1722591779000 | 1 | None | None | Other Works | Re-construction of collapsed RCC retaining wall with compound wall at colony side of 66/11 KV sub-station Hosakerehalli, Bengaluru. | 2304604.66 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3675197 | 134459 | None | code01 | PART-A
Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness. In area of thorny jungle
(KPWD SR 2023-24, Vol-3, P - 7 / I - 2.4 (i) B) | Sqm | 19.47 | 19.47 | 3000.0 | False | None | None | False | None | False | 58410.0 | 0 | 3675198 | 134459 | None | code02 | Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material to the appropriate disposal area as per direction of Engineer-in-charge. In cement mortar
(KPWD SR 2023-24, Vol-3, P - 187 / I - 19.7.3) | Cum | 1335.64 | 1335.64 | 20.0 | False | None | None | False | None | False | 26712.8 | 0 | 3675199 | 134459 | None | code03 | Demolishing stone rubble masonry manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material to the appropriate disposal area as per direction of Engineering- charge. In cement mortar
(KPWD SR 2023-24, Vol-3, P - 187 / I - 19.9.2) | Cum | 2185.83 | 2185.83 | 25.0 | False | None | None | False | None | False | 54645.75 | 0 | 3675200 | 134459 | None | code04 | Earth work excavation by manual means for drains, canals, waste weir, draft, approach channels, key trenches, foundation of bridges and such similar works in all kinds of soils , as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter, excavated surface levelled and sides neatly dressed disposing off the excavated stuff or sorting & stacking the selected stuff for reuse in a radius of 50 m and lift up to 1.5 m including cost of labour, tools & other appurtenances required to complete the work Depth exceeding 1.5m, but not exceeding 3 m. Note: Cost of De-watering up to 10 % may be added , where required assessment for dewatering shall be made as per site condition
(KPWD SR 2023-24, Vol-1, P - 5 / I - 1.4.2 | Cum | 336.18 | 336.18 | 210.0 | False | None | None | False | None | False | 70597.8 | 0 | 3675201 | 134459 | None | code05 | Providing and laying in position plain cement concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machineries, curing, and all the other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement & formwork shall be paid separately) Mix 1:4:8( M5) Using 40 mm nominal size graded crushed coarse aggregates
(KPWD SR 2023-24, Vol-1, P - 15 / I - 2.1.2 | Cum | 7351.87 | 7351.87 | 20.0 | False | None | None | False | None | False | 147037.4 | 0 | 3675202 | 134459 | None | code06 | Providing and laying in position Reinforced cement concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement & formwork to be paid separately. M20 Design Mix Using 20 mm and down size graded crushed coarse aggregates (KPWD SR 2023-24 Volume-I Chapter-2 page 17 Item No:2.4.2) | Cum | 8953.37 | 8953.37 | 92.0 | False | None | None | False | None | False | 823710.04 | 0 | 3675203 | 134459 | None | code07 | Providing Thermo-Mechanically Treated bars of grade Fe-500D or more Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position, binding and anchoring to adjacent members wherever necessary complete as per Design including cost of material, labour, usage charges complete as per specifications. (The laps and wastages shall not be measured separately) (KPWD SR 2023-24 Volume-II Chapter-11 page 84 Item No: 11.32) | t | 102556.28 | 102556.28 | 7.8 | False | None | None | False | None | False | 799938.984 | 0 | 3675204 | 134459 | None | code08 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m. (KPWD SR 2023-24 Volume-I Chapter-1 page 7 Item No:1.9) | Cum | 207.68 | 207.68 | 135.0 | False | None | None | False | None | False | 28036.8 | 0 | 3675205 | 134459 | None | code09 | Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/ return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing face. Complete as per drawing and Technical Specifications (KPWD SR 2023-24 Volume-3, page 99 Item No: 13.3) | Rmtr | 179.12 | 179.12 | 55.0 | False | None | None | False | None | False | 9851.6 | 0 | 3675206 | 134459 | None | code10 | Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. (KPWD SR 2023-24 Volume-2, page 17 Item No: 6.32) | Sqm | 1700.38 | 1700.38 | 85.0 | False | None | None | False | None | False | 144532.3 | 0 | 3675207 | 134459 | None | code11 | Providing and laying in position Reinforced cement concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement & formwork to be paid separately) Mix 1:2:4 (M15) Using 20 mm nominal size graded crushed coarse aggregates.
(KPWD SR 2023-24 Volume-1, Page 17 Item No: 2.4.1) | Cum | 8312.39 | 8312.39 | 1.5 | False | None | None | False | None | False | 12468.585 | 0 | 3675208 | 134459 | None | code12 | Providing 20 mm cement plaster of mix :1:4 (1 cement: 4 fine sand) to brick/stone masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. (KPWD SR 2023-24 Volume-2, page 41 Item No: 8.3.1) | Sqm | 459.49 | 459.49 | 90.0 | False | None | None | False | None | False | 41354.1 | 0 | 3675209 | 134459 | None | code13 | Providing and fixing Structural Steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge.(KPWD SR 2023-24 Volume-II Chapter-11 page 75 Item No:11.2) | Kg | 146.67 | 146.67 | 270.0 | False | None | None | False | None | False | 39600.9 | 0 | 3675210 | 134459 | None | code14 | Fencing with G.I. barbed wire Angle iron post placed at required distance embedded in cement concrete blocks, every 15th post, last but one end post and corner post shall be strutted on both sides and end post on one side only and provided with horizontal lines and two diagonals interwoven with horizontal wires, of barbed wire weighing 9.38 kg per 100 m (minimum), between the two posts fitted and fixed with G.I. staples, turn buckles etc. complete. (Cost of posts, struts, earth work and concrete work to be paid for separately). Payment to be made per metre cost of total length of barbed wire used. With G.I. barbed wire
.(KPWD SR 2023-24 Volume-II Chapter-11 page 95 Item No:11.57.1) | Rmtr | 23.36 | 23.36 | 500.0 | False | None | None | False | None | False | 11680.0 | 0 | 3675211 | 134459 | None | code15 | Applying priming coat: With ready mixed pink or Grey primer of approved brand and manufacture on wood work (hard and soft wood) including preparing the surface after thoroughly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge.
(KPWD SR 2023-24 Volume-II, Page 47 Item No:8.34.1) | Sqm | 68.79 | 68.79 | 90.0 | False | None | None | False | None | False | 6191.1 | 0 | 3675212 | 134459 | None | code16 | Wall painting with acrylic emulsion paint of approved brand and manufacture to give an even shade :Two coats on new work after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge.
.(KPWD SR 2023-24 Volume-II, Page 48 Item No:8.39) | Sqm | 164.85 | 164.85 | 90.0 | False | None | None | False | None | False | 14836.5 | 0 | 3675213 | 134459 | None | code17 | PART-B Credit to the Estimate
Available stone from I.No. 03 | Nos | 10.0 | 10.0 | 1500.0 | False | None | None | False | None | False | 15000.0 | 0 |
|