tenderSubEstimateList | createdTs | version | createdDate | modifiedDate | workCategoryName | subEstimateName | estimateTotal | itemList |
---|
1722946481000 | 0 | None | None | Buildings | 1 TOTAL COST OF PLANTED DRYING BEDS AND SCREENING CHAMBERS | 3471912.82 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3705707 | 136607 | None | AEEBDM001 | TOTAL COST OF PLANTED DRYING BEDS AND SCREENING CHAMBERS Lowering and Levelling:Earth work in surface excavation by mechanical means for lowering & leveling the ground for all works other than foundation in all kinds ofsoils & upto depth not exceeding 300mm as per drawing and technical specifications, including setting out, shoring, strutting, barricading,caution lights, removal of stumps and other deleterious matterincluding dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenances required to complete the work CSR 2023-24 Vol-I sl no 1.1 Page no 5 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 95.55 | 95.55 | 169.18 | False | None | None | False | None | False | 16165.149 | 0 | 3705708 | 136607 | None | AEEBDM002 | Earth work excavation for Foundation by mechanical means for all
works & depth upto 3 m, as per drawing and technical specifications,
including setting out, shoring, strutting, barricading, caution lights,
including dressing of excavated surfaces, disposing off or levelling the
excavated earth or sorting & stacking the selected earth for reuse in a
radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage
of machinery & other appurtenaces required to complete the work Upto 1.5M CSR 2023-24 Vol-I sl no 1.15.1 Page no 8 in ordinary /soft rock without blasting upto 1.5m depth and 3m with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 381.15 | 381.15 | 507.53 | False | None | None | False | None | False | 193445.0595 | 0 | 3705709 | 136607 | None | AEEBDM003 | Earth work excavation for Foundation by mechanical means for all
works & depth upto 3 m, as per drawing and technical specifications,including setting out, shoring, strutting, barricading, caution lights,including dressing of excavated surfaces, disposing off or levelling theexcavated earth or sorting & stacking the selected earth for reuse in aradius of 50 m and lift upto 1.5 m including cost of labour, tools, usageof machinery & other appurtenaces required to complete the workFrom 1.5M to 3 M CSR 2023-24 Vol-I sl no 1.15.1 Page no 8 in ordinary /soft rock without blasting upto 1.5m depth and 3km with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 446.25 | 446.25 | 83.23 | False | None | None | False | None | False | 37141.3875 | 0 | 3705710 | 136607 | None | AEEBDM004 | Plain Cement Concrete Providing and layingin position plain cemen tconcrete for levelling course for all works in foundation.The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed,laid in layers not exceeding 150mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machineries, curing, and all the other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement & form works hall be paid separately. Mix1:4:8(M7.5) Using 20mm nominal size graded crushed coarse aggregates CSR 2023-24 Vol-I sl no 2.1.2 Page no 15 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 5947.2 | 5947.2 | 31.04 | False | None | None | False | None | False | 184601.088 | 0 | 3705711 | 136607 | None | AEEBDM005 | Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes,
labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates CSR 2023-24 Vol-I sl no 2.2.3 Page no 15 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 6652.8 | 6652.8 | 124.77 | False | None | None | False | None | False | 830069.856 | 0 | 3705712 | 136607 | None | AEEBDM006 | Extra for providing and mixing waterproofing material in cement plaster work inproportion recommended by the manufacturers including cost of material etc as per specifications and as perdirections of the Engineer in-Charge with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 197.66 | 197.66 | 9.36 | False | None | None | False | None | False | 1850.0976 | 0 | 3705713 | 136607 | None | AEEBDM007 | Providing T.M.T steel reinforcement for R.C.C work including straightening, cutting, bending, hooking, placingin position, lapping and/ or welding wherever required, tying with binding wire and anchoring to the adjoining members wherever necessary complete as per design (laps,hooks and wastages hall not be measured and paid)including for OHT & reservoier,cost of materials,labour,HOM of machinery complete as per specifications. TMT bars Fe 550 CSR 2023-24 Volume-I sl no 2.11(h) page no 18 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Kg | 93.93 | 93.93 | 14972.4 | False | None | None | False | None | False | 1406357.532 | 0 | 3705714 | 136607 | None | AEEBDM008 | Providing and removing centering, shuttering, strutting, proppingetc., and removal of formwork for foundations, footings, bases of columns for mass concrete including cost of all materials, labour complete as per specificaitons.For Foundation works PCC foundation CSR 2023-24 Volume-I Addendeum sl no 3&11 page no 111&112 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 5947.2 | 5947.2 | 1.55 | False | None | None | False | None | False | 9218.16 | 0 | 3705715 | 136607 | None | AEEBDM009 | Providing and removing centering, shuttering, strutting, propping etc.,and removal of formwork for foundations, footings, bases of columns for mass concrete including cost of all materials, labour complete as per specificaitons. For Foundation works RCC foundation CSR 2023-24 Volume-I Addendeum sl no 3&11 page no 111&112 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 6652.8 | 6652.8 | 2.71 | False | None | None | False | None | False | 18029.088 | 0 | 3705716 | 136607 | None | AEEBDM010 | Providing and removing centering, shuttering, strutting, propping etc., and removal of formwork for foundations, footings, bases of columns for mass concrete including cost of all materials, labour complete as per specificaitons. For Foundation works RCC WALLS CSR 2023-24 Volume-I Addendeum sl no 3&11 page no 111&112 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 6652.8 | 6652.8 | 4.92 | False | None | None | False | None | False | 32731.776 | 0 | 3705717 | 136607 | None | AEEBDM011 | Providing 20 mm cement plaster of mix :1:4 (1 cement: 4 fine sand) to brick/stone masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per direc tions of Engineer-in-charge CSR 2023-24 Voll-II Sl no 8.3.1 Page no 41 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 371.7 | 371.7 | 937.2 | False | None | None | False | None | False | 348357.24 | 0 | 3705718 | 136607 | None | AEEBDM012 | Extra for providing and mixing waterproofing material in cement plaster work in proportion recommended by the manufacturer s including cost of material etc as per specifications and as per directions of the Engineer in-Charge with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 197.66 | 197.66 | 70.29 | False | None | None | False | None | False | 13893.5214 | 0 | 3705719 | 136607 | None | AEEBDM013 | Providing PVC ringtite pipes conforming to IS 4985:2000 with latest amendments and conveying to worksite, rolling and lowering into trenches, laying true to line and level and perfect linking at joints, testing and commissioning, including loading unloading at both destinations and cuts of pipes wherever necessary including jointing of PVC pipes and specials (excluding cost of specials) with jointing of approved type, with all labour with all lead & lift including encasing the pipe alround to a depth of not less than 15 cms. with soft gravel or selected earth available from the excavation etc. complete and giving necessary hydraulic test to the required pressure as per ISS (Contractor will make his own arrangements for procuring water for testing) etc.110mm dia(PDB inlet & Distribution pipe 72mtr, 110 mm dia vent pipe 30mtr, 110mm dia PDB outlet and interconnecting pipes between registers 21.600mtr CSR 2023-24 Voll-V Sl no 10.1.7 Page no 113 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Mtr | 431.55 | 431.55 | 123.6 | False | None | None | False | None | False | 53339.58 | 0 | 3705720 | 136607 | None | AEEBDM014 | Supply and delivery at site special moulded variety PVC tee as per IS 7834/ 1987 and fabricated as per IG124/ 1984 with ISI mark with its latest amendments 100mm dia PVC tees CSR Vol-V Sl no 10.108 Page no 117 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | No | 263.55 | 263.55 | 24.0 | False | None | None | False | None | False | 6325.2 | 0 | 3705721 | 136607 | None | AEEBDM015 | Supply and delivery at site special moulded variety PVC elbows as per IS 7834/ 1987 and fabricated as per IG124/ 1984 with ISI mark with its latest amendments 100mm dia PVC elbow CSR Vol-V Sl no 10.9.8 Page no 117 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | No | 317.1 | 317.1 | 60.0 | False | None | None | False | None | False | 19026.0 | 0 | 3705722 | 136607 | None | AEEBDM016 | Providing PVC ringtite pipes conforming to IS 4985:2000 with latest amendments and conveying to worksite, rolling and lowering into trenches, laying true to line and level and perfect linking at joints, testing and commissioning, including loading unloading at both destinations and cuts of pipes wherever necessary including jointing of PVC pipes and specials (excluding cost of specials) with jointing of approved type, with all labour with all lead & lift including encasing the pipe alround to a depth of not less than 15 cms. with soft gravel or selected earth available from the excavation etc. complete and giving necessary hydraulic test to the required pressure as per ISS (Contractorwill make his own arrangements for procuring water for testing) etcPVC pipes 160mm dia 6kg/sqcm & class 3 CSR 2023-24 Vol-V Sl no 10.1.9 Page no 113 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Mtr | 648.9 | 648.9 | 61.2 | False | None | None | False | None | False | 39712.68 | 0 | 3705723 | 136607 | None | AEEBDM017 | 100mm nominal dia endcap with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Each | 115.5 | 115.5 | 12.0 | False | None | None | False | None | False | 1386.0 | 0 | 3705724 | 136607 | None | AEEBDM018 | Supply and delivery at site special moulded variety PVC tee as per IS 7834/ 1987 and fabricated as per IG124/ 1984 with ISI mark with its latest amendments 160 mm dia PVC Tee CSR 2023-24 Vol-V sl no 10.10.10 Page no 118 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | No | 489.3 | 489.3 | 36.0 | False | None | None | False | None | False | 17614.8 | 0 | 3705725 | 136607 | None | AEEBDM019 | Providing and laying coarse aggregate size as below after washing and seiving to make it free from fines and dust: 53 mm nominal zize with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 1391.37 | 1391.37 | 29.4 | False | None | None | False | None | False | 40906.278 | 0 | 3705726 | 136607 | None | AEEBDM020 | Providing and laying coarse aggregate size as below after washing and seiving to make it free from fines and dust: 20 mm nominal zize with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 1543.44 | 1543.44 | 14.7 | False | None | None | False | None | False | 22688.568 | 0 | 3705727 | 136607 | None | AEEBDM021 | Providing and laying coarse aggregate size as below after washing and seiving to make it free from fines and dust: 6 mm nominal zize with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 1625.09 | 1625.09 | 14.7 | False | None | None | False | None | False | 23888.823 | 0 | 3705728 | 136607 | None | AEEBDM022 | Providing and laying coarse aggregate size as below after washing and seiving to make it free from fines and dust:sand/artificial sand/manufactured sand(0.75 to 4.75mm) with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 1695.09 | 1695.09 | 29.4 | False | None | None | False | None | False | 49835.646 | 0 | 3705729 | 136607 | None | AEEBDM023 | Perforated Slab Supplying/Casting and fixing Precast Reinforced Cement Concrete per forated slabs (2"diahole of following thickness in RCC 1:2:4, using following HBGS jelly including cost of reinforcement steel inposition, cost of moulding charges, casting of slab, finishing, curing and fixingin positioninall floors etc., complete complying with standard specification and as directed. Percolate channel perforated slabs (850mmx500mmX75mm) with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Each | 487.25 | 487.25 | 48.0 | False | None | None | False | None | False | 23388.0 | 0 | 3705730 | 136607 | None | AEEBDM024 | Plantation Loading and unloading of polythene bagged seedlings:Loading of polythene bagged seedlings in to vehicle at the nursery site and unloading at site nearest to planting site. Seedlings raised in14"X20"bags CSR 2021-22 Vol-III Sl no 2.3f Page 11 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | 1000 / Nos | 12202.26 | 12202.26 | 0.588 | False | None | None | False | None | False | 7174.92888 | 0 | 3705731 | 136607 | None | AEEBDM025 | Transportation of polythene bagged seedlings in hired truck from nursery site to plantation site.Seedlings raised in14"X20"bags:Distance upto 10km CSR 2021-22 Vol-III Sl no 2.4f Page 12 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | 1000 / Nos | 8092.54 | 8092.54 | 0.588 | False | None | None | False | None | False | 4758.41352 | 0 | 3705732 | 136607 | None | AEEBDM026 | Conveyance of polythene bagged seedling on head load from dumping site to planting location,near each trench/pits(Distanceupto3km) CSR 2021-22 Vol-III Sl no 2.5af Page 12 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | 1000 / Nos | 13191.56 | 13191.56 | 0.588 | False | None | None | False | None | False | 7756.63728 | 0 | 3705733 | 136607 | None | AEEBDM027 | Planting of polythene bagged seedlings after tearing with blade and removing polythene bags in trenches/pits including scoopings oil to required depth , pressing soil gently around seedling after planting. CSR 2021-22 Vol-III Sl no 2.6f Page 12 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | 1000 / Nos | 14296.88 | 14296.88 | 0.588 | False | None | None | False | None | False | 8406.56544 | 0 | 3705734 | 136607 | None | AEEBDM028 | Painting with synthetic enamel paint of approved brand and
manufacture of required colour to give an even shade :Two coats on new work over an under coat of suitable shade with ordinary paint of approved brand and manufacture after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labourcomplete as per specifications and as per directions of Engineer-in-charge. CSR 2023-24 Vol-II sl no 8.41 Page no 48 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 175.35 | 175.35 | 307.07 | False | None | None | False | None | False | 53844.7245 | 0 |
| 1722946481000 | 0 | None | None | Buildings | 2 TOTAL COST OF INTEGRATED SETTLER AND ANAEROBIC FILTER | 326290.17 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3705735 | 136608 | None | AEEBDM01 | TOTAL COST OF INTEGRATED SETTLER AND ANAEROBIC FILTER Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work Upto 1.5M CSR 2023-24 Vol-I sl no 1.15.1 Page no 8 in ordinary /soft rock without blasting upto 1.5m depth and 3km with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 381.15 | 381.15 | 49.82 | False | None | None | False | None | False | 18988.893 | 0 | 3705736 | 136608 | None | AEEBDM02 | Earth work excavation for Foundation by mechanical means for all
works & depth upto 3 m, as per drawing and technical specifications,including setting out, shoring, strutting, barricading, caution lights,including dressing of excavated surfaces, disposing off or levelling theexcavated earth or sorting & stacking the selected earth for reuse in aradius of 50 m and lift upto 1.5 m including cost of labour, tools, usageof machinery & other appurtenaces required to complete the workFrom 1.5M to 3 M CSR 2023-24 Vol-I sl no 1.15.1 Page no 8 in ordinary /soft rock without blasting upto 1.5m depth and 3km with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 446.25 | 446.25 | 1.66 | False | None | None | False | None | False | 740.775 | 0 | 3705737 | 136608 | None | AEEBDM03 | Plain Cement Concrete Providing and laying in position plain cement concrete for levelling course for all works infoundation.The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machineries, curing, and all the other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement & form work shall be paid separately. Mix1:4:8(M7.5) Using 20mm nominal size graded crushed coarse aggregates CSR 2023-24 Vol-I sl no 2.1.2 Page no 15 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 5947.2 | 5947.2 | 3.23 | False | None | None | False | None | False | 19209.456 | 0 | 3705738 | 136608 | None | AEEBDM04 | Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances
required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates CSR 2023-24 Vol-I sl no 2.2.3 Page no 15 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 6652.8 | 6652.8 | 11.93 | False | None | None | False | None | False | 79367.904 | 0 | 3705739 | 136608 | None | AEEBDM05 | Providing T.M.T steel reinforcement for R.C.C work including straightening, cutting, bending, hooking, placing in position, lapping and/or welding wherever required, tying with binding wire and anchoring to the adjoining members wherever necessary complete as per design(laps,hooks and wastages hall not be measured and paid)including for OHT & reservoier, cost of materials, labour, HOM of machinery complete as per specifications. TMT bars Fe 550 CSR 2023-24 Volume-I sl no 2.11(h) page no 18 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Kg | 93.93 | 93.93 | 1431.6 | False | None | None | False | None | False | 134470.188 | 0 | 3705740 | 136608 | None | AEEBDM06 | Providing and removing centering, shuttering, strutting, proppingetc., and removal of formwork for foundations, footings, bases of columns form assconcrete including cost of all materials, labour complete as per specificaitons.For Foundation works PCC foundation CSR 2023-24 Volume-I Addendeum sl no 3&11 page no 111&112 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 5947.2 | 5947.2 | 0.05 | False | None | None | False | None | False | 297.36 | 0 | 3705741 | 136608 | None | AEEBDM07 | Providing and removing centering, shuttering, strutting, proppingetc., and removal of formwork for foundations, footings, bases of columns form assconcrete including cost of all materials, labour complete as per specificaitons.For Foundation works RCC foundation CSR 2023-24 Volume-I Addendeum sl no 3&11 page no 111&112 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 6652.8 | 6652.8 | 0.05 | False | None | None | False | None | False | 332.64 | 0 | 3705742 | 136608 | None | AEEBDM08 | Providing and removing centering, shuttering, strutting, proppingetc., and removal of formwork for foundations, footings, bases of columns form assconcrete including cost of all materials, labour complete as per specificaitons.For Foundation works RCC WALLS CSR 2023-24 Volume-I Addendeum sl no 3&11 page no 111&112 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 6652.8 | 6652.8 | 0.1 | False | None | None | False | None | False | 665.28 | 0 | 3705743 | 136608 | None | AEEBDM09 | Providing and constructing non load bearing wall with solid concrete blocks of size 400x100x200 mm having a block density not less than1800 kg/m3 having a minimum average compressive strength of 4.00N/mm2 confirming toI S2185 (Part1):2005 and constructed with CM1:4,as per IS 2572:2005 including cost of all materials, labour charges, scaffolding, curing, hire charges of machineries etc., complete as per specifications SBM wall to support perforated slab CSR 2023-24 Volume-2 sl no 6.34 page no 17 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 1159.2 | 1159.2 | 0.48 | False | None | None | False | None | False | 556.416 | 0 | 3705744 | 136608 | None | AEEBDM10 | Plastering Providing 20mm cement plaster of mix:1:4 (1cement:4finesand) to brick/ stone masonary including rounding off corners wherever required smooth rendering, providing and removing scaf folding,including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge CSR 2023-24 Volume-2 sl no 8.3.1 page no 41 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 371.7 | 371.7 | 131.61 | False | None | None | False | None | False | 48919.437 | 0 | 3705745 | 136608 | None | AEEBDM11 | Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineer in-Charge with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 197.66 | 197.66 | 9.87 | False | None | None | False | None | False | 1950.9042 | 0 | 3705746 | 136608 | None | AEEBDM12 | Providing PVC ringtite pipes conforming to IS 4985:2000 with latest amendments and conveying to worksite, rolling and lowering into trenches, laying true to line and level and perfect linking at joints, testing and commissioning, including loading unloading at both destinations and cuts of pipes wherever necessary including jointing of PVC pipes and specials (excluding cost of specials) with jointing of approved type, with all labour with all lead & lift including encasing the pipe alround to a depth of not less than 15 cms. with soft gravel or selected earth available from the excavation etc. complete and giving necessary hydraulic test to the required pressure as per ISS (Contractor will make his own arrangements for procuring water for testing) etc. 100mm dia (settler inlet from register 5.47m, 100mm dia AF pipes 15m, 100mm dia AF outlet 1.2m, 110mm dia vent pipe 2.5mtr) CSR 2023-24 Volu-V 10.1 page no 113 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Rmtr | 431.55 | 431.55 | 24.17 | False | None | None | False | None | False | 10430.5635 | 0 | 3705747 | 136608 | None | AEEBDM13 | Supply and delivery at site special moulded variety PVC tee as per IS 7834/ 1987 and fabricated as per IG124/ 1984 with ISI mark with its latest amendments 100mm dia PVC tees CSR Vol-V Sl no 10.108 Page no 117 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | No | 263.55 | 263.55 | 11.0 | False | None | None | False | None | False | 2899.05 | 0 | 3705748 | 136608 | None | AEEBDM14 | Providing and laying of cinder of 120mm-150mm size free from debris and dust,includes procurring,transportation and laying into the anaerobic filter as per instruction of engineer in charge with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 788.77 | 788.77 | 2.0 | False | None | None | False | None | False | 1577.54 | 0 | 3705749 | 136608 | None | AEEBDM15 | Supplying/casting and fixing precast reinforced cement concrete perforated slabs(2" dia hole) of following thickness in RCC 1:2:4 using following HBGS jelly including cost of reinforcement steel in position,cost of moulding charges casting of slab Maintatinance covers 600mmx600mmx50mm with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Each | 282.32 | 282.32 | 3.0 | False | None | None | False | None | False | 846.96 | 0 | 3705750 | 136608 | None | AEEBDM16 | Supplying/casting and fixing precast reinforced cement concrete perforated slabs(2" dia hole) of following thickness in RCC 1:2:4 using following HBGS jelly including cost of reinforcement steel in position,cost of moulding charges casting of slab Maintatinance covers 485mmx985mmx50mm with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Each | 276.05 | 276.05 | 8.0 | False | None | None | False | None | False | 2208.4 | 0 | 3705751 | 136608 | None | AEEBDM17 | Painting with synthetic enamel paint of approved brand and
manufacture of required colour to give an even shade :Two coats on new work over an under coat of suitable shade with ordinary paint of approved brand and manufacture after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge.CSR 2023-24 volume 2 Sl no 8.41 Page no 48 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 175.35 | 175.35 | 16.13 | False | None | None | False | None | False | 2828.3955 | 0 |
| 1722946481000 | 0 | None | None | Buildings | 3 TOTAL COST OF PLANTED GRAVEL FILTER | 293265.94 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3705752 | 136609 | None | AEEBDM01 | TOTAL COST OF PLANTED GRAVEL FILTER Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work Upto 1.5M CSR 2023-24 Vol-I sl no 1.15.1 Page no 8 in ordinary /soft rock without blasting upto 1.5m depth and 3km with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 381.15 | 381.15 | 75.78 | False | None | None | False | None | False | 28883.547 | 0 | 3705753 | 136609 | None | AEEBDM02 | Plain Cement Concrete Providing and layingin position plain cement concrete for levelling course for all works in foundation.The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machineries, curing, and all the other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement & form work shall be paid separately. Mix1:4:8(M7.5) Using 20mm nominal size graded crushed coarse aggregates CSR 2023-24 Vol-I sl no 2.1.2 Page no 15 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 5947.2 | 5947.2 | 3.14 | False | None | None | False | None | False | 18674.208 | 0 | 3705754 | 136609 | None | AEEBDM03 | Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances
required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates CSR 2023-24 Vol-I sl no 2.2.3 Page no 15 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 6652.8 | 6652.8 | 12.21 | False | None | None | False | None | False | 81230.688 | 0 | 3705755 | 136609 | None | AEEBDM04 | Providing T.M.T steel reinforcement for R.C.C work including straightening, cutting, bending, hooking, placing in position,lapping and/or welding wherever required, tying with binding wire and anchoring to the adjoining members wherever necessary complete as per design (laps,hooks and wastages hall not be measured and paid)including for OHT & reservoier, cost of materials,labour,HOM of machinery complete as per specifications. TMT bars Fe 550 CSR 2023-24 Volume-I sl no 2.11(h) page no 18 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Kg | 93.93 | 93.93 | 1464.0 | False | None | None | False | None | False | 137513.52 | 0 | 3705756 | 136609 | None | AEEBDM05 | Providing and removing centering, shuttering, strutting, proppingetc., and removal of formwork for foundations, footings, bases of columns form assconcrete including cost of all materials,labour complete as per specificaitons.For Foundation works PCC foundation CSR 2023-24 Volume-I Addendeum sl no 3&11 page no 111&112 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 5947.2 | 5947.2 | 0.16 | False | None | None | False | None | False | 951.552 | 0 | 3705757 | 136609 | None | AEEBDM06 | Providing and removing centering, shuttering, strutting, proppingetc., and removal of form work for foundations, footings, bases of columns for mass concrete including cost of all materials, labour complete as per specificaitons.For Foundation works RCC foundation CSR 2023-24 Volume-I Addendeum sl no 3&11 page no 111&112 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 6652.8 | 6652.8 | 0.29 | False | None | None | False | None | False | 1929.312 | 0 | 3705758 | 136609 | None | AEEBDM07 | Providing and removing centering, shuttering, strutting, proppingetc., and removal of form work for foundations, footings, bases of columns for mass concrete including cost of all materials, labour complete as per specificaitons.For Foundation works RCC foundation CSR 2023-24 Volume-I Addendeum sl no 3&11 page no 111&112 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 6652.8 | 6652.8 | 0.56 | False | None | None | False | None | False | 3725.568 | 0 | 3705759 | 136609 | None | AEEBDM08 | Plastering Providing20 mm cement plaster of mix:1:4 (1cement:4finesand)to brick/stone masonary including rounding off corners wherever required smooth rendering, providing and removing scaf folding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge CSR 2023-24 Volume-2 sl no 8.3.1 page no 41 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 371.7 | 371.7 | 30.9 | False | None | None | False | None | False | 11485.53 | 0 | 3705760 | 136609 | None | AEEBDM09 | Extra for providing and mixing waterproofing material incement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineer in-Charge with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 197.66 | 197.66 | 2.32 | False | None | None | False | None | False | 458.5712 | 0 | 3705761 | 136609 | None | AEEBDM10 | Providing PVC ringtite pipes conforming to IS 4985:2000 with latest amendments and conveying to worksite, rolling and lowering into trenches, laying true to line and level and perfect linking at joints, testing and commissioning, including loading unloading at both destinations and cuts of pipes wherever necessary including jointing of PVC pipes and specials (excluding cost of specials) with jointing of approved type, with all labour with all lead & lift including encasing the pipe alround to a depth of not less than 15 cms. with soft gravel or selected earth available from the excavation etc. complete and giving necessary hydraulic test to the required pressure as per ISS (Contractor will make his own arrangements for procuring water for testing) etc. 100mm dia vent pipe and outlet CSR 2023-24 Volu-V 10.1 page no 113 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Rmtr | 431.55 | 431.55 | 2.5 | False | None | None | False | None | False | 1078.875 | 0 | 3705762 | 136609 | None | AEEBDM11 | 100mm dia perforated sampling pipe with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Rmtr | 730.68 | 730.68 | 0.9 | False | None | None | False | None | False | 657.612 | 0 | 3705763 | 136609 | None | AEEBDM12 | 100mm dia perforated pipe with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Rmtr | 730.83 | 730.83 | 2.2 | False | None | None | False | None | False | 1607.826 | 0 | 3705764 | 136609 | None | AEEBDM13 | Providing and laying coarse aggregate size as below after washing and sieving to make it free from fines and dust 120-80 mm nominal size(at inlet) with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 1341.94 | 1341.94 | 0.41 | False | None | None | False | None | False | 550.1954 | 0 | 3705765 | 136609 | None | AEEBDM14 | Providing and laying coarse aggregate size as below after washing and sieving to make it free from fines and dust 40-20mm nominal size with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 1543.44 | 1543.44 | 1.01 | False | None | None | False | None | False | 1558.8744 | 0 | 3705766 | 136609 | None | AEEBDM15 | Providing and laying coarse aggregate size as below after washing and sieving to make it free from fines and dust 20mm nominal size with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 1543.44 | 1543.44 | 0.68 | False | None | None | False | None | False | 1049.5392 | 0 | 3705767 | 136609 | None | AEEBDM16 | Providing and laying coarse aggregate size as below after washing and sieving to make it free from fines and dust 12-10mm nominal size with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 1543.44 | 1543.44 | 0.68 | False | None | None | False | None | False | 1049.5392 | 0 | 3705768 | 136609 | None | AEEBDM17 | Painting with synthetic enamel paint of approved brand and
manufacture of required colour to give an even shade :Two coats on new work over an under coat of suitable shade with ordinary paint of approved brand and manufacture after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter includingpreparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge.CSR 2023-24 volume 2 Sl no 8.41 Page no 48 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 175.35 | 175.35 | 4.91 | False | None | None | False | None | False | 860.9685 | 0 |
| 1722946481000 | 0 | None | None | Buildings | 4 TOTAL COST OF COLLECTION TANK | 44136.19 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3705769 | 136610 | None | AEEBDM01 | TOTAL COST OF COLLECTION TANK Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work Upto 1.5M CSR 2023-24 Vol-I sl no 1.15.1 Page no 8 in ordinary /soft rock without blasting upto 1.5m depth and 3km with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 381.15 | 381.15 | 4.95 | False | None | None | False | None | False | 1886.6925 | 0 | 3705770 | 136610 | None | AEEBDM02 | Earth work excavation for Foundation by mechanical means for all
works & depth upto 3 m, as per drawing and technical specifications,including setting out, shoring, strutting, barricading, caution lights,including dressing of excavated surfaces, disposing off or levelling theexcavated earth or sorting & stacking the selected earth for reuse in aradius of 50 m and lift upto 1.5 m including cost of labour, tools, usageof machinery & other appurtenaces required to complete the workFrom 1.5M to 3 M CSR 2023-24 Vol-I sl no 1.15.1 Page no 8 in ordinary /soft rock without blasting upto 1.5m depth and 3km with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 446.25 | 446.25 | 1.71 | False | None | None | False | None | False | 763.0875 | 0 | 3705771 | 136610 | None | AEEBDM03 | Plain Cement Concrete Providing and layingin position plain cement concrete for levelling course for all works infoundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding150mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machineries, curing, and all the other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement & form work shall be paid separately.Mix1:4:8(M7.5) Using 20 mm nominal size graded crushed coarse aggregates CSR 2023-24 Vol-I sl no 2.1.2 Page no 15 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 5947.2 | 5947.2 | 0.4 | False | None | None | False | None | False | 2378.88 | 0 | 3705772 | 136610 | None | AEEBDM04 | Providing and removing centering, shuttering, strutting, propping etc.,and removal of form work for foundations, footings, bases of columns for mass concrete including cost of all materials, labour complete as per specificaitons.For Foundation works PCC foundation CSR 2023-24 Volume-I Addendeum sl no 3&11 page no 111&112 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 5947.2 | 5947.2 | 0.02 | False | None | None | False | None | False | 118.944 | 0 | 3705773 | 136610 | None | AEEBDM05 | Precast concrete ring For 1.8m dia(clear) rings of steining thickness 0.075mm upto 18m depth with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Each | 1662.15 | 1662.15 | 7.0 | False | None | None | False | None | False | 11635.05 | 0 | 3705774 | 136610 | None | AEEBDM06 | Plastering Providing 20 mm cement plaster of mix :1:4 (1 cement: 4 fine sand) to brick/stone masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge CSR 2023-24 Volume-2 sl no 8.3.1 page no 41 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 371.7 | 371.7 | 14.41 | False | None | None | False | None | False | 5356.197 | 0 | 3705775 | 136610 | None | AEEBDM07 | Precast Concrete Cover Supplying/Casting and fixing Precast Reinforced Cement Concretes labs of following thickness in RCC1:2:4(one cement, two sandand four aggregates),using following HBGS jelly including cost of reinforcement steel inposition,cost of moulding charges,casting of slab, finishing, curing and fixing inposition in all floors etc.,complete complying with standard specification and as directed. 1650mm dia (top slab) with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Each | 3267.23 | 3267.23 | 1.0 | False | None | None | False | None | False | 3267.23 | 0 | 3705776 | 136610 | None | AEEBDM08 | Wastewater pipes Supplying PVC ring tite pipes conforming to IS 4985:2000 with latest amendments and conveying to work site, rolling and lowering into trenches, laying true to line and level and perfect linking at joints, testing and commissioning, including loading unloading at both destinations and cuts of pipes wherever necessary including jointing of PVC pipes and specials (excluding cost of specials)with jointing of approved type, with all labour with all lead & lift includingen casing the pipe alround to a depth of no tless than15cms. with soft gravel orselectede arth available from the excavationetc. complete and giving necessary hydraulictestto the required pressure as per ISS(Contract or will make his own arrangements for procuring water fortesting) etc. for:PVC pipes 110mm dia., 6 kg/sqcm & class 3 110mm nominal dia inlet with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Rmtr | 431.55 | 431.55 | 2.6 | False | None | None | False | None | False | 1122.03 | 0 | 3705777 | 136610 | None | AEEBDM09 | Wastewater pipes Supplying PVC ring tite pipes conforming to IS 4985:2000 with latest amendment sand conveying to work site,rolling and lowering into trenches, laying true to line and level and perfec tlinking at joints, testing and commissioning, including loading unloading at both destinations and cuts of pipes wherever necessary including jointing of PVC pipes and specials(excluding cost of specials)with jointing of approved type, with all labour with all lead & lift includingen casing the pipe alround to a depth of not less than15cms.with soft gravel or selected earth available from the excavation etc. complete and giving necessary hydraulictest to the required pressure as per ISS (Contractor will make his own arrangements for procuring water fortesting) etc. for:PVC pipes 110mm dia., 6 kg/sqcm & class 3 110mm nominal dia outlet with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Rmtr | 431.55 | 431.55 | 1.6 | False | None | None | False | None | False | 690.48 | 0 | 3705778 | 136610 | None | AEEBDM10 | Supply and delivery at site special moulded variety PVC tee as per IS 7834/ 1987 and fabricated as per IG124/ 1984 with ISI mark with its latest amendments 100mm dia PVC tees CSR Vol-V Sl no 10.108 Page no 117 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Each | 263.55 | 263.55 | 2.0 | False | None | None | False | None | False | 527.1 | 0 | 3705779 | 136610 | None | AEEBDM11 | Pump Supply and delivery of Centrifugal pumpset at site brand new best make and with discharge duty confirming to ISI standards and its latest amendments.(2 HP, Size 65x50 Head 13M, Discharge 462 LPM) PWD UGD 2023-24 Vol-V Sl no 13.40 Page no 157 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Each | 16390.5 | 16390.5 | 1.0 | False | None | None | False | None | False | 16390.5 | 0 |
| 1722946481000 | 0 | None | None | Buildings | 5 TOTAL COST OF INFILTRATION TRENCH | 7348.93 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3705780 | 136611 | None | AEEBDM01 | TOTAL COST OF INFILTRATION TRENCH Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications,including setting out, shoring, strutting, barricading, caution lights,including dressing of excavated surfaces, disposing off or levelling theexcavated earth or sorting & stacking the selected earth for reuse in aradius of 50 m and lift upto 1.5 m including cost of labour, tools, usageof machinery & other appurtenaces required to complete the workFrom 1.5M to 3 M CSR 2023-24 Vol-I sl no 1.15.1 Page no 8 in ordinary /soft rock without blasting upto 1.5m depth and 3km with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 446.25 | 446.25 | 3.0 | False | None | None | False | None | False | 1338.75 | 0 | 3705781 | 136611 | None | AEEBDM02 | Providing and laying coarse aggregate size as below after washing and sieving to make it free from fines and dust 40-20mm nominal size with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 1543.43 | 1543.43 | 2.0 | False | None | None | False | None | False | 3086.86 | 0 | 3705782 | 136611 | None | AEEBDM03 | 100mm dia perforated pipe with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Rmtr | 730.83 | 730.83 | 4.0 | False | None | None | False | None | False | 2923.32 | 0 |
| 1722946481000 | 0 | None | None | Buildings | 6 TOTAL FOR PERCOLATE DRAIN | 239850.54 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3705783 | 136612 | None | AEEBDM01 | TOTAL FOR PERCOLATE DRAIN Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work Upto 1.5M CSR 2023-24 Vol-I sl no 1.15.1 Page no 8 in ordinary /soft rock without blasting upto 1.5m depth and 3km PDB register drain with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 381.15 | 381.15 | 94.88 | False | None | None | False | None | False | 36163.512 | 0 | 3705784 | 136612 | None | AEEBDM02 | Plain Cement Concrete Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in
layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications..Mix1:4:8(M7.5)Using20mmnominalsizegraded crushed coarse aggregates CSR 2023-24 Vol-I sl no 2.1.2 Page no 15 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 5947.2 | 5947.2 | 6.34 | False | None | None | False | None | False | 37705.248 | 0 | 3705785 | 136612 | None | AEEBDM03 | Precast cover 600mmx600mmx50mm with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Each | 274.94 | 274.94 | 76.0 | False | None | None | False | None | False | 20895.44 | 0 | 3705786 | 136612 | None | AEEBDM04 | Solid Block Masonry Providing and constructing load bearing wal lwith Solid Concrete blocks of size 400x150x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00N/mm 2 conforming to IS2185(Part-I)- 2005 and constructed with CM1:4 as per IS 2572:2005i ncluding cost of all materials, labour, scaf folding and curing, usage charges of machinery etc complete as per specifications PDB register drain with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 1292.55 | 1292.55 | 66.01 | False | None | None | False | None | False | 85321.2255 | 0 | 3705787 | 136612 | None | AEEBDM05 | PlasteringProviding 20 mm cement plaster of mix :1:4 (1 cement: 4 fine sand) to brick/stone masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge CSR 2023-24 Volume-2 sl no 8.3.1 page no 41 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 371.7 | 371.7 | 154.62 | False | None | None | False | None | False | 57472.254 | 0 | 3705788 | 136612 | None | AEEBDM06 | Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineer in-Charge with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 197.66 | 197.66 | 11.6 | False | None | None | False | None | False | 2292.856 | 0 |
| 1722946481000 | 0 | None | None | Buildings | 7 TOTAL COST OF CC PAVEMENT | 450774.24 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3705789 | 136613 | None | AEEBDM01 | TOTAL COST OF CC PAVEMENT Providing and Filling in foundation with granite / trap broken metal 100mm. and down size & with approved sand including hand packing, ramming, watering, including cost of all materials and labour with all lead and lift complete as per specifications CSR 2023-24 Vol-1 Sl no 1.23 page no 54 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 2816.1 | 2816.1 | 44.4 | False | None | None | False | None | False | 125034.84 | 0 | 3705790 | 136613 | None | AEEBDM02 | Interlocking Pavers Providing and laying 60mm thick factory made cement concrete paver block of approved shape and colour of M -30 grade made of C&D waste by block making machine with vibratory compaction laid in required pattern and including over 50mm thick compacted bed of coarse sand, filling the joints with fine sand etc. all complete as per the direction of Engineer-in-charge. CSR 2023-24 Vol-II Sl no 9.25 Page no 64 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 840.0 | 840.0 | 372.13 | False | None | None | False | None | False | 312589.2 | 0 | 3705791 | 136613 | None | AEEBDM03 | Stone pitching Providing and constructing dry rubble stone pitching with pin headers at 2 per m2 using stones and stone chips from approved source including cost of all materials, labour, hand packing / wedging stone chips, finishing and all other ancillary operations complete.250mm thick CSR water supply UGD 2023-24 Vol-IV Sl no 3.41.1 Page no 54 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 424.2 | 424.2 | 31.0 | False | None | None | False | None | False | 13150.2 | 0 |
| 1722946481000 | 0 | None | None | Buildings | 8 TOTAL COST OF EMBANKMENT AND RAMP | 609114.27 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3705792 | 136614 | None | AEEBDM01 | TOTAL COST OF EMBANKMENT AND RAMP Construction of Embankment by excavating the available approved Gravel/Murrum deposited at a place or borrow pits during or prior excavation with all
lifts and lead, transportation to site, spreading, grading to required slope and compacting to meet the requirement complete as per specifications, including cost of labour,rolling,water,all materials,usage& all other appurtenaces required to complete the work. CSR 2023-24 Vol-I Sl no 1.80 Page no 07 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 497.7 | 497.7 | 247.5 | False | None | None | False | None | False | 123180.75 | 0 | 3705793 | 136614 | None | AEEBDM02 | Compacting original ground supporting embankment Loosening, leveling and Compacting original ground supporting embankment to facilitate placement of first layer of embankment, scarified to a depth of 150 mm, mixed with water at OMC and then compacted by rolling so as to achieve minimum dry density as given in Table 300-2 for embankment construction.CSR 2023-24 Vol-III Sl no 3.7 Page no 17 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 110.25 | 110.25 | 117.4 | False | None | None | False | None | False | 12943.35 | 0 | 3705794 | 136614 | None | AEEBDM03 | Earth work excavation for Foundation by mechanical means for all
works & depth upto 3 m, as per drawing and technical specifications,
including setting out, shoring, strutting, barricading, caution lights,
including dressing of excavated surfaces, disposing off or levelling the
excavated earth or sorting & stacking the selected earth for reuse in a
radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage
of machinery & other appurtenaces required to complete the work Upto 1.5M CSR 2023-24 Vol-I sl no 1.15.1 Page no 8 in ordinary /soft rock without blasting upto 1.5m depth and 3km PDB register drain with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 381.15 | 381.15 | 31.5 | False | None | None | False | None | False | 12006.225 | 0 | 3705795 | 136614 | None | AEEBDM04 | Plain Cement Concrete Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in
layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications..(The cost of steel reinforcement & form work shall be paid separately.Mix1:4:8(M7.5) Using20 mm nominal size graded crushed coarse aggregates CSR 2023-24 Vol-I sl no 2.1.2 Page no 15 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 5947.2 | 5947.2 | 2.48 | False | None | None | False | None | False | 14749.056 | 0 | 3705796 | 136614 | None | AEEBDM05 | Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates CSR 2023-24 Vol-I sl no 2.2.3 Page no 15 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 6652.8 | 6652.8 | 14.94 | False | None | None | False | None | False | 99392.832 | 0 | 3705797 | 136614 | None | AEEBDM06 | Extra for providing and mixing waterproofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineer in-Charge with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 197.66 | 197.66 | 14.94 | False | None | None | False | None | False | 2953.0404 | 0 | 3705798 | 136614 | None | AEEBDM07 | Providing T.M.T steel reinforcement for R.C.C work including straightening, cutting, bending, hooking, placing in position, lapping and/or welding wherever required, tying with binding wire and anchoring to the adjoining members wherever necessary complete as per design (laps,hooks and wastage shall not be measured and paid)including for OHT & reservoier, cost of materials, labour, HOM of machinery complete as per specifications. TMT bars Fe 550 CSR 2023-24 Volume-I sl no 2.11(h) page no 18 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Kg | 93.93 | 93.93 | 747.0 | False | None | None | False | None | False | 70165.71 | 0 | 3705799 | 136614 | None | AEEBDM08 | Providing and removing centering, shuttering, strutting, proppingetc., and removal of form work for foundations, footings, bases of columns for mass concrete including cost of all materials,labour complete as per specificaitons.For Foundation works PCC base slab CSR 2023-24 Volume-I Addendeum sl no 3&11 page no 111&112 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 5947.2 | 5947.2 | 0.12 | False | None | None | False | None | False | 713.664 | 0 | 3705800 | 136614 | None | AEEBDM09 | Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for foundations, footings, bases of columns for mass concrete including cost of all materials, labour complete as per specificaitons.For Foundation worksRCC base slab CSR 2023-24 Volume-I Addendeum sl no 3&11 page no 111&112 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 6652.8 | 6652.8 | 0.26 | False | None | None | False | None | False | 1729.728 | 0 | 3705801 | 136614 | None | AEEBDM10 | Providing and removing centering, shuttering, strutting, proppingetc., and removal of form work for foundations, footings, bases of columns for mass concrete including cost of all materials, labour complete as per specificaitons.For Foundation works RCC wall CSR 2023-24 Volume-I Addendeum sl no 3&11 page no 111&112 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 6652.8 | 6652.8 | 0.97 | False | None | None | False | None | False | 6453.216 | 0 | 3705802 | 136614 | None | AEEBDM11 | Providing and fixing chain link fencing consisting of 3m long 65x65x6mm M.Sangles witht op 50cm bentat 30 degree to vertical fixedat 2.5 min tervalsin C.C1:3:6 proportionusing 20mm down graded coarse aggregate for 70cm depth, fixing 50x50mm opening 8gauge G.I chain link mesh upto1.8m height of poles using 8gauge stretcher wire at top and bottom and 30x30x5mm M.Sangles with bolts/nuts/washers(4boltsforeachpole),fixing3rowsof12 gauge (4barbsat7.5cmc/c)G.I barbed wire for top bent portion of poles,including cost of all materials,machinery,labour,excavation of pit,mixing and laying concrete,curing,drilling holes in angles,cleaning angles,painting angles and Chain links with 2coats of syntheticenamel paint over acoat of primer etc.,complete with all lead and lifts. CSR 2023-24 Volume-Ii sl no 11.59 page no 95 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Rmtr | 883.05 | 883.05 | 299.9 | False | None | None | False | None | False | 264826.695 | 0 |
| 1722946481000 | 0 | None | None | Buildings | 9 TOTAL COST OF ROOF FOR TWO SET OF PLANTED DRYING BEDS | 933259.49 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3705803 | 136615 | None | AEEBDM01 | TOTAL COST OF ROOF FOR TWO SET OF PLANTED DRYING BEDS Providing and fixing Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete. Hot finished seamless type tubes including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. Roof truss members -Main columns SHS,Truss main members RHS, Purlins RHS, Anchol bolts, Base platesCSR 2023-24 Vol-II Sl no 11.16.2 Page no 82 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Kg | 154.35 | 154.35 | 4573.2 | False | None | None | False | None | False | 705873.42 | 0 | 3705804 | 136615 | None | AEEBDM02 | Providing and fixing precoated galvanised iron profile sheets (size, shape and pitch of corrugation as approved by Engineer-in-charge) 0.50 mm (+ 0.05 %) total coated thickness with zinc coating 120 g/m2as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns. Sheet should have protective guard film of 25 microns minimum to avoid scratches during transportation and should be supplied in single length upto 12 m or as desired by Engineer in-charge. The sheet shall be fixed using self drilling/self tapping screws of size (5.5x 55 mm) with EPDM seal, complete upto any pitch in horizontal/ vertical or curved surfaces, excluding the cost of purlins, rafters and trusses and including cutting to size and shape wherever required.for PDB roof CSR 2023-24 Vol-II Sl no 7.38 Page no 26 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 596.4 | 596.4 | 295.42 | False | None | None | False | None | False | 176188.488 | 0 | 3705805 | 136615 | None | AEEBDM03 | Providing and fixing precoated galvanised steel sheet roofing accessories 0.50 mm (+0.05 %) total coated thickness, Zinc coating 120 g/m2 as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns using self drilling/ self tapping screws complete : Gutter (600 mm over all girth) CSR 2023-24 Vol-II Sl no 7.39.6 Page no 27 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Mtr | 1127.7 | 1127.7 | 45.4 | False | None | None | False | None | False | 51197.58 | 0 |
| 1722946481000 | 0 | None | None | Buildings | 10 ESTIMATE OF OPERATOR ROOM, TOILET BLOCK | 727258.57 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3705806 | 136616 | None | AEEBDM1 | ESTIMATE OF OPERATOR ROOM, TOILET BLOCK Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work Upto 1.5M CSR 2023-24 Vol-I sl no 1.15.1 Page no 8 in ordinary /soft rock without blasting upto 1.5m depth and 3m with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 381.15 | 381.15 | 105.55 | False | None | None | False | None | False | 40230.3825 | 0 | 3705807 | 136616 | None | AEEBDM2 | Providing and Filling in foundation with granite / trap broken metal 100mm. and down size & with approved sand including hand packing, ramming, watering, including cost of all materials and labour with all lead and lift complete as per specifications CSR 2023-24 Vol-1 Sl no 1.23 page no 54 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 2816.1 | 2816.1 | 4.5 | False | None | None | False | None | False | 12672.45 | 0 | 3705808 | 136616 | None | AEEBDM3 | Plain Cement Concrete Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in
layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications..(Thecostofsteelreinforcement&formworkshallbepaidseparately.Mix1:4:8(M7.5)Using20mmnominalsizegraded crushed coarse aggregates CSR 2023-24 Vol-I sl no 2.1.2 Page no 15 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 5947.2 | 5947.2 | 1.99 | False | None | None | False | None | False | 11834.928 | 0 | 3705809 | 136616 | None | AEEBDM4 | Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the
work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates CSR 2023-24 Vol-1 Sl no 2.1.4 page no 15 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 6527.85 | 6527.85 | 2.25 | False | None | None | False | None | False | 14687.6625 | 0 | 3705810 | 136616 | None | AEEBDM5 | Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates CSR 2023-24 Vol-I sl no 2.2.3 Page no 15 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 6652.8 | 6652.8 | 7.81 | False | None | None | False | None | False | 51958.368 | 0 | 3705811 | 136616 | None | AEEBDM6 | Providing T.M.T steel reinforcement for R.C.C work including straightening, cutting, bending, hooking, placing in position, lapping and/or welding wherever required, tying with binding wire and anchoring to the adjoining members wherever necessary complete as per design (laps,hooks and wastage shall not be measured and paid)including for OHT & reservoier,costofmaterials,labour,HOM of machinery complete as per specifications. TMT bars Fe 550 CSR 2023-24 Volume-I sl no 2.11(h) page no 18 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Kg | 93.93 | 93.93 | 937.2 | False | None | None | False | None | False | 88031.196 | 0 | 3705812 | 136616 | None | AEEBDM7 | Providing and removing centering, shuttering, strutting, proppingetc., and removal of form work for foundations, footings, bases of columns for mass concrete including cost of all materials,labour complete as per specificaitons.For Foundation works PCC foundation CSR 2023-24 Volume-I Addendeum sl no 3&11 page no 111&112 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 5947.2 | 5947.2 | 0.1 | False | None | None | False | None | False | 594.72 | 0 | 3705813 | 136616 | None | AEEBDM8 | Providing and removing centering, shuttering, strutting, proppingetc., and removal of form work for foundations, footings, bases of columns for mass concrete including cost of all materials,labour complete as per specificaitons.For Foundation works PCC above soling CSR 2023-24 Volume-I Addendeum sl no 3&11 page no 111&112 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 6527.85 | 6527.85 | 0.11 | False | None | None | False | None | False | 718.0635 | 0 | 3705814 | 136616 | None | AEEBDM9 | Providing and removing centering, shuttering, strutting, proppingetc., and removal of form work for foundations, footings, bases of columns for mass concrete including cost of all materials,labour complete as per specificaitons.For Foundation works RCC PB CSR 2023-24 Volume-I Addendeum sl no 3&11 page no 111&112 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 6652.8 | 6652.8 | 0.63 | False | None | None | False | None | False | 4191.264 | 0 | 3705815 | 136616 | None | AEEBDM10 | Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for foundations, footings, bases of columns for mass concrete including cost of all materials, labour complete as per specificaitons.For Foundation works RCC RB CSR 2023-24 Volume-I Addendeum sl no 3&11 page no 111&112 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 6652.8 | 6652.8 | 1.57 | False | None | None | False | None | False | 10444.896 | 0 | 3705816 | 136616 | None | AEEBDM11 | Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for foundations, footings, bases of columns for mass concrete including cost of all materials, labour complete as per specificaitons.For Foundation works RCC Top slab CSR 2023-24 Volume-I Addendeum sl no 3&11 page no 111&112 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 6652.8 | 6652.8 | 1.57 | False | None | None | False | None | False | 10444.896 | 0 | 3705817 | 136616 | None | AEEBDM12 | Providing and removing centering, shuttering, strutting, proppingetc., and removal of form work for foundations, footings, bases of columns for mass concrete including cost of all materials,labour complete as per specificaitons.For Foundation works RCC lintel CSR 2023-24 Volume-I Addendeum sl no 3&11 page no 111&112 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 6652.8 | 6652.8 | 0.22 | False | None | None | False | None | False | 1463.616 | 0 | 3705818 | 136616 | None | AEEBDM13 | Providing and removing centering, shuttering, strutting, proppingetc., and removal of form work for foundations, footings, bases of columns for mass concrete including cost of all materials,labour complete as per specificaitons.For Foundation works RCC chejja CSR 2023-24 Volume-I Addendeum sl no 3&11 page no 111&112 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 6652.8 | 6652.8 | 0.2 | False | None | None | False | None | False | 1330.56 | 0 | 3705819 | 136616 | None | AEEBDM14 | Providing Brick work with common burnt clay modular bricks of class designation 3.5 in foundation and plinth in Cement mortar 1:4 (1 cement : 4 coarse sand) including cost of all materials, labour, scaffolding and usage charges of machinery & other incidental charges complete as per the direction of engineer incharge of work CSR 2023-24 Vol-II Sl no 6.3 Page no 13 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 9317.7 | 9317.7 | 13.52 | False | None | None | False | None | False | 125975.304 | 0 | 3705820 | 136616 | None | AEEBDM15 | Plastering Providing 20mm cement plaster of mix:1:4(1cement:4finesand)to brick/stone masonary including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials,labour,curing complete as per specifications and as per directions of Engineer-in-charge CSR 2023-24 Volume-2 sl no 8.3.1 page no 41 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 371.7 | 371.7 | 160.41 | False | None | None | False | None | False | 59624.397 | 0 | 3705821 | 136616 | None | AEEBDM16 | Providing 12 mm cement plaster finished with a floating coat of neat cement of mix :1:4 (1 cement: 4 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge.CSR 2023-24 Volume-2 sl no 8.4.2 page no 41 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 327.6 | 327.6 | 52.2 | False | None | None | False | None | False | 17100.72 | 0 | 3705822 | 136616 | None | AEEBDM17 | Providing 15 mm cement plaster on the rough side of single or half brick wall of mix :1:6 (1 cement: 6 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer in charge CSR 2023-24 Volume-II Sl no 8.2.2 Page no 41 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 292.95 | 292.95 | 38.22 | False | None | None | False | None | False | 11196.549 | 0 | 3705823 | 136616 | None | AEEBDM18 | Extra for providing and mixing waterproofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineer in-Charge with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 197.66 | 197.66 | 250.83 | False | None | None | False | None | False | 49579.0578 | 0 | 3705824 | 136616 | None | AEEBDM19 | Providing cement mortar of mix1:2(1cement:2sand)including cost of all materials, labour charges, HOM of machinery complete as per specifications. CSR 2023-24 Volume-I Sl no 3.2 Page no 23 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 6550.95 | 6550.95 | 1.13 | False | None | None | False | None | False | 7402.5735 | 0 | 3705825 | 136616 | None | AEEBDM20 | Providing and laying redoxide flooring 40mmthick, with anunder layer of 30mm thick M-15 cement concrete, using broken granite metal of 12.5mm nomina lsize and top layer of 10mm thick plaster with1:3 cement mortar mixed with redoxide (using3.5kg of redoxide per 50kg of cement)finished with floating coat of neat cement mixed with redoxide (mix of same proportion), including cost of materials, labour, curing, complete as per specifications. CSR 2023-24 Volume-II Sl no 9.12.2 Page no 60 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 1202.25 | 1202.25 | 13.5 | False | None | None | False | None | False | 16230.375 | 0 | 3705826 | 136616 | None | AEEBDM21 | Providing and fixing 10mm thick acid and/oralkali resistant tiles of ap proved make and colour using acid and/oralkali resisting mortar bedding for Bathrooms:Toilet:Chemically exposed areas andjoints filled with acid and/oralkali resisting cement as per IS:4457,complete as per the direction of Engineer-in- Charge. CSR 2023-24 Volume-II Sl no 97.1 Page no 59 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 1308.3 | 1308.3 | 9.0 | False | None | None | False | None | False | 11774.7 | 0 | 3705827 | 136616 | None | AEEBDM22 | Providing skirting, dadooing, rises of steps with colour glazed tiles10mm thickon10mm thick cement plaster1:3and jointed with white cement slurry over existing rough plaster surface using glazed tiles of approved make and size including cost of materials, labour, complete as per specifications. Da doing at toilet(Colour glazed tiles15x15cms10mm thick CSR 2023-24 Volume-II Sl no 9.39 Page no 65 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 1521.45 | 1521.45 | 25.5 | False | None | None | False | None | False | 38796.975 | 0 | 3705828 | 136616 | None | AEEBDM23 | Providing and fixing 1mm thick M.S. sheet door with frame of 40x40x6
mm angle iron and 3 mm M.S. gusset plates at the junctions and
corners, all necessary fittings complete, including applying a priming
coat of approved steel primer. Using M.S. angels 40x40x6 mm for diagonalbraces including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge..CSR 2023-24 Volume-II Sl no11.5.1 Page no75 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 4701.9 | 4701.9 | 6.72 | False | None | None | False | None | False | 31596.768 | 0 | 3705829 | 136616 | None | AEEBDM24 | Providing and fixing double glazed hermetically sealed glazing in aluminium windows, ventilators and partition etc. with 6 mm thick clear float glass both side, having 12 mm air gap, including providing EPDM gasket, perforated aluminium spacers, desiccants, sealant (Both primary and secondary sealant) etc. as per specifications, drawings and direction of Engineer-in-charge complete including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. CSR 2023-24 Volume-II Sl no11.44 Page no91 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 4562.25 | 4562.25 | 3.41 | False | None | None | False | None | False | 15557.2725 | 0 | 3705830 | 136616 | None | AEEBDM25 | Providingand fixing M.S.grill workfor windows and ventilators weighing 21kg/sqm using M.S.flats, or M.S.square rods,or combination of M.S.flats and square rods as per approved design, drawing including cutting steelsections and welding the same to required pattern with a coat of red lead primer, cost of materials, fixtures, labourand HOM of machinery complete as per specifications. CSR 2023-24 Volume-II Sl no11.34bPage no86 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Kg | 192.15 | 192.15 | 71.51 | False | None | None | False | None | False | 13740.6465 | 0 | 3705831 | 136616 | None | AEEBDM26 | Painting with synthetic enamel paint of approved brand and
manufacture of required colour to give an even shade :Two coats on newwork over an under coat of suitable shade with ordinary paint of approved brand and manufacture after thoroughly brooming the surface to removeall dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge..CSR 2023-24 Volume-II Sl no8.41Page no 48 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 175.35 | 175.35 | 160.41 | False | None | None | False | None | False | 28127.8935 | 0 | 3705832 | 136616 | None | AEEBDM27 | Providing and applying painting in two coats with plastic emulsion paint of approved brands had eonceiling and/or sloping roof after throughly brushing the surface, free from mortar drops and other foreign matter including preparing the surface even and sand paper smooth,cost of materials, labour, complete as per specifications. with primer CSR 2023-24 Volume-II Sl no 8.39 Page no48 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 133.35 | 133.35 | 52.2 | False | None | None | False | None | False | 6960.87 | 0 | 3705833 | 136616 | None | AEEBDM28 | Providing and fixing water closet squatting pan (Indian type W.C. pan ) with 100 mm sand cast Iron P or S trap, 10 litre low level white P.V.C. flushing cistern, including flush pipe, with manually controlled
device (handle lever) conforming to IS : 7231, with all fittings and fixtures complete, including cutting and making good the walls and floors wherever required White Vitreous china Orissa pattern W.C. pan of size 580x440 mm with integral type foot rests CSR 2023-24 vol-2 Sl no 14.1.1 page no 131 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Each | 5128.2 | 5128.2 | 2.0 | False | None | None | False | None | False | 10256.4 | 0 | 3705834 | 136616 | None | AEEBDM29 | Providing and fixing white vitreous china flat back or wall corner type lipped front urinal basin of 430x260x350 mm and 340x410x265 mm sizes respectively with automatic flushing cistern with standard flush pipe and C.P. brass spreaders with brass unions and G.I clamps complete, including painting of fittings and brackets, cutting and making good the walls and floors wherever required :One urinal basin with 5 litre white P.V.C. automatic flushing cistern CSR 2023-24 vol-2 Sl no 14.4.1 page no 131 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Each | 4676.7 | 4676.7 | 1.0 | False | None | None | False | None | False | 4676.7 | 0 | 3705835 | 136616 | None | AEEBDM30 | Providing and fixing wash basin with C.I. brackets, 15 mm C.P. brass pillar taps, 32 mm C.P. brass waste of standard pattern, including painting of fittings and brackets, cutting and making good the walls wherever require White Vitreous China Wash basin size 630x450 mm with a pair of 15 mm C.P. brass pillar taps CSR 2023-24 Volu-2 Sl no 14.7.1 Page no 132 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Each | 3236.1 | 3236.1 | 2.0 | False | None | None | False | None | False | 6472.2 | 0 | 3705836 | 136616 | None | AEEBDM31 | Providing and fixing 100 mm sand cast Iron grating for gully trap.CSR 2023-24 Volu-2 Sl no 14.29 Page no 136 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Each | 49.35 | 49.35 | 4.0 | False | None | None | False | None | False | 197.4 | 0 | 3705837 | 136616 | None | AEEBDM32 | Providing and fixing brass bib cock of approved quality :20 mm nominal bore CSR 2023-24 Vol-2 Sl no 13.2.2 Page no 117 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Each | 320.25 | 320.25 | 4.0 | False | None | None | False | None | False | 1281.0 | 0 | 3705838 | 136616 | None | AEEBDM33 | Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply,including all CPVC
plain & brass threaded fittings, including fixing the pipe with clamps at 1.00 m spacing. This includes jointing of pipes &fittings with one step CPVC solvent cement and testing ofjoints complete as per direction of
Engineer in Charge.Internal work - Exposed on wall 20 mm nominal dia Pipes CSR 2023-24 Vol-2 Sl no 13.31.2 page no 122 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Mtr | 254.1 | 254.1 | 20.0 | False | None | None | False | None | False | 5082.0 | 0 | 3705839 | 136616 | None | AEEBDM34 | Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply, including all CPVC plain & brass threaded fittings, including fixing the pipe with clamps at 1.00 m spacing. This includes jointing of pipes & fittings with one step CPVC solvent cement and testing of joints complete as per direction of
Engineer in Charge.Internal work - Exposed on wall 50 mm nominal dia Pipes CSR 2023-24 Vol-2 Sl no 13.31.6 page no 122 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Mtr | 820.05 | 820.05 | 15.0 | False | None | None | False | None | False | 12300.75 | 0 | 3705840 | 136616 | None | AEEBDM35 | Providing and placing on terrace (at all floor levels) polyethylene
water storage tank, IS : 12701 marked, with cover and suitable locking arrangement and making necessary holes for inlet, outlet and overflow pipes but without fittings and the base support for tank.CSR 2023-24 Volume-2 Sl no 13.34 page no 123 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Ltr | 9.45 | 9.45 | 500.0 | False | None | None | False | None | False | 4725.0 | 0 |
| 1722946481000 | 0 | None | None | Buildings | 11 TOTAL FOR ELECTRICAL WORK FOR OPERATER ROOM, TOILET BLOCKS AND STREET LIGHTS | 111347.82 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3705841 | 136617 | None | AEEBDM1 | TOTAL FOR ELECTRICAL WORK FOR OPERATER ROOM, TOILET BLOCKS AND STREET LIGHTS Earth work in surface excavation for stripping, seating of bund, Road way, by manual means for lowering & leveling the ground for all works other than foundation & depth in all kinds of soil not exceeding 300mm as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter including dressing of excavated surfaces, disposing off or leveling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage & other appurtenances required to complete the work. CSR 2023-24 Vol-1 Sl no 1.1 page no 5 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 95.55 | 95.55 | 31.5 | False | None | None | False | None | False | 3009.825 | 0 | 3705842 | 136617 | None | AEEBDM2 | Supplying fixing and wiring earth electrode forgrounding of lifts, transformers, DG sets etc. using 40mm dia 2.9mm thick 2.5 mtr long GI pipe with GI funnel with meshand suitable size reducer fixed on the top of the earth electrode.The funnel should be enclosed in a CC chamber o f400x400x400mm with a cast iron cover.The earth electrode shall have staggered holes of 12mm dia and the electrode should be covered150mmall-round with alternate layers of salt and charcoal from the bottom of the CCchamber.The connection from the electrode is to be established through GI strip using GI bolts and nuts. CSR KPTCL 2023-24 Sl no 7 Page no 116 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | No | 4687.2 | 4687.2 | 1.0 | False | None | None | False | None | False | 4687.2 | 0 | 3705843 | 136617 | None | AEEBDM3 | Supplying and running of GI/Copper strips for grounding connections,using necessary fixing materials as required. GI strip 25x3mm PWD Electrical SOR Sl no 12.58.2 Page no 54 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Mtr | 86.1 | 86.1 | 5.0 | False | None | None | False | None | False | 430.5 | 0 | 3705844 | 136617 | None | AEEBDM4 | 600x600x3mm GI Plate PWD Electrical SOR Sl no 12.58.6 Page no 55 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Each | 918.75 | 918.75 | 1.0 | False | None | None | False | None | False | 918.75 | 0 | 3705845 | 136617 | None | AEEBDM5 | Conduit system for supply from nearest power source 40mm dia 2.5mm thick PWD Electrical SOR 2023-24 Sl no 1.2.4 Page no 02 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Mtr | 154.35 | 154.35 | 10.0 | False | None | None | False | None | False | 1543.5 | 0 | 3705846 | 136617 | None | AEEBDM6 | Wiring from nearest power source Wiring for lighting/ power circuit using one of FRLSPVC insulated 1100V grade,multi strand copper wire with low conductor resistance single core in open or concealed system of wiring with specified IS-694:confirming to latest amendments. 16 sqmm PWD Electrical SR i no 2.3.7 page no 6 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Mtr | 333.9 | 333.9 | 10.0 | False | None | None | False | None | False | 3339.0 | 0 | 3705847 | 136617 | None | AEEBDM7 | LT panel, MCB and Switch Board Supplying and fixing regular MCCB distribution Panel confirming to IS/IEC61439-3 and IK09 tested as per IS/IEC62262 with minimum IP43 protection provided with Polyurethane(PUR)gasket,with suitable earthing system, on wall/wood board/flushmounting using required clA,bolts,nuts,etc.,with provision for fixing of suitable type capacity MCCB' sasanincome rfor3phase Double door with necessary busbar completely wired to use on440V3 phase 4wire powder coated painting etc., complete with aprovision for fixing of single/three phase suitable capacity MCB' s as out goings confirm ingtoIS/IEC 60898 - 2. 4 way PWD Electrical SR i no5.17.1page no 17 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Each | 10845.45 | 10845.45 | 1.0 | False | None | None | False | None | False | 10845.45 | 0 | 3705848 | 136617 | None | AEEBDM8 | Supplying and fixing superior quality modulars witch mounting polycarbonate plate withn ecessary supporting backplate with required nos.of machine screws,bolts nutsetc.,complete on th eexisting metal/PVC box 6 Module PWD Electrical SR i no3.5.4page no 08 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Each | 245.7 | 245.7 | 1.0 | False | None | None | False | None | False | 245.7 | 0 | 3705849 | 136617 | None | AEEBDM9 | Supplying and fixing miniature circuit breakers on existing MCB distribution boards using necessary fixing materials and' C'Type curve, indicat or ON/OFF, energy cross-3 with Shortcircuit breaking capacity of 10K and complete wiring as required confirming to IEC 60898. 6-32Amps SP PWD Electrical SR i no5.18.1page no 17 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Each | 435.75 | 435.75 | 3.0 | False | None | None | False | None | False | 1307.25 | 0 | 3705850 | 136617 | None | AEEBDM10 | Point Wiring Point wirin gusing Copper wire with switch.Supplying and wiring adopting loop system in existing PVC Conduit/ casing capping using 1100V grade, COPPER conductor flexible multistrand FRLSPV Cinsulated,2X1.5Sq.mm Cable confirming to the GTP,with a6Amps flushtype SP control switch shall be fixed on the existing plastic sheet/gangbox,the other end of the wires shall be terminated with sufficient loose length in a wood/ PVC round block.complete for each outlet. GROUP A Short point upto 3Mtr from tapping point to out let via switch PWD Electrical SR i no2.2.1 page no 05 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Point | 282.45 | 282.45 | 1.0 | False | None | None | False | None | False | 282.45 | 0 | 3705851 | 136617 | None | AEEBDM11 | Wiring for lighting/power circuit using one FRLS PVC insulated 1100V grade, multistand copper with low conductor resistance single core wire in open or conceled system of wiring with specified IS 694-1990 and confirming to GTP of group A 2.5Sqmm PWDElectrical SR 2023-24 P.No 05 of 105 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Mtr | 44.1 | 44.1 | 70.0 | False | None | None | False | None | False | 3087.0 | 0 | 3705852 | 136617 | None | AEEBDM12 | Light Fixtures Supplyingoffeet-PVC Batten within tegrated LED tube W with high quality diffuser with Life of 25000 burning hours&70%lumen maintenance with CRI80.Power Input:220-240V@50/60Hz& Powerfactor0.9 along with CE approved.2yearsWarranty against any manufacturing defect working under standard electrical condition. one in each toilet and operator room LED light fitting 1x4-20/22w PWD electrical SR 2023-24 P no 43 of 105 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Each | 724.5 | 724.5 | 3.0 | False | None | None | False | None | False | 2173.5 | 0 | 3705853 | 136617 | None | AEEBDM13 | Fabricating,supplying and erection of...ms long hot dip Galvanized Octagonal hot dip Pole with BSEN 10025 grade S 355JO steel plate for shaft, IS 2062 for base plate with door opening arrangements, including suitable boards, Bakelite sheet and MCBs as per IS specifications suitable to with stand the wind speed of 47m/s for.......m Pole in single section and single joint welded as per IS 9595/IS10178AW Shaving dimensions bottom.....mm,top....mm with 3 mmthick, suitable base plate and 4Nos of.....long J bolts along with template and the Pole shall be hot dip galvanized in single dipping with not less than 65 micron as per ASTM-A123 and 153 etc., (excluding foundation) as per drawing appended. 5meters - Top 70mm and bottom 130 mm dia PWD electrical SR 2023-24 P no 11 of 105 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | No | 10395.0 | 10395.0 | 5.0 | False | None | None | False | None | False | 51975.0 | 0 | 3705854 | 136617 | None | AEEBDM14 | Street Light Pole Supply of LED flood light luminaire with pressuredie cast aluminium housing body for optimal thermal dissipation. Lamp compartment comprising of anti glare clear diffuser with Injection moulde dpolycarbonate /clear glass material,delivering superior light out put Rated life Burning Hrs50000hr @ Lumen Maintenance of 70%,CCT 5500K, IP66 optical and electrical compartment & impac tresistance of complete luminaire IK08. Power Factor 0.9 with mains, Surge Protection-Min 5K V along with Over voltage/ Overload, shortcircuit/miss-wiring protection. Compatible for polemauling without erdia of 40mm to 50mm. Universal Voltage drivert ooperate wide voltage range from100Vto270V50/60 Hzapplication.Compliance to IS10322/IEC60598,LM79& LM80A dherence with RoHS.UL approved MCPCB. Top access street light with single screw to ensure ease of maintenance at the sight site location with minimize dminimal tools.LED Light fixture with.......W System Power consumption.LED Efficiency 1301m/w,nominalCRI 75.Luminaire manufacturer should have in-house facility accredited by NABL/CPRI& any Government certified agency & Design & Development facility certified by ISO9001:2008. Housing with supplier wordmark/name shall be Engraved/Embos sing on the die castho using/Body part Warranty of 2 Years against any manufacturing defect working under standard electrical conditions asmentioned above should be given by LED manufacturer &C ree/Nichia/Lumileds/Osrammake LED Source. 70W PWD electrical SR 2023-24 P no 46 of 105 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Each | 7106.4 | 7106.4 | 3.0 | False | None | None | False | None | False | 21319.2 | 0 | 3705855 | 136617 | None | AEEBDM15 | Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes,
labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates CSR 2023-24 Vol-I sl no 2.2.3 Page no 15 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Cum | 6652.8 | 6652.8 | 0.38 | False | None | None | False | None | False | 2528.064 | 0 | 3705856 | 136617 | None | AEEBDM16 | Providing T.M.T steel reinforcement for R.C.C work including straightening, cutting, bending, hooking, placingin position, lapping and/or welding wherever required,tying with bindingwire and anchoring to the adjoining members wherever necessary complete as per design(laps,hooks and wastage shall not be measured and paid)including for OHT & reservoier, cost of materials,labour,HOM of machinery complete as per specifications. TMT bars Fe 550 CSR 2023-24 Volume-I sl no 2.11(h) page no 18 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Kg | 93.93 | 93.93 | 37.5 | False | None | None | False | None | False | 3522.375 | 0 | 3705857 | 136617 | None | AEEBDM17 | Providingandremovingcentering,shuttering,strutting,proppingetc.,andremovalofformworkforfoundations,footings,basesofcolumnsformassconcreteincludingcostofallmaterials,labourcompleteasper specificaitons.For Foundation worksRCC base slab CSR 2023-24 Volume-I Addendeum sl no 3&11 page no 111&112 with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Sqm | 6652.8 | 6652.8 | 0.02 | False | None | None | False | None | False | 133.056 | 0 |
| 1722946481000 | 0 | None | None | Buildings | 12 STAINLESS STEEL SCREEN | 233640.0 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
3705858 | 136618 | None | AEEBDM1 | STAINLESS STEEL SCREEN Providing, fabricating,fixing of SS Screens using SS 304 bars, 20 mm spacing of 4 mm thick with handle (7.5kg) including cost of material, transportation, labour charges etc complete as per direction of Engineer in charge with all lead and lifts loading & unloading etc. complete as per direction of Engineer-in-charge | Each | 19470.0 | 19470.0 | 12.0 | False | None | None | False | None | False | 233640.0 | 0 |
|
|
---|