tenderSubEstimateList | createdTs | version | createdDate | modifiedDate | workCategoryName | subEstimateName | estimateTotal | itemList |
---|
1726918253000 | 1 | None | None | Buildings | CIVIL WORKS | 5608036.68 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
4048993 | 157176 | None | SR 2023-24 Item No : 1.14.1 , Page No : 8 Vol 1 | Earth work excavation for Foundation In all kinds of soils
Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work In all kinds of soils Depth upto 3 m ( SR 2023-24 / Item No : 1.14.1 , Page No : 8 Vol 1 )
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 107.1 | 107.1 | 192.05 | False | None | None | False | None | False | 20568.555 | 0 | 4048994 | 157176 | None | 2.1.3 , Page No : 15 Vol 1 | P/L PCC of mix 1:3:6 (M 10)
Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates ( SR 2023-24 / Item No : 2.1.3 , Page No : 15 Vol 1)
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 6288.45 | 6288.45 | 18.56 | False | None | None | False | None | False | 116713.632 | 0 | 4048995 | 157176 | None | Vol-2, SL.No. 5.3, p. No.9 | Coursed rubble masonry
Providing Coursed rubble masonry (second sort) with hard stone in foundation & plinth with Cement mortar 1:6 (1 cement : 6 coarse sand) (COMMON SR 2023-24,Vol-2, SL.No. 5.3, p. No.9).
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 6515.25 | 6515.25 | 20.85 | False | None | None | False | None | False | 135842.9625 | 0 | 4048996 | 157176 | None | SR 2023-24, Vol-2 SL.No. 5.4, P. No. 9 | Size Stone masonry
"Providing Size Stone masonry with hard stone in foundation & plinth with
Cement mortar 1:6 (1 cement : 6 coarse sand) (SR 2023-24, Vol-2 SL.No. 5.4, P. No. 9)."
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 6708.45 | 6708.45 | 15.99 | False | None | None | False | None | False | 107268.1155 | 0 | 4048997 | 157176 | None | SR 2023-24, Vol-2,SL.No. 8.3.1, P. No.41 | Providing 20 mm cement plaster of mix :1:4
Providing 20 mm cement plaster of mix :1:4 (1 cement: 4 fine sand) to brick/stone masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. (SR 2023-24, Vol-2,SL.No. 8.3.1, P. No.41).
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Sqm | 371.7 | 371.7 | 68.25 | False | None | None | False | None | False | 25368.525 | 0 | 4048998 | 157176 | None | SR 2023-24 , Item No : 2.4.3 , Page No : 16 , Vol | RCC works M25 For Foundation work
Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates. ( SR 2023-24 , Item No : 2.4.3 , Page No : 16 , Vol 1 )
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 6652.8 | 6652.8 | 35.28 | False | None | None | False | None | False | 234710.784 | 0 | 4048999 | 157176 | None | SR 2021-22 , Appendix 1 , Page No : 115 , Vol 1 . | Additionalities for Formwork, Centering & Scaffolding ( SR 2021-22 , Appendix 1 , Page No : 115 , Vol 1 . ) Percentage on finished rate of concrete per m3
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 532.22 | 532.22 | 35.28 | False | None | None | False | None | False | 18776.7216 | 0 | 4049000 | 157176 | None | 2023-24 , Item No : 2.4.3 , Page No : 16 , Vol 1 | Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates. ( SR 2023-24 , Item No : 2.4.3 , Page No : 16 , Vol 1 )
Columns upto Plinth Beam Bottom
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 6652.8 | 6652.8 | 3.67 | False | None | None | False | None | False | 24415.776 | 0 | 4049001 | 157176 | None | SR 2021-22 , Appendix 1 , Page No : 115 , Vol 1 | Additionalities for Formwork, Centering & Scaffolding ( SR 2021-22 , Appendix 1 , Page No : 115 , Vol 1 . ) Percentage on finished rate of concrete per m3
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 4656.96 | 4656.96 | 3.67 | False | None | None | False | None | False | 17091.0432 | 0 | 4049002 | 157176 | None | SR 2021-22 , Appendix 1 , Page No : 115 , Vol 1 | Additionalities for Formwork, Centering & Scaffolding ( SR 2021-22 , Appendix 1 , Page No : 115 , Vol 1 . ) Percentage on finished rate of concrete per m3
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 3326.4 | 3326.4 | 9.7 | False | None | None | False | None | False | 32266.08 | 0 | 4049003 | 157176 | None | SR 2023-24 , Item No : 2.5.2 , Page No : 16 , Vol | P/ L RCC works M25 for Super structures
Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates ( SR 2023-24 , Item No : 2.5.2 , Page No : 16 , Vol 1 )
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 7185.15 | 7185.15 | 6.09 | False | None | None | False | None | False | 43757.5635 | 0 | 4049004 | 157176 | None | SR 2021-22 , Appendix 1 , Page No : 115 , Vol 1 | Additionalities for Formwork, Centering & Scaffolding ( SR 2021-22 , Appendix 1 , Page No : 115 , Vol 1 . ) Percentage on finished rate of concrete per m3
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 5029.61 | 5029.61 | 6.09 | False | None | None | False | None | False | 30630.3249 | 0 | 4049005 | 157176 | None | SR 2021-22 , Appendix 1 , Page No : 115 , Vol 1 | Additionalities for Formwork, Centering & Scaffolding ( SR 2021-22 , Appendix 1 , Page No : 115 , Vol 1 . ) Percentage on finished rate of concrete per m3
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 4311.09 | 4311.09 | 3.67 | False | None | None | False | None | False | 15821.7003 | 0 | 4049006 | 157176 | None | SR 2023-24 , Item No : 2.5.2 , Page No : 16 , Vol | Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates ( SR 2023-24 , Item No : 2.5.2 , Page No : 16 , Vol 1 )
Roof Beam
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 7185.15 | 7185.15 | 13.1 | False | None | None | False | None | False | 94125.465 | 0 | 4049007 | 157176 | None | SR 2021-22 , Appendix 1 , Page No : 115 , Vol 1 | Additionalities for Formwork, Centering & Scaffolding ( SR 2021-22 , Appendix 1 , Page No : 115 , Vol 1 . ) Percentage on finished rate of concrete per m3
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 4311.09 | 4311.09 | 13.1 | False | None | None | False | None | False | 56475.279 | 0 | 4049008 | 157176 | None | SR 2023-24 , Item No : 2.5.2 , Page No : 16 , Vol | Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates ( SR 2023-24 , Item No : 2.5.2 , Page No : 16 , Vol 1 )
Roof Slab
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 7185.15 | 7185.15 | 44.86 | False | None | None | False | None | False | 322325.829 | 0 | 4049009 | 157176 | None | SR 2021-22 , Appendix 1 , Page No : 115 , Vol 1 | Additionalities for Formwork, Centering & Scaffolding ( SR 2021-22 , Appendix 1 , Page No : 115 , Vol 1 . ) Percentage on finished rate of concrete per m3
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 7185.15 | 7185.15 | 1.63 | False | None | None | False | None | False | 11711.7945 | 0 | 4049010 | 157176 | None | SR 2021-22 , Appendix 1 , Page No : 115 , Vol 1 | Additionalities for Formwork, Centering & Scaffolding ( SR 2021-22 , Appendix 1 , Page No : 115 , Vol 1 . ) Percentage on finished rate of concrete per m3
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 3233.32 | 3233.32 | 1.58 | False | None | None | False | None | False | 5108.6456 | 0 | 4049011 | 157176 | None | SR 2023-24 , Item No : 2.1.4 , Page No : 15 , Vol | P/L PCC works M10 for Cill Concrete
Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the\ work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates ( SR 2023-24 , Item No : 2.1.4 , Page No : 15 , Vol 1 )
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 6527.85 | 6527.85 | 2.31 | False | None | None | False | None | False | 15079.3335 | 0 | 4049012 | 157176 | None | SR 2023-24 , Item No : 2.11 a, Page No : 18 , Vol | P/F of TMT Bars Fe-550D
Supplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification, a. Buildings ( SR 2023-24 , Item No : 2.11 a, Page No : 18 , Vol 1 )
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Tonne | 93929.85 | 93929.85 | 11.09 | False | None | None | False | None | False | 1041682.0365 | 0 | 4049013 | 157176 | None | COMMON SR 2023-24,Vol-1 SL.No. 1.9, P. No. 34 | Filling available excavated earth
Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. (COMMON SR 2023-24,Vol-1 SL.No. 1.9, P. No. 34)
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 279.3 | 279.3 | 99.51 | False | None | None | False | None | False | 27793.143 | 0 | 4049014 | 157176 | None | COMMON SR 2023-24, Vol-1, SI.No.1.8, P.No -33 | Construction of Embankment
Construction of Embankment by excavating the available approved Gravel/Murrum deposited at a place or borrow pits during or prior excavation with all lifts and lead, transportation to site, spreading, grading to required slope and compacting to meet the requirement complete as per specifications, including cost of labour,rolling,water,all materials,usage & all other appurtenaces required to complete the work (COMMON SR 2023-24, Vol-1, SI.No.1.8, P.No -33)
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 497.7 | 497.7 | 189.4 | False | None | None | False | None | False | 94264.38 | 0 | 4049015 | 157176 | None | SR 2023-24 Item No : 2.1.3 , Page No : 15 Vol 1 | P/L Floor Bed PCC of mix 1:3:6 (M 10)
Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates ( SR 2023-24 / Item No : 2.1.3 , Page No : 15 Vol 1)
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 6288.45 | 6288.45 | 25.95 | False | None | None | False | None | False | 163185.2775 | 0 | 4049016 | 157176 | None | COMMON SR 2023-24, Vol-2, SL.No. 6.2, Pg. No. 13 | Providing Brick work with common burnt clay Non Modular bricks
Providing Brick work with common burnt clay Non Modular bricks of class designation 3.5 in foundation and plinth in Cement mortar 1:6 (1 cement : 6 coarse sand) including cost of all materials, labour, scaffolding and usage charges of machinery & other incidental charges complete as per the direction of engineer incharge of work. (COMMON SR 2023-24, Vol-2, SL.No. 6.2, Pg. No. 13).
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 8376.9 | 8376.9 | 100.04 | False | None | None | False | None | False | 838025.076 | 0 | 4049017 | 157176 | None | SR 2023-24 Ballari Circle Item No.12.13.2, Page No | Providing Red Salwood frames
Providing Red Salwood frames of doors, windows, clerestory windows, ventilators and other frames, wrought, framed or assembled including making plaster groves (excluding cost of cement concrete and side clamps), but including cost of materials, labour, usage charges complete as per specifications. (PWD SR 2023-24 Ballari Circle Item No.12.13.2, Page No.100 Vol 2)
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 104580.0 | 104580.0 | 0.26 | False | None | None | False | None | False | 27190.8 | 0 | 4049018 | 157176 | None | PWD SR 2023-24 Ballari Circle Item No.12.57.1., Pa | Providing and fixing flush door shutter
Providing and fixing flush door shutter made out of solid core block board type, well seasoned , chemicaly treated hard wood battens and internal frame with minimum 45 mm wide wooden frame alround door shutters covered with cross bonded wooden sheets (core veneer) hot pressed and fastened on both sides of the door useing liquid phenol formaldehyde resin as per IS specifications 2202 (part-I) 1991. from manufacturer complete as per spcification. (PWD SR 2023-24 Ballari Circle Item No.12.57.1., Page No.105 vol 2)
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Sqm | 4245.15 | 4245.15 | 12.6 | False | None | None | False | None | False | 53488.89 | 0 | 4049019 | 157176 | None | PWD SR 2023-24 Ballari Circle Item No.12.90, Page | Providing & fixing of 3-track x 2-panel sliding windows
Providing & fixing of 3-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having an overall size of 108mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm x 75mm with GI reinforcement of 2mm and mesh sash of size 37mm x 58mm. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24 mm. Windows shall be provided with 6mm plain float glass, standard hardware& Multi point locking system with touch lock. Wall thickness of frame & sash shall be of 2mm-2.5mm. Maximum possible size 2419mm x 2200mm. (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made)(PWD SR 2023-24 Ballari Circle Item No.12.90, Page No.110 Vol 2) ---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Sqm | 7070.7 | 7070.7 | 19.44 | False | None | None | False | None | False | 137454.408 | 0 | 4049020 | 157176 | None | PWD SR 2023-24 Ballari Circle Item No.12.85, Page | Providing & fixing of louvered ventilator
Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) (PWD SR 2023-24 Ballari Circle Item No.12.85, Page No.109 Vol 2)
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Sqm | 6004.95 | 6004.95 | 12.96 | False | None | None | False | None | False | 77824.152 | 0 | 4049021 | 157176 | None | PWD SR 2023-24 Ballari Circle Item No.11.34B, Page | Providing and fixing M.S. grills
Providing and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. (PWD SR 2023-24 Ballari Circle Item No.11.34B, Page No.85 Vol 2)
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Kg | 192.15 | 192.15 | 408.24 | False | None | None | False | None | False | 78443.316 | 0 | 4049022 | 157176 | None | SR 2023-24 Ballari Circle Item No.8.1.2, Page No.4 | Providing 12 mm cement plaster ( Internal )
Providing 12 mm cement plaster with cement mortar 1:6 (1 cement:6 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials,labour, curing complete as per specifications and as per directions of Engineer-in-charge. (PWD SR 2023-24 Ballari Circle Item No.8.1.2, Page No.41 Vol 2)
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Sqm | 339.15 | 339.15 | 465.06 | False | None | None | False | None | False | 157725.099 | 0 | 4049023 | 157176 | None | SR 2023-24 Ballari Circle Item No.8.9, Page No.42 | Providing 18 mm cement plaster ( External )
Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) and a top layer 6 mm thick cement plaster with cement mortar 1:3 (1 cement : 3 coarse sand) finished rough with sponge to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. (PWD SR 2023-24 Ballari Circle Item No.8.9, Page No.42 Vol 2)
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Sqm | 404.25 | 404.25 | 263.6 | False | None | None | False | None | False | 106560.3 | 0 | 4049024 | 157176 | None | PWD SR 2023-24 Ballari Circle Item No.9.12.2, Page | Providing and laying vitrified floor tiles
Providing and laying vitrified floor tiles with thickness 9-10 mm in different sizes with water absorption less than 0.08% and conforming to IS: 15622, of approved make, in all colours and shades, laid on 20mm thick cement mortar 1:4 (1 cement : 4 coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including grouting the joints with white cement and matching pigments etc., complete. Size of Tile 600x600 mm (PWD SR 2023-24 Ballari Circle Item No.9.12.2, Page No.60 Vol 2)
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Sqm | 1202.25 | 1202.25 | 259.46 | False | None | None | False | None | False | 311935.785 | 0 | 4049025 | 157176 | None | PWD SR 2023-24 Ballari Circle Item No.9.38, Page N | Providing skirting, dadooing
Providing skirting, dadooing, rises of steps with white glazed tiles 6mm thick on 10mm thick cement plaster 1:3 and jointed with white cement slurry over existing rough plaster surface using glazed tiles of approved make and size including cost of materials, labour, complete as per specifications. (PWD SR 2023-24 Ballari Circle Item No.9.38, Page No.65 Vol 2)
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Sqm | 1461.6 | 1461.6 | 12.3 | False | None | None | False | None | False | 17977.68 | 0 | 4049026 | 157176 | None | PWD SR 2023-24 Item No. 9.24, Page No.63 Vol 2 | Providing and laying Polished Granite stone flooring
Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. (PWD SR 2023-24 Item No. 9.24, Page No.63 Vol 2)
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Sqm | 2589.3 | 2589.3 | 128.0 | False | None | None | False | None | False | 331430.4 | 0 | 4049027 | 157176 | None | SR 2023-24 Ballari Circle Item No.8.51, Page No.50 | Providing and applying white cement based putty
Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. (SR 2023-24 Ballari Circle Item No.8.51, Page No.50 Vol 2)
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Sqm | 105.0 | 105.0 | 724.56 | False | None | None | False | None | False | 76078.8 | 0 | 4049028 | 157176 | None | SR 2023-24 Ballari Circle Item No.8.54.2, Page No. | Internal Wall painting with premium acrylic emulsion paint
Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. (SR 2023-24 Ballari Circle Item No.8.54.2, Page No.50 Vol 2)
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Sqm | 115.5 | 115.5 | 724.67 | False | None | None | False | None | False | 83699.385 | 0 | 4049029 | 157176 | None | SR 2023-24 Ballari Circle Item No.8.27, Page No.45 | Applying one coat of water thinnable cement primer
Applying one coat of water thinnable cement primer of approved brand and manufacture on wall surface :Water thinnable cement primer to give an even shade after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. (SR 2023-24 Ballari Circle Item No.8.27, Page No.45 Vol 2)
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Sqm | 55.65 | 55.65 | 724.67 | False | None | None | False | None | False | 40327.8855 | 0 | 4049030 | 157176 | None | SR 2023-24 Ballari Circle Item No.8.27, Page No.45 | Applying one coat of water thinnable cement primer of approved brand and manufacture on wall surface :Water thinnable cement primer to give an even shade after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. (SR 2023-24 Ballari Circle Item No.8.27, Page No.45 Vol 2)
Quantity same as External Plastering
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Sqm | 55.65 | 55.65 | 263.6 | False | None | None | False | None | False | 14669.34 | 0 | 4049031 | 157176 | None | SR 2023-24 Ballari Circle Item No.8.28, Page No.45 | External Painting with water proofing cement paint ( External )
Finishing walls with water proofing cement paint of required shade :New work (Two coats applied @ 4.84 kg/10 m²) to give an even shade after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. (SR 2023-24 Ballari Circle Item No.8.28, Page No.45 Vol 2)
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Sqm | 93.45 | 93.45 | 263.6 | False | None | None | False | None | False | 24633.42 | 0 | 4049032 | 157176 | None | PWD SR 2023-24 Ballari Circle Item No.8.41, Page N | P/F Applying enamel metal paint two coats
Painting with synthetic enamel paint of approved brand and manufacture of required colour to give an even shade :Two coats on new work over an under coat of suitable shade with ordinary paint of approved brand and manufacture after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. (PWD SR 2023-24 Ballari Circle Item No.8.41, Page No.48 vol 2)
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Sqm | 175.35 | 175.35 | 19.44 | False | None | None | False | None | False | 3408.804 | 0 | 4049033 | 157176 | None | COMMON SR 2023-24, SL No 8.34.1, VOL-2, P.No .47 | Applying priming coat
Applying priming coat: With ready mixed pink or Grey primer of approved brand and manufacture on wood work (hard and soft wood) including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. (COMMON SR 2023-24, SL No 8.34.1, VOL-2, P.No .47)
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Sqm | 55.65 | 55.65 | 25.2 | False | None | None | False | None | False | 1402.38 | 0 | 4049034 | 157176 | None | PWD SR 2023-24 Ballari Circle Item No.11.28 Page N | P/F Stainless steel railing for Entrance Steps
Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners, stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in- charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.) including cost of materials, labour, usage charges of machinery completeas per specifications and as per directions of the Engineer-in-Charge. (PWD SR 2023-24 Ballari Circle Item No.11.28 Page No.85 Vol 2)
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Kg | 593.25 | 593.25 | 54.0 | False | None | None | False | None | False | 32035.5 | 0 | 4049035 | 157176 | None | SR 2023-24 , Item No : 2.4.3 , Page No : 16 , Vol | Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates. ( SR 2023-24 , Item No : 2.4.3 , Page No : 16 , Vol 1 )
Plinth Beam
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 6652.8 | 6652.8 | 9.71 | False | None | None | False | None | False | 64598.688 | 0 | 4049036 | 157176 | None | SR 2023-24 , Item No : 2.5.2 , Page No : 16 , Vol | Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates ( SR 2023-24 , Item No : 2.5.2 , Page No : 16 , Vol 1 )
RCC Lintel
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 7185.15 | 7185.15 | 3.67 | False | None | None | False | None | False | 26369.5005 | 0 | 4049037 | 157176 | None | SR 2021-22 , Appendix 1 , Page No : 115 , Vol 1 | Additionalities for Formwork, Centering & Scaffolding ( SR 2021-22 , Appendix 1 , Page No : 115 , Vol 1 . ) Percentage on finished rate of concrete per m3
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Cum | 3592.58 | 3592.58 | 44.86 | False | None | None | False | None | False | 161163.1388 | 0 | 4049038 | 157176 | None | COMMON SR 2023-24 Vol 2 Page No. 149 SL.No. 15 | Providing and laying water proofing
Providing and laying water proofing treatment to the Roof with PU based single component elastomeric pure polyurethane based coating on New terrace/Chajjas/Sunken portion of WC:Bathroom, cold applied PU waterproofing membrane that is highly elastic with elongation greater than 400% and tensile strength greater than 2MPa as per ASTM D412. The waterproofing membrane to be applied in 2coats @ 1.6 kg/m2 to achieve final DFT (Dry Film Thickness) of 1mm including prime coat of epoxy primer @150 g/m2 and protection with 120gsm Geo-textile over the waterproofing membrane. The finished cost to include surface preparation, making coving at Junction, Bore Packing, treatment of construction joints completely as per specification. (COMMON SR 2023-24, Vol-2, Page No. 149. SL.No. 15.1)
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Sqm | 857.85 | 857.85 | 299.06 | False | None | None | False | None | False | 256548.621 | 0 | 4049039 | 157176 | None | PWD SR 2023-24 ,Item No.8.16.3, Page No.43 Vol 2) | Providing and fixing suitable plaster mesh
Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment.Plaster mesh 100mm wide (PWD SR 2023-24 ,Item No.8.16.3, Page No.43 Vol 2)
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | m | 46.2 | 46.2 | 650.7 | False | None | None | False | None | False | 30062.34 | 0 |
| 1726918253000 | 0 | None | None | Buildings | Electrification Works (Internal) | 618761.39 | id | tenderSubEstimateId | categoryName | itemCode | description | uomName | baseRate | finalRate | quantity | modifyQuantityYn | minQuantity | maxQuantity | buyBackYn | buyBackValue | hideYn | netAmount | taxCount |
---|
4049040 | 157177 | None | 1.2.1 | Concealed Conduit Pipes
Supplying heavy gauge PVC conduit pipe . mm dia.mm thick confirming to IS 2509 with suitable size bends, metal/PVC Junction boxes, adhesive paste etc., and running before concreting the slab. The conduit should be tied to the reinforcement rods by using binding wires and unused ways of junction boxes and pipe ends should be covered using PVC end enclosures, run with 18SWG GI fish wire wherever necessary. PWD Ele SR 2 23-24, (Page No- 2 Vol-6)
19/20 mm dia 2 mm thick
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Mtr | 69.3 | 69.3 | 90.0 | False | None | None | False | None | False | 6237.0 | 0 | 4049041 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 2 Vol-6)1.2.2 | Supplying heavy gauge PVC conduit pipe . mm dia.mm thick confirming to IS 2509 with suitable size bends, metal/PVC Junction boxes, adhesive paste etc., and running before concreting the slab. The conduit should be tied to the reinforcement rods by using binding wires and unused ways of junction boxes and pipe ends should be covered using PVC end enclosures, run with 18SWG GI fish wire wherever necessary.
25 mm dia 2 mm thick
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Mtr | 81.9 | 81.9 | 100.0 | False | None | None | False | None | False | 8190.0 | 0 | 4049042 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 3 Vol-6)1.5.2 | PVC/metal conduit Deep junction box
Supplying and fixing PVC/metal conduit Deep junction box
25 mm deep Junction box
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 58.8 | 58.8 | 32.0 | False | None | None | False | None | False | 1881.6 | 0 | 4049043 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 8 Vol-6)3.4.3 | Sheet metal box made
Supplying and flush mounting powder coated / galvanized metal box suitable for mounting modular switch plates. The box should be firmly flush mounted after due groove cutting in Brick/Stone/C.C wall
4-5 Way
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 185.85 | 185.85 | 4.0 | False | None | None | False | None | False | 743.4 | 0 | 4049044 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 8 Vol-6)3.4.4 | Supplying and flush mounting powder coated / galvanized metal box suitable for mounting modular switch plates. The box should be firmly flush mounted after due groove cutting in Brick/Stone/C.C wall
6 Way
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 231.0 | 231.0 | 40.0 | False | None | None | False | None | False | 9240.0 | 0 | 4049045 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 8 Vol-6)3.4.6 | Supplying and flush mounting powder coated / galvanized metal box suitable for mounting modular switch plates. The box should be firmly flush mounted after due groove cutting in Brick/Stone/C.C wall
10-12 Way Each
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 334.95 | 334.95 | 10.0 | False | None | None | False | None | False | 3349.5 | 0 | 4049046 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 8 Vol-6)3.4.8 | Supplying and flush mounting powder coated / galvanized metal box suitable for mounting modular switch plates. The box should be firmly flush mounted after due groove cutting in Brick/Stone/C.C wall
18 Way
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 425.25 | 425.25 | 4.0 | False | None | None | False | None | False | 1701.0 | 0 | 4049047 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 8 Vol-6)3.5.3 | Polycarbonate plate
Supplying and fixing superior quality modular switch mounting polycarbonate plate with necessary supporting back plate with required nos. of machine screws, bolts nuts etc., complete on the existing metal/PVC box.
4 Module
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 183.75 | 183.75 | 4.0 | False | None | None | False | None | False | 735.0 | 0 | 4049048 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 8 Vol-6)3.5.4 | Supplying and fixing superior quality modular switch mounting polycarbonate plate with necessary supporting back plate with required nos. of machine screws, bolts nuts etc., complete on the existing metal/PVC box.
6 Module
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 245.7 | 245.7 | 40.0 | False | None | None | False | None | False | 9828.0 | 0 | 4049049 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 8 Vol-6)3.5.6 | Supplying and fixing superior quality modular switch mounting polycarbonate plate with necessary supporting back plate with required nos. of machine screws, bolts nuts etc., complete on the existing metal/PVC box.
10-12 Module
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 361.2 | 361.2 | 10.0 | False | None | None | False | None | False | 3612.0 | 0 | 4049050 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 8 Vol-6)3.5.8 | Supplying and fixing superior quality modular switch mounting polycarbonate plate with necessary supporting back plate with required nos. of machine screws, bolts nuts etc., complete on the existing metal/PVC box.
18 Module
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 479.85 | 479.85 | 4.0 | False | None | None | False | None | False | 1919.4 | 0 | 4049051 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 3 Vol-6)1.7.1 | Extra for Grove Cutting
Extra for Groove cutting in brick wall/CC floor to the suitable depth for concealing of Conduit/GI pipe and plastering, finishing upto wall surface complete.
upto 50mm Conduit in Brick Walls
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | m | 30.45 | 30.45 | 95.0 | False | None | None | False | None | False | 2892.75 | 0 | 4049052 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 4 Vol-6)1.13 | Metal Fan Box
Supplying And Fixing Metal Fan Box with Round Hook.
Metal Fan Box with Round Hook.
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | No | 122.85 | 122.85 | 32.0 | False | None | None | False | None | False | 3931.2 | 0 | 4049053 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 5 Vol-6)2.2.1 | Point Wiring
Point wiring Copper without switch.Supplying and wiring adopting loop system in existing PVC Conduit /casing usingf 1100v Grade , COPPER conductor flexible multistrand FRLS PVC insulated., 2x1.5 Sqm. Cable confirming to the GTP without switch, the other end of the wires shall be terminated with sufficient loose length in a wood /PVC round block. Complete for each outlet(5/2.3) Group
Short point upto 3m from tapping point to out let via switch box
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Point | 282.45 | 282.45 | 40.0 | False | None | None | False | None | False | 11298.0 | 0 | 4049054 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 5 Vol-6)2.2.2 | Point wiring Copper without switch.Supplying and wiring adopting loop system in existing PVC Conduit /casing usingf 1100v Grade , COPPER conductor flexible multistrand FRLS PVC insulated., 2x1.5 Sqm. Cable confirming to the GTP without switch, the other end of the wires shall be terminated with sufficient loose length in a wood /PVC round block. Complete for each outlet(5/2.3) Group
Medium point above 3m upto 6m from tapping point to out let via switch box
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Point | 397.95 | 397.95 | 40.0 | False | None | None | False | None | False | 15918.0 | 0 | 4049055 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 5 Vol-6)2.2.3 | Point wiring Copper without switch.Supplying and wiring adopting loop system in existing PVC Conduit /casing usingf 1100v Grade , COPPER conductor flexible multistrand FRLS PVC insulated., 2x1.5 Sqm. Cable confirming to the GTP without switch, the other end of the wires shall be terminated with sufficient loose length in a wood /PVC round block. Complete for each outlet(5/2.3) Group
long point above 6m upto 10m from tapping point to out let via switch box
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Point | 582.75 | 582.75 | 42.0 | False | None | None | False | None | False | 24475.5 | 0 | 4049056 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 5 Vol-6)2.3.1 | Wires for Lightings/Power Circuit
Wiring for lighting/power circuit using one of FRLS PVC insulated 1100V grade, multistrand copper wire with low conductor resistance single core in open or concealed system of wiring with specified IS-694:confirming to latest amendments.
1.0 Sqmm
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Mtr | 367.5 | 367.5 | 320.0 | False | None | None | False | None | False | 117600.0 | 0 | 4049057 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 5 Vol-6)2.3.2 | Wiring for lighting/power circuit using one of FRLS PVC insulated 1100V grade, multistrand copper wire with low conductor resistance single core in open or concealed system of wiring with specified IS-694:confirming to latest amendments.
1.5 Sqmm
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Mtr | 27.3 | 27.3 | 580.0 | False | None | None | False | None | False | 15834.0 | 0 | 4049058 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 5 Vol-6)2.3.3 | Wiring for lighting/power circuit using one of FRLS PVC insulated 1100V grade, multistrand copper wire with low conductor resistance single core in open or concealed system of wiring with specified IS-694:confirming to latest amendments.
2.5 Sqmm
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Mtr | 44.1 | 44.1 | 500.0 | False | None | None | False | None | False | 22050.0 | 0 | 4049059 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 5 Vol-6)2.3.4 | Wiring for lighting/power circuit using one of FRLS PVC insulated 1100V grade, multistrand copper wire with low conductor resistance single core in open or concealed system of wiring with specified IS-694:confirming to latest amendments.
4 mm2
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Mtr | 66.15 | 66.15 | 220.0 | False | None | None | False | None | False | 14553.0 | 0 | 4049060 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 5 Vol-6)2.3.5 | Wiring for lighting/power circuit using one of FRLS PVC insulated 1100V grade, multistrand copper wire with low conductor resistance single core in open or concealed system of wiring with specified IS-694:confirming to latest amendments.
6 Sqmm
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Mtr | 96.6 | 96.6 | 115.0 | False | None | None | False | None | False | 11109.0 | 0 | 4049061 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 9 Vol-6)3.6.1 | Modular Switches/Sockets/Regulators etc
Supplying and fixing of modular switch & connected accessories on existing modular switch plate as per IS 3854 and IS 1293.
6A One Way Switch
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 107.1 | 107.1 | 170.0 | False | None | None | False | None | False | 18207.0 | 0 | 4049062 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 9 Vol-6)3.6.2 | Supplying and fixing of modular switch & connected accessories on existing modular switch plate as per IS 3854 and IS 1293.
6A Two Way Switch
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 174.3 | 174.3 | 4.0 | False | None | None | False | None | False | 697.2 | 0 | 4049063 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 9 Vol-6)3.6.4 | Supplying and fixing of modular switch & connected accessories on existing modular switch plate as per IS 3854 and IS 1293.
Stepped Fan Regulator Two Module
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 374.85 | 374.85 | 32.0 | False | None | None | False | None | False | 11995.2 | 0 | 4049064 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 9 Vol-6)3.6.9 | Supplying and fixing of modular switch & connected accessories on existing modular switch plate as per IS 3854 and IS 1293.
32A DP Switch
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 342.3 | 342.3 | 4.0 | False | None | None | False | None | False | 1369.2 | 0 | 4049065 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 9 Vol-6)3.6.11 | Supplying and fixing of modular switch & connected accessories on existing modular switch plate as per IS 3854 and IS 1293.
TV/Telephone Socket
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 163.8 | 163.8 | 2.0 | False | None | None | False | None | False | 327.6 | 0 | 4049066 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 9 Vol-6)3.6.7 | Supplying and fixing of modular switch & connected accessories on existing modular switch plate as per IS 3854 and IS 1293.
16A One Way Switch
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 189.0 | 189.0 | 4.0 | False | None | None | False | None | False | 756.0 | 0 | 4049067 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 9 Vol-6)3.6.10 | Supplying and fixing of modular switch & connected accessories on existing modular switch plate as per IS 3854 and IS 1293.
6/16A Universal Socket
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 247.8 | 247.8 | 80.0 | False | None | None | False | None | False | 19824.0 | 0 | 4049068 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 10 Vol-6)3.14.5 | Electrical accessories on existing switch board.
Supplying And fixing/replacing of 6/16/32A electrical accessories on existing switch board
6A Bakelite Ceiling Rose
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | No | 81.9 | 81.9 | 67.0 | False | None | None | False | None | False | 5487.3 | 0 | 4049069 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 10 Vol-6)3.14.6 | Supplying And fixing/replacing of 6/16/32A electrical accessories on existing switch board
6A Pendant Holder
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | No | 74.55 | 74.55 | 35.0 | False | None | None | False | None | False | 2609.25 | 0 | 4049070 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 43 Vol-6)11.3.2 | LIGHT FIXTURES &ACCESSORIES
PVC Batten with LED Tubes
Supplying of .feet -PVC Batten with integrated LED tube . W with high quality diffuser with Life of 25000 burning hours & 70% lumen maintenance with CRI 80. Power Input: 220-240V@ 50/60Hz & Power factor 0.9 along with CE approved. 2 years Warranty against any manufacturing defect working under standard electrical condition.
LED light fighting 1 x4'- 20/22 w
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 724.5 | 724.5 | 28.0 | False | None | None | False | None | False | 20286.0 | 0 | 4049071 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 44 Vol-6)11.5.2 | LED Down Lights
Supply of round/square recess/surface mounted rolling type LED Down light with .W GU 10 LED Lamp Rib Fabricated from Die cast aluminium with white powder coated prewired to mains connector & has swiveling unit of aluminium die cast eye ball & LED Lamp position retained by circular wire spring, with Life of 25000 burning hours & 70% lumen maintenance with CRI 80. Power Input: 220-240V @ 50/60Hz & Power factor PWD Ele SR 2 23-24, (Page No- 44 Vol-6)
0.9 along with CE approved. 2 years Warranty against any manufacturing defect working under standard electrical condition LED square or round down light 10-12W
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 929.25 | 929.25 | 15.0 | False | None | None | False | None | False | 13938.75 | 0 | 4049072 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 44 Vol-6)11.6.1 | Supplying of recess mounting non integral type
Supplying of recess mounting non integral type . LED w luminaire comprising of pressure decast/extruded aluminium housing, with spring loaded false ceiling clA, Power LEDs with CCT 6500 degree K, CRI 70%. efficacy 100 lumen per W, 120degree beam spread, life 25000 burning hours and Compliance to IS 10322/IEC 60598, LM 79 & LM 80. The lamp compartment is enclosed with anti glare opal diffuser which enhances the lighting level LEDs are driven by HF electronic driver integrated in a separate control gear assembly., with PF 0.95, power loss should 5% of lamp Wage., short circuit & open circuit protection to be integrated in the circuit, THD less than 20%, Life as per LM 79. The operating input voltage should be between 130 to 275 V. BIS Approved and Tested by NABL/CPRI accredited laboratory with 2 years Warranty against any manufacturing defect working under standard electrical condition.
LED modular down light 1'x1' 18W
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 3294.9 | 3294.9 | 5.0 | False | None | None | False | None | False | 16474.5 | 0 | 4049073 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 50 Vol-6)12.25.2 | Patty Type Fitting
Supplying of patty fitting, made out of CRCA Sheet metal body with locking type holder completely wired with HF Electronic Ballast, Operating voltage range from 180V to 265V, 50Hz AC power supply excluding Tube
1 x 4' Tube light fitting.
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 357.0 | 357.0 | 28.0 | False | None | None | False | None | False | 9996.0 | 0 | 4049074 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 30 Vol-6)6.4.1 | Ceiling Fans
"Supplying of Ceiling Fan with Capacitor rating As per guideline of BEE 5 star rating and IS:374/79 and also comply with IS: 1709/1984 with latest amendment, Rated
voltage 220 V/50 Hz, Rated power input 48 W +/- 10 %, Rated current As per IS:374/79, Rated power factor 0.9 lagging(min), Rated speed 350 +/- 10% RPM, Rated air delivery 210 +/- 10% Cubic Meter Minimum, Rated service value 4.2 CMM / W, Three Blades of blade leaf 1.05 mm thick Aluminium Alloy sheet, Class B motor insulation, Bearing Two ball bearings, Top 6202, Bottom 6201, as per IS specification,Motor winding. Temp rise Shall not exceed 75 deg C over and ambient of 40 0C by resistance method at 245 V, Insulation resistance Shall not be less than Two Mega Ohms (2M Ohms), Leakage current Should not exceed 210 Micro Amp, Power input, W& current, Air Delivery & Fan Speed as per IS:374/1979 with latest amendment, 2 year manufacturer Warranty."
48" Sweep 5 Star (1200 mm)
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 2810.85 | 2810.85 | 32.0 | False | None | None | False | None | False | 89947.2 | 0 | 4049075 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 56 Vol-6)3.7.1 | Fixing all type of Luminaries
Fixing all types and all capacities of fluorescent / false ceiling / spot light / CFL / LED fittings indoor on the wall / ceiling / rafters / girders using 23/0.0076” twin twisted PVC insulated wires, required Nos of round blocks and clamps.
On wall / ceiling / Rafter / Girders
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 128.1 | 128.1 | 52.0 | False | None | None | False | None | False | 6661.2 | 0 | 4049076 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 57 Vol-6)13.11 | Fixing Ceiling Fan
Fixing a ceiling /wall mounting fan of all capacities and all types, with necessary clA and 'S' hook made out of 15mm dia MS rod, with 5 A. ceiling rose of approved quality with necessary length of 23/0.0076 inch PVC insulated twin twisted wire of approved quality, mounted on a suitable size wooden board and wired.
Ceiling Fan
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 330.75 | 330.75 | 32.0 | False | None | None | False | None | False | 10584.0 | 0 | 4049077 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 18 Vol-6)5.19.12 | MCB Distribution Boards
Supplying and fixing regular MCB distribution boards on wall / wood board / flush mounting using required clamps, bolts, nuts etc., with provision for fixing suitable type capacity MCB's single phase / 3 phase / single door with powder coated painting. Made out of 14 SWG MS enclosure.
6 Way TP & N
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 5187.0 | 5187.0 | 1.0 | False | None | None | False | None | False | 5187.0 | 0 | 4049078 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 17 Vol-6)5.18.1 | Miniature Circuit Breakers
Supplying and fixing miniature circuit breakers on existing MCB distribution boards using necessary fixing materials and 'C' Type curve, indicator ON/OFF, energy cross-3 with Short circuit breaking capacity of 10K and complete wiring as required confirming to IEC 60898.
6-32 A SP
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 435.75 | 435.75 | 14.0 | False | None | None | False | None | False | 6100.5 | 0 | 4049079 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 17 Vol-6)5.18.4 | Supplying and fixing miniature circuit breakers on existing MCB distribution boards using necessary fixing materials and 'C' Type curve, indicator ON/OFF, energy cross-3 with Short circuit breaking capacity of 10K and complete wiring as required confirming to IEC 60898.
6-32 A DP
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 775.95 | 775.95 | 3.0 | False | None | None | False | None | False | 2327.85 | 0 | 4049080 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 17 Vol-6)5.18.9 | Supplying and fixing miniature circuit breakers on existing MCB distribution boards using necessary fixing materials and 'C' Type curve, indicator ON/OFF, energy cross-3 with Short circuit breaking capacity of 10K and complete wiring as required confirming to IEC 60898.
50-63 A TPN
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 3242.4 | 3242.4 | 1.0 | False | None | None | False | None | False | 3242.4 | 0 | 4049081 | 157177 | None | PWD Ele SR 2 23-24, (Page No- 17 Vol-6)5.15.9 | Moulded Case Circuit Breaker (MCCB)
Supplying and fixing Moulded Case Circuit Breaker (MCCB) over the existing wood/panel board using necessary screws, bolts, nuts, necessary phase separators, handle and wiring complete. Protection of Overload and Short circuit in Thermal Magnetic Release. Micro processor release shall have Earth Fault as per IS-13947. (Icu=100% lcs). In 4P MCCB, all Poles should have protection for Short-Cicrcuit/Over Load. For Microprocessor MCCBS Facility for segregating Priority and Non Priority loads must be available in the MCCB. MCCB shall be provided with double insulation (insulation between front cover and internal power circuits to avoid any accidental contact with live current carrying path with the front cover open). Multi-pole breakers shall be designed to break all the poles simultaneously and they shall have a single mechanism.
100 A 25 kA For LT Panel
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 8911.35 | 8911.35 | 1.0 | False | None | None | False | None | False | 8911.35 | 0 | 4049082 | 157177 | None | ELE SR 2023-24, (Page No- 20 PWD Ele SR Part-2 ,)5 | MS Sheet
Fabricating supplying and mounting MS box made out … SWG suitable for floor / wall mounting, fully weather proof with provision for better heat dissipation, provided with hinged front cover, equipped with tamper proof locking arrangements, with suitable size clamps with necessary cable entry pipe with gland and box should be finished with 2 coats of red oxide primer paint and finally finished with approved colour enameled metal paint etc., complete.
MS Sheet 14 SWG
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Sq CM | 0.53 | 0.53 | 26000.0 | False | None | None | False | None | False | 13780.0 | 0 | 4049083 | 157177 | None | ELE SR 2023-24, (Page No- 20 PWD Ele SR 2 ,)5 Vol | MS IRON FRAME
Supplying and fixing angle iron frame work fabricated out of M.S. angle iron. and M.S. Flat.with bolts, washers etc., and painted with 2 coats of red oxide and then two coats of approved paint.
40 x 40 x 6 mm
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Mtr | 320.25 | 320.25 | 2.0 | False | None | None | False | None | False | 640.5 | 0 | 4049084 | 157177 | None | ELE SR 2023-24,, (Page No- 20, Pwd Part-I ,)5.40.1 | Bus bar
Supplying . amps rated 3phase with neutral bus bar using required capacity electrolytic aluminium strips covered with heat shrinkable coloured PVC sleeve, mounted on phenolic/FRP/DMC insulator which are mounted on powder coated 40x6mm M.S.flat frame work in existing panel board. The bus bar shall have suitable holes for termination of incoming and outgoing cables as per IS specification with necessary bolts, nuts and washers etc., complete.
For LT Panel
100 A 4 x 30 x 6 mm Aluminium Strips
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | m | 2588.25 | 2588.25 | 2.0 | False | None | None | False | None | False | 5176.5 | 0 | 4049085 | 157177 | None | ELE SR 2023-24, (Page No- 19, Pwd Vol_6 ,)5.33 | Supplying of multi function digital meter
Supplying of multi function digital meter with three line back light LC type display for voltage, Current, frequency,Power, power factor, KVA, KWH, KVAR suitable for 3 phase, 4 wire LT network with IP 54 degree of protection and completely wired as required with communication Port and Class 0.5s accuracy.
For LT Panel
Multi function digital meter
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 9780.75 | 9780.75 | 1.0 | False | None | None | False | None | False | 9780.75 | 0 | 4049086 | 157177 | None | ELE SR 2023-24, (Page No- 19, Pwd Vol_6 ,)5.31 | Trivector Meter
Supplying and fixing Electronic Trivector Meter (ETV) suitable for operation LT operation and -CT operated meter in polycarbonate body in class 0.5 accuracy as per IS 14697 and completely wired
For LT Panel
Trivector Meter (ETV)
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 4609.5 | 4609.5 | 1.0 | False | None | None | False | None | False | 4609.5 | 0 | 4049087 | 157177 | None | PWD Ele ESCOMS SR 2-23-24, (Page No- 13, Vol-6 32. | 1.1 KV LT UG Cable
Supplying, fixing and wiring 50/5 to 400/5A 5VA burden Current Transformer Class 0.5 accuracy with Tape Wound
For LT Panel
25 Sqmm, 3.5 Core, (12 GI Strips - 4 x 0.8 mm)
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Km | 146526.45 | 146526.45 | 0.05 | False | None | None | False | None | False | 7326.3225 | 0 | 4049088 | 157177 | None | PWD SR 2-23-24, (Page No- 06, Vol-1 ,)1.6.1 | Digging of Trench
Earth work excavation for pipelines/cables by Manual means upto 600 mm trench width, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter, including dressing of excavated surfaces, disposing off or leveling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m. Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering and lift upto 1.5 m including cost of labour, tools, usage& other appurtenances required to complete the work
For LT Panel
In all kinds of soils. Depth upto 1.50m
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Mtr | 508.2 | 508.2 | 50.0 | False | None | None | False | None | False | 25410.0 | 0 | 4049089 | 157177 | None | ELE SR 2023-24, (Page No- 52, ESCOMs SR 2023-24 ,2 | Labour Charges
Labour charges for laying of 1.1 KV class UG cable in existing trench GI pipe / stoneware pipe / on wall / on pole as required.
For LT Panel
2.5 to 25 Sqmm
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Km | 21930.3 | 21930.3 | 0.05 | False | None | None | False | None | False | 1096.515 | 0 | 4049090 | 157177 | None | PWD Ele SR 2-23-24, (Page No- 14, Vol-6 ,)5.7.3 | Supplying & fixing of Porcelain fuse channel
Supplying & fixing of Porcelain fuse channel with cut out onexisting wooden/panel using necessary nuts, bolts andwashers.
63 A
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Each | 725.55 | 725.55 | 3.0 | False | None | None | False | None | False | 2176.65 | 0 | 4049091 | 157177 | None | ESCOMS SR 2023-24, (Page No- 22, VOL-06 ,)51.01 | Earth Electrode for Grounding
GI Grounding pipe, B - Class, 42 mm dia, 2.5 Mtr long, 3.2 mm thick with bolt, nut, GI Strips and washer complete Minimum Weight of GI Pipe: 7.3 Kg
For LT Panel & Floors
Earth electrode
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Nos | 780.15 | 780.15 | 2.0 | False | None | None | False | None | False | 1560.3 | 0 | 4049092 | 157177 | None | ESCOMS SR 2023-24, (Page No- 22, VOL-06 ,)51.02 | Good Quality well burnt Charcoal for grounding purposes packed in non returnable gunny bag of 30 Kg each
Charcoal
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Nos | 709.8 | 709.8 | 5.0 | False | None | None | False | None | False | 3549.0 | 0 | 4049093 | 157177 | None | ESCOMS SR 2023-24, (Page No- 22, VOL-06 ,)51.03 | Good Quality Salt for grounding purposes packed in 50 Kg gunny bag
Salt
---- with all lead, lifts, loading, un-loading charges, including cost of all materials, cost of labour, HoM all Machineries, transportation of all materials and machineries to site of work, labour, incidental and equipment charges, etc., complete as per specification and as per the directions of Engineer-in-charge for finished item of work. | Bag | 325.5 | 325.5 | 5.0 | False | None | None | False | None | False | 1627.5 | 0 |
|
|
---|