createdTsNone
versionNone
createdDateNone
modifiedDateNone
noticeInvitingTenderDTO
createdTs1721285372395
version5
createdDateNone
modifiedDateNone
tenderTypeRFQ
evaluationTypeTWO_COVER
evaluationTypeTextTwo Cover
invitingStrategyOPEN
invitingStrategyTextOpen
taxTypeINCLUSIVE_TAX
tenderFee5000.00
emd572000.00
bidValueTypeITEM_WISE
bidValueTypeTextItem wise
tenderReceiptClose03-08-2024 16:00:00
tenderQueryClose30-07-2024 12:00:17
technicalBidOpen05-08-2024 11:00:00
publishedDate24-07-2024 18:32:36
publishedByPostPWD_EE_DIV_BLR
publishedByUserKPE10627 - HEMARAJA
bidValidityPeriod90
noOfCalls1
preBidMeetingDate30-07-2024 11:00:00
preBidMeetingYnTrue
preQualificationBidOpenNone
denominationTypeRUPEES
denominationTypeTextRupees
retenderedYnNone
percentageRateTypeTextNone
contactPersonTechnical Assistant
splitEmdRequiredYnTrue
emdBankGuarantee472000.00
emdCash100000.00
bgValidityPeriod135
hideWeightageNone
multipleCurrencySelectionAllowedYnFalse
isTechWeightageAllowedFalse
highestBidderSelectionFalse
isVariableEmdAllowedNone
qcbsTenderYnNone
itemwiseEmdRequiredYnNone
sampleSubmissionDateNone
officeNumber08392266123
mobileNumberNone
tenderSupplierListNone
tenderSchedule
createdTs1721285372430
version7
createdDateNone
modifiedDateNone
tenderNumberPWD/2024-25/RD/WORK_INDENT11287
titleConstruction of Cement Concrete Road in Annapurneshwari Camp, Srinivasnagar, Dammuru-Shantinagar, Kallukumba, Kyadigehal of Kurugodu Taluk and Chanal, Sridhargadde, Balajingar Camp and Lakshminagar Camp in Ballari Taluk, Under 5054 (Plan) MDR Improvements for the year 2024-25.
descriptionConstruction of Cement Concrete Road in Annapurneshwari Camp, Srinivasnagar, Dammuru-Shantinagar, Kallukumba, Kyadigehal of Kurugodu Taluk and Chanal, Sridhargadde, Balajingar Camp and Lakshminagar Camp in Ballari Taluk, Under 5054 (Plan) MDR Improvements for the year 2024-25.
categoryWORKS
categoryTextWorks
ecv38123283.28
deptNamePublic Works Department
statusPUBLISHED
statusTextPublished
remarksNone
csrValueNone
ecvtenderYnTrue
location1693
locationNamePWD Division Office Ballari
provisionalAmount45000000.0
groupOverheadTotal0.0
fileNumberKPWD/AEE/PWD/SDN/BAL/NABARD/2024-25
tenderSubEstimateList
createdTsversioncreatedDatemodifiedDateworkCategoryNamesubEstimateNameestimateTotalitemList
17212853720000NoneNoneRoadsImprovement of Cement Concrete Road in Shreedharagadde Village in Ballari Taluk. (CC Road)4564395.25
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3539792127688NoneI.No. 1.12Earth work in surface excavation by mechanical means for lowering & leveling the ground for all works other than foundation in all kinds of soils & upto depth not exceeding 300mm as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenances required to complete the work. In all kinds of soils upto 300 mm depth (COMMON SR 2023-24, Vol-1, P.NO -8, SL. No -1.12) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum99.7599.75581.25FalseNoneNoneFalseNoneFalse57979.68750
3539793127688NoneI.No. 3.7Compacting original ground supporting embankment : Loosening, leveling and Compacting original ground supporting embankment to facilitate placement of first layer of embankment, scarified to a depth of 150 mm, mixed with water at OMC and then compacted by rolling so as to achieve minimum dry density as given in Table 300-2 for embankment construction (COMMON SR 2023-24, Vol-3, Sl.No.3.7 ,P.No - 17) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum110.25110.25348.75FalseNoneNoneFalseNoneFalse38449.68750
3539794127688NoneI.No. 3.6Construction of Subgrade and Earthen Shoulders Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2 305 (COMMON SR 2023-24,Vol-3, Sl.No. 3.6 ,P.No -17) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum517.65517.65263.5FalseNoneNoneFalseNoneFalse136400.7750
3539795127688NoneI.No. 4.1.A.(v)Granular Sub-Base A Plant Mix Method Construction of Granular Sub-Base of required grading as per design mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 (v) For Grading -V Material (COMMON SR 2023-24, Vol-3 Sl.No.4.1.A.(v) ,P.No - 23) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum2611.352611.35232.5FalseNoneNoneFalseNoneFalse607138.8750
3539796127688NoneI.No. 4.17Wet Mix Macadam (Plant mix method)Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver/grader in sub-base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. (COMMON SR 2023-24, Vol-3 Sl.No.4.17 ,P.No - 26.) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum2686.952686.95383.62FalseNoneNoneFalseNoneFalse1030767.7590
3539797127688NoneI.No. 16.28Providing and constructing un-reinforced plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a concrete mixer of not less than 0.2 cum capacity and appropriate weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with shovels, rakes, compacted using needle, screed and plate vibrators and finished in continuous operation including construction joints, , primer, sealant , curing of concrete slabs for 14days, and water finishing to lines and grade as per drawing and technical specification clause 1501 with all lead, lifts, loading & unloading charges, cost and conveyance of all materials, labour, equipments etc., complete. as per the directions of the Engineer-in charge of the work. (COMMON SR 2021-22, Vol-3 Sl.No.16.28 ,P.No - 149) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum7091.77091.7378.5FalseNoneNoneFalseNoneFalse2684208.450
3539798127688NoneI.No. 8.54Providing and fixing board displaying information, such as 'Name of work, Tender cost, Name of Contractor, Work completion and liability period etc', having rectangular shape of 1.20m x 0.90m size made out 18 gauge (1.25mm) thick mild steel sheet painted with one coat of Zinc chromate stoving primer and two coats of enamel paint on front side and grey stove enamel on back side and border / messages / symbols etc. with approved colour shade paint complete, on M.S.angle of size 35 x 35 x 3 mm frame with properly cross braced M.S. angles of size 35mmx35mmx3mm duly painted including Two M.S. angle iron posts of size 65 mm x 65 mm x 6 mm, 3.65 m long painted with alternate black and white bands of 25 cm width including all fixtures etc.and fixing the boards in 1:4:8 concrete block of size 60 cm x 60 cm x 75 cm including, excavation, refilling, transportation, and labour etc complete. Spec. No. As directed by Engineer in Charge & MoRTH specification 804 (COMMON SR 2023-24, Vol-3 Sl.No. 8.54 ,P.No - 78) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.No9450.09450.01.0FalseNoneNoneFalseNoneFalse9450.00
17212853720000NoneNoneRoadsImprovement of Cement Concrete Road in Shreedharagadde Village in Ballari Taluk. (CC Drain)640711.7
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3539799127689None2.8 (ii), ADismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete,wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead, By Mechanical Means. A. Cement Concrete Grade M-15 & M-20 (COMMON SR 2023-24, Vol-3 Sl.No. 2.8 (ii), A ,P.No - 10) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum754.95754.9527.0FalseNoneNoneFalseNoneFalse20383.650
3539800127689NoneI.No. 1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work In all kinds of soils Depth upto 3 m (COMMON SR 2023-24, Vol-1, P.NO -8, SL. No -1.14.1) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum107.1107.172.0FalseNoneNoneFalseNoneFalse7711.20
3539801127689NoneI.No. 2.1.3Providing and laying in position plain cement concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machineries, curing, and all the other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement & formwork shall be paid separately) Mix 1:3:6 (M10) Using 40 mm nominal size graded crushed coarse aggregates (COMMON SR 2023-24 Vol-1, P.NO -15, SI.No -2.1.3) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum6288.456288.457.2FalseNoneNoneFalseNoneFalse45276.840
3539802127689NoneI.No. 2.4.2Providing and laying in position Reinforced cement concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necesary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement & formwork to be paid separately) M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates (COMMON SR 2023-24 Vol-1, P.NO -16, SI.No -2.4.2) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum6639.156639.1538.4FalseNoneNoneFalseNoneFalse254943.360
3539803127689NoneI.No. 2.4.2Appendix I - Additionalities for Formwork, Centering & Scaffolding S.N.2 35 percent P.N. 115 ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum2323.72323.738.4FalseNoneNoneFalseNoneFalse89230.080
3539804127689NoneI.No. 2.11Supplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. h. All other type of structures (COMMON SR 2023-24 Vol-1, P.NO -18, SI.No -2.11) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Tonne82961.5582961.552.69FalseNoneNoneFalseNoneFalse223166.56950
17212853720000NoneNoneRoadsImprovement of Cement Concrete Road in Balaji Nagar Camp in Ballari Taluk. (CC Road)4215629.6
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3539805127690NoneI.No. 2.5 (ii).AClearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness..(ii) By Mechanical Means using Dozer (A) In area of light jungle (COMMON SR 2023-24, Vol-3 Sl.No. 2.5 (ii).A, P.No - 9) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum412.65412.654.55FalseNoneNoneFalseNoneFalse1877.55750
3539806127690NoneI.No. 3.7Compacting original ground supporting embankment : Loosening, leveling and Compacting original ground supporting embankment to facilitate placement of first layer of embankment, scarified to a depth of 150 mm, mixed with water at OMC and then compacted by rolling so as to achieve minimum dry density as given in Table 300-2 for embankment construction (COMMON SR 2023-24, Vol-3, Sl.No.3.7 ,P.No - 17) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum110.25110.25480.75FalseNoneNoneFalseNoneFalse53002.68750
3539807127690NoneI.No. 3.6Construction of Subgrade and Earthen Shoulders Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2 305 (COMMON SR 2023-24,Vol-3, Sl.No. 3.6 ,P.No -17) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum517.65517.65605.63FalseNoneNoneFalseNoneFalse313504.36950
3539808127690NoneI.No. 4.1.A.(v)Granular Sub-Base A Plant Mix Method Construction of Granular Sub-Base of required grading as per design mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 (v) For Grading -V Material (COMMON SR 2023-24, Vol-3 Sl.No.4.1.A.(v) ,P.No - 23) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum2611.352611.35290.25FalseNoneNoneFalseNoneFalse757944.33750
3539809127690NoneI.No. 4.17Wet Mix Macadam (Plant mix method)Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver/grader in sub-base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. (COMMON SR 2023-24, Vol-3 Sl.No.4.17 ,P.No - 26.) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum2686.952686.95191.62FalseNoneNoneFalseNoneFalse514873.3590
3539810127690NoneI.No. 16.28Providing and constructing un-reinforced plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a concrete mixer of not less than 0.2 cum capacity and appropriate weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with shovels, rakes, compacted using needle, screed and plate vibrators and finished in continuous operation including construction joints, , primer, sealant , curing of concrete slabs for 14days, and water finishing to lines and grade as per drawing and technical specification clause 1501 with all lead, lifts, loading & unloading charges, cost and conveyance of all materials, labour, equipments etc., complete. as per the directions of the Engineer-in charge of the work. (COMMON SR 2021-22, Vol-3 Sl.No.16.28 ,P.No - 149) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum6692.76692.7383.25FalseNoneNoneFalseNoneFalse2564977.2750
3539811127690NoneI.No. 8.54Providing and fixing board displaying information, such as 'Name of work, Tender cost, Name of Contractor, Work completion and liability period etc', having rectangular shape of 1.20m x 0.90m size made out 18 gauge (1.25mm) thick mild steel sheet painted with one coat of Zinc chromate stoving primer and two coats of enamel paint on front side and grey stove enamel on back side and border / messages / symbols etc. with approved colour shade paint complete, on M.S.angle of size 35 x 35 x 3 mm frame with properly cross braced M.S. angles of size 35mmx35mmx3mm duly painted including Two M.S. angle iron posts of size 65 mm x 65 mm x 6 mm, 3.65 m long painted with alternate black and white bands of 25 cm width including all fixtures etc.and fixing the boards in 1:4:8 concrete block of size 60 cm x 60 cm x 75 cm including, excavation, refilling, transportation, and labour etc complete. Spec. No. As directed by Engineer in Charge & MoRTH specification 804 (COMMON SR 2023-24, Vol-3 Sl.No. 8.54 ,P.No - 78) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.No9450.09450.01.0FalseNoneNoneFalseNoneFalse9450.00
17212853720000NoneNoneRoadsImprovement of Cement Concrete Road in Balaji Nagar Camp in Ballari Taluk. (Cross Drainage)118799.1
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3539812127691NoneI.No. 1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work In all kinds of soils Depth upto 3 m (COMMON SR 2023-24, Vol-1, P.NO -8, SL. No -1.14.1) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum107.1107.16.3FalseNoneNoneFalseNoneFalse674.730
3539813127691NoneI.No. 2.1.3Providing and laying in position plain cement concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machineries, curing, and all the other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement & formwork shall be paid separately) Mix 1:3:6 (M10) Using 40 mm nominal size graded crushed coarse aggregates (COMMON SR 2023-24 Vol-1, P.NO -15, SI.No -2.1.3) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum6288.456288.452.1FalseNoneNoneFalseNoneFalse13205.7450
3539814127691NoneI.No. 16.15.BProviding and laying reinforced cement concrete pipe NP3 for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works,backfilling, concrete and masonry works in head walls and parapets Clause 1101.6 (COMMON SR 2023-24, Vol-3 Sl.No. 16.15.B, P.No - 146) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Mtr3501.753501.7522.5FalseNoneNoneFalseNoneFalse78789.3750
3539815127691NoneI.No. 1.8Construction of Embankment by excavating the available approved Gravel/ Murrum deposited at a place or borrow pits during or prior excavation with all lifts and lead, transportation to site, spreading, grading to required slope andcompacting to meet the requirement complete as per specifications, includingcost of labour,rolling,water,all materials,usage& all other appurtenaces required to complete the work. (COMMON SR 2023-24, Vol-1, SI.No.1.8, P.No - 7) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum497.7497.752.5FalseNoneNoneFalseNoneFalse26129.250
17212853720000NoneNoneRoadsImprovement of Cement Concrete Road in Laxmi Nagar Camp in Ballari Taluk. (CC Road)3434740.6
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3539816127692NoneI.No. 2.5 (ii).AClearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness..(ii) By Mechanical Means using Dozer (A) In area of light jungle (COMMON SR 2023-24, Vol-3 Sl.No. 2.5 (ii).A, P.No - 9) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum412.65412.653.64FalseNoneNoneFalseNoneFalse1502.0460
3539817127692NoneI.No. 3.7Compacting original ground supporting embankment : Loosening, leveling and Compacting original ground supporting embankment to facilitate placement of first layer of embankment, scarified to a depth of 150 mm, mixed with water at OMC and then compacted by rolling so as to achieve minimum dry density as given in Table 300-2 for embankment construction (COMMON SR 2023-24, Vol-3, Sl.No.3.7 ,P.No - 17) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum110.25110.25390.0FalseNoneNoneFalseNoneFalse42997.50
3539818127692NoneI.No. 3.6Construction of Subgrade and Earthen Shoulders Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2 305 (COMMON SR 2023-24,Vol-3, Sl.No. 3.6 ,P.No -17) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum517.65517.65507.0FalseNoneNoneFalseNoneFalse262448.550
3539819127692NoneI.No. 4.1.A.(v)Granular Sub-Base A Plant Mix Method Construction of Granular Sub-Base of required grading as per design mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 (v) For Grading -V Material (COMMON SR 2023-24, Vol-3 Sl.No.4.1.A.(v) ,P.No - 23) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum2611.352611.35234.0FalseNoneNoneFalseNoneFalse611055.90
3539820127692NoneI.No. 4.17Wet Mix Macadam (Plant mix method)Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver/grader in sub-base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. (COMMON SR 2023-24, Vol-3 Sl.No.4.17 ,P.No - 26.) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum2686.952686.95156.0FalseNoneNoneFalseNoneFalse419164.20
3539821127692NoneI.No. 16.28Providing and constructing un-reinforced plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a concrete mixer of not less than 0.2 cum capacity and appropriate weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with shovels, rakes, compacted using needle, screed and plate vibrators and finished in continuous operation including construction joints, , primer, sealant , curing of concrete slabs for 14days, and water finishing to lines and grade as per drawing and technical specification clause 1501 with all lead, lifts, loading & unloading charges, cost and conveyance of all materials, labour, equipments etc., complete. as per the directions of the Engineer-in charge of the work. (COMMON SR 2021-22, Vol-3 Sl.No.16.28 ,P.No - 149) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum6692.76692.7312.0FalseNoneNoneFalseNoneFalse2088122.40
3539822127692NoneI.No. 8.54Providing and fixing board displaying information, such as 'Name of work, Tender cost, Name of Contractor, Work completion and liability period etc', having rectangular shape of 1.20m x 0.90m size made out 18 gauge (1.25mm) thick mild steel sheet painted with one coat of Zinc chromate stoving primer and two coats of enamel paint on front side and grey stove enamel on back side and border / messages / symbols etc. with approved colour shade paint complete, on M.S.angle of size 35 x 35 x 3 mm frame with properly cross braced M.S. angles of size 35mmx35mmx3mm duly painted including Two M.S. angle iron posts of size 65 mm x 65 mm x 6 mm, 3.65 m long painted with alternate black and white bands of 25 cm width including all fixtures etc.and fixing the boards in 1:4:8 concrete block of size 60 cm x 60 cm x 75 cm including, excavation, refilling, transportation, and labour etc complete. Spec. No. As directed by Engineer in Charge & MoRTH specification 804 (COMMON SR 2023-24, Vol-3 Sl.No. 8.54 ,P.No - 78) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.No9450.09450.01.0FalseNoneNoneFalseNoneFalse9450.00
17212853720000NoneNoneRoadsImprovement of Cement Concrete Road in Laxmi Nagar Camp in Ballari Taluk. (Cross Drainage)75715.5
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3539823127693NoneI.No. 1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work In all kinds of soils Depth upto 3 m (COMMON SR 2023-24, Vol-1, P.NO -8, SL. No -1.14.1) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum107.1107.14.2FalseNoneNoneFalseNoneFalse449.820
3539824127693NoneI.No. 2.1.3Providing and laying in position plain cement concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machineries, curing, and all the other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement & formwork shall be paid separately) Mix 1:3:6 (M10) Using 40 mm nominal size graded crushed coarse aggregates (COMMON SR 2023-24 Vol-1, P.NO -15, SI.No -2.1.3) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum6288.456288.451.4FalseNoneNoneFalseNoneFalse8803.830
3539825127693NoneI.No. 16.15.BProviding and laying reinforced cement concrete pipe NP3 for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works,backfilling, concrete and masonry works in head walls and parapets Clause 1101.6 (COMMON SR 2023-24, Vol-3 Sl.No. 16.15.B, P.No - 146) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Mtr3501.753501.7515.0FalseNoneNoneFalseNoneFalse52526.250
3539826127693NoneI.No. 1.8Construction of Embankment by excavating the available approved Gravel/ Murrum deposited at a place or borrow pits during or prior excavation with all lifts and lead, transportation to site, spreading, grading to required slope andcompacting to meet the requirement complete as per specifications, includingcost of labour,rolling,water,all materials,usage& all other appurtenaces required to complete the work. (COMMON SR 2023-24, Vol-1, SI.No.1.8, P.No - 7) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum497.7497.728.0FalseNoneNoneFalseNoneFalse13935.60
17212853720000NoneNoneRoadsImprovement of Cement Concrete Road in Dammur Village in Ballari Taluk. (CC Road)2484975.51
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3539827127694NoneI.No. 2.5 (ii).AClearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness..(ii) By Mechanical Means using Dozer (A) In area of light jungle (COMMON SR 2023-24, Vol-3 Sl.No. 2.5 (ii).A, P.No - 9) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum412.65412.653.57FalseNoneNoneFalseNoneFalse1473.16050
3539828127694NoneI.No. 3.7Compacting original ground supporting embankment : Loosening, leveling and Compacting original ground supporting embankment to facilitate placement of first layer of embankment, scarified to a depth of 150 mm, mixed with water at OMC and then compacted by rolling so as to achieve minimum dry density as given in Table 300-2 for embankment construction (COMMON SR 2023-24, Vol-3, Sl.No.3.7 ,P.No - 17) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum110.25110.25229.5FalseNoneNoneFalseNoneFalse25302.3750
3539829127694NoneI.No. 3.6Construction of Subgrade and Earthen Shoulders Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2 305 (COMMON SR 2023-24,Vol-3, Sl.No. 3.6 ,P.No -17) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum517.65517.65433.5FalseNoneNoneFalseNoneFalse224401.2750
3539830127694NoneI.No. 4.1.A.(v)Granular Sub-Base A Plant Mix Method Construction of Granular Sub-Base of required grading as per design mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 (v) For Grading -V Material (COMMON SR 2023-24, Vol-3 Sl.No.4.1.A.(v) ,P.No - 23) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum2611.352611.35127.5FalseNoneNoneFalseNoneFalse332947.1250
3539831127694NoneI.No. 4.17Wet Mix Macadam (Plant mix method)Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver/grader in sub-base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. (COMMON SR 2023-24, Vol-3 Sl.No.4.17 ,P.No - 26.) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum2686.952686.95210.37FalseNoneNoneFalseNoneFalse565253.67150
3539832127694NoneI.No. 16.28Providing and constructing un-reinforced plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a concrete mixer of not less than 0.2 cum capacity and appropriate weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with shovels, rakes, compacted using needle, screed and plate vibrators and finished in continuous operation including construction joints, , primer, sealant , curing of concrete slabs for 14days, and water finishing to lines and grade as per drawing and technical specification clause 1501 with all lead, lifts, loading & unloading charges, cost and conveyance of all materials, labour, equipments etc., complete. as per the directions of the Engineer-in charge of the work. (COMMON SR 2021-22, Vol-3 Sl.No.16.28 ,P.No - 149) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum7091.77091.7187.0FalseNoneNoneFalseNoneFalse1326147.90
3539833127694NoneI.No. 8.54Providing and fixing board displaying information, such as 'Name of work, Tender cost, Name of Contractor, Work completion and liability period etc', having rectangular shape of 1.20m x 0.90m size made out 18 gauge (1.25mm) thick mild steel sheet painted with one coat of Zinc chromate stoving primer and two coats of enamel paint on front side and grey stove enamel on back side and border / messages / symbols etc. with approved colour shade paint complete, on M.S.angle of size 35 x 35 x 3 mm frame with properly cross braced M.S. angles of size 35mmx35mmx3mm duly painted including Two M.S. angle iron posts of size 65 mm x 65 mm x 6 mm, 3.65 m long painted with alternate black and white bands of 25 cm width including all fixtures etc.and fixing the boards in 1:4:8 concrete block of size 60 cm x 60 cm x 75 cm including, excavation, refilling, transportation, and labour etc complete. Spec. No. As directed by Engineer in Charge & MoRTH specification 804 (COMMON SR 2023-24, Vol-3 Sl.No. 8.54 ,P.No - 78) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.No9450.09450.01.0FalseNoneNoneFalseNoneFalse9450.00
17212853720000NoneNoneRoadsImprovement of Cement Concrete Road in Dammur Village in Ballari Taluk. (CC Drain)737184.36
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3539834127695NoneI.No. 8.24.2Excavation and removal of silt and silt mixed with sand from canal bed by manual means including disposing off the same in spoil bank or on the canal embankment in layers as directed with all other ancillary operations complete. in slussy condition (COMMON SR 2023-24, Vol-1, P.NO -104, SL. No - 8.24.2) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum373.8373.896.0FalseNoneNoneFalseNoneFalse35884.80
3539835127695NoneI.No. 1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work In all kinds of soils Depth upto 3 m (COMMON SR 2023-24, Vol-1, P.NO -8, SL. No -1.14.1) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum107.1107.1256.0FalseNoneNoneFalseNoneFalse27417.60
3539836127695NoneI.No. 2.1.3Providing and laying in position plain cement concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machineries, curing, and all the other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement & formwork shall be paid separately) Mix 1:3:6 (M10) Using 40 mm nominal size graded crushed coarse aggregates (COMMON SR 2023-24 Vol-1, P.NO -15, SI.No -2.1.3) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum6288.456288.4514.0FalseNoneNoneFalseNoneFalse88038.30
3539837127695NoneI.No. 2.4.2Providing and laying in position Reinforced cement concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necesary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement & formwork to be paid separately) M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates (COMMON SR 2023-24 Vol-1, P.NO -16, SI.No -2.4.2) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum6639.156639.1545.0FalseNoneNoneFalseNoneFalse298761.750
3539838127695NoneI.No. 2.4.2Appendix I - Additionalities for Formwork, Centering & Scaffolding S.N.2 35 percent P.N. 115 ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Mtr2323.72323.745.0FalseNoneNoneFalseNoneFalse104566.50
3539839127695NoneI.No. 2.11Supplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. h. All other type of structures (COMMON SR 2023-24 Vol-1, P.NO -18, SI.No -2.11) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Tonne82961.5582961.552.2FalseNoneNoneFalseNoneFalse182515.410
17212853720000NoneNoneRoadsImprovement of Cement Concrete Road in Dammur Village in Ballari Taluk. (Cross Drainage)988959.76
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3539840127696NoneI.No. 2.11Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead. iv. Dismantling Stone Masonry By Mechanical means Dismantling Brick / Tile work / rubble masonry / pitching / etc by mechanical means (COMMON SR 2023-24, Vol-3, P.NO -10, SL. No -2.11 ) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum189.0189.02.7FalseNoneNoneFalseNoneFalse510.30
3539841127696NoneI.No. 1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work In all kinds of soils Depth upto 3 m (COMMON SR 2023-24, Vol-1, P.NO -8, SL. No -1.14.1) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum107.1107.1119.0FalseNoneNoneFalseNoneFalse12744.90
3539842127696NoneI.No. 2.1.3Providing and laying in position plain cement concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machineries, curing, and all the other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement & formwork shall be paid separately) Mix 1:3:6 (M10) Using 40 mm nominal size graded crushed coarse aggregates (COMMON SR 2023-24 Vol-1, P.NO -15, SI.No -2.1.3) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum6288.456288.4510.5FalseNoneNoneFalseNoneFalse66028.7250
3539843127696NoneI.No. 2.4.2Providing and laying in position Reinforced cement concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necesary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement & formwork to be paid separately) M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates (COMMON SR 2023-24 Vol-1, P.NO -16, SI.No -2.4.2) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum6639.156639.1561.6FalseNoneNoneFalseNoneFalse408971.640
3539844127696NoneI.No. 2.4.2Appendix I - Additionalities for Formwork, Centering & Scaffolding S.N.2 35 percent P.N. 115 ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Mtr2323.72323.761.6FalseNoneNoneFalseNoneFalse143139.920
3539845127696NoneI.No. 2.11Supplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. h. All other type of structures (COMMON SR 2023-24 Vol-1, P.NO -18, SI.No -2.11) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Tonne82961.5582961.554.31FalseNoneNoneFalseNoneFalse357564.28050
17212853720000NoneNoneRoadsImprovement of Cement Concrete Road in Chanal Village in Ballari Taluk. (CC Road)852954.37
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3539846127697NoneI.No. 2.5 (ii).AClearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness.(ii) By Mechanical Means using Dozer (A) In area of light jungle (COMMON SR 2023-24, Vol-3 Sl.No. 2.5 (ii).A, P.No - 9) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Sqm412.65412.65170.0FalseNoneNoneFalseNoneFalse70150.50
3539847127697NoneI.No. 3.7Compacting original ground supporting embankment : Loosening, leveling and Compacting original ground supporting embankment to facilitate placement of first layer of embankment, scarified to a depth of 150 mm, mixed with water at OMC and then compacted by rolling so as to achieve minimum dry density as given in Table 300-2 for embankment construction (COMMON SR 2023-24, Vol-3, Sl.No.3.7 ,P.No - 17) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum110.25110.2563.75FalseNoneNoneFalseNoneFalse7028.43750
3539848127697NoneI.No. 3.6Construction of Subgrade and Earthen Shoulders Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2 305 (COMMON SR 2023-24,Vol-3, Sl.No. 3.6 ,P.No -17) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum517.65517.65106.25FalseNoneNoneFalseNoneFalse55000.31250
3539849127697NoneI.No. 4.1.A.(v)Granular Sub-Base A Plant Mix Method Construction of Granular Sub-Base of required grading as per design mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 (v) For Grading -V Material (COMMON SR 2023-24, Vol-3 Sl.No.4.1.A.(v) ,P.No - 23) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum2611.352611.3540.0FalseNoneNoneFalseNoneFalse104454.00
3539850127697NoneI.No. 4.17Wet Mix Macadam (Plant mix method)Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver/grader in sub-base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. (COMMON SR 2023-24, Vol-3 Sl.No.4.17 ,P.No - 26.) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum2686.952686.9567.5FalseNoneNoneFalseNoneFalse181369.1250
3539851127697NoneI.No. 16.28Providing and constructing un-reinforced plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a concrete mixer of not less than 0.2 cum capacity and appropriate weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with shovels, rakes, compacted using needle, screed and plate vibrators and finished in continuous operation including construction joints, , primer, sealant , curing of concrete slabs for 14days, and water finishing to lines and grade as per drawing and technical specification clause 1501 with all lead, lifts, loading & unloading charges, cost and conveyance of all materials, labour, equipments etc., complete. as per the directions of the Engineer-in charge of the work. (COMMON SR 2021-22, Vol-3 Sl.No.16.28 ,P.No - 149) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum7091.77091.760.0FalseNoneNoneFalseNoneFalse425502.00
3539852127697NoneI.No. 8.54Providing and fixing board displaying information, such as 'Name of work, Tender cost, Name of Contractor, Work completion and liability period etc', having rectangular shape of 1.20m x 0.90m size made out 18 gauge (1.25mm) thick mild steel sheet painted with one coat of Zinc chromate stoving primer and two coats of enamel paint on front side and grey stove enamel on back side and border / messages / symbols etc. with approved colour shade paint complete, on M.S.angle of size 35 x 35 x 3 mm frame with properly cross braced M.S. angles of size 35mmx35mmx3mm duly painted including Two M.S. angle iron posts of size 65 mm x 65 mm x 6 mm, 3.65 m long painted with alternate black and white bands of 25 cm width including all fixtures etc.and fixing the boards in 1:4:8 concrete block of size 60 cm x 60 cm x 75 cm including, excavation, refilling, transportation, and labour etc complete. Spec. No. As directed by Engineer in Charge & MoRTH specification 804 (COMMON SR 2023-24, Vol-3 Sl.No. 8.54 ,P.No - 78) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.No9450.09450.01.0FalseNoneNoneFalseNoneFalse9450.00
17212853720000NoneNoneRoadsImprovement of Cement Concrete Road in Chanal Village in Ballari Taluk. (CC Drain)1934546.73
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3539853127698NoneI.No. 8.24.2Excavation and removal of silt and silt mixed with sand from canal bed by manual means including disposing off the same in spoil bank or on the canal embankment in layers as directed with all other ancillary operations complete. in slussy condition (COMMON SR 2023-24, Vol-1, P.NO -104, SL. No - 8.24.2) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum373.8373.8170.3FalseNoneNoneFalseNoneFalse63658.140
3539854127698NoneI.No. 1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work In all kinds of soils Depth upto 3 m (COMMON SR 2023-24, Vol-1, P.NO -8, SL. No -1.14.1) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum107.1107.1280.8FalseNoneNoneFalseNoneFalse30073.680
3539855127698NoneI.No. 2.1.3Providing and laying in position plain cement concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machineries, curing, and all the other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement & formwork shall be paid separately) Mix 1:3:6 (M10) Using 40 mm nominal size graded crushed coarse aggregates (COMMON SR 2023-24 Vol-1, P.NO -15, SI.No -2.1.3) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum6288.456288.4529.7FalseNoneNoneFalseNoneFalse186766.9650
3539856127698NoneI.No. 2.4.2Providing and laying in position Reinforced cement concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necesary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement & formwork to be paid separately) M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates (COMMON SR 2023-24 Vol-1, P.NO -16, SI.No -2.4.2) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum6639.156639.15109.35FalseNoneNoneFalseNoneFalse725991.05250
3539857127698NoneI.No. 2.4.2Appendix I - Additionalities for Formwork, Centering & Scaffolding S.N.2 35 Percent P.N. 115 ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum2323.72323.7109.35FalseNoneNoneFalseNoneFalse254096.5950
3539858127698NoneI.No. 2.11Supplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. h. All other type of structures (COMMON SR 2023-24 Vol-1, P.NO -18, SI.No -2.11) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Tonne82961.5582961.555.25FalseNoneNoneFalseNoneFalse435548.13750
3539859127698NoneI.No. 12.3.ABack filling behind abutment, wing wall and return wall complete including compaction as per drawing and Technical Specification . A Granular material 710.1.4.of IRC:78 &2200 (COMMON SR 2023-24 Vol-3, P.NO -117, SI.No -12.3.A) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum1226.41226.4194.4FalseNoneNoneFalseNoneFalse238412.160
17212853720000NoneNoneRoadsImprovement of Cement Concrete Road in Chanal Village in Ballari Taluk. (Cross Drainage)1445091.11
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3539860127699NoneI.No. 2.11Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead. iv. Dismantling Stone Masonry By Mechanical means Dismantling Brick / Tile work / rubble masonry / pitching / etc by mechanical means (COMMON SR 2023-24, Vol-3, P.NO -10, SL. No -2.11 ) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum189.0189.054.0FalseNoneNoneFalseNoneFalse10206.00
3539861127699NoneI.No. 2.8 ii aDismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead. By Mechanical Means Cement Concrete Grade M-15 & M-20 (COMMON SR 2023-24, Vol-3, P.NO -10, SL. No -2.8 ii a) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum754.95754.9512.0FalseNoneNoneFalseNoneFalse9059.40
3539862127699NoneI.No. 1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work In all kinds of soils Depth upto 3 m (COMMON SR 2023-24, Vol-1, P.NO -8, SL. No -1.14.1) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum107.1107.1154.0FalseNoneNoneFalseNoneFalse16493.40
3539863127699NoneI.No. 2.1.3Providing and laying in position plain cement concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machineries, curing, and all the other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement & formwork shall be paid separately) Mix 1:3:6 (M10) Using 40 mm nominal size graded crushed coarse aggregates (COMMON SR 2023-24 Vol-1, P.NO -15, SI.No -2.1.3) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum6288.456288.4513.2FalseNoneNoneFalseNoneFalse83007.540
3539864127699NoneI.No. 2.4.2Providing and laying in position Reinforced cement concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necesary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement & formwork to be paid separately) M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates (COMMON SR 2023-24 Vol-1, P.NO -16, SI.No -2.4.2) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum6639.156639.1583.6FalseNoneNoneFalseNoneFalse555032.940
3539865127699NoneI.No. 2.4.2Appendix I - Additionalities for Formwork, Centering & Scaffolding S.N.2 35 percent P.N. 115 ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Mtr2323.72323.783.6FalseNoneNoneFalseNoneFalse194261.320
3539866127699NoneI.No. 2.11Supplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. h. All other type of structures (COMMON SR 2023-24 Vol-1, P.NO -18, SI.No -2.11) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Tonne82961.5582961.556.37FalseNoneNoneFalseNoneFalse528465.07350
3539867127699NoneI.No. 12.3.ABack filling behind abutment, wing wall and return wall complete including compaction as per drawing and Technical Specification . A Granular material 710.1.4.of IRC:78 &2200 (COMMON SR 2023-24 Vol-3, P.NO -117, SI.No -12.3.A) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum1226.41226.439.6FalseNoneNoneFalseNoneFalse48565.440
17212853720000NoneNoneRoadsImprovement of Cement Concrete Road in Annapoorneshwari Camp in Ballari Taluk. (CC Road)3704297.46
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3539868127700NoneI.No. 2.5 (ii).AClearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness..(ii) By Mechanical Means using Dozer (A) In area of light jungle (COMMON SR 2023-24, Vol-3 Sl.No. 2.5 (ii).A, P.No - 9) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum412.65412.6511.2FalseNoneNoneFalseNoneFalse4621.680
3539869127700NoneI.No. 3.7Compacting original ground supporting embankment : Loosening, leveling and Compacting original ground supporting embankment to facilitate placement of first layer of embankment, scarified to a depth of 150 mm, mixed with water at OMC and then compacted by rolling so as to achieve minimum dry density as given in Table 300-2 for embankment construction (COMMON SR 2023-24, Vol-3, Sl.No.3.7 ,P.No - 17) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum110.25110.25393.0FalseNoneNoneFalseNoneFalse43328.250
3539870127700NoneI.No. 3.6Construction of Subgrade and Earthen Shoulders Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2 305 (COMMON SR 2023-24,Vol-3, Sl.No. 3.6 ,P.No -17) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum517.65517.65564.0FalseNoneNoneFalseNoneFalse291954.60
3539871127700NoneI.No. 4.1.A.(v)Granular Sub-Base A Plant Mix Method Construction of Granular Sub-Base of required grading as per design mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 (v) For Grading -V Material (COMMON SR 2023-24, Vol-3 Sl.No.4.1.A.(v) ,P.No - 23) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum2611.352611.35233.5FalseNoneNoneFalseNoneFalse609750.2250
3539872127700NoneI.No. 4.17Wet Mix Macadam (Plant mix method)Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver/grader in sub-base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. (COMMON SR 2023-24, Vol-3 Sl.No.4.17 ,P.No - 26.) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum2686.952686.95255.75FalseNoneNoneFalseNoneFalse687187.46250
3539873127700NoneI.No. 16.28Providing and constructing un-reinforced plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a concrete mixer of not less than 0.2 cum capacity and appropriate weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with shovels, rakes, compacted using needle, screed and plate vibrators and finished in continuous operation including construction joints, , primer, sealant , curing of concrete slabs for 14days, and water finishing to lines and grade as per drawing and technical specification clause 1501 with all lead, lifts, loading & unloading charges, cost and conveyance of all materials, labour, equipments etc., complete. as per the directions of the Engineer-in charge of the work. (COMMON SR 2021-22, Vol-3 Sl.No.16.28 ,P.No - 149) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum6692.76692.7307.5FalseNoneNoneFalseNoneFalse2058005.250
3539874127700NoneI.No. 8.54Providing and fixing board displaying information, such as 'Name of work, Tender cost, Name of Contractor, Work completion and liability period etc', having rectangular shape of 1.20m x 0.90m size made out 18 gauge (1.25mm) thick mild steel sheet painted with one coat of Zinc chromate stoving primer and two coats of enamel paint on front side and grey stove enamel on back side and border / messages / symbols etc. with approved colour shade paint complete, on M.S.angle of size 35 x 35 x 3 mm frame with properly cross braced M.S. angles of size 35mmx35mmx3mm duly painted including Two M.S. angle iron posts of size 65 mm x 65 mm x 6 mm, 3.65 m long painted with alternate black and white bands of 25 cm width including all fixtures etc.and fixing the boards in 1:4:8 concrete block of size 60 cm x 60 cm x 75 cm including, excavation, refilling, transportation, and labour etc complete. Spec. No. As directed by Engineer in Charge & MoRTH specification 804 (COMMON SR 2023-24, Vol-3 Sl.No. 8.54 ,P.No - 78) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.No9450.09450.01.0FalseNoneNoneFalseNoneFalse9450.00
17212853720000NoneNoneRoadsImprovement of Cement Concrete Road in Annapoorneshwari Camp in Ballari Taluk. (Electrical Line work - Material)88683.6
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3539875127701NoneI.No. 1.04PSCC Pole - 8 Mtr Long, 140 Kg WL, ELE SR 2021-22, (Page No- 1, BESCOM III ,) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.No2496.02496.06.0FalseNoneNoneFalseNoneFalse14976.00
3539876127701NoneI.No. 6.0511 kV, 5 kN Composite/Polymeric Pin Insulator ELE SR 2021-22, (Page No- 2, BESCOM III ,) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.No221.0221.060.0FalseNoneNoneFalseNoneFalse13260.00
3539877127701NoneI.No. 5LT 4 Pin Cross Arm with clamps, bolts, nuts and washers ELE SR 2021-22, (Page No- 5, BESCOM V Cost Data Sheet-1,) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Set439.0439.012.0FalseNoneNoneFalseNoneFalse5268.00
3539878127701NoneI.No. 6.0845 KN Disk Insulators ELE SR 2021-22, (Page No- 2, BESCOM III ,) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.No470.0470.060.0FalseNoneNoneFalseNoneFalse28200.00
3539879127701NoneI.No. 7.01Weasel ACSR (6/2.59 mm Al + 1/2.59 mm St), Std Wt: 128 Kg/KM ELE SR 2021-22, (Page No- 3, BESCOM III ,) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.m37.0237.02480.0FalseNoneNoneFalseNoneFalse17769.60
3539880127701NoneI.No. 2.16Spiral Earth Electrode ELE SR 2021-22, (Page No- 2, BESCOM III ,) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.No248.0248.06.0FalseNoneNoneFalseNoneFalse1488.00
3539881127701NoneI.No. 5.12Anchor Raod using 12mm round/G ELE SR 2021-22, (Page No- 2, BESCOM III ,) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.No265.0265.06.0FalseNoneNoneFalseNoneFalse1590.00
3539882127701NoneI.No. 5.11Turn buckle (GI) ELE SR 2021-22, (Page No- 2, BESCOM III ,) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.No252.0252.06.0FalseNoneNoneFalseNoneFalse1512.00
3539883127701NoneI.No. 54.01G.I Grounding pipe,B-Class, 4 ELE SR 2021-22, (Page No- 17, BESCOM III ,) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.No770.0770.06.0FalseNoneNoneFalseNoneFalse4620.00
17212853720000NoneNoneRoadsImprovement of Cement Concrete Road in Annapoorneshwari Camp in Ballari Taluk. (Electrical Line work - Labour)30925.2
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3539884127702NoneI.No. 1.04PSCC Pole - 8 Mtr Long, 140 Kg WL, ELE SR 2021-22, (Page No- 1, BESCOM III ,) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.No2037.02037.06.0FalseNoneNoneFalseNoneFalse12222.00
3539885127702NoneI.No. 5LT 4 Pin Cross Arm with clamps, bolts, nuts and washers ELE SR 2021-22, (Page No- 5, BESCOM V Cost Data Sheet-1,) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Set232.0232.012.0FalseNoneNoneFalseNoneFalse2784.00
3539886127702NoneI.No. 6.01Stringing of Conductor (including pin binding, providing jumps, dead ending, etc.,) -Weasel ELE SR 2021-22, (Page No- 3, BESCOM IV ,) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.m2.912.91480.0FalseNoneNoneFalseNoneFalse1396.80
3539887127702NoneI.No. 6.04Releasing of Conductor-Weasel ELE SR 2021-22, (Page No- 3, BESCOM IV ,) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.m2.182.18480.0FalseNoneNoneFalseNoneFalse1046.40
3539888127702NoneI.No. 2.16Spiral Earth Electrode ELE SR 2021-22, (Page No- 2, BESCOM III ,) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.No70.070.06.0FalseNoneNoneFalseNoneFalse420.00
3539889127702NoneI.No. 5.12Anchor Raod using 12mm round/G ELE SR 2021-22, (Page No- 2, BESCOM III ,) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.No448.0448.06.0FalseNoneNoneFalseNoneFalse2688.00
3539890127702NoneI.No. 5.11Turn buckle (GI) ELE SR 2021-22, (Page No- 2, BESCOM III ,) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.No242.0242.06.0FalseNoneNoneFalseNoneFalse1452.00
3539891127702NoneI.No. 54.01G.I Grounding pipe,B-Class, 4 ELE SR 2021-22, (Page No- 17, BESCOM III ,) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.No1486.01486.06.0FalseNoneNoneFalseNoneFalse8916.00
17212853720000NoneNoneRoadsImprovement of Cement Concrete Road in Kyadigehal Village in Ballari Taluk. (CC Road)3369274.65
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3539892127703NoneI.No. 2.19Dismantling of cement concrete pavement by mechanical means using pneumatic tools, breaking to pieces not exceeding 0.02 m3 in volume and stock piling at designated locations and disposal of dismantled materials and stacking serviceable and unserviceable materials separately (COMMON SR 2023-24, Vol-3, P.NO -12, SL. No -2.19) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum591.15591.15225.0FalseNoneNoneFalseNoneFalse133008.750
3539893127703NoneI.No. 3.7Compacting original ground supporting embankment : Loosening, leveling and Compacting original ground supporting embankment to facilitate placement of first layer of embankment, scarified to a depth of 150 mm, mixed with water at OMC and then compacted by rolling so as to achieve minimum dry density as given in Table 300-2 for embankment construction (COMMON SR 2023-24, Vol-3, Sl.No.3.7 ,P.No - 17) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum110.25110.25306.0FalseNoneNoneFalseNoneFalse33736.50
3539894127703NoneI.No. 3.6Construction of Subgrade and Earthen Shoulders Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2 305 (COMMON SR 2023-24,Vol-3, Sl.No. 3.6 ,P.No -17) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum517.65517.65408.0FalseNoneNoneFalseNoneFalse211201.20
3539895127703NoneI.No. 4.1.A.(v)Granular Sub-Base A Plant Mix Method Construction of Granular Sub-Base of required grading as per design mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 (v) For Grading -V Material (COMMON SR 2023-24, Vol-3 Sl.No.4.1.A.(v) ,P.No - 23) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum2611.352611.35187.0FalseNoneNoneFalseNoneFalse488322.450
3539896127703NoneI.No. 4.17Wet Mix Macadam (Plant mix method)Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver/grader in sub-base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. (COMMON SR 2023-24, Vol-3 Sl.No.4.17 ,P.No - 26.) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum2686.952686.95255.0FalseNoneNoneFalseNoneFalse685172.250
3539897127703NoneI.No. 16.28Providing and constructing un-reinforced plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a concrete mixer of not less than 0.2 cum capacity and appropriate weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with shovels, rakes, compacted using needle, screed and plate vibrators and finished in continuous operation including construction joints, , primer, sealant , curing of concrete slabs for 14days, and water finishing to lines and grade as per drawing and technical specification clause 1501 with all lead, lifts, loading & unloading charges, cost and conveyance of all materials, labour, equipments etc., complete. as per the directions of the Engineer-in charge of the work. (COMMON SR 2021-22, Vol-3 Sl.No.16.28 ,P.No - 149) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum7091.77091.7255.0FalseNoneNoneFalseNoneFalse1808383.50
3539898127703NoneI.No. 8.54Providing and fixing board displaying information, such as 'Name of work, Tender cost, Name of Contractor, Work completion and liability period etc', having rectangular shape of 1.20m x 0.90m size made out 18 gauge (1.25mm) thick mild steel sheet painted with one coat of Zinc chromate stoving primer and two coats of enamel paint on front side and grey stove enamel on back side and border / messages / symbols etc. with approved colour shade paint complete, on M.S.angle of size 35 x 35 x 3 mm frame with properly cross braced M.S. angles of size 35mmx35mmx3mm duly painted including Two M.S. angle iron posts of size 65 mm x 65 mm x 6 mm, 3.65 m long painted with alternate black and white bands of 25 cm width including all fixtures etc.and fixing the boards in 1:4:8 concrete block of size 60 cm x 60 cm x 75 cm including, excavation, refilling, transportation, and labour etc complete. Spec. No. As directed by Engineer in Charge & MoRTH specification 804 (COMMON SR 2023-24, Vol-3 Sl.No. 8.54 ,P.No - 78) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.No9450.09450.01.0FalseNoneNoneFalseNoneFalse9450.00
17212853720000NoneNoneRoadsImprovement of Cement Concrete Road in Kyadigehal Village in Ballari Taluk. (CC Drain)420916.71
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3539899127704NoneI.No. 2.8 ii aDismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead. By Mechanical Means Cement Concrete Grade M-15 & M-20 (COMMON SR 2023-24, Vol-3, P.NO -10, SL. No -2.8 ii a) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum754.95754.9534.8FalseNoneNoneFalseNoneFalse26272.260
3539900127704NoneI.No. 1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work In all kinds of soils Depth upto 3 m (COMMON SR 2023-24, Vol-1, P.NO -8, SL. No -1.14.1) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum107.1107.183.2FalseNoneNoneFalseNoneFalse8910.720
3539901127704NoneI.No. 2.1.3Providing and laying in position plain cement concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machineries, curing, and all the other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement & formwork shall be paid separately) Mix 1:3:6 (M10) Using 40 mm nominal size graded crushed coarse aggregates (COMMON SR 2023-24 Vol-1, P.NO -15, SI.No -2.1.3) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum6288.456288.458.8FalseNoneNoneFalseNoneFalse55338.360
3539902127704NoneI.No. 2.4.2Providing and laying in position Reinforced cement concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necesary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement & formwork to be paid separately) M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates (COMMON SR 2023-24 Vol-1, P.NO -16, SI.No -2.4.2) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum6639.156639.1525.2FalseNoneNoneFalseNoneFalse167306.580
3539903127704NoneI.No. 2.4.2Appendix I - Additionalities for Formwork, Centering & Scaffolding S.N.2 35 Percent P.N. 115 ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum2323.72323.725.2FalseNoneNoneFalseNoneFalse58557.240
3539904127704NoneI.No. 2.11Supplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. h. All other type of structures (COMMON SR 2023-24 Vol-1, P.NO -18, SI.No -2.11) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Tonne82961.5582961.551.26FalseNoneNoneFalseNoneFalse104531.5530
17212853720000NoneNoneRoadsImprovement of Cement Concrete Road in Kyadigehal Village in Ballari Taluk. (Cross Drainage)632340.8
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3539905127705NoneI.No. 1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work In all kinds of soils Depth upto 3 m (COMMON SR 2023-24, Vol-1, P.NO -8, SL. No -1.14.1) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum107.1107.184.0FalseNoneNoneFalseNoneFalse8996.40
3539906127705NoneI.No. 2.1.3Providing and laying in position plain cement concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machineries, curing, and all the other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement & formwork shall be paid separately) Mix 1:3:6 (M10) Using 40 mm nominal size graded crushed coarse aggregates (COMMON SR 2023-24 Vol-1, P.NO -15, SI.No -2.1.3) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum6288.456288.457.2FalseNoneNoneFalseNoneFalse45276.840
3539907127705NoneI.No. 2.4.2Providing and laying in position Reinforced cement concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necesary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement & formwork to be paid separately) M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates (COMMON SR 2023-24 Vol-1, P.NO -16, SI.No -2.4.2) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum6639.156639.1538.4FalseNoneNoneFalseNoneFalse254943.360
3539908127705NoneI.No. 2.4.2Appendix I - Additionalities for Formwork, Centering & Scaffolding S.N.2 35 percent P.N. 115 ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Mtr2323.72323.738.4FalseNoneNoneFalseNoneFalse89230.080
3539909127705NoneI.No. 2.11Supplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. h. All other type of structures (COMMON SR 2023-24 Vol-1, P.NO -18, SI.No -2.11) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Tonne82961.5582961.552.5FalseNoneNoneFalseNoneFalse207403.8750
3539910127705NoneI.No. 12.3.ABack filling behind abutment, wing wall and return wall complete including compaction as per drawing and Technical Specification . A Granular material 710.1.4.of IRC:78 &2200 (COMMON SR 2023-24 Vol-3, P.NO -117, SI.No -12.3.A) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum1226.41226.421.6FalseNoneNoneFalseNoneFalse26490.240
17212853720000NoneNoneRoadsImprovement of Cement Concrete Road in Srinivas Camp in Ballari Taluk. (CC Road)3862587.2
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3539911127706NoneI.No. 2.5 (ii).AClearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness..(ii) By Mechanical Means using Dozer (A) In area of light jungle (COMMON SR 2023-24, Vol-3 Sl.No. 2.5 (ii).A, P.No - 9) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Sqm412.65412.653.85FalseNoneNoneFalseNoneFalse1588.70250
3539912127706NoneI.No. 3.7Compacting original ground supporting embankment : Loosening, leveling and Compacting original ground supporting embankment to facilitate placement of first layer of embankment, scarified to a depth of 150 mm, mixed with water at OMC and then compacted by rolling so as to achieve minimum dry density as given in Table 300-2 for embankment construction (COMMON SR 2023-24, Vol-3, Sl.No.3.7 ,P.No - 17) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum110.25110.25434.62FalseNoneNoneFalseNoneFalse47916.8550
3539913127706NoneI.No. 3.6Construction of Subgrade and Earthen Shoulders Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2 305 (COMMON SR 2023-24,Vol-3, Sl.No. 3.6 ,P.No -17) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum517.65517.65558.37FalseNoneNoneFalseNoneFalse289040.23050
3539914127706NoneI.No. 4.1.A.(v)Granular Sub-Base A Plant Mix Method Construction of Granular Sub-Base of required grading as per design mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 (v) For Grading -V Material (COMMON SR 2023-24, Vol-3 Sl.No.4.1.A.(v) ,P.No - 23) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum2611.352611.35262.25FalseNoneNoneFalseNoneFalse684826.53750
3539915127706NoneI.No. 4.17Wet Mix Macadam (Plant mix method)Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver/grader in sub-base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. (COMMON SR 2023-24, Vol-3 Sl.No.4.17 ,P.No - 26.) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum2686.952686.95176.06FalseNoneNoneFalseNoneFalse473064.4170
3539916127706NoneI.No. 16.28Providing and constructing un-reinforced plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a concrete mixer of not less than 0.2 cum capacity and appropriate weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with shovels, rakes, compacted using needle, screed and plate vibrators and finished in continuous operation including construction joints, , primer, sealant , curing of concrete slabs for 14days, and water finishing to lines and grade as per drawing and technical specification clause 1501 with all lead, lifts, loading & unloading charges, cost and conveyance of all materials, labour, equipments etc., complete. as per the directions of the Engineer-in charge of the work. (COMMON SR 2021-22, Vol-3 Sl.No.16.28 ,P.No - 149) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum6692.76692.7352.13FalseNoneNoneFalseNoneFalse2356700.4510
3539917127706NoneI.No. 8.54Providing and fixing board displaying information, such as 'Name of work, Tender cost, Name of Contractor, Work completion and liability period etc', having rectangular shape of 1.20m x 0.90m size made out 18 gauge (1.25mm) thick mild steel sheet painted with one coat of Zinc chromate stoving primer and two coats of enamel paint on front side and grey stove enamel on back side and border / messages / symbols etc. with approved colour shade paint complete, on M.S.angle of size 35 x 35 x 3 mm frame with properly cross braced M.S. angles of size 35mmx35mmx3mm duly painted including Two M.S. angle iron posts of size 65 mm x 65 mm x 6 mm, 3.65 m long painted with alternate black and white bands of 25 cm width including all fixtures etc.and fixing the boards in 1:4:8 concrete block of size 60 cm x 60 cm x 75 cm including, excavation, refilling, transportation, and labour etc complete. Spec. No. As directed by Engineer in Charge & MoRTH specification 804 (COMMON SR 2023-24, Vol-3 Sl.No. 8.54 ,P.No - 78) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.No9450.09450.01.0FalseNoneNoneFalseNoneFalse9450.00
17212853730000NoneNoneRoadsImprovement of Cement Concrete Road in Srinivas Camp in Ballari Taluk. (Cross Drainage)79199.4
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3539918127707NoneI.No. 1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work In all kinds of soils Depth upto 3 m (COMMON SR 2023-24, Vol-1, P.NO -8, SL. No -1.14.1) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum107.1107.14.2FalseNoneNoneFalseNoneFalse449.820
3539919127707NoneI.No. 2.1.3Providing and laying in position plain cement concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machineries, curing, and all the other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement & formwork shall be paid separately) Mix 1:3:6 (M10) Using 40 mm nominal size graded crushed coarse aggregates (COMMON SR 2023-24 Vol-1, P.NO -15, SI.No -2.1.3) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum6288.456288.451.4FalseNoneNoneFalseNoneFalse8803.830
3539920127707NoneI.No. 16.15.BProviding and laying reinforced cement concrete pipe NP3 for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works,backfilling, concrete and masonry works in head walls and parapets Clause 1101.6 (COMMON SR 2023-24, Vol-3 Sl.No. 16.15.B, P.No - 146) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Mtr3501.753501.7515.0FalseNoneNoneFalseNoneFalse52526.250
3539921127707NoneI.No. 1.8Construction of Embankment by excavating the available approved Gravel/Murrum deposited at a place or borrow pits during or prior excavation with all lifts and lead, transportation to site, spreading, grading to required slope andcompacting to meet the requirement complete as per specifications, includingcost of labour,rolling,water,all materials,usage& all other appurtenaces required to complete the work. (COMMON SR 2023-24, Vol-1, SI.No.1.8, P.No - 7) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum497.7497.735.0FalseNoneNoneFalseNoneFalse17419.50
17212853730000NoneNoneRoadsImprovement of Cement Concrete Road in Kallukamba Village in Ballari Taluk. (CC Road)4441354.67
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3539922127708NoneI.No. 2.5 (ii).AClearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness..(ii) By Mechanical Means using Dozer (A) In area of light jungle (COMMON SR 2023-24, Vol-3 Sl.No. 2.5 (ii).A, P.No - 9) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Sqm412.65412.653.01FalseNoneNoneFalseNoneFalse1242.07650
3539923127708NoneI.No. 1.12Earth work in surface excavation by mechanical means for lowering & leveling the ground for all works other than foundation in all kinds of soils & upto depth not exceeding 300mm as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenances required to complete the work. In all kinds of soils upto 300 mm depth (COMMON SR 2023-24, Vol-1, P.NO -8, SL. No -1.12) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum99.7599.751657.5FalseNoneNoneFalseNoneFalse165335.6250
3539924127708NoneI.No. 3.7Compacting original ground supporting embankment : Loosening, leveling and Compacting original ground supporting embankment to facilitate placement of first layer of embankment, scarified to a depth of 150 mm, mixed with water at OMC and then compacted by rolling so as to achieve minimum dry density as given in Table 300-2 for embankment construction (COMMON SR 2023-24, Vol-3, Sl.No.3.7 ,P.No - 17) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum110.25110.25497.25FalseNoneNoneFalseNoneFalse54821.81250
3539925127708NoneI.No. 3.6Construction of Subgrade and Earthen Shoulders Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2 305 (COMMON SR 2023-24,Vol-3, Sl.No. 3.6 ,P.No -17) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum517.65517.65664.87FalseNoneNoneFalseNoneFalse344169.95550
3539926127708NoneI.No. 4.1.A.(v)Granular Sub-Base A Plant Mix Method Construction of Granular Sub-Base of required grading as per design mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 (v) For Grading -V Material (COMMON SR 2023-24, Vol-3 Sl.No.4.1.A.(v) ,P.No - 23) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum2611.352611.35294.25FalseNoneNoneFalseNoneFalse768389.73750
3539927127708NoneI.No. 4.17Wet Mix Macadam (Plant mix method)Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver/grader in sub-base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. (COMMON SR 2023-24, Vol-3 Sl.No.4.17 ,P.No - 26.) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum2686.952686.95192.75FalseNoneNoneFalseNoneFalse517909.61250
3539928127708NoneI.No. 16.28Providing and constructing un-reinforced plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a concrete mixer of not less than 0.2 cum capacity and appropriate weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with shovels, rakes, compacted using needle, screed and plate vibrators and finished in continuous operation including construction joints, , primer, sealant , curing of concrete slabs for 14days, and water finishing to lines and grade as per drawing and technical specification clause 1501 with all lead, lifts, loading & unloading charges, cost and conveyance of all materials, labour, equipments etc., complete. as per the directions of the Engineer-in charge of the work. (COMMON SR 2021-22, Vol-3 Sl.No.16.28 ,P.No - 149) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.Cum6692.76692.7385.5FalseNoneNoneFalseNoneFalse2580035.850
3539929127708NoneI.No. 8.54Providing and fixing board displaying information, such as 'Name of work, Tender cost, Name of Contractor, Work completion and liability period etc', having rectangular shape of 1.20m x 0.90m size made out 18 gauge (1.25mm) thick mild steel sheet painted with one coat of Zinc chromate stoving primer and two coats of enamel paint on front side and grey stove enamel on back side and border / messages / symbols etc. with approved colour shade paint complete, on M.S.angle of size 35 x 35 x 3 mm frame with properly cross braced M.S. angles of size 35mmx35mmx3mm duly painted including Two M.S. angle iron posts of size 65 mm x 65 mm x 6 mm, 3.65 m long painted with alternate black and white bands of 25 cm width including all fixtures etc.and fixing the boards in 1:4:8 concrete block of size 60 cm x 60 cm x 75 cm including, excavation, refilling, transportation, and labour etc complete. Spec. No. As directed by Engineer in Charge & MoRTH specification 804 (COMMON SR 2023-24, Vol-3 Sl.No. 8.54 ,P.No - 78) ---- including cost of all materials, with all lead and lifts, loading and un-loading charges, cost of labour, HOM charges of all machineries, incidental and equipment charges, and implementation of Environmental and Social Safeguards etc., complete and as per the directions of engineer-in-charge of work.No9450.09450.01.0FalseNoneNoneFalseNoneFalse9450.00
generalCriterionList
createdTsversioncreatedDatemodifiedDatecriterionTypedescriptiontenderEligibilityCriterionDocumentList
17212853740000NoneNoneELIGIBILITYTenders from Joint ventures are not acceptable.None
17212853740000NoneNoneELIGIBILITYBidders shall not be under a declaration of ineligibility for corrupt and fraudulent practices issued by Government of Karnataka None
17212853740000NoneNoneELIGIBILITYBidders shall ensure upload of relevant document certifying his/her status as Scheduled Caste/ Scheduled Tribe/other reserved category as prescribed in the tender document.None
17212853740000NoneNoneELIGIBILITYIt shall be the responsibility of the Bidder to ensure credit of Tender Processing Fee and EMD into the respective receiving bank accounts of e-Procurement on or before the last date and time of bid submission.None
17212853740000NoneNoneELIGIBILITYEMD Payments through e-Payment mode shall be made as one single transaction and payments made in part are liable for rejection.None
17216355090000NoneNoneELIGIBILITYIt shall be the responsibility of the Bidder to ensure credit of Tender Processing Fee and EMD into the respective receiving bank accounts of e-Procurement on or before the last date and time of bid submission.None
17216355230000NoneNoneELIGIBILITYThe bidder is required to ensure browser compatibility of the computer well in advance to the last date and time for receipt of tenders. The departments shall not be responsible for non accessibility of e Procurement portal due to internet connectivity issues and technical glitches at bidders end.None
17216355320000NoneNoneELIGIBILITYAs per Karnataka State Government order No LD/300/LET/2006 Bangalore Dated 01.01.2007 and Government Letter No.PW/134/BMS/2007 Dated 27.07.2007, a sum amounting to 1%of the bill amount will be deducted towards Construction Labour Welfare fund.None
17216355440000NoneNoneELIGIBILITYEMD Payments through e-Payment mode shall be made as one single transaction and payments made in part are liable for rejection.None
17216355560000NoneNoneELIGIBILITYThe Item Rate quoted shall include the Royalty Charges on construction materials and other taxes as per prevailing Government Orders, except GST, which will be paid separately.None
17216355650000NoneNoneELIGIBILITYConditional tenders will not be accepted.None
17216355760000NoneNoneELIGIBILITYThe Tenderer shall obtain the required work done certificates from the Competent Authority not below the rank of Executive Engineer or equivalent.None
17216355860000NoneNoneELIGIBILITYFinancial Year will be reckoned as the period between first day of April and Thirty first day of March of succeeding year (both days inclusive).None
17216355960000NoneNoneELIGIBILITYThe Tenderer shall scan Original Ownership Documents/ Lease/ Hire commitment Agreement for the Machineries and attach the scanned file to the Bid. The Original Documents shall be produced at the time of opening of technical Bids for physical verification.None
17216356140000NoneNoneELIGIBILITYThe Employer reserves the right to reject any or all Tenders without assigning any reason or whatsoever.None
17216356310000NoneNoneELIGIBILITYThe tenderer shall maintain the Road/Building during the defect liability period at his own cost.None
17216356420000NoneNoneELIGIBILITYThe Department is not responsible for any delay in accessing e-procurement portal.None
17216356530000NoneNoneELIGIBILITYTenderer shall note that the Tenders of those found Eligible as mentioned in Clause 3 - Qualification of the Tenderer in Section 2: Instructions to Tenderers (ITT), will only be considered for evaluation.None
17216356650000NoneNoneELIGIBILITYThe star rates in respect of specified materials (Cement, Steel and Bitumen) shall be payable as per Government Circular No.PWD/159/CRM/2009 Dated 30-09-2010 (If applicable for this work).None
17216356780000NoneNoneELIGIBILITYThe proposed methodology and program of construction, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability of execution and completion of the work as per technical specifications within the stipulated period of completion.None
17216356890000NoneNoneELIGIBILITYAgency shall comply with ISO14001 (Environmental Management System) requirement during execution of work.None
17216357010000NoneNoneELIGIBILITYIt is mandatory to use Manufactured Sand for works costing more than 10.00 crores, as per Government Circular No.PWD/72/BMS/2013 dated 31-07-2013. Also it is mandatory that the bidders should upload the required documents which demonstrate that, the bidder owns sand manufacturing unit or an agreement with the manufactured sand suppliers. The manufactured sand that should be got tested to confirm IS 383-2007 before use. Further, the contractor shall have his own Artificial sand manufacturing plant Unit.None
17216357120000NoneNoneELIGIBILITYContractor should establish a fully functional laboratory at site at their own cost and risk in order to carry out all the required tests as per approved Quality Assurance Plan (QAP) for satisfactory completion.None
17216357260000NoneNoneELIGIBILITYAll safety precautions, warning signs, night illumination, reflectors, deployment of security guards has to be ensured so that no untoward incident happens on account of negligence or any project activity till completion. Contractor should indemnify the client to that extent.None
17216357340000NoneNoneELIGIBILITYContractor should adhere to HSE policy applicable for similar projects. Contractor to that extent should submit HSE document defining all the procedure including the policies before execution of the project.None
17216357440000NoneNoneELIGIBILITYContractor should follow strictly the prevailing rules of Labour Act and applicable any other law as concerned to work.None
17216357530000NoneNoneELIGIBILITYIf undue delay caused by the contractor, the progressive damages caused to road will be assessed and make good at the cost and risk of the contractor. In addition, suitable action will be initiated against the contractor for the damages occurred during the undue delay period in accordance with the Karnataka Highway Act, 1964.None
17216357790000NoneNoneELIGIBILITYFinancial turnover of previous years shall be given a weightage of 10% per year to bring them to the price level of the 2024-25. And Value at 2024-25 price level, of existing commitments and on-going works to be executed during the next 12 months (Financial commitment of previous years shall be given a weightage of 10% per year to bring them to the price level of the 2024-25) in the Technical Qualification Criteria mentioned in the next section.None
17216357870000NoneNoneELIGIBILITYIt is mandatory for the contractor to upload the work done certificate issued by an officer not below the rank of Executive Engineer duly indicating the work indent numbers for works costing more than Rs.5.00 lakhs.None
17216357970000NoneNoneELIGIBILITYThe tenderer shall note that, the GST at 18% shall be paid to the tendered amount separately.None
17216358060000NoneNoneELIGIBILITYThe tenderer shall note that, the increase in GST shall not be paid in the extended period of contract for which the contractor alone is responsible for delay as determined by the authority while granting the extension of time.None
17216358150000NoneNoneELIGIBILITYThe tenderers shall note that, as per The Karnataka Minor Mineral Concession Rules-1964, it is mandatory to submit the Mineral dispatch Permits (MDPs) issued by a competent authority, along with the bills. If not, penalty will be levied as per the prevailing clauses.None
17216358250000NoneNoneELIGIBILITYAny dispute or difference or claim arising out of or in connection with or relating to the present contract or the breach, termination or invalidity thereof shall be referred and settled under the arbitration Centre-Karnataka (Domestic and International) Rules 2012 by one or more arbitrators appointed in accordance with its rules.None
17216358360000NoneNoneELIGIBILITYIt is mandatory to furnish the information regarding works which are yet to be completed, as on date of submission of his tender, in format-5. The tenderer shall note that, deliberately not furnishing the correct information is liable for rejection of such tenders.None
17216358460000NoneNoneELIGIBILITYThe time stipulated for completion of work is 9 (Nine) calendar months including rainy season.None
17216358540000NoneNoneELIGIBILITYThe defect liability period for the work is 5 (Five) YearsNone
17216358860001NoneNoneELIGIBILITYAs Per the Government order, the defect liability period for this project is 5 Years (Five) Years (For Initial 2 years after completion of work, road shall be maintained by the contractor at his own cast and risk. subsequently, for 3rd, 4th and 5th years, maintenance shall be carried out as per BOQNone
preQualCriterionListNone
technicalCriterionList
createdTsversioncreatedDatemodifiedDatedescriptioncriterionCategoryTextcriterionTypeOthersValuetenderTechnicalCriterionDocumentList
NoneNoneNoneNoneTenderer or his identified Sub Contractor should possess valid license for executing water supply / sanitary engineering works and should have executed similar works totallng Rs. xxxxxx (not less than 50% of electrical works) n any one yearNoneNone
NoneNoneNoneNoneOwning the following key and critical equipment for this work (xxxx, xxxx, xxxx)NoneNone
NoneNoneNoneNoneTotal value of civl engineering works executed and payments received in the last five years (year-wise)NoneNone
NoneNoneNoneNoneList of works for which tenders already submittedNoneNone
NoneNoneNoneNoneBanker Details for referenceNoneNone
NoneNoneNoneNoneConstruction equipment owned by the tenderer and equipment proposed to be deployed on this contract, if awardedNoneNone
NoneNoneNoneNoneReports on the financial standing of the tenderer, such as profit and loss statements and auditor’s reports for the last five yearsNoneNone
NoneNoneNoneNoneQualification and experience of the key technical and management personnel in permanent employment with the tenderer and those that are proposed to be deployed on this contract, if awardedNoneNone
NoneNoneNoneNoneList of Financial Resources with CertificatesNoneNone
NoneNoneNoneNoneTo qualify for award of this contract, each Tenderer in his/her name should have in the last five years i.e., 2019-20, 2020-21, 2021-22, 2022-23 and 2023-24, achieved in at least two financial years an annual financial turnover (in all classes of civil engineering construction works only) of Rs.762.47 Lakhs.Past ExperienceNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneAudited CA Certificate of Annual Turnover
NoneNoneNoneNoneTo qualify for award of this contract, each Tenderer in his/her name should have in the last five years i.e., 2019-20, 2020-21, 2021-22, 2022-23 and 2023-24, satisfactorily completed as prime contractor, at least one Similar Nature of Work such as Construction of cement concrete road and drain work of value not less than Rs.190.62 Lakhs.Past ExperienceNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneSatisfactory Performance Certificate
NoneNoneNoneNoneTo qualify for award of this contract, each Tenderer in his/her name should have in the last five years i.e., 2019-20, 2020-21, 2021-22, 2022-23 and 2023-24 had executed in any one Financial year, the following minimum quantities items of work (a)Earthwork Excavation/Formation of Road Embankment/Sub-grade/sub-base-6236 Cum. (b) Granular sub-base-1521 Cum (c) Wet Mix Macadam/Water bound macadam - 1511 Cum (d) PCC/RCC-2494 Cum (e) Steel reinforcement - 20 MTPast ExperienceNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneOthers -- Quanity wise work done certificate
NoneNoneNoneNoneTenderer shall further demonstrate : Availability Tippers, by Own - 2 No. and by Own / Hire / Lease - 2 No. (The documents in proof of ownership shall have to be attested by Notary or Government Gazetted Officer). At the time of opening of the Technical Bid, the documents to be submitted in original for verification.Capabilities of VendorNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneOthers -- Documents of machinaries
NoneNoneNoneNoneTenderer shall further demonstrate : Availability Vehicle mounted water tanker (a) By own- 1 No and (b) By own/Hire/Lease -1 No. (The documents in proof of ownership shall have to be attested by Notary or Government Gazetted Officer). At the time of opening of the Technical Bid, the documents to be submitted in original for verificationCapabilities of VendorNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneOthers -- Documents of machineries
NoneNoneNoneNoneTenderer shall further demonstrate : Availability by Own/Hire/Lease -Hydraulic Excavator - 1 No (The documents in proof of ownership shall have to be attested by Notary or Government Gazetted Officer). At the time of opening of the Technical Bid, the documents to be submitted in original for verification.Capabilities of VendorNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneOthers -- Documents of machineries
NoneNoneNoneNoneTenderer shall further demonstrate : Availability of Self loading mobile concrete mixer by own-1 No and by own/hire/lease-1 No (The documents in proof of ownership shall have to be attested by Notary or Government Gazetted Officer). At the time of opening of the Technical Bid, the documents to be submitted in original for verification.Capabilities of VendorNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneOthers -- Documents of machineries
NoneNoneNoneNoneTenderer shall further demonstrate : Availability by Own - Vibratory Road Roller - 1 No (The documents in proof of ownership shall have to be attested by Notary or Government Gazetted Officer). At the time of opening of the Technical Bid, the documents to be submitted in original for verification.Capabilities of VendorNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneOthers -- Documents of machineries
NoneNoneNoneNoneLiquid Assets and /or availability of credit facilities of no less than Rs.127.08 Lakhs (Un-conditional Credit Lines/letter of credit/ certificates from the banks for meeting the fund requirement etc. from any nationalized or scheduled bank.Financial StatusNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneLine of Credit
NoneNoneNoneNoneCopy of Registration for having registered in KPWD under Class-II and above categoryOthersConstitutional and Legal Status of Tenderer
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNonePWD Registration Certificate (Class I/II/III/IV)
NoneNoneNoneNoneDetailed information on committed offers of works on hand and on going works which are yet to be completed.OthersExisting commitments
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneOthers -- Existing commitments
NoneNoneNoneNoneDetailed information of the works for which Tenderer has submitted his tender in different departments either Central or State.OthersTendered Works
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneOthers -- Tendered works
NoneNoneNoneNoneDetailed information on litigation in which the Tenderer is involved as concerned to Government worksOthersLitigation
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneOthers -- Litigation
NoneNoneNoneNoneDetailed information of the works for which LOA received for the works tendered from different departments either Central or State.OthersNew works
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneOthers -- New works
tenderCriterionDocumentList
documentNameoptionaldocumentTypeText
Annual Turnover Certificate issued by Chartered accountant compulsorily indicating UDINTrueTechnical Bid
Contractor Registration certificate for having registered under Class-II and above category in KPWDTrueTechnical Bid
Similar work done certificate issued by an officer not below the rank of Executive EngineerTrueTechnical Bid
Quantity wise work done certificate issued by an officer not below the rank of Executive EngineerTrueTechnical Bid
Un-conditional Bank line of credit from any Nationalized or scheduled bankTrueTechnical Bid
Documents of machineriesTrueTechnical Bid
Current contract commitmentsTrueTechnical Bid
tenderWorkLocationList
tenderAddress
createdTs1721737056000
version0
createdDateNone
modifiedDateNone
blockNumberOffice of the Executive Engineer, Fort Main Road
streetNone
cityBallari
stateKarnataka
pin583102
tenderRecallDTONone