectorised cautionary, mandatory and informatory sign as per IRC.67.2022 made of Class b Type XI retro reflective sheeting fixed over 2 mm thick aluminium sheeting vide clause 801.3, 3mm/4mm thick Aluminium composite material sheet depending on the size of the sign fixed over the back support frame of min 25 x 25 x 3mm angle mounted on a mild steel circular pipe 65 NB, 3.2 mm thickness firmly fixed to the ground by means of properly designed foundation with M25 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing.The sign shall be maintained as per section 12 of IRC.67.2022. (ii) 90 cm equilateral triangle ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Each | 5527.12 | 5527.12 | 20.0 | False | None | None | False | None | False | 110542.4 | 0 | 3409787 | 120487 | None | Item No. 8.5 A (xv) Page No. 65 Vol.03 | Retro-Reflectorised Traffic Signs Providing and fixing of retro- reflectorised cautionary, mandatory and informatory sign as per IRC:67:2022 made of Class BType XI retro reflective sheeting fixed over 2 mm thick aluminium sheeting vide clause 801.3, 3mm/4mm thick Aluminium composite material sheet depending on the size of the sign fixed over the back support frame of min 25 x 25 x 3mm angle mounted on a mild steel circular pipe 65 NB, 3.2 mm thickness firmly fixed to the ground by means of properly designed foundation with M25 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing.The sign shall be maintained as per section 12 of IRC:67:2022. (xv) 90 cm high octagon ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Each | 7672.36 | 7672.36 | 6.0 | False | None | None | False | None | False | 46034.16 | 0 | 3409788 | 120487 | None | Item No. 8.48 Page No. 76 Vol.03 | Chevron Boards Supply and installation of retro- reflective Chevron signboards of 600x450mm made out of cube corner micro prismatic grade sheeting confirming to Type XI standards of IRC:67:2022 & ASTM D 4956-09 specification & fixed over 3 mm thick Aluminium Composite Panel sheet having minimum 0.30 mm thick aluminum skin on both sides & fixed over back support frame of 25x25x3mm MS angle frame. Supported on 75 mm dia OR 75x75x6mm Mild steel with clear height of not less than 2.1 m from the ground level to the bottom of the Sign board & 60 cm below ground level. The sign post should be painted with one coat of red oxide paint and two coats of synthetic enamel paint of black and white colour with bands of 30 cm height, firmly fixed to the ground by means of foundation with M 20 grade cement, concrete foundation size of 45cm x 45 cm x 60 cm including cost & conveyance of all materials, equipment,machinery & Labour with all leads and lifts for satisfactory completion of the work as directed by Engineer incharge ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | No | 4231.48 | 4231.48 | 8.0 | False | None | None | False | None | False | 33851.84 | 0 | 3409789 | 120487 | None | Item No. 8.7 Page No. 65 Vol.03 | Direction and Place Identification Signs upto 0.9 m2 Size Board. Providing and erecting direction and place identification retroreflectorised sign as per IRC:67:2022 made of high intensity grade sheeting vide clause 801.3, fixed over aluminium sheeting, 2 mm thick or Aluminium composite material sheet with overall thickness of 4mm with area not exceeding 0.9 m2 fixed over back support frame of min 35 x 35 x 3mm angle mounted on a mild steel circular pipe 65 NB, firmly fixed to the ground by means of properly designed foundation with M25 grade cement concrete 45 x 45 x 60 cm, 60 cm below ground level as per approved drawing ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 10631.8 | 10631.8 | 2.16 | False | None | None | False | None | False | 22964.688 | 0 | 3409790 | 120487 | None | Item No. 8.15 Page No. 67 Vol.03 | Road Marking with Hot Applied Thermoplastic Compound with Reflectorising Glass Beads on Bituminous Surface Providing and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads at 250 g/m2 area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35:2015.The finished surface to be level, uniform and free from streaks and holes. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 625.4 | 625.4 | 657.9 | False | None | None | False | None | False | 411450.66 | 0 | 3409791 | 120487 | None | Item No. 8.43 Page No. 74 Vol.03 | Supplying and Fixing of Molded Shank Raised Pavement Markers / Cats Eye made of polycarbonate and ABS moulded body and reflective panels with micro prismatic lens capable of providing total internal reflection of the light entering the lens face and shall support a load of 16000 kg tested in accordance to ASTM D 4280 Type H and complying to Specifications of Category A of MORTH Circular No RW/NH/33023/10-97 DO III Dt 11.06. 1997. The height, width and length shall not exceed 50 mm, 100 mm and 102 2 mm and with minimum reflective area of 13 cm2 on each side and the slope to the base shall be 35 5 degree. The strength of detachment of the integrated cylindrical shanks, (of diameter not less than 19 2 mm and height not less than 30. 2 mm) from the body is to be a minimum value of 500 Kg. Fixing will be by drilling holes on the road for the shanks to go inside, without nails and using epoxy resin based adhesive as per manufacturers recommendation and complete as directed by the engineer.The contractor shall submit a two year warranty for satisfactory field performance including stipulated retro-reflectance of the reflecting panel, to the Engineer ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | No | 430.7 | 430.7 | 300.0 | False | None | None | False | None | False | 129210.0 | 0 | 3409792 | 120487 | None | Item No. 16.29 Page No. 149 Vol.03 | Project Display Board
i) The board will be a composite unit consisting of three plates of Aluminium Composite Materials (ACM), material specifications as per Clause 1701.3.7. The top most platewill be in Rectangular shape of 600mm x 600 mm size, riveted over welded M.S. angle iron frame of 25 mm x 25mm x 5 mm size on back on edges. The middle plate will be 1200 mm x 150 mm size riveted over welded M.S. angle iron frame of 25mm x 25mmx 5 mm size on back on edges. The main lower most plate will be 1500 mm x 600 mm size, riveted over welded M.S. angle iron frame of 25 mm x 25 mm x 5 mm size. Welding of all the sheets over angle iron frame will be done neatly to have plain surface on one side. The angle iron frames of the lower most plate and the middle plate will be welded to two nos. 75 mm x 75 mm (12 SWG) sheet tubes posts placed at 1125 mm apart centre to centre. The top of the middle plate will be flushed with the top of 75 mm dia medium steel tube posts and these posts will be embedded in cement concrete M15 grade blocks of 450 mm x 450 mm x 600 mm below ground level. The height of bottom of the lower most plate will be 1200 mm from normal ground level and the bottom of middle plate will be 100 mm above the top level of the lower most plate. The Rectangular shaped plate mounted over angle iron frame will be connected to middle plate by square medium steel section of 47 mm x 47 mm thickness 12 SWG having a spacing of 100 mm between the Rectangular shaped plate and middle plate and this square section will be welded to the bottom point of the Rectangular shaped plate. (ii) The lettering and borders, etc. of middle and bottom plate, SHDP logo on top plate shall be as per clause 1701.4.6 essages/Borders. All the sections of frame and posts will be painted with primer and two coats of Epoxy paint. The steel tube below ground level will be painted with three coats of Epoxy paint. The design, painting and lettering shall be done as per approved drawing. (iii) For warranty and durability the clause 1701.5 and for maintenance the clause 1911 shall be applicable. (iv) A reference number along with the month and year of installation should be placed on the back of a sign in
a contrasting colour or by stamping in characters not exceeding 50 mm in height.485777/2019/Dir(Tech) 7Retro Reflective Trafic Sign As per IRC 67 Clause 1701.3.8.1 Class A Type 1 (Item No. 16.29/ Page No. 149/Vol.03/Common SR-2023-24) - Including cost of all materials, with all lead lift and labour charges, complete as directed by the Engineer-in-charge of the work."
---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 18115.36 | 18115.36 | 1.0 | False | None | None | False | None | False | 18115.36 | 0 | 3409793 | 120487 | None | Item No. 8.16 (i) Page No. 67 Vol.03 | Reinforced cement concrete M15grade kilometre stone of standard design as per IRC:8-1980, fixing in position including painting and printing etc 5th kilometre stone (precast) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Each | 5995.58 | 5995.58 | 1.0 | False | None | None | False | None | False | 5995.58 | 0 | 3409794 | 120487 | None | Item No. 8.16 (ii)Page No. 67 Vol.03 | Reinforced cement concrete M15grade kilometre stone of standard design as per IRC:8-1980, fixing in position including painting and printing etc Ordinary kilometer stone (precast) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Each | 3453.86 | 3453.86 | 2.0 | False | None | None | False | None | False | 6907.72 | 0 | 3409795 | 120487 | None | Item No. 8.16 (iii) Page No. 67Vol.03 | Reinforced cement concrete M15grade kilometre stone of standard design as per IRC:8-1980, fixing in position including painting and printing etc 200 m stone (precast) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Each | 993.56 | 993.56 | 10.0 | False | None | None | False | None | False | 9935.6 | 0 | 3409796 | 120487 | None | Item No. 8.17 Page No. 8.17 Vol.03 | Road DelineatorsSupplying and installation of delineators (road way indicators, hazard markers, object markers), 80-100 cm high above ground level, painted black and white in 15 cm wide strips, fitted with 80 x 100 mm rectangular or 75 mm dia circular reflectorised panels at the top, buried or pressed into the ground and conforming to IRC-79-2019 and the drawings. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Each | 2384.78 | 2384.78 | 24.0 | False | None | None | False | None | False | 57234.72 | 0 | 3409797 | 120487 | None | Item No. 8.25 (i) Page No. 69 Vol.03 | Providing and erecting a W metal beam crash barrier system comprising of 3 mm thick corrugated sheet metal beam rail, 70 cm above road/ground level, fixed on ISMC series channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to centre, 1.8 m high, 1.1 m below ground/road level, all steel parts and fitments to be galvanised by hot dip process, all fittings to conform to IS:1367 and IS:1364, metal beam rail to be fixed on the vertical post with a spacer of channel section 150 x 75 x 5 mm, 330 mm long complete as per clause 811 ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | m | 4295.2 | 4295.2 | 70.0 | False | None | None | False | None | False | 300664.0 | 0 | 3409798 | 120487 | None | Item No. 8.60.2 (iii) Page No. 80 Vol.03 | Providing Speed Breakers/Raised pedestrian crossings in Trapezoidal section with 2.5 m Top width and transition length of 0.8 m length and height of 0.1 m as per IRC 99:2018 using Dense Bituminous Macadam (DBM) Gr II and Bituminous Concrete (BC) Gr II for entire formation width & WBM Gr II for Shoulder hump portion only (150 mm thick), completing with road marking paint with applied thermoplastic compound with reflecting glass beeds on bituminous surface and providing 2 Nos. retro reflective traffic signs as per IRC 67 -2022 Two lane with formation width of 9.00 m ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | No | 61205.42 | 61205.42 | 2.0 | False | None | None | False | None | False | 122410.84 | 0 |
| 1719647716000 | 0 | None | None | Roads | Construction of Box Culverts | 391926.1 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3409799 | 120488 | None | Item No. 2.11 (ii) A Page No. 10 Vol.03 | Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead By Mechanical Means (A)Dismantling Brick / Tile work / rubble masonry / pitching / etc bymechanical means ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 212.4 | 212.4 | 5.92 | False | None | None | False | None | False | 1257.408 | 0 | 3409800 | 120488 | None | Item No. 2.17 (ix) BPage No. 11 Vol.03 | Removing all type of Hume Pipes and Stacking including Earthwork and Dismantling of Masonry Works. Above 600 mm to 900 mm dia ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | m | 1293.28 | 1293.28 | 10.0 | False | None | None | False | None | False | 12932.8 | 0 | 3409801 | 120488 | None | Item No. 1.14 Page No. 8 Vol.01 | Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 120.36 | 120.36 | 31.2 | False | None | None | False | None | False | 3755.232 | 0 | 3409802 | 120488 | None | Item No. 2.1.3 Page No. 15 Vol.01 | Providing and laying in Position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 7067.02 | 7067.02 | 4.32 | False | None | None | False | None | False | 30529.5264 | 0 | 3409803 | 120488 | None | Item No. 2.4.3 Page No. 16 Vol.01 | Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 8971.78 | 8971.78 | 15.66 | False | None | None | False | None | False | 140498.0748 | 0 | 3409804 | 120488 | None | Item No. 2.5.2 Page No. 16 Vol.01 | Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 9689.69 | 9689.69 | 5.38 | False | None | None | False | None | False | 52130.5322 | 0 | 3409805 | 120488 | None | Item No. 2.11 h Page No. 18 Vol.01 | Supplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. All other type of structures ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 93232.98 | 93232.98 | 1.61 | False | None | None | False | None | False | 150105.0978 | 0 | 3409806 | 120488 | None | Item No. 8.10 Page No. 66 Vol.03 | Painting Two Coats on New Concrete Surfaces Painting two coats after filling the surface with synthetic enamel paint in all shades on new plastered concrete surfaces ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 128.62 | 128.62 | 3.6 | False | None | None | False | None | False | 463.032 | 0 | 3409807 | 120488 | None | Item No. 8.4 Page No. 64 Vol.03 | Printing New Letter Printing New Letter and Figures of any Shade Printing new letter and figures of any shade with synthetic enamel paint black or any other approved colour to give an even shade-English and Roman ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | cm | 1.06 | 1.06 | 240.0 | False | None | None | False | None | False | 254.4 | 0 |
| 1719647716000 | 0 | None | None | Roads | Maintenance of first year | 0.0 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3409808 | 120489 | None | 2.5(ii) a | Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness. By Mechanical Means using Dozer A) In area of light jungle Inclusive of all lift and leads and all complete as per direction of Engineer-in-charge.
UNI SR 2023-24, V-3, Page No. 9, Item No. 2.5(ii) a (Quantity to be executed 43.36) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | 100 Sqm | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3409809 | 120489 | None | 16.19 | Maintenance of Drains - The maintenance of drains include erosion, repair, clearing, cleaning, reshaping, regrading, deepening of side drains as well as catch water drains as per technical specification Clause 1908. Inclusive of all lift and leads and all complete as per direction of Engineer-in-charge.
UNI SR 2023-24, V-3, Page No. 147, Item No. 16.19 (Quantity to be executed 3252) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Rmtr | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3409810 | 120489 | None | 10.3 | Maintenance of Earth Shoulder (stripping excess soil)-Stripping excess soil from the shoulder surface to a minimum depth of 150mm to achieve the approved level and compacting with plate compactor including cost of materials, labour, HOM complete as per specifications. MORTH Specification No. 3003. Inclusive of all lift and leads and all complete as per direction of Engineer-in-charge.
UNI SR 2023-24, V-3, Page No. 91, Item No. 10.3(Quantity to be executed =2710) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3409811 | 120489 | None | 10.2 | Maintenance of Earthen Shoulder (filling with fresh soil) - Making up loss of material I irregularities on shoulder to a minimum depth of 150mm to the design level by adding fresh approved soil and compacting it with appropriate equipment including cost of materials, labour, HOM complete as per specifications etc. MORTH Specification No.3003. Inclusive of all lift and leads and all complete as per direction of Engineer-in-charge.
UNI SR 2023-24, V-3, Page No. 91, Item No. 10.2.(Quantity to be executed =2710) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3409812 | 120489 | None | 10.5 | Filling Pot-holes and Patch Repairs with BituminousRemoval of all failed material, trimming of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 504 using HMP 40/60 TPH Capacity compacting, trimming and finishing the surface to form a smooth continuous surface, all as per clause 3004.2
UNI SR 2023-24, V-3, Page No. 91, Item No. 10.5.(Quantity to be executed =298.10) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3409813 | 120489 | None | 1.12 | Nala Training: Earthwork in surface excavation by mechanical means for lowering & leveling the ground for all works other than foundation in all kinds of soils & upto depth not exceeding 300mm as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking thes elected earth for re use inaradius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenances required to complete the work.In all kinds of soils upto 300 mm depthUNI SR 2023-24, V-1, Page No. 8, Item No. 1.12(Quantity to be executed =225) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 |
| 1719647716000 | 0 | None | None | Roads | Maintenance of second year | 0.0 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3409814 | 120490 | None | 2.5(ii) a | Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness. By Mechanical Means using Dozer A) In area of light jungle Inclusive of all lift and leads and all complete as per direction of Engineer-in-charge.
UNI SR 2023-24, V-3, Page No. 9, Item No. 2.5(ii) a(Quantity to be executed =65.04) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | 100 Sqm | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3409815 | 120490 | None | 16.19 | Maintenance of Drains - The maintenance of drains include erosion, repair, clearing, cleaning, reshaping, regrading, deepening of side drains as well as catch water drains as per technical specification Clause 1908. Inclusive of all lift and leads and all complete as per direction of Engineer-in-charge.
UNI SR 2023-24, V-3, Page No. 147, Item No. 16.19(Quantity to be executed =4336) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Rmtr | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3409816 | 120490 | None | 10.3 | Maintenance of Earth Shoulder (stripping excess soil) - Stripping excess soil from the shoulder surface to a minimum depth of 150mm to achieve the approved level and compacting with plate compactor including cost of materials, labour, HOM complete as per specifications. MORTH Specification No. 3003 . Inclusive of all lift and leads and all complete as per direction of Engineer-in-charge.
UNI SR 2023-24, V-2, Page No. 91, Item No. 10.3.(Quantity to be executed =813) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3409817 | 120490 | None | 10.2 | Maintenance of Earthen Shoulder (filling with fresh soil) - Making up loss of material I irregularities on shoulder to a minimum depth of 150mm to the design level by adding fresh approved soil and compacting it with appropriate equipment including cost of materials, labour, HOM complete as per specifications etc. MORTH Specification No.3003. Inclusive of all lift and leads and all complete as per direction of Engineer-in-charge.
UNI SR 2023-24, V-3, Page No. 91, Item No. 10.2.(Quantity to be executed =2710) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3409818 | 120490 | None | 10.5 | Filling Pot-holes and Patch Repairs with BituminousRemovalofallfailedmaterial,trimmingofcompletedexcavationtoprovidefirmverticalfaces,cleaningofsurface,paintingoftackcoatonthesidesandbaseofexcavationasperclause503,backfillingthepotholeswithhotbituminousmaterialasperclause504usingHMP40/60TPHCapacitycompacting,trimmingandfinishingthesurfacetoformasmoothcontinuoussurface,allasperclause 3004.2
UNI SR 2023-24, V-3, Page No. 91, Item No. 10.5(Quantity to be executed =379.40) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 | 3409819 | 120490 | None | 1.12 | Nala Training : Earth work in surface excavation by mechanical means for lowering & leveling the ground for all works other than foundation in all kinds of soils & upto depth not exceeding 300mm as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenances required to complete the work.In all kinds of soils upto 300 mm depth
UNI SR 2023-24, V-1, Page No. 8, Item No. 1.12(Quantity to be executed =225) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 0.01 | 0.01 | 0.01 | False | None | None | False | None | False | 0.0001 | 0 |
| 1719647716000 | 0 | None | None | Roads | Maintenance of third year | 205664.79 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3409820 | 120491 | None | Item No. 2.5 (ii) b Page No. 9 Vol.03 | Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness. (ii) By Mechanical Means using Dozer (a) In area of light jungle ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 519.39 | 519.39 | 30.6 | False | None | None | False | None | False | 15893.334 | 0 | 3409821 | 120491 | None | Item No. 16.19 Page No.147 Vol.03 | Maintenance of Drains - The maintenance of drains include erosion, repair, clearing, cleaning, reshaping, regrading, deepening of side drains as well as catch water drains as per technical specification Clause 1908 ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Rmtr | 7.93 | 7.93 | 2040.0 | False | None | None | False | None | False | 16177.2 | 0 | 3409822 | 120491 | None | Item No. 10.3 Page No.91 Vol.03 | Maintenance of Earth Shoulder (stripping excess soil) - Stripping excess soil from the shoulder surface to a minimum depth of 150mm to achieve the approved level and compacting with plate compactor including cost of materials, labour, HOM complete as per specifications. MORTH Specification No. 3003 ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 51.54 | 51.54 | 229.5 | False | None | None | False | None | False | 11828.43 | 0 | 3409823 | 120491 | None | Item No. 10.2 Page No.91 Vol.03 | Maintenance of Earthen Shoulder (filling with fresh soil) - Making up loss of material I irregularities on shoulder to a minimum depth of 150mm to the design level by adding fresh approved soil and compacting it with appropriate equipment including cost of materials, labour, HOM complete as per specifications. MORTH Specification No.3003 ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 128.2 | 128.2 | 765.0 | False | None | None | False | None | False | 98073.0 | 0 | 3409824 | 120491 | None | Item No. 10.5 Page No.91 Vol.03 | Filling Pot-holes and Patch Repairs with Bituminous concrete, 40mm (using VG-30 Grade Bitumen) - Removal of all failed material, trimming of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 510 using HMP 40/60 TPH Capacity compacting, trimming and finishing the surface to form a smooth continuous surface, all as per clause 3004.2 - as per the direction of Engineer-in-charge. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 563.0 | 563.0 | 89.25 | False | None | None | False | None | False | 50247.75 | 0 | 3409825 | 120491 | None | Item No. 16.22 Page No.147 Vol.03 | Maintenance of Road Signs- Maintenance of road signs by way of cleaning and repainting of mandatory / requlatory / cautionary / informatory and place identifications sign board as perdrawings and technical specification Clause 1910 ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Km | 2622.05 | 2622.05 | 2.55 | False | None | None | False | None | False | 6686.2275 | 0 | 3409826 | 120491 | None | Item No. 16.24i Page No.148 Vol.03 | Maintenance of 200 m and km stones - Maintenance of 200 metre and km stones-Maintenance of 200 metre km stone by way of refiting of tilted stones repairing with cement mortar, cleaning, repairing and lettering on 200 metre km stone and 5th km stone as per drawing and technical specification Clause 1912 Painting two coats with synthetic enamel paint ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Km | 272.25 | 272.25 | 2.55 | False | None | None | False | None | False | 694.2375 | 0 | 3409827 | 120491 | None | V 1 Page No.8. Item No.1.12 | Nala Training: Earth work in surface excavation by mechanical means for lowering & leveling the ground for all works other than foundation in all kinds of soils & upto depth not exceeding 300mm as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenances required to complete the work ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 125.55 | 125.55 | 45.0 | False | None | None | False | None | False | 5649.75 | 0 | 3409828 | 120491 | None | Item No. 8.1 Page No.66 Vol.03 | Painting two coats on New Concrete Surface : Painting two coats after filling the surface with synthetic enamel paint in all shades on new plastered concrete surfaces complete as per specifications. MORTH Specification No. 803 ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 144.05 | 144.05 | 2.88 | False | None | None | False | None | False | 414.864 | 0 |
| 1719647716000 | 0 | None | None | Roads | Maintenance of forth year | 204923.49 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3409829 | 120492 | None | Item No. 2.5 (ii) b Page No. 9 Vol.03 | Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness. (ii) By Mechanical Means using Dozer (a) In area of light jungle ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 537.94 | 537.94 | 30.6 | False | None | None | False | None | False | 16460.964 | 0 | 3409830 | 120492 | None | Item No. 16.19 Page No.147 Vol.03 | Maintenance of Drains - The maintenance of drains include erosion, repair, clearing, cleaning, reshaping, regrading, deepening of side drains as well as catch water drains as per technical specification Clause 1908 ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Rmtr | 8.21 | 8.21 | 2040.0 | False | None | None | False | None | False | 16748.4 | 0 | 3409831 | 120492 | None | Item No. 10.3 Page No.91 Vol.03 | Maintenance of Earth Shoulder (stripping excess soil) - Stripping excess soil from the shoulder surface to a minimum depth of 150mm to achieve the approved level and compacting with plate compactor including cost of materials, labour, HOM complete as per specifications. MORTH Specification No. 3003 ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 53.38 | 53.38 | 229.5 | False | None | None | False | None | False | 12250.71 | 0 | 3409832 | 120492 | None | Item No. 10.2 Page No.91 Vol.03 | Maintenance of Earthen Shoulder (filling with fresh soil) - Making up loss of material I irregularities on shoulder to a minimum depth of 150mm to the design level by adding fresh approved soil and compacting it with appropriate equipment including cost of materials, labour, HOM complete as per specifications. MORTH Specification No.3003 ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 132.77 | 132.77 | 765.0 | False | None | None | False | None | False | 101569.05 | 0 | 3409833 | 120492 | None | Item No. 10.5 Page No.91 Vol.03 | Filling Pot-holes and Patch Repairs with Bituminous concrete, 40mm (using VG-30 Grade Bitumen) - Removal of all failed material, trimming of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 510 using HMP 40/60 TPH Capacity compacting, trimming and finishing the surface to form a smooth continuous surface, all as per clause 3004.2 - as per the direction of Engineer-in-charge. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 583.11 | 583.11 | 89.25 | False | None | None | False | None | False | 52042.5675 | 0 | 3409834 | 120492 | None | V 1 Page No.8. Item No.1.12 | Nala Training: Earth work in surface excavation by mechanical means for lowering & leveling the ground for all works other than foundation in all kinds of soils & upto depth not exceeding 300mm as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenances required to complete the work ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 130.04 | 130.04 | 45.0 | False | None | None | False | None | False | 5851.8 | 0 |
| 1719647716000 | 0 | None | None | Roads | Maintenance of fifth year | 265842.5 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3409835 | 120493 | None | Item No. 2.5 (ii) b Page No. 9 Vol.03 | Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness. (ii) By Mechanical Means using Dozer (a) In area of light jungle ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 556.49 | 556.49 | 30.6 | False | None | None | False | None | False | 17028.594 | 0 | 3409836 | 120493 | None | Item No. 16.19 Page No.147 Vol.03 | Maintenance of Drains - The maintenance of drains include erosion, repair, clearing, cleaning, reshaping, regrading, deepening of side drains as well as catch water drains as per technical specification Clause 1908 ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Rmtr | 8.5 | 8.5 | 2040.0 | False | None | None | False | None | False | 17340.0 | 0 | 3409837 | 120493 | None | Item No. 10.3 Page No.91 Vol.03 | Maintenance of Earth Shoulder (stripping excess soil) - Stripping excess soil from the shoulder surface to a minimum depth of 150mm to achieve the approved level and compacting with plate compactor including cost of materials, labour, HOM complete as per specifications. MORTH Specification No. 3003 ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 55.22 | 55.22 | 229.5 | False | None | None | False | None | False | 12672.99 | 0 | 3409838 | 120493 | None | Item No. 10.2 Page No.91 Vol.03 | Maintenance of Earthen Shoulder (filling with fresh soil) - Making up loss of material I irregularities on shoulder to a minimum depth of 150mm to the design level by adding fresh approved soil and compacting it with appropriate equipment including cost of materials, labour, HOM complete as per specifications. MORTH Specification No.3003 ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 137.35 | 137.35 | 765.0 | False | None | None | False | None | False | 105072.75 | 0 | 3409839 | 120493 | None | Item No. 10.5 Page No.91 Vol.03 | Filling Pot-holes and Patch Repairs with Bituminous concrete, 40mm (using VG-30 Grade Bitumen) - Removal of all failed material, trimming of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 510 using HMP 40/60 TPH Capacity compacting, trimming and finishing the surface to form a smooth continuous surface, all as per clause 3004.2 - as per the direction of Engineer-in-charge. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 603.22 | 603.22 | 178.5 | False | None | None | False | None | False | 107674.77 | 0 | 3409840 | 120493 | None | V 1 Page No.8. Item No.1.12 | Nala Training: Earth work in surface excavation by mechanical means for lowering & leveling the ground for all works other than foundation in all kinds of soils & upto depth not exceeding 300mm as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenances required to complete the work ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 134.52 | 134.52 | 45.0 | False | None | None | False | None | False | 6053.4 | 0 |
| 1719647716000 | 1 | None | None | Roads | SIXTH YEAR | 10522156.07 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3409841 | 120494 | None | Item No. 16.22 Page No.147 Vol.03 | Maintenance of Road Signs- Maintenance of road signs by way of cleaning and repainting of mandatory / requlatory / cautionary / informatory and place identifications sign board as perdrawings and technical specification Clause 1910 ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Km | 2902.99 | 2902.99 | 2.55 | False | None | None | False | None | False | 7402.6245 | 0 | 3409842 | 120494 | None | Item No. 16.24i Page No.148 Vol.03 | Maintenance of 200 m and km stones - Maintenance of 200 metre and km stones-Maintenance of 200 metre km stone by way of refiting of tilted stones repairing with cement mortar, cleaning, repairing and lettering on 200 metre km stone and 5th km stone as per drawing and technical specification Clause 1912 Painting two coats with synthetic enamel paint ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Km | 301.42 | 301.42 | 2.55 | False | None | None | False | None | False | 768.621 | 0 | 3409843 | 120494 | None | Item No. 8.1 Page No.66 Vol.03 | Painting two coats on New Concrete Surface : Painting two coats after filling the surface with synthetic enamel paint in all shades on new plastered concrete surfaces complete as per specifications. MORTH Specification No. 803 ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 159.49 | 159.49 | 3.6 | False | None | None | False | None | False | 574.164 | 0 | 3409844 | 120494 | None | Item No. 8.4 Page No. 64 Vol.03 | Printing New Letter Printing New Letter and Figures of any Shade Printing new letter and figures of any shade with synthetic enamel paint black or any other approved colour to give an even shade-English and Roman ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | cm | 1.32 | 1.32 | 240.0 | False | None | None | False | None | False | 316.8 | 0 | 3409845 | 120494 | None | Item No. 5.3i Page No.31 Vol.03 | Providing and applying tack coat with RS1 Bituminous Emulsion using emulsion pressure distributor at the rate of 0.20 kg/m2 on the prepared bituminous surface cleaned with mechanical broom ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 17.56 | 17.56 | 19748.73 | False | None | None | False | None | False | 346787.6988 | 0 | 3409846 | 120494 | None | Item No. 5.16 C Page No. 38 Vol.03 | Bituminous Concrete Grading II for traffic 20 MSA Providing and laying Bituminous Concrete with 40/60 TPH capacity hot mix plant using crushed aggregates of specified grading, premixed with bituminous binder VG-30, @ 5.4 per cent of mix and filler, transporting the hot mix to work site, laying with mechanical paver finisher to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respects ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Cum | 16027.89 | 16027.89 | 592.46 | False | None | None | False | None | False | 9495883.7094 | 0 | 3409847 | 120494 | None | Item No. 8.15 Page No.67 Vol.03 | Providing and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 g/m2 area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35:2015.The finished surface to be level, uniform and free from streaks and holes ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Sqm | 775.5 | 775.5 | 657.9 | False | None | None | False | None | False | 510201.45 | 0 | 3409848 | 120494 | None | Item No. 8.43 Page No. 74 Vol.03 | Supplying and Fixing of Molded Shank Raised Pavement Markers / Cat's Eye made of polycarbonate and ABS moulded body and reflective panels with micro prismatic lens capable of providing total internal reflection of the light entering the lens face and shall support a load of 16000 kg tested in accordance to ASTM D 4280 Type H and complying to Specifications of Category A of MORTH Circular No RW/NH/33023/10-97 DO III Dt 11.06. 1997. The height, width and length shall not exceed 50 mm, 100 mm and 102 +/- 2 mm and with minimum reflective area of 13 cm2 on each side and the slope to the base shall be 35 +/- 5 degree. The strength of detachment of the integrated cylindrical shanks, (of diameter not less than 19 2 mm and height not less than 30 2 mm) from the body is to be a minimum value of 500 Kg. Fixing will be by drilling holes on the road for the shanks to go inside, without nails and using epoxy resin based adhesive as per manufacturer's recommendation and complete as directed by the engineer.The contractor shall submit a two year warranty for satisfactory field performance including stipulated retro-reflectance of the reflecting panel, to the Engineer. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | No | 534.07 | 534.07 | 300.0 | False | None | None | False | None | False | 160221.0 | 0 |
| 1719647716000 | 0 | None | None | Roads | Electrical Pole Shifting | 1217624.15 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3409849 | 120495 | None | Item No 1.02 Page No 03 81 Material No 200106 | Line Supports (Pole)RCC Pole - 9 Mtr Long, 150 Kg WL Sq Section (Dwg No. BESCOM/GM/QS&S/51 Dtd 24.11.2018) as per IS-785 ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 9812.88 | 9812.88 | 21.0 | False | None | None | False | None | False | 206070.48 | 0 | 3409850 | 120495 | None | Item No 2.02 Page No 44 81 Material No | Erection of PolesErection of RCC/PSCC Pole of 9 to 10 Mtr long in a pit of 1.8 Mtr depth ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 1313.34 | 1313.34 | 21.0 | False | None | None | False | None | False | 27580.14 | 0 | 3409851 | 120495 | None | Item No 1.05 Page No 03 81 Material No 200004 | Line Supports (Pole)PSCC Pole - 8 Mtr Long, 200 Kg WL (Dwg No. BESCOM/GM/QS&S/49 Dtd 24.11.2018) as per REC Standards. ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 4364.82 | 4364.82 | 7.0 | False | None | None | False | None | False | 30553.74 | 0 | 3409852 | 120495 | None | Item No 2.01 Page No 44 81 Material No | Erection of PolesErection of RCC/PSCC Pole of 7.5 to 8 Mtr long in a pit of 1.5 Mtr depth ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 1087.96 | 1087.96 | 7.0 | False | None | None | False | None | False | 7615.72 | 0 | 3409853 | 120495 | None | Item No 1.07 Page No 03 81 Material No 200120 | Line Supports (Pole)Pre-Stressed Tubular Spun Pole - 11 Mtr Long, 500 Kg WL (Dwg No. BESCOM/GM/QS&S/45 Dtd 24.11.2018) as per IS-13158: 1991 ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 20888.36 | 20888.36 | 6.0 | False | None | None | False | None | False | 125330.16 | 0 | 3409854 | 120495 | None | Item No 2.05 Page No 44 81 Material No | Erection of PolesErection of 11 Mtr long Concrete Spun Pole in a pit of 2.5 Mtr depth (Mechnised Labour) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 3001.92 | 3001.92 | 6.0 | False | None | None | False | None | False | 18011.52 | 0 | 3409855 | 120495 | None | Item No 2.01 Page No 03 81 Material No 279020 | 11 kV, Horizontal Cross Arm - Mild Steel (MS) (Dwg No. BESCOM/GM/QS&S/04 Dtd 24.11.2018) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 438.96 | 438.96 | 34.0 | False | None | None | False | None | False | 14924.64 | 0 | 3409856 | 120495 | None | Item No 2.11 Page No 04 81 Material No 279092 | HT ST Support 50x6 mm Flat - MS (Dwg No. BESCOM/GM/QS&S/04 Dtd 24.11.2018) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 107.38 | 107.38 | 102.0 | False | None | None | False | None | False | 10952.76 | 0 | 3409857 | 120495 | None | Item No 5.06 Page No 45 81 Material No | Fixing of HT/LT Single Top Support ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Each | 132.16 | 132.16 | 102.0 | False | None | None | False | None | False | 13480.32 | 0 | 3409858 | 120495 | None | Item No 2.07 Page No 04 81 Material No 279012 | LT 2 Pin Cross Arm - MS (Dwg No. BESCOM/GM/QS&S/32 Dtd 24.11.2018) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 155.76 | 155.76 | 20.0 | False | None | None | False | None | False | 3115.2 | 0 | 3409859 | 120495 | None | Item No 2.05 Page No 04 81 Material No 279014 | LT 4 Pin Cross Arm - MS(Dwg No. BESCOM/GM/QS&S/32 Dtd 24.11.2018) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 341.02 | 341.02 | 20.0 | False | None | None | False | None | False | 6820.4 | 0 | 3409860 | 120495 | None | Item No 5.01 and 5.02 Page No 45 81 Material No | Fixing of 2 Pin cross arm with Insulator and Braces fixing / Fixing of 4 Pin cross arm with Insulator and Braces fixing ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 188.8 | 188.8 | 75.0 | False | None | None | False | None | False | 14160.0 | 0 | 3409861 | 120495 | None | Item No 6.1 Page No 05 81 Material No 283320 | 11 kV, 45 kN Polymeric Insulator ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 219.48 | 219.48 | 8.0 | False | None | None | False | None | False | 1755.84 | 0 | 3409862 | 120495 | None | Item No 6.06 Page No 05 81 Material No 283008 | 11 kV, 5 kN Composite/Polymeric Pin Insulator ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 241.9 | 241.9 | 41.0 | False | None | None | False | None | False | 9917.9 | 0 | 3409863 | 120495 | None | Item No 7.02 Page No 05 81 Material No 284108 | Rabbit ACSR conductor ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Km | 60731.06 | 60731.06 | 1.4 | False | None | None | False | None | False | 85023.484 | 0 | 3409864 | 120495 | None | Cost Data Sheet 25 | Erection of 3 Phase, 11kV/433V, 63 kVA BEE - 4/5 Star Rated Distribution Transformer Centre Using 9 Mtr RCC Pole DPTC ( WithOut Transformer) ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Set | 115431.14 | 115431.14 | 3.0 | False | None | None | False | None | False | 346293.42 | 0 | 3409865 | 120495 | None | Item No 51.01 Page No 22 81 Material No 281674 | GI Grounding pipe, B - Class, 42 mm dia, 2.5 Mtr long, 3.2 mm thick with bolt, nut, GI Strips and washer complete Minimum Weight of GI Pipe: 7.3 Kg ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 880.28 | 880.28 | 6.0 | False | None | None | False | None | False | 5281.68 | 0 | 3409866 | 120495 | None | Item No 51.02 Page No 22 81 Material No 600095 | Good Quality well burnt Charcoal for grounding purposes packed in non returnable gunny bag of 30 Kg each ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 797.68 | 797.68 | 6.0 | False | None | None | False | None | False | 4786.08 | 0 | 3409867 | 120495 | None | item No 51.03 Page No 22 81 Material No 607054 | Good Quality Salt for grounding purposes packed in 50 Kg gunny bag ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Bag | 365.8 | 365.8 | 6.0 | False | None | None | False | None | False | 2194.8 | 0 | 3409868 | 120495 | None | Item No 51.04 Page No 23 81 Material No 281685 | Rod type of earthing using 40 mm Dia, 3 Mtr long MS rod as ground rod, in earth pit of 300 mm width and 3300 mm depth and using 50x6 mm flat welded to ground rod as terminal & connected to equipment ground terminal using PVC Al wire as specified ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 2562.96 | 2562.96 | 6.0 | False | None | None | False | None | False | 15377.76 | 0 | 3409869 | 120495 | None | Item No 1.2.2 Page No 43 81 Material No | Digging of Pit - Digging of Pit 1.6 Mtr depth for erection of 7.5/8 Mtr Long Steel/RCC/PSCC supports as per approved Drawing. - Hard Soil ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Per Pit | 1187.08 | 1187.08 | 68.0 | False | None | None | False | None | False | 80721.44 | 0 | 3409870 | 120495 | None | Item No Page No Material No | R and R of 9mt pole ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 2495.35 | 2495.35 | 40.0 | False | None | None | False | None | False | 99814.0 | 0 | 3409871 | 120495 | None | Item No Page No Material No | R and R of X-Arm ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 358.72 | 358.72 | 34.0 | False | None | None | False | None | False | 12196.48 | 0 | 3409872 | 120495 | None | Item No Page No Material No | R and R of HTST ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Nos | 251.1 | 251.1 | 136.0 | False | None | None | False | None | False | 34149.6 | 0 | 3409873 | 120495 | None | Item No 7.02 &and 7.04 Page No 46 81 Material No | R and R of Rabbit ---- Including cost and conveyance of all materials. labour, hire charges of machineries and equipments with all lead and lifts, loading and unloading charges etc... complete as directed as per the specification and direction of Engineer-in-charge of the work and including 18percent GST and in first and second year, have to rectify the potholes irrespective of quantities | Km | 9880.14 | 9880.14 | 4.2 | False | None | None | False | None | False | 41496.588 | 0 |
|
|
---|