createdTsNone
versionNone
createdDateNone
modifiedDateNone
noticeInvitingTenderDTO
createdTs1726205729462
version6
createdDateNone
modifiedDateNone
tenderTypeRFQ
evaluationTypeTWO_COVER
evaluationTypeTextTwo Cover
invitingStrategyOPEN
invitingStrategyTextOpen
taxTypeINCLUSIVE_TAX
tenderFee7500.00
emd3333000.00
bidValueTypeITEM_WISE
bidValueTypeTextItem wise
tenderReceiptClose03-10-2024 17:00:00
tenderQueryClose20-09-2024 11:00:00
technicalBidOpen04-10-2024 17:01:00
publishedDate13-09-2024 16:25:44
publishedByPostKREIS_EE1_EEOFF_BNG
publishedByUserKPE16759 - M JAYACHANDRARAJU
bidValidityPeriod90
noOfCalls1
preBidMeetingDate20-09-2024 11:00:00
preBidMeetingYnTrue
preQualificationBidOpenNone
denominationTypeRUPEES
denominationTypeTextRupees
retenderedYnNone
percentageRateTypeTextNone
contactPersonM JAYACHANDRA RAJU
splitEmdRequiredYnTrue
emdBankGuarantee3233000.00
emdCash100000.00
bgValidityPeriod135
hideWeightageNone
multipleCurrencySelectionAllowedYnFalse
isTechWeightageAllowedFalse
highestBidderSelectionFalse
isVariableEmdAllowedNone
qcbsTenderYnNone
itemwiseEmdRequiredYnNone
sampleSubmissionDateNone
officeNumber08022283366
mobileNumber8050810068
tenderSupplierListNone
tenderSchedule
createdTs1726205729487
version18
createdDateNone
modifiedDateNone
tenderNumberKREIS/2024-25/BD/WORK_INDENT337
titleConstruction of Dr B R Ambedkar Residential school complex (SC) at Ambale, Chikkamagaluru taluk & District and Construction of Dr B R Ambedkar Girls Residential school complex (ST) at Shivani, Tarikere taluk, Chikkamagaluru District
descriptionConstruction of Dr B R Ambedkar Residential school complex (SC) at Ambale, Chikkamagaluru taluk & District and Construction of Dr B R Ambedkar Girls Residential school complex (ST) at Shivani, Tarikere taluk, Chikkamagaluru District
categoryWORKS
categoryTextWorks
ecv333295436.24
deptNameKarnataka Residential Educational Institutions Society
statusPUBLISHED
statusTextPublished
remarksNone
csrValueNone
ecvtenderYnTrue
location2893
locationNameKREIS Executive Engineer Section Bengaluru
provisionalAmount440000000.0
groupOverheadTotalNone
fileNumberChikkamagaluru
tenderSubEstimateList
createdTsversioncreatedDatemodifiedDateworkCategoryNamesubEstimateNameestimateTotalitemList
17262057290001NoneNoneBuildingsAcademic Block (Amble)31262651.23
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3994648154591NoneVOL - 3, C - 2 2.1 a (i) MoRT&H 201Cutting of Trees, excluding removal of stumps and roots of trees. (i) Girth from 300 mm to 600 mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each595.0595.0200.0FalseNoneNoneFalseNoneFalse119000.00
3994649154591NoneVOL - 3, C - 2 2.2 b (i) MoRT&H 201Removal of stumps and roots including backfilling with suitable material to required compaction (i) Girth from 300 mm to 600 mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each356.0356.0200.0FalseNoneNoneFalseNoneFalse71200.00
3994650154591None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.02361.4583FalseNoneNoneFalseNoneFalse240868.74660
3994651154591None1.15.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In ordinary/soft rock without blasting upto 1.5 m depth ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum363.0363.0542.2264FalseNoneNoneFalseNoneFalse196828.18320
3994652154591None1.16.1Earth work excavation for Foundation by Mechanical means depth upto 1.50m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including cost of explosives, dressing of excavated surfaces, disposing off or levelling the excavated stuff or sorting & stacking the selected stuff for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, blasting materials, tools, usage of Machinery & all other appurtenaces required to complete the work. In Hard Rock ( requiring blasting) Depth upto 1.50m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum554.0554.067.7783FalseNoneNoneFalseNoneFalse37549.17820
3994653154591None1.9Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum266.0266.01043.7291FalseNoneNoneFalseNoneFalse277631.94060
3994654154591None4.1Providing and injecting chemical emulsion for Pre-constructional Anti-Termite Treatment, creating continuous chemical barrier under and around the column pits, walls, trenches, basement excavation, top surface of the plinth filling, junction of wall and floor, along the external perimeter of building, expansion joints, over the top surface of consolidated earth on which apron is to be laid, surrounding of pipes and conduits with Chlorpyriphos 20% E.C. / Lindane 20% E.C. @ 3.19 l/m2 including cost of chemical, diluting in water to one percent concentration, labour, usage charges of machinery, complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm118.0118.0810.0FalseNoneNoneFalseNoneFalse95580.00
3994655154591None2.1.3Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5989.05989.0133.0FalseNoneNoneFalseNoneFalse796537.00
3994656154591None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6217.06217.06.855FalseNoneNoneFalseNoneFalse42617.5350
3994657154591None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7460.47460.42.4621FalseNoneNoneFalseNoneFalse18368.250840
3994658154591None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7522.577522.572.2FalseNoneNoneFalseNoneFalse16549.6540
3994659154591None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7584.747584.743.1FalseNoneNoneFalseNoneFalse23512.6940
3994660154591None2.1.6Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:2:4 Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6243.06243.04.0FalseNoneNoneFalseNoneFalse24972.00
3994661154591None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Footing concrete ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6842.886842.88193.0207FalseNoneNoneFalseNoneFalse1320817.4876160
3994662154591None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Pedastals ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10771.210771.211.1846FalseNoneNoneFalseNoneFalse120471.563520
3994663154591None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Columns Concrete Upto PB ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10771.210771.25.3634FalseNoneNoneFalseNoneFalse57770.254080
3994664154591None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Plinth Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9504.09504.021.7339FalseNoneNoneFalseNoneFalse206558.98560
3994665154591None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Grade Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9504.09504.037.0723FalseNoneNoneFalseNoneFalse352335.13920
3994666154591None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Columns Concrete Up to Roof ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11633.111633.125.6793FalseNoneNoneFalseNoneFalse298729.864830
3994667154591None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10948.810948.837.2586FalseNoneNoneFalseNoneFalse407936.959680
3994668154591None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10264.510264.5123.1868FalseNoneNoneFalseNoneFalse1264450.90860
3994669154591None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Lintel Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10948.810948.89.4446FalseNoneNoneFalseNoneFalse103407.036480
3994670154591None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Staircase ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10264.510264.57.77FalseNoneNoneFalseNoneFalse79755.1650
3994671154591None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor For Columns Concrete Up to Roof ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11749.4311749.4324.3432FalseNoneNoneFalseNoneFalse286018.7243760
3994672154591None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11058.2811058.2831.1038FalseNoneNoneFalseNoneFalse343954.5294640
3994673154591None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10367.1410367.1497.1454FalseNoneNoneFalseNoneFalse1007119.9621560
3994674154591None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor For Lintel Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11058.2811058.287.9935FalseNoneNoneFalseNoneFalse88394.361180
3994675154591None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor For Staircase ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10367.1410367.143.885FalseNoneNoneFalseNoneFalse40276.33890
3994676154591None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor For Columns ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11865.7611865.761.6767FalseNoneNoneFalseNoneFalse19895.3197920
3994677154591None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11167.7711167.779.0838FalseNoneNoneFalseNoneFalse101445.7891260
3994678154591None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10469.7910469.798.7956FalseNoneNoneFalseNoneFalse92088.0849240
3994679154591None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10780.2710780.276.0FalseNoneNoneFalseNoneFalse64681.620
3994680154591None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t89457.089457.041.7963FalseNoneNoneFalseNoneFalse3738971.60910
3994681154591None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t90351.5790351.5717.1262FalseNoneNoneFalseNoneFalse1547379.0581340
3994682154591None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t91246.1491246.142.9328FalseNoneNoneFalseNoneFalse267606.6793920
3994683154591None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1310.01310.0805.0FalseNoneNoneFalseNoneFalse1054550.00
3994684154591None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1323.11323.1642.0FalseNoneNoneFalseNoneFalse849430.20
3994685154591None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1336.21336.2191.0FalseNoneNoneFalseNoneFalse255214.20
3994686154591None6.34Providing and constructing load bearing wall with Solid Concrete blocks of size 400x100x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1104.01104.0128.0FalseNoneNoneFalseNoneFalse141312.00
3994687154591None6.34Providing and constructing load bearing wall with Solid Concrete blocks of size 400x100x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1115.041115.0498.0FalseNoneNoneFalseNoneFalse109273.920
3994688154591None12.13.1Providing Salwood frames of doors, windows, clerestory windows, ventilators and other frames, wrought, framed or assembled including making plaster groves (excluding cost of cement concrete and side clamps), but including cost of materials, labour, usage charges complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum98815.098815.00.9FalseNoneNoneFalseNoneFalse88933.50
3994689154591None12.13.1Providing Salwood frames of doors, windows, clerestory windows, ventilators and other frames, wrought, framed or assembled including making plaster groves (excluding cost of cement concrete and side clamps), but including cost of materials, labour, usage charges complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum99803.1599803.150.8FalseNoneNoneFalseNoneFalse79842.520
3994690154591None12.17Providing and fixing in position fully panelled Honne wood shutters for doors with , stiles and rails of 35mm. thick with bottom and lock rails 180mm wide top rail and stiles 100mm wide as per drawing and panels of 25mm thick including cost of materials, labour, usage charges complete as per specifications. (excluding cost of fixtures) Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm7085.07085.05.0FalseNoneNoneFalseNoneFalse35425.00
3994691154591None12.57.3Providing and fixing flush door shutter made out of solid core block board type, well seasoned , chemicaly treated hard wood battens and internal frame with minimum 45 mm wide wooden frame alround door shutters covered with cross bonded wooden sheets (core veneer) hot pressed and fastened on both sides of the door useing liquid phenol formaldehyde resin as per IS specifications 2202 (part-I) 1991. from manufacturer complete as per spcification.-do- 30 mm thick both side commercial Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3005.03005.026.0FalseNoneNoneFalseNoneFalse78130.00
3994692154591None12.57.3Providing and fixing flush door shutter made out of solid core block board type, well seasoned , chemicaly treated hard wood battens and internal frame with minimum 45 mm wide wooden frame alround door shutters covered with cross bonded wooden sheets (core veneer) hot pressed and fastened on both sides of the door useing liquid phenol formaldehyde resin as per IS specifications 2202 (part-I) 1991. from manufacturer complete as per spcification.-do- 30 mm thick both side commercial First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3035.053035.0526.0FalseNoneNoneFalseNoneFalse78911.30
3994693154591None12.51Fixing of door frame in an existing opening including embedding frame in floor and walls after cutting masonry for holdfasts for embedding holdfast in cement concrete 1:3:6 of 20mm and down size granite metal painting two coats of coal tar to sides of frame, making good the damages to walls and floor as required and disposal of the debris with lead upto 50 m. including cost of materials, labour charges, complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1016.01016.010.0FalseNoneNoneFalseNoneFalse10160.00
3994694154591None12.51Fixing of door frame in an existing opening including embedding frame in floor and walls after cutting masonry for holdfasts for embedding holdfast in cement concrete 1:3:6 of 20mm and down size granite metal painting two coats of coal tar to sides of frame, making good the damages to walls and floor as required and disposal of the debris with lead upto 50 m. including cost of materials, labour charges, complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1026.161026.169.0FalseNoneNoneFalseNoneFalse9235.440
3994695154591None12.93.1Providing and fixing factory made single extruded WPC (Wood Polymer Composite) solid door/window/Clerestory windows & other Frames/ Chowkhat comprising of virgin PVC polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibres (wood powder/rice husk/ wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) fabricated with miter joints after applying PVC solvent cement and screwed with full body threaded star headed SS screws having minimum frame density of 850 kg/m3, screw withdrawal strength of 2200 N (Face) & 1100 N (Edge), minimum compressive strength of 58 N/mm2 , modulus of elasticity 900 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixed in position with M.S hold fast/lugs/SS dash fasteners of required dia and length complete as per direction of Engineer-InCharge. (Fixtures shall be paid for separately) Size 62 x 100mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr702.0702.0101.0FalseNoneNoneFalseNoneFalse70902.00
3994696154591None12.93.1Providing and fixing factory made single extruded WPC (Wood Polymer Composite) solid door/window/Clerestory windows & other Frames/ Chowkhat comprising of virgin PVC polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibres (wood powder/rice husk/ wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) fabricated with miter joints after applying PVC solvent cement and screwed with full body threaded star headed SS screws having minimum frame density of 850 kg/m3, screw withdrawal strength of 2200 N (Face) & 1100 N (Edge), minimum compressive strength of 58 N/mm2 , modulus of elasticity 900 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixed in position with M.S hold fast/lugs/SS dash fasteners of required dia and length complete as per direction of Engineer-InCharge. (Fixtures shall be paid for separately) Size 62 x 100mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr709.02709.0291.0FalseNoneNoneFalseNoneFalse64520.820
3994697154591None12.94.1Providing and fixing factory made Green certified, Anti Termite, UV resistant, high water absorbant single extruded WPC (Wood PolymerComposite) solid plain flush door shutter of required size comprising of virgin polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibers (wood powder/rice husk/wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) having minimum density of 650 kg/m3 and screw withdrawal strength of 1800 N (Face) & 900 N (Edge), minimum compressive strength of 50 N/mm2 , modulus of elasticity 850 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixing with stainless steel butt hinges of required size with necessary full body threaded star headed counter sunk S.S screws The cost includes cost of materials, transportation, labour and fixing charges.(Cost of Fixtures to be paid separately) 30 mm thickness Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3485.03485.033.0FalseNoneNoneFalseNoneFalse115005.00
3994698154591None12.94.1Providing and fixing factory made Green certified, Anti Termite, UV resistant, high water absorbant single extruded WPC (Wood PolymerComposite) solid plain flush door shutter of required size comprising of virgin polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibers (wood powder/rice husk/wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) having minimum density of 650 kg/m3 and screw withdrawal strength of 1800 N (Face) & 900 N (Edge), minimum compressive strength of 50 N/mm2 , modulus of elasticity 850 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixing with stainless steel butt hinges of required size with necessary full body threaded star headed counter sunk S.S screws The cost includes cost of materials, transportation, labour and fixing charges.(Cost of Fixtures to be paid separately) 30 mm thickness First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3519.853519.8529.0FalseNoneNoneFalseNoneFalse102075.650
3994699154591None12.88Providing & fixing of 2-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having a overall size of 60mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm X 58mm with GI reinforcement of 1mm for the frame and 1.5 mm for the sash. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24mm. Windows shall be provided with 5mm plain float glass, standard hardware& single point locking system with touch lock. Wall thickness of frame & sash shall be of 2-2.5 mm. Maximum possible size 1819mm x 1819mm (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5390.05390.0104.0FalseNoneNoneFalseNoneFalse560560.00
3994700154591None12.88Providing & fixing of 2-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having a overall size of 60mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm X 58mm with GI reinforcement of 1mm for the frame and 1.5 mm for the sash. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24mm. Windows shall be provided with 5mm plain float glass, standard hardware& single point locking system with touch lock. Wall thickness of frame & sash shall be of 2-2.5 mm. Maximum possible size 1819mm x 1819mm (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5443.95443.992.0FalseNoneNoneFalseNoneFalse500838.80
3994701154591None12.88Providing & fixing of 2-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having a overall size of 60mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm X 58mm with GI reinforcement of 1mm for the frame and 1.5 mm for the sash. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24mm. Windows shall be provided with 5mm plain float glass, standard hardware& single point locking system with touch lock. Wall thickness of frame & sash shall be of 2-2.5 mm. Maximum possible size 1819mm x 1819mm (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5497.85497.82.0FalseNoneNoneFalseNoneFalse10995.60
3994702154591None12.85Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5719.05719.058.0FalseNoneNoneFalseNoneFalse331702.00
3994703154591None12.85Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5776.195776.1953.0FalseNoneNoneFalseNoneFalse306138.070
3994704154591None12.85Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5833.385833.381.0FalseNoneNoneFalseNoneFalse5833.380
3994705154591None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs183.0183.02907.0FalseNoneNoneFalseNoneFalse531981.00
3994706154591None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs184.83184.832589.0FalseNoneNoneFalseNoneFalse478524.870
3994707154591None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs186.66186.6649.0FalseNoneNoneFalseNoneFalse9146.340
3994708154591None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2852.02852.0775.0FalseNoneNoneFalseNoneFalse2210300.00
3994709154591None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2880.522880.52523.0FalseNoneNoneFalseNoneFalse1506511.960
3994710154591None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2909.042909.045.0FalseNoneNoneFalseNoneFalse14545.20
3994711154591None9.11Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved make, in all colours, shades, except White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick bed of cement mortar 1:4 (1 Cement : 4 Coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including pointing the joints with white cement and matching pigments etc., complete. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm889.0889.065.0FalseNoneNoneFalseNoneFalse57785.00
3994712154591None9.11Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved make, in all colours, shades, except White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick bed of cement mortar 1:4 (1 Cement : 4 Coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including pointing the joints with white cement and matching pigments etc., complete. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm897.89897.8954.0FalseNoneNoneFalseNoneFalse48486.060
3994713154591None9.39Providing skirting, dadooing, rises of steps with colour glazed tiles 6mm thick on 10mm thick cement plaster 1:3 and jointed with white cement slurry over existing rough plaster surface using glazed tiles of approved make and size including cost of materials, labour, complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1449.01449.0266.0FalseNoneNoneFalseNoneFalse385434.00
3994714154591None9.39Providing skirting, dadooing, rises of steps with colour glazed tiles 6mm thick on 10mm thick cement plaster 1:3 and jointed with white cement slurry over existing rough plaster surface using glazed tiles of approved make and size including cost of materials, labour, complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1463.491463.49179.0FalseNoneNoneFalseNoneFalse261964.710
3994715154591None10.2Providing edge moulding to 18mm thick Granite stone counters, vanities etc including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr328.0328.0157.0FalseNoneNoneFalseNoneFalse51496.00
3994716154591None10.2Providing edge moulding to 18mm thick Granite stone counters, vanities etc including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr331.28331.2866.0FalseNoneNoneFalseNoneFalse21864.480
3994717154591None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm295.0295.01611.0FalseNoneNoneFalseNoneFalse475245.00
3994718154591None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm297.95297.951284.0FalseNoneNoneFalseNoneFalse382567.80
3994719154591None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm300.9300.946.0FalseNoneNoneFalseNoneFalse13841.40
3994720154591None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm371.0371.0665.0FalseNoneNoneFalseNoneFalse246715.00
3994721154591None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm374.71374.71822.0FalseNoneNoneFalseNoneFalse308011.620
3994722154591None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm378.42378.42452.0FalseNoneNoneFalseNoneFalse171045.840
3994723154591None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg64.064.0100.0FalseNoneNoneFalseNoneFalse6400.00
3994724154591None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg64.6464.64124.0FalseNoneNoneFalseNoneFalse8015.360
3994725154591None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg65.2865.2867.8FalseNoneNoneFalseNoneFalse4425.9840
3994726154591None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm295.0295.0275.0FalseNoneNoneFalseNoneFalse81125.00
3994727154591None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm297.95297.95188.0FalseNoneNoneFalseNoneFalse56014.60
3994728154591None8.16 aProviding lath plaster with cement mortar 1:3, 5cms thick with 6mm dia mild steel bars at 20 cms. c to c both horizontally and vertically fixing chicken mesh for drop chajja, facia, backing to cup boards including cost of all materials, labour, providing and removing form work usage charges, curing complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1238.01238.05.0FalseNoneNoneFalseNoneFalse6190.00
3994729154591None8.16 aProviding lath plaster with cement mortar 1:3, 5cms thick with 6mm dia mild steel bars at 20 cms. c to c both horizontally and vertically fixing chicken mesh for drop chajja, facia, backing to cup boards including cost of all materials, labour, providing and removing form work usage charges, curing complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1250.381250.385.0FalseNoneNoneFalseNoneFalse6251.90
3994730154591None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm100.0100.02441.2034FalseNoneNoneFalseNoneFalse244120.340
3994731154591None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. First floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm101.0101.01914.4572FalseNoneNoneFalseNoneFalse193360.17720
3994732154591None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm102.0102.069.1128FalseNoneNoneFalseNoneFalse7049.50560
3994733154591None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm110.0110.02202.0284FalseNoneNoneFalseNoneFalse242223.1240
3994734154591None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. First floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm111.1111.11696.5622FalseNoneNoneFalseNoneFalse188488.060420
3994735154591None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm112.2112.269.1128FalseNoneNoneFalseNoneFalse7754.456160
3994736154591None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.053.02441.2034FalseNoneNoneFalseNoneFalse129383.78020
3994737154591None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.5353.531914.4572FalseNoneNoneFalseNoneFalse102480.8939160
3994738154591None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. TerraceFloor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm54.0654.0669.1128FalseNoneNoneFalseNoneFalse3736.2379680
3994739154591None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm174.0174.0665.0FalseNoneNoneFalseNoneFalse115710.00
3994740154591None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm175.74175.74822.0FalseNoneNoneFalseNoneFalse144458.280
3994741154591None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm177.48177.48452.0FalseNoneNoneFalseNoneFalse80220.960
3994742154591None8.34.1Applying priming coat: With ready mixed pink or Grey primer of approved brand and manufacture on wood work (hard and soft wood) including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.053.072.0FalseNoneNoneFalseNoneFalse3816.00
3994743154591None8.34.1Applying priming coat: With ready mixed pink or Grey primer of approved brand and manufacture on wood work (hard and soft wood) including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.5353.5362.0FalseNoneNoneFalseNoneFalse3318.860
3994744154591None8.33.2Painting wood work with Deluxe Multi Surface Paint of required shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @0.75 L/10 m² of approved brand and manufacture to give an even shade including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, sand papering and knotting , cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm138.0138.072.0FalseNoneNoneFalseNoneFalse9936.00
3994745154591None8.33.2Painting wood work with Deluxe Multi Surface Paint of required shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @0.75 L/10 m² of approved brand and manufacture to give an even shade including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, sand papering and knotting , cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm139.38139.3862.0FalseNoneNoneFalseNoneFalse8641.560
3994746154591None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @ 0.80 L/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm139.0139.0162.0FalseNoneNoneFalseNoneFalse22518.00
3994747154591None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @ 0.80 L/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm140.39140.39144.0FalseNoneNoneFalseNoneFalse20216.160
3994748154591None8.4Painting with synthetic enamel paint of approved brand and manufacture to give an even shade :Two coats on new work after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm115.0115.0239.175FalseNoneNoneFalseNoneFalse27505.1250
3994749154591None8.4Painting with synthetic enamel paint of approved brand and manufacture to give an even shade :Two coats on new work after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm116.15116.15217.895FalseNoneNoneFalseNoneFalse25308.504250
3994750154591None11.28Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners, stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in- charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.) including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs565.0565.0369.0FalseNoneNoneFalseNoneFalse208485.00
3994751154591None11.28Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners, stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in- charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.) including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs570.65570.6572.0FalseNoneNoneFalseNoneFalse41086.80
3994752154591None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr66.066.0382.0FalseNoneNoneFalseNoneFalse25212.00
3994753154591None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr66.6666.66348.0FalseNoneNoneFalseNoneFalse23197.680
3994754154591None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr67.3267.3241.0FalseNoneNoneFalseNoneFalse2760.120
3994755154591None7.18Providing and laying cinder concrete in cement 1:15 ( 1 cement : 15 cinder of 12.5mm nominal gauge) on terraced roof or sunken slabs, laid to slope compacting, including cost of materials, labour, curing complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum2037.172037.1725.0FalseNoneNoneFalseNoneFalse50929.250
3994756154591None15.7Integral Crystalline Water Proofing Admixture Providing and supplying crystalline integral concrete waterproofing admixture that waterproofs concrete by forming crystals deep in the pores, capillaries and microcracks of the concrete, self-seal waterproofing compound to bridge shrinkage cracks upto 0.5mm in width & resist hydro-static pressure upto 16bar for both positive & negative pressure confirming to DIN 1048 part 5 for 56% reduction in depth of penetration against control, resistance to chloride penetration confirming to ASTM C 1202 with 64% improvement against control & protecting steel reinforcement against corrosion mixed @ 1% by weight of cementitious content in concrete. ie., integral crystaline waterproofing admix @ 0.5 kg/bag of cement. (For calculation purpose 320 kg of Cement for M-20 grade of Concrete is considered in the analysis) First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm621.15621.1580.0FalseNoneNoneFalseNoneFalse49692.00
3994757154591None9.25Providing and laying 60mm thick factory made cement concrete paver block of approved shape and colour of M -30 grade made of C&D waste by block making machine with vibratory compaction laid in required pattern and including over 50mm thick compacted bed of coarse sand, filling the joints with fine sand etc. all complete as per the direction of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm800.0800.044.58FalseNoneNoneFalseNoneFalse35664.00
3994758154591None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9613.59613.54.0515FalseNoneNoneFalseNoneFalse38949.095250
3994759154591None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9679.89679.83.7672FalseNoneNoneFalseNoneFalse36465.742560
3994760154591None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9746.19746.11.0FalseNoneNoneFalseNoneFalse9746.10
3994761154591NoneVOL - 5 7.1.1Providing and fixing MS ladder between landings, 45 cms wide using angle iron of specified sizes, 20mm MS bars at 25 cms. centre to centre, with necessary supports of same angle iron etc. as directed, including hand railing on both sides with 25mm dia. GI pipes with angle iron props at 2 mtrs. intervals and 0.5M heigh, including fixing in ground with CC 1:2:4 and two coats of anticorrosive bituminous paint etc. with all lead and lifts etc. complete with: MS angle of 65 x 65 x 8mm Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr4464.544464.544.5FalseNoneNoneFalseNoneFalse20090.430
3994762154591None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.038.0378.0FalseNoneNoneFalseNoneFalse14364.00
3994763154591None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.3838.38309.6FalseNoneNoneFalseNoneFalse11882.4480
3994764154591None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.7638.7614.4FalseNoneNoneFalseNoneFalse558.1440
3994765154591None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.038.0429.56FalseNoneNoneFalseNoneFalse16323.280
3994766154591None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.3838.38358.02FalseNoneNoneFalseNoneFalse13740.80760
3994767154591None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.7638.7618.0FalseNoneNoneFalseNoneFalse697.680
3994768154591None22.15.7Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Tower Bolts 250x10mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos200.0200.030.0FalseNoneNoneFalseNoneFalse6000.00
3994769154591None22.15.7Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Tower Bolts 250x10mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos202.0202.026.0FalseNoneNoneFalseNoneFalse5252.00
3994770154591None22.15.8Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS hinges 125 mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos50.050.0101.0FalseNoneNoneFalseNoneFalse5050.00
3994771154591None22.15.8Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS hinges 125 mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos50.550.587.0FalseNoneNoneFalseNoneFalse4393.50
3994772154591None22.15.1Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Handles 200mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos450.0450.060.0FalseNoneNoneFalseNoneFalse27000.00
3994773154591None22.15.1Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Handles 200mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos454.5454.552.0FalseNoneNoneFalseNoneFalse23634.00
3994774154591None22.15.4Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Aldrop 16mm dia, 300mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos375.0375.029.0FalseNoneNoneFalseNoneFalse10875.00
3994775154591None22.15.4Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Aldrop 16mm dia, 300mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos378.75378.7526.0FalseNoneNoneFalseNoneFalse9847.50
3994776154591None22.15.10Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Door stopper 75mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos100.0100.011.0FalseNoneNoneFalseNoneFalse1100.00
3994777154591None22.15.10Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Door stopper 75mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos101.0101.09.0FalseNoneNoneFalseNoneFalse909.00
3994778154591None11.16.1Providing and fixing Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete. Hot finished welded type tubes including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs138.72138.7218000.0FalseNoneNoneFalseNoneFalse2496960.00
3994779154591None7.38Providing and fixing precoated galvanised iron profile sheets (size, shape and pitch of corrugation as approved by Engineer-in-charge) 0.50 mm (+ 0.05 %) total coated thickness with zinc coating 120 grams per m2 as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns. Sheet should have protective guard film of 25 microns minimum to avoid scratches during transportation and should be supplied in single length upto 12 m or as desired by Engineer-in-charge. The sheet shall be fixed using self drilling/self tapping screws of size (5.5x 55 mm) with EPDM seal, complete upto any pitch in horizontal/ vertical or curved surfaces, excluding the cost of purlins, rafters and trusses and including cutting to size and shape wherever required. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm579.36579.36690.0FalseNoneNoneFalseNoneFalse399758.40
3994780154591None7.4.1Providing & fixing ridges or hips of width 60 cm overall width plain G.S. sheet fixed with polymer coated J or L hooks, bolts and nuts 8 mm dia G.I. limpet and bitumen washers complete as per design drawings. 0.63 mm thick with zinc coating not less than 275 g/m² ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m651.78651.7860.0FalseNoneNoneFalseNoneFalse39106.80
3994781154591None7.6Providing and fixing 15 cm wide, 45 cm overall semi-circular plain G.S. sheet gutter with iron brackets 40x3mm size, bolts, nuts and washers etc., including making necessary connections with rain water pipes complete. (0.63 mm thick with zinc coating not less than 275 g/m²) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m657.9657.9103.0FalseNoneNoneFalseNoneFalse67763.70
3994782154591None20.107Providing and fixing plain rolled glass 4mm thick with teakwood beading of 10mm thick. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1147.01147.04.965FalseNoneNoneFalseNoneFalse5694.8550
3994783154591None20.107Providing and fixing plain rolled glass 4mm thick with teakwood beading of 10mm thick. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1158.471158.474.365FalseNoneNoneFalseNoneFalse5056.721550
17262057300000NoneNoneBuildingsGirls Dormitory (Amble)25170223.63
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3994784154592NoneVOL - 3, C - 2 2.1 a (i) MoRT&H 201Cutting of Trees, excluding removal of stumps and roots of trees. (i) Girth from 300 mm to 600 mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each595.0595.0165.0FalseNoneNoneFalseNoneFalse98175.00
3994785154592NoneVOL - 3, C - 2 2.2 b (i) MoRT&H 201Removal of stumps and roots including backfilling with suitable material to required compaction (i) Girth from 300 mm to 600 mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each356.0356.0165.0FalseNoneNoneFalseNoneFalse58740.00
3994786154592None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.01308.1611FalseNoneNoneFalseNoneFalse133432.43220
3994787154592None1.15.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In ordinary/soft rock without blasting upto 1.5 m depth ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum363.0363.0492.8094FalseNoneNoneFalseNoneFalse178889.81220
3994788154592None1.16.1Earth work excavation for FOUNDATION by Mechanical means depth upto 1.50m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including cost of explosives, dressing of excavated surfaces, disposing off or levelling the excavated stuff or sorting & stacking the selected stuff for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, blasting materials, tools, usage of Machinery & all other appurtenaces required to complete the work. In Hard Rock ( requiring blasting) Depth upto 1.50m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum554.0554.061.6011FalseNoneNoneFalseNoneFalse34127.00940
3994789154592None1.9Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum266.0266.0762.3514FalseNoneNoneFalseNoneFalse202785.47240
3994790154592None4.1Providing and injecting chemical emulsion for Pre-constructional Anti-Termite Treatment, creating continuous chemical barrier under and around the column pits, walls, trenches, basement excavation, top surface of the plinth filling, junction of wall and floor, along the external perimeter of building, expansion joints, over the top surface of consolidated earth on which apron is to be laid, surrounding of pipes and conduits with Chlorpyriphos 20% E.C. / Lindane 20% E.C. @ 3.19 l/m2 including cost of chemical, diluting in water to one percent concentration, labour, usage charges of machinery, complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm118.0118.0404.0FalseNoneNoneFalseNoneFalse47672.00
3994791154592None2.1.3Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5989.05989.085.0FalseNoneNoneFalseNoneFalse509065.00
3994792154592None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6217.06217.05.0FalseNoneNoneFalseNoneFalse31085.00
3994793154592None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7460.47460.40.9929FalseNoneNoneFalseNoneFalse7407.431160
3994794154592None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7522.577522.571.1201FalseNoneNoneFalseNoneFalse8426.0306570
3994795154592None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7584.747584.741.1278FalseNoneNoneFalseNoneFalse8554.0697720
3994796154592None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7646.917646.911.9FalseNoneNoneFalseNoneFalse14529.1290
3994797154592None2.1.6Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:2:4 Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6243.06243.04.0FalseNoneNoneFalseNoneFalse24972.00
3994798154592None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Footing concrete ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6842.886842.88152.2742FalseNoneNoneFalseNoneFalse1041994.0776960
3994799154592None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Pedastals ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10771.210771.27.9922FalseNoneNoneFalseNoneFalse86085.584640
3994800154592None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Columns Concrete Upto PB ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10771.210771.23.6855FalseNoneNoneFalseNoneFalse39697.25760
3994801154592None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Plinth Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9504.09504.016.1598FalseNoneNoneFalseNoneFalse153582.73920
3994802154592None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Grade Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9504.09504.030.7629FalseNoneNoneFalseNoneFalse292370.60160
3994803154592None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Columns Concrete Up to Roof ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11633.111633.119.0496FalseNoneNoneFalseNoneFalse221605.901760
3994804154592None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10948.810948.824.0478FalseNoneNoneFalseNoneFalse263294.552640
3994805154592None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10264.510264.568.8187FalseNoneNoneFalseNoneFalse706389.546150
3994806154592None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Lintel Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10948.810948.86.3535FalseNoneNoneFalseNoneFalse69563.20080
3994807154592None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Staircase ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10264.510264.58.0469FalseNoneNoneFalseNoneFalse82597.405050
3994808154592None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor For Columns Concrete Up to Roof ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11749.4311749.4318.3816FalseNoneNoneFalseNoneFalse215973.3224880
3994809154592None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11058.2811058.2824.1333FalseNoneNoneFalseNoneFalse266872.7887240
3994810154592None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10367.1410367.1461.8004FalseNoneNoneFalseNoneFalse640693.3988560
3994811154592None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor For Lintel Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11058.2811058.286.1206FalseNoneNoneFalseNoneFalse67683.3085680
3994812154592None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor For Staircase ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10367.1410367.148.0469FalseNoneNoneFalseNoneFalse83423.3388660
3994813154592None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Second Floor For Columns Concrete Up to Roof ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11865.7611865.7614.7798FalseNoneNoneFalseNoneFalse175373.5596480
3994814154592None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Second Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11167.7711167.7718.3455FalseNoneNoneFalseNoneFalse204878.3245350
3994815154592None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Second Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10469.7910469.7939.1743FalseNoneNoneFalseNoneFalse410146.6943970
3994816154592None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Second Floor For Lintel Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11167.7711167.774.2021FalseNoneNoneFalseNoneFalse46928.0863170
3994817154592None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Second Floor For Staircase ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10469.7910469.794.0234FalseNoneNoneFalseNoneFalse42124.1530860
3994818154592None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor For Columns ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11982.0911982.093.205FalseNoneNoneFalseNoneFalse38402.598450
3994819154592None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11277.2611277.2612.52FalseNoneNoneFalseNoneFalse141191.29520
3994820154592None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10572.4310572.4311.9266FalseNoneNoneFalseNoneFalse126093.1436380
3994821154592None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10885.9610885.964.0FalseNoneNoneFalseNoneFalse43543.840
3994822154592None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t89457.089457.029.8125FalseNoneNoneFalseNoneFalse2666936.81250
3994823154592None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t90351.5790351.5712.7707FalseNoneNoneFalseNoneFalse1153852.7949990
3994824154592None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t91246.1491246.148.8672FalseNoneNoneFalseNoneFalse809097.7726080
3994825154592None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t92140.7192140.713.6145FalseNoneNoneFalseNoneFalse333042.5962950
3994826154592None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1310.01310.0612.0FalseNoneNoneFalseNoneFalse801720.00
3994827154592None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1323.11323.1553.0FalseNoneNoneFalseNoneFalse731674.30
3994828154592None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1336.21336.2382.0FalseNoneNoneFalseNoneFalse510428.40
3994829154592None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1349.31349.3117.0FalseNoneNoneFalseNoneFalse157868.10
3994830154592None6.34Providing and constructing load bearing wall with Solid Concrete blocks of size 400x100x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1104.01104.0110.0FalseNoneNoneFalseNoneFalse121440.00
3994831154592None6.34Providing and constructing load bearing wall with Solid Concrete blocks of size 400x100x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1115.041115.0480.0FalseNoneNoneFalseNoneFalse89203.20
3994832154592None6.34Providing and constructing load bearing wall with Solid Concrete blocks of size 400x100x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1126.081126.0853.0FalseNoneNoneFalseNoneFalse59682.240
3994833154592None12.13.1Providing Salwood frames of doors, windows, clerestory windows, ventilators and other frames, wrought, framed or assembled including making plaster groves (excluding cost of cement concrete and side clamps), but including cost of materials, labour, usage charges complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum98815.098815.00.6FalseNoneNoneFalseNoneFalse59289.00
3994834154592None12.13.1Providing Salwood frames of doors, windows, clerestory windows, ventilators and other frames, wrought, framed or assembled including making plaster groves (excluding cost of cement concrete and side clamps), but including cost of materials, labour, usage charges complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum99803.1599803.150.4FalseNoneNoneFalseNoneFalse39921.260
3994835154592None12.13.1Providing Salwood frames of doors, windows, clerestory windows, ventilators and other frames, wrought, framed or assembled including making plaster groves (excluding cost of cement concrete and side clamps), but including cost of materials, labour, usage charges complete as per specifications. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum100791.3100791.30.4FalseNoneNoneFalseNoneFalse40316.520
3994836154592None12.17Providing and fixing in position fully panelled Honne wood shutters for doors with , stiles and rails of 35mm. thick with bottom and lock rails 180mm wide top rail and stiles 100mm wide as per drawing and panels of 25mm thick including cost of materials, labour, usage charges complete as per specifications. (excluding cost of fixtures) Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm7085.07085.03.8FalseNoneNoneFalseNoneFalse26923.00
3994837154592None12.57.3Providing and fixing flush door shutter made out of solid core block board type, well seasoned , chemicaly treated hard wood battens and internal frame with minimum 45 mm wide wooden frame alround door shutters covered with cross bonded wooden sheets (core veneer) hot pressed and fastened on both sides of the door useing liquid phenol formaldehyde resin as per IS specifications 2202 (part-I) 1991. from manufacturer complete as per spcification.-do- 30 mm thick both side commercial Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3005.03005.013.3FalseNoneNoneFalseNoneFalse39966.50
3994838154592None12.57.3Providing and fixing flush door shutter made out of solid core block board type, well seasoned , chemicaly treated hard wood battens and internal frame with minimum 45 mm wide wooden frame alround door shutters covered with cross bonded wooden sheets (core veneer) hot pressed and fastened on both sides of the door useing liquid phenol formaldehyde resin as per IS specifications 2202 (part-I) 1991. from manufacturer complete as per spcification.-do- 30 mm thick both side commercial First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3035.053035.0512.0FalseNoneNoneFalseNoneFalse36420.60
3994839154592None12.57.3Providing and fixing flush door shutter made out of solid core block board type, well seasoned , chemicaly treated hard wood battens and internal frame with minimum 45 mm wide wooden frame alround door shutters covered with cross bonded wooden sheets (core veneer) hot pressed and fastened on both sides of the door useing liquid phenol formaldehyde resin as per IS specifications 2202 (part-I) 1991. from manufacturer complete as per spcification.-do- 30 mm thick both side commercial Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3065.13065.110.1FalseNoneNoneFalseNoneFalse30957.510
3994840154592None12.51Fixing of door frame in an existing opening including embedding frame in floor and walls after cutting masonry for holdfasts for embedding holdfast in cement concrete 1:3:6 of 20mm and down size granite metal painting two coats of coal tar to sides of frame, making good the damages to walls and floor as required and disposal of the debris with lead upto 50 m. including cost of materials, labour charges, complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1016.01016.07.0FalseNoneNoneFalseNoneFalse7112.00
3994841154592None12.51Fixing of door frame in an existing opening including embedding frame in floor and walls after cutting masonry for holdfasts for embedding holdfast in cement concrete 1:3:6 of 20mm and down size granite metal painting two coats of coal tar to sides of frame, making good the damages to walls and floor as required and disposal of the debris with lead upto 50 m. including cost of materials, labour charges, complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1026.161026.165.0FalseNoneNoneFalseNoneFalse5130.80
3994842154592None12.51Fixing of door frame in an existing opening including embedding frame in floor and walls after cutting masonry for holdfasts for embedding holdfast in cement concrete 1:3:6 of 20mm and down size granite metal painting two coats of coal tar to sides of frame, making good the damages to walls and floor as required and disposal of the debris with lead upto 50 m. including cost of materials, labour charges, complete as per specifications. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1036.321036.324.0FalseNoneNoneFalseNoneFalse4145.280
3994843154592None12.93.1Providing and fixing factory made single extruded WPC (Wood Polymer Composite) solid door/window/Clerestory windows & other Frames/ Chowkhat comprising of virgin PVC polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibres (wood powder/rice husk/ wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) fabricated with miter joints after applying PVC solvent cement and screwed with full body threaded star headed SS screws having minimum frame density of 850 kg/m3, screw withdrawal strength of 2200 N (Face) & 1100 N (Edge), minimum compressive strength of 58 N/mm2 , modulus of elasticity 900 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixed in position with M.S hold fast/lugs/SS dash fasteners of required dia and length complete as per direction of Engineer-InCharge. (Fixtures shall be paid for separately) Size 62 x 100mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr702.0702.0110.4FalseNoneNoneFalseNoneFalse77500.80
3994844154592None12.93.1Providing and fixing factory made single extruded WPC (Wood Polymer Composite) solid door/window/Clerestory windows & other Frames/ Chowkhat comprising of virgin PVC polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibres (wood powder/rice husk/ wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) fabricated with miter joints after applying PVC solvent cement and screwed with full body threaded star headed SS screws having minimum frame density of 850 kg/m3, screw withdrawal strength of 2200 N (Face) & 1100 N (Edge), minimum compressive strength of 58 N/mm2 , modulus of elasticity 900 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixed in position with M.S hold fast/lugs/SS dash fasteners of required dia and length complete as per direction of Engineer-InCharge. (Fixtures shall be paid for separately) Size 62 x 100mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr709.02709.02105.0FalseNoneNoneFalseNoneFalse74447.10
3994845154592None12.93.1Providing and fixing factory made single extruded WPC (Wood Polymer Composite) solid door/window/Clerestory windows & other Frames/ Chowkhat comprising of virgin PVC polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibres (wood powder/rice husk/ wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) fabricated with miter joints after applying PVC solvent cement and screwed with full body threaded star headed SS screws having minimum frame density of 850 kg/m3, screw withdrawal strength of 2200 N (Face) & 1100 N (Edge), minimum compressive strength of 58 N/mm2 , modulus of elasticity 900 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixed in position with M.S hold fast/lugs/SS dash fasteners of required dia and length complete as per direction of Engineer-InCharge. (Fixtures shall be paid for separately) Size 62 x 100mm Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr716.04716.0447.4FalseNoneNoneFalseNoneFalse33940.2960
3994846154592None12.94.1Providing and fixing factory made Green certified, Anti Termite, UV resistant, high water absorbant single extruded WPC (Wood PolymerComposite) solid plain flush door shutter of required size comprising of virgin polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibers (wood powder/rice husk/wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) having minimum density of 650 kg/m3 and screw withdrawal strength of 1800 N (Face) & 900 N (Edge), minimum compressive strength of 50 N/mm2 , modulus of elasticity 850 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixing with stainless steel butt hinges of required size with necessary full body threaded star headed counter sunk S.S screws The cost includes cost of materials, transportation, labour and fixing charges.(Cost of Fixtures to be paid separately) 30 mm thickness Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3485.03485.033.4FalseNoneNoneFalseNoneFalse116399.00
3994847154592None12.94.1Providing and fixing factory made Green certified, Anti Termite, UV resistant, high water absorbant single extruded WPC (Wood PolymerComposite) solid plain flush door shutter of required size comprising of virgin polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibers (wood powder/rice husk/wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) having minimum density of 650 kg/m3 and screw withdrawal strength of 1800 N (Face) & 900 N (Edge), minimum compressive strength of 50 N/mm2 , modulus of elasticity 850 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixing with stainless steel butt hinges of required size with necessary full body threaded star headed counter sunk S.S screws The cost includes cost of materials, transportation, labour and fixing charges.(Cost of Fixtures to be paid separately) 30 mm thickness First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3519.853519.8531.5FalseNoneNoneFalseNoneFalse110875.2750
3994848154592None12.94.1Providing and fixing factory made Green certified, Anti Termite, UV resistant, high water absorbant single extruded WPC (Wood PolymerComposite) solid plain flush door shutter of required size comprising of virgin polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibers (wood powder/rice husk/wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) having minimum density of 650 kg/m3 and screw withdrawal strength of 1800 N (Face) & 900 N (Edge), minimum compressive strength of 50 N/mm2 , modulus of elasticity 850 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixing with stainless steel butt hinges of required size with necessary full body threaded star headed counter sunk S.S screws The cost includes cost of materials, transportation, labour and fixing charges.(Cost of Fixtures to be paid separately) 30 mm thickness Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3554.73554.714.5FalseNoneNoneFalseNoneFalse51543.150
3994849154592None12.9Providing & fixing of 3-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having an overall size of 108mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm x 75mm with GI reinforcement of 2mm and mesh sash of size 37mm x 58mm. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24 mm. Windows shall be provided with 6mm plain float glass, standard hardware& Multi point locking system with touch lock. Wall thickness of frame & sash shall be of 2mm-2.5mm. Maximum possible size 2419mm x 2200mm. (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm6734.06734.030.0FalseNoneNoneFalseNoneFalse202020.00
3994850154592None12.9Providing & fixing of 3-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having an overall size of 108mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm x 75mm with GI reinforcement of 2mm and mesh sash of size 37mm x 58mm. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24 mm. Windows shall be provided with 6mm plain float glass, standard hardware& Multi point locking system with touch lock. Wall thickness of frame & sash shall be of 2mm-2.5mm. Maximum possible size 2419mm x 2200mm. (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm6801.346801.3432.0FalseNoneNoneFalseNoneFalse217642.880
3994851154592None12.9Providing & fixing of 3-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having an overall size of 108mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm x 75mm with GI reinforcement of 2mm and mesh sash of size 37mm x 58mm. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24 mm. Windows shall be provided with 6mm plain float glass, standard hardware& Multi point locking system with touch lock. Wall thickness of frame & sash shall be of 2mm-2.5mm. Maximum possible size 2419mm x 2200mm. (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm6868.686868.6837.0FalseNoneNoneFalseNoneFalse254141.160
3994852154592None12.9Providing & fixing of 3-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having an overall size of 108mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm x 75mm with GI reinforcement of 2mm and mesh sash of size 37mm x 58mm. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24 mm. Windows shall be provided with 6mm plain float glass, standard hardware& Multi point locking system with touch lock. Wall thickness of frame & sash shall be of 2mm-2.5mm. Maximum possible size 2419mm x 2200mm. (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm6936.026936.023.0FalseNoneNoneFalseNoneFalse20808.060
3994853154592None12.85Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5719.05719.024.0FalseNoneNoneFalseNoneFalse137256.00
3994854154592None12.85Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5776.195776.1919.0FalseNoneNoneFalseNoneFalse109747.610
3994855154592None12.85Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5833.385833.3820.0FalseNoneNoneFalseNoneFalse116667.60
3994856154592None12.85Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5890.575890.572.0FalseNoneNoneFalseNoneFalse11781.140
3994857154592None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs183.0183.0961.0FalseNoneNoneFalseNoneFalse175863.00
3994858154592None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs184.83184.83896.0FalseNoneNoneFalseNoneFalse165607.680
3994859154592None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs186.66186.661013.0FalseNoneNoneFalseNoneFalse189086.580
3994860154592None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs188.49188.4959.0FalseNoneNoneFalseNoneFalse11120.910
3994861154592None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2852.02852.0411.0FalseNoneNoneFalseNoneFalse1172172.00
3994862154592None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2880.522880.52364.0FalseNoneNoneFalseNoneFalse1048509.280
3994863154592None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2909.042909.04232.0FalseNoneNoneFalseNoneFalse674897.280
3994864154592None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2937.562937.568.0FalseNoneNoneFalseNoneFalse23500.480
3994865154592None9.11Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved make, in all colours, shades, except White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick bed of cement mortar 1:4 (1 Cement : 4 Coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including pointing the joints with white cement and matching pigments etc., complete. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm889.0889.072.0FalseNoneNoneFalseNoneFalse64008.00
3994866154592None9.11Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved make, in all colours, shades, except White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick bed of cement mortar 1:4 (1 Cement : 4 Coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including pointing the joints with white cement and matching pigments etc., complete. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm897.89897.8969.0FalseNoneNoneFalseNoneFalse61954.410
3994867154592None9.11Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved make, in all colours, shades, except White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick bed of cement mortar 1:4 (1 Cement : 4 Coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including pointing the joints with white cement and matching pigments etc., complete. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm906.78906.7831.0FalseNoneNoneFalseNoneFalse28110.180
3994868154592None9.39Providing skirting, dadooing, rises of steps with colour glazed tiles 6mm thick on 10mm thick cement plaster 1:3 and jointed with white cement slurry over existing rough plaster surface using glazed tiles of approved make and size including cost of materials, labour, complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1449.01449.0262.0FalseNoneNoneFalseNoneFalse379638.00
3994869154592None9.39Providing skirting, dadooing, rises of steps with colour glazed tiles 6mm thick on 10mm thick cement plaster 1:3 and jointed with white cement slurry over existing rough plaster surface using glazed tiles of approved make and size including cost of materials, labour, complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1463.491463.49240.0FalseNoneNoneFalseNoneFalse351237.60
3994870154592None9.39Providing skirting, dadooing, rises of steps with colour glazed tiles 6mm thick on 10mm thick cement plaster 1:3 and jointed with white cement slurry over existing rough plaster surface using glazed tiles of approved make and size including cost of materials, labour, complete as per specifications. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1477.981477.9892.0FalseNoneNoneFalseNoneFalse135974.160
3994871154592None10.2Providing edge moulding to 18mm thick Granite stone counters, vanities etc including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr328.0328.086.0FalseNoneNoneFalseNoneFalse28208.00
3994872154592None10.2Providing edge moulding to 18mm thick Granite stone counters, vanities etc including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr331.28331.2867.0FalseNoneNoneFalseNoneFalse22195.760
3994873154592None10.2Providing edge moulding to 18mm thick Granite stone counters, vanities etc including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineer-in-charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr334.56334.5634.0FalseNoneNoneFalseNoneFalse11375.040
3994874154592None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm295.0295.01105.0FalseNoneNoneFalseNoneFalse325975.00
3994875154592None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm297.95297.951048.0FalseNoneNoneFalseNoneFalse312251.60
3994876154592None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm300.9300.9626.0FalseNoneNoneFalseNoneFalse188363.40
3994877154592None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm303.85303.8574.0FalseNoneNoneFalseNoneFalse22484.90
3994878154592None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm371.0371.0510.0FalseNoneNoneFalseNoneFalse189210.00
3994879154592None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm374.71374.71516.0FalseNoneNoneFalseNoneFalse193350.360
3994880154592None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm378.42378.42497.0FalseNoneNoneFalseNoneFalse188074.740
3994881154592None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm382.13382.13311.0FalseNoneNoneFalseNoneFalse118842.430
3994882154592None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg64.064.077.0FalseNoneNoneFalseNoneFalse4928.00
3994883154592None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg64.6464.6478.0FalseNoneNoneFalseNoneFalse5041.920
3994884154592None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg65.2865.2874.55FalseNoneNoneFalseNoneFalse4866.6240
3994885154592None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg65.9265.9246.65FalseNoneNoneFalseNoneFalse3075.1680
3994886154592None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm295.0295.0279.0FalseNoneNoneFalseNoneFalse82305.00
3994887154592None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm297.95297.95255.0FalseNoneNoneFalseNoneFalse75977.250
3994888154592None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm300.9300.999.0FalseNoneNoneFalseNoneFalse29789.10
3994889154592None8.16 aProviding lath plaster with cement mortar 1:3, 5cms thick with 6mm dia mild steel bars at 20 cms. c to c both horizontally and vertically fixing chicken mesh for drop chajja, facia, backing to cup boards including cost of all materials, labour, providing and removing form work usage charges, curing complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1238.01238.03.0FalseNoneNoneFalseNoneFalse3714.00
3994890154592None8.16 aProviding lath plaster with cement mortar 1:3, 5cms thick with 6mm dia mild steel bars at 20 cms. c to c both horizontally and vertically fixing chicken mesh for drop chajja, facia, backing to cup boards including cost of all materials, labour, providing and removing form work usage charges, curing complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1250.381250.383.0FalseNoneNoneFalseNoneFalse3751.140
3994891154592None8.16 aProviding lath plaster with cement mortar 1:3, 5cms thick with 6mm dia mild steel bars at 20 cms. c to c both horizontally and vertically fixing chicken mesh for drop chajja, facia, backing to cup boards including cost of all materials, labour, providing and removing form work usage charges, curing complete as per specifications. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1262.761262.763.0FalseNoneNoneFalseNoneFalse3788.280
3994892154592None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm100.0100.01574.0067FalseNoneNoneFalseNoneFalse157400.670
3994893154592None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. First floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm101.0101.01468.5176FalseNoneNoneFalseNoneFalse148320.27760
3994894154592None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm102.0102.0895.6766FalseNoneNoneFalseNoneFalse91359.01320
3994895154592None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm103.0103.0123.8334FalseNoneNoneFalseNoneFalse12754.84020
3994896154592None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm110.0110.01425.5917FalseNoneNoneFalseNoneFalse156815.0870
3994897154592None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. First floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm111.1111.11319.5626FalseNoneNoneFalseNoneFalse146603.404860
3994898154592None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm112.2112.2748.3416FalseNoneNoneFalseNoneFalse83963.927520
3994899154592None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm113.3113.3123.8334FalseNoneNoneFalseNoneFalse14030.324220
3994900154592None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.053.01574.0067FalseNoneNoneFalseNoneFalse83422.35510
3994901154592None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.5353.531468.5176FalseNoneNoneFalseNoneFalse78609.7471280
3994902154592None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm54.0654.06895.6766FalseNoneNoneFalseNoneFalse48420.2769960
3994903154592None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm54.5954.59123.8334FalseNoneNoneFalseNoneFalse6760.0653060
3994904154592None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm174.0174.0510.0FalseNoneNoneFalseNoneFalse88740.00
3994905154592None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm175.74175.74516.0FalseNoneNoneFalseNoneFalse90681.840
3994906154592None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Second floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm177.48177.48497.0FalseNoneNoneFalseNoneFalse88207.560
3994907154592None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm179.22179.22311.0FalseNoneNoneFalseNoneFalse55737.420
3994908154592None8.34.1Applying priming coat: With ready mixed pink or Grey primer of approved brand and manufacture on wood work (hard and soft wood) including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.053.041.0FalseNoneNoneFalseNoneFalse2173.00
3994909154592None8.34.1Applying priming coat: With ready mixed pink or Grey primer of approved brand and manufacture on wood work (hard and soft wood) including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.5353.5325.0FalseNoneNoneFalseNoneFalse1338.250
3994910154592None8.34.1Applying priming coat: With ready mixed pink or Grey primer of approved brand and manufacture on wood work (hard and soft wood) including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm54.0654.0625.0FalseNoneNoneFalseNoneFalse1351.50
3994911154592None8.33.2Painting wood work with Deluxe Multi Surface Paint of required shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @0.75 L/10 m² of approved brand and manufacture to give an even shade including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, sand papering and knotting , cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm138.0138.041.0FalseNoneNoneFalseNoneFalse5658.00
3994912154592None8.33.2Painting wood work with Deluxe Multi Surface Paint of required shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @0.75 L/10 m² of approved brand and manufacture to give an even shade including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, sand papering and knotting , cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm139.38139.3825.0FalseNoneNoneFalseNoneFalse3484.50
3994913154592None8.33.2Painting wood work with Deluxe Multi Surface Paint of required shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @0.75 L/10 m² of approved brand and manufacture to give an even shade including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, sand papering and knotting , cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm140.76140.7625.0FalseNoneNoneFalseNoneFalse3519.00
3994914154592None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @ 0.80 L/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm139.0139.054.0FalseNoneNoneFalseNoneFalse7506.00
3994915154592None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @ 0.80 L/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm140.39140.3950.0FalseNoneNoneFalseNoneFalse7019.50
3994916154592None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @ 0.80 L/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm141.78141.7857.0FalseNoneNoneFalseNoneFalse8081.460
3994917154592None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @ 0.80 L/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm143.17143.174.0FalseNoneNoneFalseNoneFalse572.680
3994918154592None8.4Painting with synthetic enamel paint of approved brand and manufacture to give an even shade :Two coats on new work after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm115.0115.0148.415FalseNoneNoneFalseNoneFalse17067.7250
3994919154592None8.4Painting with synthetic enamel paint of approved brand and manufacture to give an even shade :Two coats on new work after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm116.15116.15148.955FalseNoneNoneFalseNoneFalse17301.123250
3994920154592None8.4Painting with synthetic enamel paint of approved brand and manufacture to give an even shade :Two coats on new work after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm117.3117.3147.335FalseNoneNoneFalseNoneFalse17282.39550
3994921154592None11.28Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners, stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in- charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.) including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs565.0565.0298.0FalseNoneNoneFalseNoneFalse168370.00
3994922154592None11.28Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners, stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in- charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.) including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs570.65570.65130.0FalseNoneNoneFalseNoneFalse74184.50
3994923154592None11.28Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners, stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in- charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.) including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. Second floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs576.3576.365.0FalseNoneNoneFalseNoneFalse37459.50
3994924154592None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr66.066.0201.0FalseNoneNoneFalseNoneFalse13266.00
3994925154592None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr66.6666.66201.0FalseNoneNoneFalseNoneFalse13398.660
3994926154592None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr67.3267.32237.0FalseNoneNoneFalseNoneFalse15954.840
3994927154592None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr67.9867.9841.0FalseNoneNoneFalseNoneFalse2787.180
3994928154592None7.18Providing and laying cinder concrete in cement 1:15 ( 1 cement : 15 cinder of 12.5mm nominal gauge) on terraced roof or sunken slabs, laid to slope compacting, including cost of materials, labour, curing complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum2037.172037.1716.0FalseNoneNoneFalseNoneFalse32594.720
3994929154592None7.18Providing and laying cinder concrete in cement 1:15 ( 1 cement : 15 cinder of 12.5mm nominal gauge) on terraced roof or sunken slabs, laid to slope compacting, including cost of materials, labour, curing complete as per specifications. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum2057.342057.3411.0FalseNoneNoneFalseNoneFalse22630.740
3994930154592None15.7Integral Crystalline Water Proofing Admixture Providing and supplying crystalline integral concrete waterproofing admixture that waterproofs concrete by forming crystals deep in the pores, capillaries and microcracks of the concrete, self-seal waterproofing compound to bridge shrinkage cracks upto 0.5mm in width & resist hydro-static pressure upto 16bar for both positive & negative pressure confirming to DIN 1048 part 5 for 56% reduction in depth of penetration against control, resistance to chloride penetration confirming to ASTM C 1202 with 64% improvement against control & protecting steel reinforcement against corrosion mixed @ 1% by weight of cementitious content in concrete. ie., integral crystaline waterproofing admix @ 0.5 kg/bag of cement. (For calculation purpose 320 kg of Cement for M-20 grade of Concrete is considered in the analysis) First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm621.15621.1566.0FalseNoneNoneFalseNoneFalse40995.90
3994931154592None15.7Integral Crystalline Water Proofing Admixture Providing and supplying crystalline integral concrete waterproofing admixture that waterproofs concrete by forming crystals deep in the pores, capillaries and microcracks of the concrete, self-seal waterproofing compound to bridge shrinkage cracks upto 0.5mm in width & resist hydro-static pressure upto 16bar for both positive & negative pressure confirming to DIN 1048 part 5 for 56% reduction in depth of penetration against control, resistance to chloride penetration confirming to ASTM C 1202 with 64% improvement against control & protecting steel reinforcement against corrosion mixed @ 1% by weight of cementitious content in concrete. ie., integral crystaline waterproofing admix @ 0.5 kg/bag of cement. (For calculation purpose 320 kg of Cement for M-20 grade of Concrete is considered in the analysis) Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm627.3627.335.0FalseNoneNoneFalseNoneFalse21955.50
3994932154592None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9613.59613.53.4015FalseNoneNoneFalseNoneFalse32700.320250
3994933154592None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9679.89679.84.2669FalseNoneNoneFalseNoneFalse41302.738620
3994934154592None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9746.19746.12.0155FalseNoneNoneFalseNoneFalse19643.264550
3994935154592None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9812.49812.433.6075FalseNoneNoneFalseNoneFalse329770.2330
3994936154592None9.25Providing and laying 60mm thick factory made cement concrete paver block of approved shape and colour of M -30 grade made of C&D waste by block making machine with vibratory compaction laid in required pattern and including over 50mm thick compacted bed of coarse sand, filling the joints with fine sand etc. all complete as per the direction of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm800.0800.025.0FalseNoneNoneFalseNoneFalse20000.00
3994937154592NoneVOL -5 7.1.1Providing and fixing MS ladder between landings, 45 cms wide using angle iron of specified sizes, 20mm MS bars at 25 cms. centre to centre, with necessary supports of same angle iron etc. as directed, including hand railing on both sides with 25mm dia. GI pipes with angle iron props at 2 mtrs. intervals and 0.5M heigh, including fixing in ground with CC 1:2:4 and two coats of anticorrosive bituminous paint etc. with all lead and lifts etc. complete with: MS angle of 65 x 65 x 8mm Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr4508.314508.314.5FalseNoneNoneFalseNoneFalse20287.3950
3994938154592None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.038.0241.2FalseNoneNoneFalseNoneFalse9165.60
3994939154592None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.3838.38165.6FalseNoneNoneFalseNoneFalse6355.7280
3994940154592None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.7638.76165.6FalseNoneNoneFalseNoneFalse6418.6560
3994941154592None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr39.1439.147.65FalseNoneNoneFalseNoneFalse299.4210
3994942154592None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.038.0243.69FalseNoneNoneFalseNoneFalse9260.220
3994943154592None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.3838.38232.09FalseNoneNoneFalseNoneFalse8907.61420
3994944154592None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.7638.76151.23FalseNoneNoneFalseNoneFalse5861.67480
3994945154592None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr39.1439.1415.11FalseNoneNoneFalseNoneFalse591.40540
3994946154592None22.15.7Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Tower Bolts 250x10mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos200.0200.029.0FalseNoneNoneFalseNoneFalse5800.00
3994947154592None22.15.7Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Tower Bolts 250x10mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos202.0202.025.0FalseNoneNoneFalseNoneFalse5050.00
3994948154592None22.15.7Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Tower Bolts 250x10mm Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos204.0204.013.0FalseNoneNoneFalseNoneFalse2652.00
3994949154592None22.15.8Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS hinges 125 mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos50.050.095.0FalseNoneNoneFalseNoneFalse4750.00
3994950154592None22.15.8Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS hinges 125 mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos50.550.580.0FalseNoneNoneFalseNoneFalse4040.00
3994951154592None22.15.8Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS hinges 125 mm Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos51.051.043.0FalseNoneNoneFalseNoneFalse2193.00
3994952154592None22.15.1Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Handles 200mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos450.0450.058.0FalseNoneNoneFalseNoneFalse26100.00
3994953154592None22.15.1Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Handles 200mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos454.5454.550.0FalseNoneNoneFalseNoneFalse22725.00
3994954154592None22.15.1Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Handles 200mm Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos459.0459.026.0FalseNoneNoneFalseNoneFalse11934.00
3994955154592None22.15.4Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Aldrop 16mm dia, 300mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos375.0375.028.0FalseNoneNoneFalseNoneFalse10500.00
3994956154592None22.15.4Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Aldrop 16mm dia, 300mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos378.75378.7525.0FalseNoneNoneFalseNoneFalse9468.750
3994957154592None22.15.4Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Aldrop 16mm dia, 300mm Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos382.5382.513.0FalseNoneNoneFalseNoneFalse4972.50
3994958154592None22.15.10Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Door stopper 75mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos100.0100.08.0FalseNoneNoneFalseNoneFalse800.00
3994959154592None22.15.10Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Door stopper 75mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos101.0101.05.0FalseNoneNoneFalseNoneFalse505.00
3994960154592None22.15.10Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Door stopper 75mm Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos102.0102.04.0FalseNoneNoneFalseNoneFalse408.00
3994961154592None15.1Providing and laying water proofing treatment to the Roof with PU based single component elastomeric pure polyurethane based coating on New rrace/Chajjas/Sunken portion of WC:Bathroom, cold applied PU waterproofing membrane that is highly elastic with elongation greater than 400% and tensile strength greater than 2MPa as per ASTM D412. The waterproofing membrane to be applied in 2coats @ 1.6kg per m2 to achieve final DFT (dry film thickness) of 1mm including prime coat of epoxy primer @150 g per m2 and protection with 120gsm Geo-textile over the waterproofing membrane. The finished cost to include surface preparation, making coving at Junction, Bore Packing, treatment of construction joints completely as per specification & with a 10 years warranty on product & work from certified manufacturers as per the direction of the Engineer In charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm841.51841.51330.0FalseNoneNoneFalseNoneFalse277698.30
3994962154592None20.107Providing and fixing plain rolled glass 4mm thick with teakwood beading of 10mm thick. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1147.01147.02.43FalseNoneNoneFalseNoneFalse2787.210
3994963154592None20.107Providing and fixing plain rolled glass 4mm thick with teakwood beading of 10mm thick. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1158.471158.471.71FalseNoneNoneFalseNoneFalse1980.98370
17262057300000NoneNoneBuildingsBoys Dormitory (Amble)25436258.63
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3994964154593NoneVOL - 3, C - 2 2.1 a (i) MoRT&H 201Cutting of Trees, excluding removal of stumps and roots of trees. (i) Girth from 300 mm to 600 mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each595.0595.0165.0FalseNoneNoneFalseNoneFalse98175.00
3994965154593NoneVOL - 3, C - 2 2.2 b (i) MoRT&H 201Removal of stumps and roots including backfilling with suitable material to required compaction (i) Girth from 300 mm to 600 mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each356.0356.0165.0FalseNoneNoneFalseNoneFalse58740.00
3994966154593None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.061.6011FalseNoneNoneFalseNoneFalse6283.31220
3994967154593None1.15.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In ordinary/soft rock without blasting upto 1.5 m depth ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum363.0363.0492.8094FalseNoneNoneFalseNoneFalse178889.81220
3994968154593None1.16.1Earth work excavation for FOUNDATION by Mechanical means depth upto 1.50m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including cost of explosives, dressing of excavated surfaces, disposing off or levelling the excavated stuff or sorting & stacking the selected stuff for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, blasting materials, tools, usage of Machinery & all other appurtenaces required to complete the work. In Hard Rock ( requiring blasting) Depth upto 1.50m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum554.0554.061.6011FalseNoneNoneFalseNoneFalse34127.00940
3994969154593None1.9Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum266.0266.01630.2FalseNoneNoneFalseNoneFalse433633.20
3994970154593None4.1Providing and injecting chemical emulsion for Pre-constructional Anti-Termite Treatment, creating continuous chemical barrier under and around the column pits, walls, trenches, basement excavation, top surface of the plinth filling, junction of wall and floor, along the external perimeter of building, expansion joints, over the top surface of consolidated earth on which apron is to be laid, surrounding of pipes and conduits with Chlorpyriphos 20% E.C. / Lindane 20% E.C. @ 3.19 l/m2 including cost of chemical, diluting in water to one percent concentration, labour, usage charges of machinery, complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm118.0118.0404.0FalseNoneNoneFalseNoneFalse47672.00
3994971154593None2.1.3Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5989.05989.085.0FalseNoneNoneFalseNoneFalse509065.00
3994972154593None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6217.06217.05.0FalseNoneNoneFalseNoneFalse31085.00
3994973154593None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7460.47460.40.9929FalseNoneNoneFalseNoneFalse7407.431160
3994974154593None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7522.577522.571.1201FalseNoneNoneFalseNoneFalse8426.0306570
3994975154593None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7584.747584.741.1278FalseNoneNoneFalseNoneFalse8554.0697720
3994976154593None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7646.917646.911.9FalseNoneNoneFalseNoneFalse14529.1290
3994977154593None2.1.6Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:2:4 Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6243.06243.04.0FalseNoneNoneFalseNoneFalse24972.00
3994978154593None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Footing concrete ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6842.886842.88152.2742FalseNoneNoneFalseNoneFalse1041994.0776960
3994979154593None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Pedastals ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10771.210771.27.9922FalseNoneNoneFalseNoneFalse86085.584640
3994980154593None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Columns Concrete Upto PB ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10771.210771.210.1568FalseNoneNoneFalseNoneFalse109400.924160
3994981154593None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Plinth Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9504.09504.016.1598FalseNoneNoneFalseNoneFalse153582.73920
3994982154593None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Grade Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9504.09504.030.7629FalseNoneNoneFalseNoneFalse292370.60160
3994983154593None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Columns Concrete Up to Roof ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11633.111633.119.0496FalseNoneNoneFalseNoneFalse221605.901760
3994984154593None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10948.810948.824.0478FalseNoneNoneFalseNoneFalse263294.552640
3994985154593None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10264.510264.568.8187FalseNoneNoneFalseNoneFalse706389.546150
3994986154593None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Lintel Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10948.810948.86.3535FalseNoneNoneFalseNoneFalse69563.20080
3994987154593None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Staircase ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10264.510264.58.0469FalseNoneNoneFalseNoneFalse82597.405050
3994988154593None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor For Columns Concrete Up to Roof ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11749.4311749.4318.3816FalseNoneNoneFalseNoneFalse215973.3224880
3994989154593None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11058.2811058.2824.1333FalseNoneNoneFalseNoneFalse266872.7887240
3994990154593None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10367.1410367.1461.8004FalseNoneNoneFalseNoneFalse640693.3988560
3994991154593None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor For Lintel Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11058.2811058.286.1206FalseNoneNoneFalseNoneFalse67683.3085680
3994992154593None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor For Staircase ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10367.1410367.148.0469FalseNoneNoneFalseNoneFalse83423.3388660
3994993154593None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Second Floor For Columns Concrete Up to Roof ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11865.7611865.7614.7798FalseNoneNoneFalseNoneFalse175373.5596480
3994994154593None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Second Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11167.7711167.7718.3455FalseNoneNoneFalseNoneFalse204878.3245350
3994995154593None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Second Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10469.7910469.7939.1743FalseNoneNoneFalseNoneFalse410146.6943970
3994996154593None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Second Floor For Lintel Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11167.7711167.774.2021FalseNoneNoneFalseNoneFalse46928.0863170
3994997154593None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Second Floor For Staircase ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10469.7910469.794.0234FalseNoneNoneFalseNoneFalse42124.1530860
3994998154593None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor For Columns ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11982.0911982.093.205FalseNoneNoneFalseNoneFalse38402.598450
3994999154593None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11277.2611277.2612.52FalseNoneNoneFalseNoneFalse141191.29520
3995000154593None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10572.4310572.4311.9266FalseNoneNoneFalseNoneFalse126093.1436380
3995001154593None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10885.9610885.964.0FalseNoneNoneFalseNoneFalse43543.840
3995002154593None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t89457.089457.030.848FalseNoneNoneFalseNoneFalse2759569.5360
3995003154593None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t90351.5790351.5712.7707FalseNoneNoneFalseNoneFalse1153852.7949990
3995004154593None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t91246.1491246.148.8672FalseNoneNoneFalseNoneFalse809097.7726080
3995005154593None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t92140.7192140.713.6145FalseNoneNoneFalseNoneFalse333042.5962950
3995006154593None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1310.01310.0612.0FalseNoneNoneFalseNoneFalse801720.00
3995007154593None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1323.11323.1553.0FalseNoneNoneFalseNoneFalse731674.30
3995008154593None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1336.21336.2382.0FalseNoneNoneFalseNoneFalse510428.40
3995009154593None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1349.31349.3117.0FalseNoneNoneFalseNoneFalse157868.10
3995010154593None6.34Providing and constructing load bearing wall with Solid Concrete blocks of size 400x100x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1104.01104.0110.0FalseNoneNoneFalseNoneFalse121440.00
3995011154593None6.34Providing and constructing load bearing wall with Solid Concrete blocks of size 400x100x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1115.041115.0480.0FalseNoneNoneFalseNoneFalse89203.20
3995012154593None6.34Providing and constructing load bearing wall with Solid Concrete blocks of size 400x100x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1126.081126.0853.0FalseNoneNoneFalseNoneFalse59682.240
3995013154593None12.13.1Providing Salwood frames of doors, windows, clerestory windows, ventilators and other frames, wrought, framed or assembled including making plaster groves (excluding cost of cement concrete and side clamps), but including cost of materials, labour, usage charges complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum98815.098815.00.6FalseNoneNoneFalseNoneFalse59289.00
3995014154593None12.13.1Providing Salwood frames of doors, windows, clerestory windows, ventilators and other frames, wrought, framed or assembled including making plaster groves (excluding cost of cement concrete and side clamps), but including cost of materials, labour, usage charges complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum99803.1599803.150.4FalseNoneNoneFalseNoneFalse39921.260
3995015154593None12.13.1Providing Salwood frames of doors, windows, clerestory windows, ventilators and other frames, wrought, framed or assembled including making plaster groves (excluding cost of cement concrete and side clamps), but including cost of materials, labour, usage charges complete as per specifications. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum100791.3100791.30.4FalseNoneNoneFalseNoneFalse40316.520
3995016154593None12.17Providing and fixing in position fully panelled Honne wood shutters for doors with , stiles and rails of 35mm. thick with bottom and lock rails 180mm wide top rail and stiles 100mm wide as per drawing and panels of 25mm thick including cost of materials, labour, usage charges complete as per specifications. (excluding cost of fixtures) Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm7085.07085.03.8FalseNoneNoneFalseNoneFalse26923.00
3995017154593None12.57.3Providing and fixing flush door shutter made out of solid core block board type, well seasoned , chemicaly treated hard wood battens and internal frame with minimum 45 mm wide wooden frame alround door shutters covered with cross bonded wooden sheets (core veneer) hot pressed and fastened on both sides of the door useing liquid phenol formaldehyde resin as per IS specifications 2202 (part-I) 1991. from manufacturer complete as per spcification.-do- 30 mm thick both side commercial Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3005.03005.013.3FalseNoneNoneFalseNoneFalse39966.50
3995018154593None12.57.3Providing and fixing flush door shutter made out of solid core block board type, well seasoned , chemicaly treated hard wood battens and internal frame with minimum 45 mm wide wooden frame alround door shutters covered with cross bonded wooden sheets (core veneer) hot pressed and fastened on both sides of the door useing liquid phenol formaldehyde resin as per IS specifications 2202 (part-I) 1991. from manufacturer complete as per spcification.-do- 30 mm thick both side commercial First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3035.053035.0512.0FalseNoneNoneFalseNoneFalse36420.60
3995019154593None12.57.3Providing and fixing flush door shutter made out of solid core block board type, well seasoned , chemicaly treated hard wood battens and internal frame with minimum 45 mm wide wooden frame alround door shutters covered with cross bonded wooden sheets (core veneer) hot pressed and fastened on both sides of the door useing liquid phenol formaldehyde resin as per IS specifications 2202 (part-I) 1991. from manufacturer complete as per spcification.-do- 30 mm thick both side commercial Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3065.13065.110.1FalseNoneNoneFalseNoneFalse30957.510
3995020154593None12.51Fixing of door frame in an existing opening including embedding frame in floor and walls after cutting masonry for holdfasts for embedding holdfast in cement concrete 1:3:6 of 20mm and down size granite metal painting two coats of coal tar to sides of frame, making good the damages to walls and floor as required and disposal of the debris with lead upto 50 m. including cost of materials, labour charges, complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1016.01016.07.0FalseNoneNoneFalseNoneFalse7112.00
3995021154593None12.51Fixing of door frame in an existing opening including embedding frame in floor and walls after cutting masonry for holdfasts for embedding holdfast in cement concrete 1:3:6 of 20mm and down size granite metal painting two coats of coal tar to sides of frame, making good the damages to walls and floor as required and disposal of the debris with lead upto 50 m. including cost of materials, labour charges, complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1026.161026.165.0FalseNoneNoneFalseNoneFalse5130.80
3995022154593None12.51Fixing of door frame in an existing opening including embedding frame in floor and walls after cutting masonry for holdfasts for embedding holdfast in cement concrete 1:3:6 of 20mm and down size granite metal painting two coats of coal tar to sides of frame, making good the damages to walls and floor as required and disposal of the debris with lead upto 50 m. including cost of materials, labour charges, complete as per specifications. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1036.321036.324.0FalseNoneNoneFalseNoneFalse4145.280
3995023154593None12.93.1Providing and fixing factory made single extruded WPC (Wood Polymer Composite) solid door/window/Clerestory windows & other Frames/ Chowkhat comprising of virgin PVC polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibres (wood powder/rice husk/ wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) fabricated with miter joints after applying PVC solvent cement and screwed with full body threaded star headed SS screws having minimum frame density of 850 kg/m3, screw withdrawal strength of 2200 N (Face) & 1100 N (Edge), minimum compressive strength of 58 N/mm2 , modulus of elasticity 900 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixed in position with M.S hold fast/lugs/SS dash fasteners of required dia and length complete as per direction of Engineer-InCharge. (Fixtures shall be paid for separately) Size 62 x 100mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr702.0702.0110.4FalseNoneNoneFalseNoneFalse77500.80
3995024154593None12.93.1Providing and fixing factory made single extruded WPC (Wood Polymer Composite) solid door/window/Clerestory windows & other Frames/ Chowkhat comprising of virgin PVC polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibres (wood powder/rice husk/ wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) fabricated with miter joints after applying PVC solvent cement and screwed with full body threaded star headed SS screws having minimum frame density of 850 kg/m3, screw withdrawal strength of 2200 N (Face) & 1100 N (Edge), minimum compressive strength of 58 N/mm2 , modulus of elasticity 900 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixed in position with M.S hold fast/lugs/SS dash fasteners of required dia and length complete as per direction of Engineer-InCharge. (Fixtures shall be paid for separately) Size 62 x 100mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr709.02709.02105.0FalseNoneNoneFalseNoneFalse74447.10
3995025154593None12.93.1Providing and fixing factory made single extruded WPC (Wood Polymer Composite) solid door/window/Clerestory windows & other Frames/ Chowkhat comprising of virgin PVC polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibres (wood powder/rice husk/ wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) fabricated with miter joints after applying PVC solvent cement and screwed with full body threaded star headed SS screws having minimum frame density of 850 kg/m3, screw withdrawal strength of 2200 N (Face) & 1100 N (Edge), minimum compressive strength of 58 N/mm2 , modulus of elasticity 900 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixed in position with M.S hold fast/lugs/SS dash fasteners of required dia and length complete as per direction of Engineer-InCharge. (Fixtures shall be paid for separately) Size 62 x 100mm Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr716.04716.0447.4FalseNoneNoneFalseNoneFalse33940.2960
3995026154593None12.94.1Providing and fixing factory made Green certified, Anti Termite, UV resistant, high water absorbant single extruded WPC (Wood PolymerComposite) solid plain flush door shutter of required size comprising of virgin polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibers (wood powder/rice husk/wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) having minimum density of 650 kg/m3 and screw withdrawal strength of 1800 N (Face) & 900 N (Edge), minimum compressive strength of 50 N/mm2 , modulus of elasticity 850 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixing with stainless steel butt hinges of required size with necessary full body threaded star headed counter sunk S.S screws The cost includes cost of materials, transportation, labour and fixing charges.(Cost of Fixtures to be paid separately) 30 mm thickness Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3485.03485.033.4FalseNoneNoneFalseNoneFalse116399.00
3995027154593None12.94.1Providing and fixing factory made Green certified, Anti Termite, UV resistant, high water absorbant single extruded WPC (Wood PolymerComposite) solid plain flush door shutter of required size comprising of virgin polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibers (wood powder/rice husk/wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) having minimum density of 650 kg/m3 and screw withdrawal strength of 1800 N (Face) & 900 N (Edge), minimum compressive strength of 50 N/mm2 , modulus of elasticity 850 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixing with stainless steel butt hinges of required size with necessary full body threaded star headed counter sunk S.S screws The cost includes cost of materials, transportation, labour and fixing charges.(Cost of Fixtures to be paid separately) 30 mm thickness First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3519.853519.8531.5FalseNoneNoneFalseNoneFalse110875.2750
3995028154593None12.94.1Providing and fixing factory made Green certified, Anti Termite, UV resistant, high water absorbant single extruded WPC (Wood PolymerComposite) solid plain flush door shutter of required size comprising of virgin polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibers (wood powder/rice husk/wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) having minimum density of 650 kg/m3 and screw withdrawal strength of 1800 N (Face) & 900 N (Edge), minimum compressive strength of 50 N/mm2 , modulus of elasticity 850 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixing with stainless steel butt hinges of required size with necessary full body threaded star headed counter sunk S.S screws The cost includes cost of materials, transportation, labour and fixing charges.(Cost of Fixtures to be paid separately) 30 mm thickness Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3554.73554.714.5FalseNoneNoneFalseNoneFalse51543.150
3995029154593None12.9Providing & fixing of 3-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having an overall size of 108mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm x 75mm with GI reinforcement of 2mm and mesh sash of size 37mm x 58mm. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24 mm. Windows shall be provided with 6mm plain float glass, standard hardware& Multi point locking system with touch lock. Wall thickness of frame & sash shall be of 2mm-2.5mm. Maximum possible size 2419mm x 2200mm. (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm6734.06734.030.0FalseNoneNoneFalseNoneFalse202020.00
3995030154593None12.9Providing & fixing of 3-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having an overall size of 108mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm x 75mm with GI reinforcement of 2mm and mesh sash of size 37mm x 58mm. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24 mm. Windows shall be provided with 6mm plain float glass, standard hardware& Multi point locking system with touch lock. Wall thickness of frame & sash shall be of 2mm-2.5mm. Maximum possible size 2419mm x 2200mm. (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm6801.346801.3432.0FalseNoneNoneFalseNoneFalse217642.880
3995031154593None12.9Providing & fixing of 3-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having an overall size of 108mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm x 75mm with GI reinforcement of 2mm and mesh sash of size 37mm x 58mm. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24 mm. Windows shall be provided with 6mm plain float glass, standard hardware& Multi point locking system with touch lock. Wall thickness of frame & sash shall be of 2mm-2.5mm. Maximum possible size 2419mm x 2200mm. (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm6868.686868.6837.0FalseNoneNoneFalseNoneFalse254141.160
3995032154593None12.9Providing & fixing of 3-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having an overall size of 108mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm x 75mm with GI reinforcement of 2mm and mesh sash of size 37mm x 58mm. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24 mm. Windows shall be provided with 6mm plain float glass, standard hardware& Multi point locking system with touch lock. Wall thickness of frame & sash shall be of 2mm-2.5mm. Maximum possible size 2419mm x 2200mm. (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm6936.026936.023.0FalseNoneNoneFalseNoneFalse20808.060
3995033154593None12.85Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5719.05719.024.0FalseNoneNoneFalseNoneFalse137256.00
3995034154593None12.85Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5776.195776.1919.0FalseNoneNoneFalseNoneFalse109747.610
3995035154593None12.85Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5833.385833.3820.0FalseNoneNoneFalseNoneFalse116667.60
3995036154593None12.85Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5890.575890.572.0FalseNoneNoneFalseNoneFalse11781.140
3995037154593None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs183.0183.0961.0FalseNoneNoneFalseNoneFalse175863.00
3995038154593None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs184.83184.83896.0FalseNoneNoneFalseNoneFalse165607.680
3995039154593None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs186.66186.661013.0FalseNoneNoneFalseNoneFalse189086.580
3995040154593None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs188.49188.4959.0FalseNoneNoneFalseNoneFalse11120.910
3995041154593None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2852.02852.0411.0FalseNoneNoneFalseNoneFalse1172172.00
3995042154593None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2880.522880.52364.0FalseNoneNoneFalseNoneFalse1048509.280
3995043154593None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2909.042909.04232.0FalseNoneNoneFalseNoneFalse674897.280
3995044154593None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2937.562937.568.0FalseNoneNoneFalseNoneFalse23500.480
3995045154593None9.11Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved make, in all colours, shades, except White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick bed of cement mortar 1:4 (1 Cement : 4 Coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including pointing the joints with white cement and matching pigments etc., complete. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm889.0889.072.0FalseNoneNoneFalseNoneFalse64008.00
3995046154593None9.11Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved make, in all colours, shades, except White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick bed of cement mortar 1:4 (1 Cement : 4 Coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including pointing the joints with white cement and matching pigments etc., complete. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm897.89897.8969.0FalseNoneNoneFalseNoneFalse61954.410
3995047154593None9.11Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved make, in all colours, shades, except White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick bed of cement mortar 1:4 (1 Cement : 4 Coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including pointing the joints with white cement and matching pigments etc., complete. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm906.78906.7831.0FalseNoneNoneFalseNoneFalse28110.180
3995048154593None9.39Providing skirting, dadooing, rises of steps with colour glazed tiles 6mm thick on 10mm thick cement plaster 1:3 and jointed with white cement slurry over existing rough plaster surface using glazed tiles of approved make and size including cost of materials, labour, complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1449.01449.0262.0FalseNoneNoneFalseNoneFalse379638.00
3995049154593None9.39Providing skirting, dadooing, rises of steps with colour glazed tiles 6mm thick on 10mm thick cement plaster 1:3 and jointed with white cement slurry over existing rough plaster surface using glazed tiles of approved make and size including cost of materials, labour, complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1463.491463.49240.0FalseNoneNoneFalseNoneFalse351237.60
3995050154593None9.39Providing skirting, dadooing, rises of steps with colour glazed tiles 6mm thick on 10mm thick cement plaster 1:3 and jointed with white cement slurry over existing rough plaster surface using glazed tiles of approved make and size including cost of materials, labour, complete as per specifications. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1477.981477.9892.0FalseNoneNoneFalseNoneFalse135974.160
3995051154593None10.2Providing edge moulding to 18mm thick Granite stone counters, vanities etc including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr328.0328.086.0FalseNoneNoneFalseNoneFalse28208.00
3995052154593None10.2Providing edge moulding to 18mm thick Granite stone counters, vanities etc including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr331.28331.2867.0FalseNoneNoneFalseNoneFalse22195.760
3995053154593None10.2Providing edge moulding to 18mm thick Granite stone counters, vanities etc including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineer-in-charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr334.56334.5634.0FalseNoneNoneFalseNoneFalse11375.040
3995054154593None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm295.0295.01105.0FalseNoneNoneFalseNoneFalse325975.00
3995055154593None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm297.95297.951048.0FalseNoneNoneFalseNoneFalse312251.60
3995056154593None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm300.9300.9626.0FalseNoneNoneFalseNoneFalse188363.40
3995057154593None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm303.85303.8574.0FalseNoneNoneFalseNoneFalse22484.90
3995058154593None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm371.0371.0510.0FalseNoneNoneFalseNoneFalse189210.00
3995059154593None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm374.71374.71516.0FalseNoneNoneFalseNoneFalse193350.360
3995060154593None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm378.42378.42497.0FalseNoneNoneFalseNoneFalse188074.740
3995061154593None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm382.13382.13311.0FalseNoneNoneFalseNoneFalse118842.430
3995062154593None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg64.064.077.0FalseNoneNoneFalseNoneFalse4928.00
3995063154593None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg64.6464.6478.0FalseNoneNoneFalseNoneFalse5041.920
3995064154593None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg65.2865.2874.55FalseNoneNoneFalseNoneFalse4866.6240
3995065154593None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg65.9265.9246.65FalseNoneNoneFalseNoneFalse3075.1680
3995066154593None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm295.0295.0279.0FalseNoneNoneFalseNoneFalse82305.00
3995067154593None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm297.95297.95255.0FalseNoneNoneFalseNoneFalse75977.250
3995068154593None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm300.9300.999.0FalseNoneNoneFalseNoneFalse29789.10
3995069154593None8.16 aProviding lath plaster with cement mortar 1:3, 5cms thick with 6mm dia mild steel bars at 20 cms. c to c both horizontally and vertically fixing chicken mesh for drop chajja, facia, backing to cup boards including cost of all materials, labour, providing and removing form work usage charges, curing complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1238.01238.03.0FalseNoneNoneFalseNoneFalse3714.00
3995070154593None8.16 aProviding lath plaster with cement mortar 1:3, 5cms thick with 6mm dia mild steel bars at 20 cms. c to c both horizontally and vertically fixing chicken mesh for drop chajja, facia, backing to cup boards including cost of all materials, labour, providing and removing form work usage charges, curing complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1250.381250.383.0FalseNoneNoneFalseNoneFalse3751.140
3995071154593None8.16 aProviding lath plaster with cement mortar 1:3, 5cms thick with 6mm dia mild steel bars at 20 cms. c to c both horizontally and vertically fixing chicken mesh for drop chajja, facia, backing to cup boards including cost of all materials, labour, providing and removing form work usage charges, curing complete as per specifications. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1262.761262.763.0FalseNoneNoneFalseNoneFalse3788.280
3995072154593None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm100.0100.01574.0067FalseNoneNoneFalseNoneFalse157400.670
3995073154593None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. First floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm101.0101.01468.5176FalseNoneNoneFalseNoneFalse148320.27760
3995074154593None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm102.0102.0895.6766FalseNoneNoneFalseNoneFalse91359.01320
3995075154593None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm103.0103.0123.8334FalseNoneNoneFalseNoneFalse12754.84020
3995076154593None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm110.0110.01425.5917FalseNoneNoneFalseNoneFalse156815.0870
3995077154593None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. First floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm111.1111.11319.5626FalseNoneNoneFalseNoneFalse146603.404860
3995078154593None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm112.2112.2748.3416FalseNoneNoneFalseNoneFalse83963.927520
3995079154593None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm113.3113.3123.8334FalseNoneNoneFalseNoneFalse14030.324220
3995080154593None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.053.01574.0067FalseNoneNoneFalseNoneFalse83422.35510
3995081154593None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.5353.531468.5176FalseNoneNoneFalseNoneFalse78609.7471280
3995082154593None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm54.0654.06895.6766FalseNoneNoneFalseNoneFalse48420.2769960
3995083154593None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm54.5954.59123.8334FalseNoneNoneFalseNoneFalse6760.0653060
3995084154593None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm174.0174.0510.0FalseNoneNoneFalseNoneFalse88740.00
3995085154593None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm175.74175.74516.0FalseNoneNoneFalseNoneFalse90681.840
3995086154593None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Second floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm177.48177.48497.0FalseNoneNoneFalseNoneFalse88207.560
3995087154593None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm179.22179.22311.0FalseNoneNoneFalseNoneFalse55737.420
3995088154593None8.34.1Applying priming coat: With ready mixed pink or Grey primer of approved brand and manufacture on wood work (hard and soft wood) including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.053.041.0FalseNoneNoneFalseNoneFalse2173.00
3995089154593None8.34.1Applying priming coat: With ready mixed pink or Grey primer of approved brand and manufacture on wood work (hard and soft wood) including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.5353.5325.0FalseNoneNoneFalseNoneFalse1338.250
3995090154593None8.34.1Applying priming coat: With ready mixed pink or Grey primer of approved brand and manufacture on wood work (hard and soft wood) including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm54.0654.0625.0FalseNoneNoneFalseNoneFalse1351.50
3995091154593None8.33.2Painting wood work with Deluxe Multi Surface Paint of required shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @0.75 L/10 m² of approved brand and manufacture to give an even shade including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, sand papering and knotting , cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm138.0138.041.0FalseNoneNoneFalseNoneFalse5658.00
3995092154593None8.33.2Painting wood work with Deluxe Multi Surface Paint of required shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @0.75 L/10 m² of approved brand and manufacture to give an even shade including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, sand papering and knotting , cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm139.38139.3825.0FalseNoneNoneFalseNoneFalse3484.50
3995093154593None8.33.2Painting wood work with Deluxe Multi Surface Paint of required shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @0.75 L/10 m² of approved brand and manufacture to give an even shade including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, sand papering and knotting , cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm140.76140.7625.0FalseNoneNoneFalseNoneFalse3519.00
3995094154593None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @ 0.80 L/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm139.0139.054.0FalseNoneNoneFalseNoneFalse7506.00
3995095154593None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @ 0.80 L/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm140.39140.3950.0FalseNoneNoneFalseNoneFalse7019.50
3995096154593None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @ 0.80 L/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm141.78141.7857.0FalseNoneNoneFalseNoneFalse8081.460
3995097154593None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @ 0.80 L/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm143.17143.174.0FalseNoneNoneFalseNoneFalse572.680
3995098154593None8.4Painting with synthetic enamel paint of approved brand and manufacture to give an even shade :Two coats on new work after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm115.0115.0148.415FalseNoneNoneFalseNoneFalse17067.7250
3995099154593None8.4Painting with synthetic enamel paint of approved brand and manufacture to give an even shade :Two coats on new work after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm116.15116.15148.955FalseNoneNoneFalseNoneFalse17301.123250
3995100154593None8.4Painting with synthetic enamel paint of approved brand and manufacture to give an even shade :Two coats on new work after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm117.3117.3147.335FalseNoneNoneFalseNoneFalse17282.39550
3995101154593None11.28Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners, stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in- charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.) including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs565.0565.0298.0FalseNoneNoneFalseNoneFalse168370.00
3995102154593None11.28Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners, stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in- charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.) including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs570.65570.65130.0FalseNoneNoneFalseNoneFalse74184.50
3995103154593None11.28Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners, stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in- charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.) including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. Second floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs576.3576.365.0FalseNoneNoneFalseNoneFalse37459.50
3995104154593None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr66.066.0201.0FalseNoneNoneFalseNoneFalse13266.00
3995105154593None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr66.6666.66201.0FalseNoneNoneFalseNoneFalse13398.660
3995106154593None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr67.3267.32237.0FalseNoneNoneFalseNoneFalse15954.840
3995107154593None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr67.9867.9841.0FalseNoneNoneFalseNoneFalse2787.180
3995108154593None7.18Providing and laying cinder concrete in cement 1:15 ( 1 cement : 15 cinder of 12.5mm nominal gauge) on terraced roof or sunken slabs, laid to slope compacting, including cost of materials, labour, curing complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum2037.172037.1716.0FalseNoneNoneFalseNoneFalse32594.720
3995109154593None7.18Providing and laying cinder concrete in cement 1:15 ( 1 cement : 15 cinder of 12.5mm nominal gauge) on terraced roof or sunken slabs, laid to slope compacting, including cost of materials, labour, curing complete as per specifications. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum2057.342057.3411.0FalseNoneNoneFalseNoneFalse22630.740
3995110154593None15.7Integral Crystalline Water Proofing Admixture Providing and supplying crystalline integral concrete waterproofing admixture that waterproofs concrete by forming crystals deep in the pores, capillaries and microcracks of the concrete, self-seal waterproofing compound to bridge shrinkage cracks upto 0.5mm in width & resist hydro-static pressure upto 16bar for both positive & negative pressure confirming to DIN 1048 part 5 for 56% reduction in depth of penetration against control, resistance to chloride penetration confirming to ASTM C 1202 with 64% improvement against control & protecting steel reinforcement against corrosion mixed @ 1% by weight of cementitious content in concrete. ie., integral crystaline waterproofing admix @ 0.5 kg/bag of cement. (For calculation purpose 320 kg of Cement for M-20 grade of Concrete is considered in the analysis) First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm621.15621.1566.0FalseNoneNoneFalseNoneFalse40995.90
3995111154593None15.7Integral Crystalline Water Proofing Admixture Providing and supplying crystalline integral concrete waterproofing admixture that waterproofs concrete by forming crystals deep in the pores, capillaries and microcracks of the concrete, self-seal waterproofing compound to bridge shrinkage cracks upto 0.5mm in width & resist hydro-static pressure upto 16bar for both positive & negative pressure confirming to DIN 1048 part 5 for 56% reduction in depth of penetration against control, resistance to chloride penetration confirming to ASTM C 1202 with 64% improvement against control & protecting steel reinforcement against corrosion mixed @ 1% by weight of cementitious content in concrete. ie., integral crystaline waterproofing admix @ 0.5 kg/bag of cement. (For calculation purpose 320 kg of Cement for M-20 grade of Concrete is considered in the analysis) Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm627.3627.335.0FalseNoneNoneFalseNoneFalse21955.50
3995112154593None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9613.59613.53.4015FalseNoneNoneFalseNoneFalse32700.320250
3995113154593None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9679.89679.84.2669FalseNoneNoneFalseNoneFalse41302.738620
3995114154593None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9746.19746.12.0155FalseNoneNoneFalseNoneFalse19643.264550
3995115154593None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9812.49812.433.6075FalseNoneNoneFalseNoneFalse329770.2330
3995116154593None9.25Providing and laying 60mm thick factory made cement concrete paver block of approved shape and colour of M -30 grade made of C&D waste by block making machine with vibratory compaction laid in required pattern and including over 50mm thick compacted bed of coarse sand, filling the joints with fine sand etc. all complete as per the direction of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm800.0800.025.0FalseNoneNoneFalseNoneFalse20000.00
3995117154593NoneVOL -5 7.1.1Providing and fixing MS ladder between landings, 45 cms wide using angle iron of specified sizes, 20mm MS bars at 25 cms. centre to centre, with necessary supports of same angle iron etc. as directed, including hand railing on both sides with 25mm dia. GI pipes with angle iron props at 2 mtrs. intervals and 0.5M heigh, including fixing in ground with CC 1:2:4 and two coats of anticorrosive bituminous paint etc. with all lead and lifts etc. complete with: MS angle of 65 x 65 x 8mm Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr4508.314508.314.5FalseNoneNoneFalseNoneFalse20287.3950
3995118154593None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.038.0241.2FalseNoneNoneFalseNoneFalse9165.60
3995119154593None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.3838.38165.6FalseNoneNoneFalseNoneFalse6355.7280
3995120154593None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.7638.76165.6FalseNoneNoneFalseNoneFalse6418.6560
3995121154593None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr39.1439.147.65FalseNoneNoneFalseNoneFalse299.4210
3995122154593None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.038.0243.69FalseNoneNoneFalseNoneFalse9260.220
3995123154593None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.3838.38232.09FalseNoneNoneFalseNoneFalse8907.61420
3995124154593None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.7638.76151.23FalseNoneNoneFalseNoneFalse5861.67480
3995125154593None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr39.1439.1415.11FalseNoneNoneFalseNoneFalse591.40540
3995126154593None22.15.7Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Tower Bolts 250x10mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos200.0200.029.0FalseNoneNoneFalseNoneFalse5800.00
3995127154593None22.15.7Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Tower Bolts 250x10mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos202.0202.025.0FalseNoneNoneFalseNoneFalse5050.00
3995128154593None22.15.7Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Tower Bolts 250x10mm Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos204.0204.013.0FalseNoneNoneFalseNoneFalse2652.00
3995129154593None22.15.8Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS hinges 125 mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos50.050.095.0FalseNoneNoneFalseNoneFalse4750.00
3995130154593None22.15.8Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS hinges 125 mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos50.550.580.0FalseNoneNoneFalseNoneFalse4040.00
3995131154593None22.15.8Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS hinges 125 mm Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos51.051.043.0FalseNoneNoneFalseNoneFalse2193.00
3995132154593None22.15.1Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Handles 200mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos450.0450.058.0FalseNoneNoneFalseNoneFalse26100.00
3995133154593None22.15.1Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Handles 200mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos454.5454.550.0FalseNoneNoneFalseNoneFalse22725.00
3995134154593None22.15.1Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Handles 200mm Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos459.0459.026.0FalseNoneNoneFalseNoneFalse11934.00
3995135154593None22.15.4Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Aldrop 16mm dia, 300mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos375.0375.028.0FalseNoneNoneFalseNoneFalse10500.00
3995136154593None22.15.4Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Aldrop 16mm dia, 300mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos378.75378.7525.0FalseNoneNoneFalseNoneFalse9468.750
3995137154593None22.15.4Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Aldrop 16mm dia, 300mm Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos382.5382.513.0FalseNoneNoneFalseNoneFalse4972.50
3995138154593None22.15.10Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Door stopper 75mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos100.0100.08.0FalseNoneNoneFalseNoneFalse800.00
3995139154593None22.15.10Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Door stopper 75mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos101.0101.05.0FalseNoneNoneFalseNoneFalse505.00
3995140154593None22.15.10Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Door stopper 75mm Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos102.0102.04.0FalseNoneNoneFalseNoneFalse408.00
3995141154593None15.1Providing and laying water proofing treatment to the Roof with PU based single component elastomeric pure polyurethane based coating on New rrace/Chajjas/Sunken portion of WC:Bathroom, cold applied PU waterproofing membrane that is highly elastic with elongation greater than 400% and tensile strength greater than 2MPa as per ASTM D412. The waterproofing membrane to be applied in 2coats @ 1.6kg per m2 to achieve final DFT (dry film thickness) of 1mm including prime coat of epoxy primer @150 g per m2 and protection with 120gsm Geo-textile over the waterproofing membrane. The finished cost to include surface preparation, making coving at Junction, Bore Packing, treatment of construction joints completely as per specification & with a 10 years warranty on product & work from certified manufacturers as per the direction of the Engineer In charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm841.51841.51330.0FalseNoneNoneFalseNoneFalse277698.30
3995142154593None20.107Providing and fixing plain rolled glass 4mm thick with teakwood beading of 10mm thick. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1147.01147.02.43FalseNoneNoneFalseNoneFalse2787.210
3995143154593None20.107Providing and fixing plain rolled glass 4mm thick with teakwood beading of 10mm thick. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1158.471158.471.71FalseNoneNoneFalseNoneFalse1980.98370
17262057300000NoneNoneBuildingsKitchen & Dining (Amble)12101449.5
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3995144154594NoneVOL - 3, C - 2 2.1 a (i) MoRT&H 201Cutting of Trees, excluding removal of stumps and roots of trees. (i) Girth from 300 mm to 600 mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each595.0595.0180.0FalseNoneNoneFalseNoneFalse107100.00
3995145154594NoneVOL - 3, C - 2 2.2 b (i) MoRT&H 201Removal of stumps and roots including backfilling with suitable material to required compaction (i) Girth from 300 mm to 600 mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each356.0356.0180.0FalseNoneNoneFalseNoneFalse64080.00
3995146154594None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.02325.2783FalseNoneNoneFalseNoneFalse237178.38660
3995147154594None1.15.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In ordinary/soft rock without blasting upto 1.5 m depth ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum363.0363.0272.6264FalseNoneNoneFalseNoneFalse98963.38320
3995148154594None1.16.1Earth work excavation for Foundation by Mechanical means depth upto 1.50m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including cost of explosives, dressing of excavated surfaces, disposing off or levelling the excavated stuff or sorting & stacking the selected stuff for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, blasting materials, tools, usage of Machinery & all other appurtenaces required to complete the work. In Hard Rock ( requiring blasting) Depth upto 1.50m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum554.0554.034.0783FalseNoneNoneFalseNoneFalse18879.37820
3995149154594None1.9Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum266.0266.0585.007FalseNoneNoneFalseNoneFalse155611.8620
3995150154594None4.1Providing and injecting chemical emulsion for Pre-constructional Anti-Termite Treatment, creating continuous chemical barrier under and around the column pits, walls, trenches, basement excavation, top surface of the plinth filling, junction of wall and floor, along the external perimeter of building, expansion joints, over the top surface of consolidated earth on which apron is to be laid, surrounding of pipes and conduits with Chlorpyriphos 20% E.C. / Lindane 20% E.C. @ 3.19 l/m2 including cost of chemical, diluting in water to one percent concentration, labour, usage charges of machinery, complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm118.0118.0446.0FalseNoneNoneFalseNoneFalse52628.00
3995151154594None2.1.3Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5989.05989.085.0FalseNoneNoneFalseNoneFalse509065.00
3995152154594None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6217.06217.04.5FalseNoneNoneFalseNoneFalse27976.50
3995153154594None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7460.47460.41.0FalseNoneNoneFalseNoneFalse7460.40
3995154154594None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7522.577522.572.1FalseNoneNoneFalseNoneFalse15797.3970
3995155154594None2.1.6Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:2:4 Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6243.06243.04.0FalseNoneNoneFalseNoneFalse24972.00
3995156154594None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Footing concrete ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6842.886842.8889.1533FalseNoneNoneFalseNoneFalse610065.3335040
3995157154594None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Pedastals ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10771.210771.27.198FalseNoneNoneFalseNoneFalse77531.09760
3995158154594None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Columns Concrete Upto PB ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10771.210771.23.0482FalseNoneNoneFalseNoneFalse32832.771840
3995159154594None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Plinth Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9504.09504.09.712FalseNoneNoneFalseNoneFalse92302.8480
3995160154594None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Grade Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9504.09504.022.808FalseNoneNoneFalseNoneFalse216767.2320
3995161154594None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Columns Concrete Up to Roof ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11633.111633.115.8675FalseNoneNoneFalseNoneFalse184588.214250
3995162154594None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10948.810948.824.961FalseNoneNoneFalseNoneFalse273292.99680
3995163154594None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10264.510264.566.7308FalseNoneNoneFalseNoneFalse684958.29660
3995164154594None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Lintel Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10948.810948.84.1886FalseNoneNoneFalseNoneFalse45860.143680
3995165154594None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Staircase ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10264.510264.52.495FalseNoneNoneFalseNoneFalse25609.92750
3995166154594None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor For Columns ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11749.4311749.430.978FalseNoneNoneFalseNoneFalse11490.942540
3995167154594None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11058.2811058.281.5649FalseNoneNoneFalseNoneFalse17305.1023720
3995168154594None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10367.1410367.142.0928FalseNoneNoneFalseNoneFalse21696.3505920
3995169154594None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10674.5810674.584.0FalseNoneNoneFalseNoneFalse42698.320
3995170154594None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t89457.089457.022.5913FalseNoneNoneFalseNoneFalse2020949.92410
3995171154594None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t90351.5790351.571.048FalseNoneNoneFalseNoneFalse94688.445360
3995172154594None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1310.01310.0406.0FalseNoneNoneFalseNoneFalse531860.00
3995173154594None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1323.11323.1142.0FalseNoneNoneFalseNoneFalse187880.20
3995174154594None6.34Providing and constructing load bearing wall with Solid Concrete blocks of size 400x100x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1104.01104.027.0FalseNoneNoneFalseNoneFalse29808.00
3995175154594None12.13.1Providing Salwood frames of doors, windows, clerestory windows, ventilators and other frames, wrought, framed or assembled including making plaster groves (excluding cost of cement concrete and side clamps), but including cost of materials, labour, usage charges complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum98815.098815.00.5FalseNoneNoneFalseNoneFalse49407.50
3995176154594None12.17Providing and fixing in position fully panelled Honne wood shutters for doors with , stiles and rails of 35mm. thick with bottom and lock rails 180mm wide top rail and stiles 100mm wide as per drawing and panels of 25mm thick including cost of materials, labour, usage charges complete as per specifications. (excluding cost of fixtures) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm7085.07085.03.8FalseNoneNoneFalseNoneFalse26923.00
3995177154594None12.57.3Providing and fixing flush door shutter made out of solid core block board type, well seasoned , chemicaly treated hard wood battens and internal frame with minimum 45 mm wide wooden frame alround door shutters covered with cross bonded wooden sheets (core veneer) hot pressed and fastened on both sides of the door useing liquid phenol formaldehyde resin as per IS specifications 2202 (part-I) 1991. from manufacturer complete as per spcification.-do- 30 mm thick both side commercial Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3005.03005.011.4FalseNoneNoneFalseNoneFalse34257.00
3995178154594None12.51Fixing of door frame in an existing opening including embedding frame in floor and walls after cutting masonry for holdfasts for embedding holdfast in cement concrete 1:3:6 of 20mm and down size granite metal painting two coats of coal tar to sides of frame, making good the damages to walls and floor as required and disposal of the debris with lead upto 50 m. including cost of materials, labour charges, complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1016.01016.07.0FalseNoneNoneFalseNoneFalse7112.00
3995179154594None12.93.1Providing and fixing factory made single extruded WPC (Wood Polymer Composite) solid door/window/Clerestory windows & other Frames/ Chowkhat comprising of virgin PVC polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibres (wood powder/rice husk/ wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) fabricated with miter joints after applying PVC solvent cement and screwed with full body threaded star headed SS screws having minimum frame density of 850 kg/m3, screw withdrawal strength of 2200 N (Face) & 1100 N (Edge), minimum compressive strength of 58 N/mm2 , modulus of elasticity 900 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixed in position with M.S hold fast/lugs/SS dash fasteners of required dia and length complete as per direction of Engineer-InCharge. (Fixtures shall be paid for separately) Size 62 x 100mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr702.0702.010.7FalseNoneNoneFalseNoneFalse7511.40
3995180154594None12.94.1Providing and fixing factory made Green certified, Anti Termite, UV resistant, high water absorbant single extruded WPC (Wood PolymerComposite) solid plain flush door shutter of required size comprising of virgin polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibers (wood powder/rice husk/wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) having minimum density of 650 kg/m3 and screw withdrawal strength of 1800 N (Face) & 900 N (Edge), minimum compressive strength of 50 N/mm2 , modulus of elasticity 850 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixing with stainless steel butt hinges of required size with necessary full body threaded star headed counter sunk S.S screws The cost includes cost of materials, transportation, labour and fixing charges.(Cost of Fixtures to be paid separately) 30 mm thickness ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3485.03485.03.5FalseNoneNoneFalseNoneFalse12197.50
3995181154594None12.88Providing & fixing of 2-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having a overall size of 60mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm X 58mm with GI reinforcement of 1mm for the frame and 1.5 mm for the sash. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24mm. Windows shall be provided with 5mm plain float glass, standard hardware& single point locking system with touch lock. Wall thickness of frame & sash shall be of 2-2.5 mm. Maximum possible size 1819mm x 1819mm (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5390.05390.040.0FalseNoneNoneFalseNoneFalse215600.00
3995182154594None12.85Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5719.05719.023.0FalseNoneNoneFalseNoneFalse131537.00
3995183154594None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs183.0183.01233.0FalseNoneNoneFalseNoneFalse225639.00
3995184154594None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2852.02852.0427.0FalseNoneNoneFalseNoneFalse1217804.00
3995185154594None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2880.522880.523.0FalseNoneNoneFalseNoneFalse8641.560
3995186154594None9.11Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved make, in all colours, shades, except White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick bed of cement mortar 1:4 (1 Cement : 4 Coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including pointing the joints with white cement and matching pigments etc., complete. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm889.0889.035.0FalseNoneNoneFalseNoneFalse31115.00
3995187154594None9.39Providing skirting, dadooing, rises of steps with colour glazed tiles 6mm thick on 10mm thick cement plaster 1:3 and jointed with white cement slurry over existing rough plaster surface using glazed tiles of approved make and size including cost of materials, labour, complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1449.01449.067.0FalseNoneNoneFalseNoneFalse97083.00
3995188154594None10.18Providing and fixing of wall cladding using 20mm thick gang saw water cut Shiva gold granite, grey granite in CM 1:3 (1 cement : 3 coarse sand) proportion cut to required shape, pattern with paper joints, finished with cement mortal using white cement and colour pigments to match the colour of slab making through jointing with sealant, making holes 25mmx12mm grooves in joints including cost of all materials, mortar, labour, curing etc., complete. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3359.03359.084.8255FalseNoneNoneFalseNoneFalse284928.85450
3995189154594None10.2Providing edge moulding to 18mm thick Granite stone counters, vanities etc including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr328.0328.080.0FalseNoneNoneFalseNoneFalse26240.00
3995190154594None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm295.0295.0582.1745FalseNoneNoneFalseNoneFalse171741.47750
3995191154594None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm297.95297.9545.0FalseNoneNoneFalseNoneFalse13407.750
3995192154594None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm371.0371.0320.0FalseNoneNoneFalseNoneFalse118720.00
3995193154594None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm374.71374.71282.92FalseNoneNoneFalseNoneFalse106012.95320
3995194154594None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg64.064.048.0FalseNoneNoneFalseNoneFalse3072.00
3995195154594None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg64.6464.6443.0FalseNoneNoneFalseNoneFalse2779.520
3995196154594None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm295.0295.0161.0FalseNoneNoneFalseNoneFalse47495.00
3995197154594None8.16 aProviding lath plaster with cement mortar 1:3, 5cms thick with 6mm dia mild steel bars at 20 cms. c to c both horizontally and vertically fixing chicken mesh for drop chajja, facia, backing to cup boards including cost of all materials, labour, providing and removing form work usage charges, curing complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1238.01238.015.0FalseNoneNoneFalseNoneFalse18570.00
3995198154594None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm100.0100.01127.4867FalseNoneNoneFalseNoneFalse112748.670
3995199154594None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm101.0101.058.952FalseNoneNoneFalseNoneFalse5954.1520
3995200154594None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm110.0110.01127.4867FalseNoneNoneFalseNoneFalse124023.5370
3995201154594None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm111.1111.158.952FalseNoneNoneFalseNoneFalse6549.56720
3995202154594None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.053.01127.4867FalseNoneNoneFalseNoneFalse59756.79510
3995203154594None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.5353.5358.952FalseNoneNoneFalseNoneFalse3155.700560
3995204154594None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm174.0174.0320.0FalseNoneNoneFalseNoneFalse55680.00
3995205154594None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm175.74175.74283.0FalseNoneNoneFalseNoneFalse49734.420
3995206154594None8.34.1Applying priming coat: With ready mixed pink or Grey primer of approved brand and manufacture on wood work (hard and soft wood) including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.053.037.0FalseNoneNoneFalseNoneFalse1961.00
3995207154594None8.33.2Painting wood work with Deluxe Multi Surface Paint of required shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @0.75 L/10 m² of approved brand and manufacture to give an even shade including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, sand papering and knotting , cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm138.0138.037.0FalseNoneNoneFalseNoneFalse5106.00
3995208154594None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @ 0.80 L/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm139.0139.069.0FalseNoneNoneFalseNoneFalse9591.00
3995209154594None11.28Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners, stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in- charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.) including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs565.0565.0270.0FalseNoneNoneFalseNoneFalse152550.00
3995210154594None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr66.066.0180.0FalseNoneNoneFalseNoneFalse11880.00
3995211154594None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr66.6666.6647.0FalseNoneNoneFalseNoneFalse3133.020
3995212154594None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9613.59613.51.8943FalseNoneNoneFalseNoneFalse18210.853050
3995213154594None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9679.89679.80.0249FalseNoneNoneFalseNoneFalse241.027020
3995214154594None9.25Providing and laying heavy duty cobble stones 60mm thick interlock pavers, using cement and course sand for manufacture of blocks of approved size, shape and colour with a minimum compressive strength of 281 kg per m2 over 50mm thick sand bed ( average thickness ) and compacting with plate vibrator having 3 tons compaction force thereby forcing part of sand underneath to come up in between joints, final compaction of paver surface joints into its final level , including cost of materials, labour and Usage charges of machinery complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm800.0800.042.0FalseNoneNoneFalseNoneFalse33600.00
3995215154594None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.038.0133.2FalseNoneNoneFalseNoneFalse5061.60
3995216154594None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.038.0181.33FalseNoneNoneFalseNoneFalse6890.540
3995217154594None22.15.7Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Tower Bolts 250x10mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos200.0200.010.0FalseNoneNoneFalseNoneFalse2000.00
3995218154594None22.15.8Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS hinges 125 mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos50.050.038.0FalseNoneNoneFalseNoneFalse1900.00
3995219154594None22.15.1Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Handles 200mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos450.0450.020.0FalseNoneNoneFalseNoneFalse9000.00
3995220154594None22.15.4Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Aldrop 16mm dia, 300mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos375.0375.09.0FalseNoneNoneFalseNoneFalse3375.00
3995221154594None22.15.10Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Door stopper 75mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos100.0100.08.0FalseNoneNoneFalseNoneFalse800.00
3995222154594None11.16.1Providing and fixing Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete. Hot finished welded type tubes including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs137.36137.3612320.0FalseNoneNoneFalseNoneFalse1692275.20
3995223154594None7.38Providing and fixing precoated galvanised iron profile sheets (size, shape and pitch of corrugation as approved by Engineer-in-charge) 0.50 mm (+ 0.05 %) total coated thickness with zinc coating 120 grams per m2 as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns. Sheet should have protective guard film of 25 microns minimum to avoid scratches during transportation and should be supplied in single length upto 12 m or as desired by Engineer-in-charge. The sheet shall be fixed using self drilling/self tapping screws of size (5.5x 55 mm) with EPDM seal, complete upto any pitch in horizontal/ vertical or curved surfaces, excluding the cost of purlins, rafters and trusses and including cutting to size and shape wherever required. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm573.68573.68472.0FalseNoneNoneFalseNoneFalse270776.960
3995224154594None7.4.1Providing & fixing ridges or hips of width 60 cm overall width plain G.S. sheet fixed with polymer coated J or L hooks, bolts and nuts 8 mm dia G.I. limpet and bitumen washers complete as per design drawings. 0.63 mm thick with zinc coating not less than 275 g/m² ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m645.39645.3948.0FalseNoneNoneFalseNoneFalse30978.720
3995225154594None7.6Providing and fixing 15 cm wide, 45 cm overall semi-circular plain G.S. sheet gutter with iron brackets 40x3mm size, bolts, nuts and washers etc., including making necessary connections with rain water pipes complete. (0.63 mm thick with zinc coating not less than 275 g/m²) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m651.45651.4565.0FalseNoneNoneFalseNoneFalse42344.250
3995226154594None20.107Providing and fixing plain rolled glass 4mm thick with teakwood beading of 10mm thick. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1147.01147.02.16FalseNoneNoneFalseNoneFalse2477.520
17262057300001NoneNoneBuildingsStaff Quarters (Amble)17636636.44
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3995227154595NoneVOL - 3, C - 2 2.1 a (i) MoRT&H 201Cutting of Trees, excluding removal of stumps and roots of trees. (i) Girth from 300 mm to 600 mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each595.0595.0131.0FalseNoneNoneFalseNoneFalse77945.00
3995228154595NoneVOL - 3, C - 2 2.2 b (i) MoRT&H 201Removal of stumps and roots including backfilling with suitable material to required compaction (i) Girth from 300 mm to 600 mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each356.0356.0131.0FalseNoneNoneFalseNoneFalse46636.00
3995229154595None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.050.177FalseNoneNoneFalseNoneFalse5118.0540
3995230154595None1.15.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In ordinary/soft rock without blasting upto 1.5 m depth ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum363.0363.0401.4161FalseNoneNoneFalseNoneFalse145714.04430
3995231154595None1.16.1Earth work excavation for FOUNDATION by Mechanical means depth upto 1.50m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including cost of explosives, dressing of excavated surfaces, disposing off or levelling the excavated stuff or sorting & stacking the selected stuff for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, blasting materials, tools, usage of Machinery & all other appurtenaces required to complete the work. In Hard Rock ( requiring blasting) Depth upto 1.50m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum554.0554.050.177FalseNoneNoneFalseNoneFalse27798.0580
3995232154595None1.9Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum266.0266.0676.091FalseNoneNoneFalseNoneFalse179840.2060
3995233154595None4.1Providing and injecting chemical emulsion for Pre-constructional Anti-Termite Treatment, creating continuous chemical barrier under and around the column pits, walls, trenches, basement excavation, top surface of the plinth filling, junction of wall and floor, along the external perimeter of building, expansion joints, over the top surface of consolidated earth on which apron is to be laid, surrounding of pipes and conduits with Chlorpyriphos 20% E.C. / Lindane 20% E.C. @ 3.19 l/m2 including cost of chemical, diluting in water to one percent concentration, labour, usage charges of machinery, complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm118.0118.0418.0FalseNoneNoneFalseNoneFalse49324.00
3995234154595None2.1.3Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5989.05989.081.0FalseNoneNoneFalseNoneFalse485109.00
3995235154595None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6217.06217.05.0FalseNoneNoneFalseNoneFalse31085.00
3995236154595None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7460.47460.40.9101FalseNoneNoneFalseNoneFalse6789.710040
3995237154595None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7522.577522.570.9101FalseNoneNoneFalseNoneFalse6846.2909570
3995238154595None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7584.747584.742.8FalseNoneNoneFalseNoneFalse21237.2720
3995239154595None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor Footing concrete ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6842.886842.88126.8392FalseNoneNoneFalseNoneFalse867945.4248960
3995240154595None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Pedastals ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10771.210771.29.0429FalseNoneNoneFalseNoneFalse97402.884480
3995241154595None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Columns Concrete Upto PB ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10771.210771.213.0869FalseNoneNoneFalseNoneFalse140961.617280
3995242154595None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Plinth Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9504.09504.011.8093FalseNoneNoneFalseNoneFalse112235.58720
3995243154595None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Grade Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9504.09504.033.9921FalseNoneNoneFalseNoneFalse323060.91840
3995244154595None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Columns Concrete Up to Roof ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11633.111633.116.9533FalseNoneNoneFalseNoneFalse197219.434230
3995245154595None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10948.810948.827.4896FalseNoneNoneFalseNoneFalse300978.132480
3995246154595None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10264.510264.568.0002FalseNoneNoneFalseNoneFalse697988.05290
3995247154595None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Lintel Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10948.810948.87.719FalseNoneNoneFalseNoneFalse84513.78720
3995248154595None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Staircase ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10264.510264.54.0431FalseNoneNoneFalseNoneFalse41500.399950
3995249154595None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor For Columns Concrete Up to Roof ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11749.4311749.4316.9533FalseNoneNoneFalseNoneFalse199191.6116190
3995250154595None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11058.2811058.2827.4896FalseNoneNoneFalseNoneFalse303987.6938880
3995251154595None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10367.1410367.1468.0002FalseNoneNoneFalseNoneFalse704967.5934280
3995252154595None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor For Lintel Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11058.2811058.287.719FalseNoneNoneFalseNoneFalse85358.863320
3995253154595None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor For Staircase ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10367.1410367.144.0431FalseNoneNoneFalseNoneFalse41915.3837340
3995254154595None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor For Columns ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11865.7611865.761.3041FalseNoneNoneFalseNoneFalse15474.1376160
3995255154595None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11167.7711167.771.3248FalseNoneNoneFalseNoneFalse14795.0616960
3995256154595None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10469.7910469.793.0195FalseNoneNoneFalseNoneFalse31613.5309050
3995257154595None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10780.2710780.275.0FalseNoneNoneFalseNoneFalse53901.350
3995258154595None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t89457.089457.025.123FalseNoneNoneFalseNoneFalse2247428.2110
3995259154595None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t90351.5790351.5711.1348FalseNoneNoneFalseNoneFalse1006046.6616360
3995260154595None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t91246.1491246.141.1617FalseNoneNoneFalseNoneFalse106000.6408380
3995261154595None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1310.01310.0661.0FalseNoneNoneFalseNoneFalse865910.00
3995262154595None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1323.11323.1784.0FalseNoneNoneFalseNoneFalse1037310.40
3995263154595None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1336.21336.2169.0FalseNoneNoneFalseNoneFalse225817.80
3995264154595None6.34Providing and constructing load bearing wall with Solid Concrete blocks of size 400x100x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1104.01104.04.0FalseNoneNoneFalseNoneFalse4416.00
3995265154595None6.34Providing and constructing load bearing wall with Solid Concrete blocks of size 400x100x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1115.041115.042.0FalseNoneNoneFalseNoneFalse2230.080
3995266154595None12.13.1Providing Salwood frames of doors, windows, clerestory windows, ventilators and other frames, wrought, framed or assembled including making plaster groves (excluding cost of cement concrete and side clamps), but including cost of materials, labour, usage charges complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum98815.098815.00.9FalseNoneNoneFalseNoneFalse88933.50
3995267154595None12.13.1Providing Salwood frames of doors, windows, clerestory windows, ventilators and other frames, wrought, framed or assembled including making plaster groves (excluding cost of cement concrete and side clamps), but including cost of materials, labour, usage charges complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum99803.1599803.151.0FalseNoneNoneFalseNoneFalse99803.150
3995268154595None12.57.3Providing and fixing flush door shutter made out of solid core block board type, well seasoned , chemicaly treated hard wood battens and internal frame with minimum 45 mm wide wooden frame alround door shutters covered with cross bonded wooden sheets (core veneer) hot pressed and fastened on both sides of the door useing liquid phenol formaldehyde resin as per IS specifications 2202 (part-I) 1991. from manufacturer complete as per spcification.-do- 30 mm thick both side commercial Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3005.03005.034.1FalseNoneNoneFalseNoneFalse102470.50
3995269154595None12.57.3Providing and fixing flush door shutter made out of solid core block board type, well seasoned , chemicaly treated hard wood battens and internal frame with minimum 45 mm wide wooden frame alround door shutters covered with cross bonded wooden sheets (core veneer) hot pressed and fastened on both sides of the door useing liquid phenol formaldehyde resin as per IS specifications 2202 (part-I) 1991. from manufacturer complete as per spcification.-do- 30 mm thick both side commercial First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3035.053035.0534.1FalseNoneNoneFalseNoneFalse103495.2050
3995270154595None12.51Fixing of door frame in an existing opening including embedding frame in floor and walls after cutting masonry for holdfasts for embedding holdfast in cement concrete 1:3:6 of 20mm and down size granite metal painting two coats of coal tar to sides of frame, making good the damages to walls and floor as required and disposal of the debris with lead upto 50 m. including cost of materials, labour charges, complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1016.01016.016.0FalseNoneNoneFalseNoneFalse16256.00
3995271154595None12.51Fixing of door frame in an existing opening including embedding frame in floor and walls after cutting masonry for holdfasts for embedding holdfast in cement concrete 1:3:6 of 20mm and down size granite metal painting two coats of coal tar to sides of frame, making good the damages to walls and floor as required and disposal of the debris with lead upto 50 m. including cost of materials, labour charges, complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1026.161026.1616.0FalseNoneNoneFalseNoneFalse16418.560
3995272154595None12.93.1Providing and fixing factory made single extruded WPC (Wood Polymer Composite) solid door/window/Clerestory windows & other Frames/ Chowkhat comprising of virgin PVC polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibres (wood powder/rice husk/ wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) fabricated with miter joints after applying PVC solvent cement and screwed with full body threaded star headed SS screws having minimum frame density of 850 kg/m3, screw withdrawal strength of 2200 N (Face) & 1100 N (Edge), minimum compressive strength of 58 N/mm2 , modulus of elasticity 900 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixed in position with M.S hold fast/lugs/SS dash fasteners of required dia and length complete as per direction of Engineer-InCharge. (Fixtures shall be paid for separately) Size 62 x 100mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr702.0702.042.0FalseNoneNoneFalseNoneFalse29484.00
3995273154595None12.93.1Providing and fixing factory made single extruded WPC (Wood Polymer Composite) solid door/window/Clerestory windows & other Frames/ Chowkhat comprising of virgin PVC polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibres (wood powder/rice husk/ wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) fabricated with miter joints after applying PVC solvent cement and screwed with full body threaded star headed SS screws having minimum frame density of 850 kg/m3, screw withdrawal strength of 2200 N (Face) & 1100 N (Edge), minimum compressive strength of 58 N/mm2 , modulus of elasticity 900 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixed in position with M.S hold fast/lugs/SS dash fasteners of required dia and length complete as per direction of Engineer-InCharge. (Fixtures shall be paid for separately) Size 62 x 100mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr709.02709.0247.4FalseNoneNoneFalseNoneFalse33607.5480
3995274154595None12.94.1Providing and fixing factory made Green certified, Anti Termite, UV resistant, high water absorbant single extruded WPC (Wood PolymerComposite) solid plain flush door shutter of required size comprising of virgin polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibers (wood powder/rice husk/wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) having minimum density of 650 kg/m3 and screw withdrawal strength of 1800 N (Face) & 900 N (Edge), minimum compressive strength of 50 N/mm2 , modulus of elasticity 850 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixing with stainless steel butt hinges of required size with necessary full body threaded star headed counter sunk S.S screws The cost includes cost of materials, transportation, labour and fixing charges.(Cost of Fixtures to be paid separately) 30 mm thickness Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3485.03485.012.6FalseNoneNoneFalseNoneFalse43911.00
3995275154595None12.94.1Providing and fixing factory made Green certified, Anti Termite, UV resistant, high water absorbant single extruded WPC (Wood PolymerComposite) solid plain flush door shutter of required size comprising of virgin polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibers (wood powder/rice husk/wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) having minimum density of 650 kg/m3 and screw withdrawal strength of 1800 N (Face) & 900 N (Edge), minimum compressive strength of 50 N/mm2 , modulus of elasticity 850 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixing with stainless steel butt hinges of required size with necessary full body threaded star headed counter sunk S.S screws The cost includes cost of materials, transportation, labour and fixing charges.(Cost of Fixtures to be paid separately) 30 mm thickness First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3519.853519.8514.5FalseNoneNoneFalseNoneFalse51037.8250
3995276154595None12.9Providing & fixing of 3-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having an overall size of 108mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm x 75mm with GI reinforcement of 2mm and mesh sash of size 37mm x 58mm. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24 mm. Windows shall be provided with 6mm plain float glass, standard hardware& Multi point locking system with touch lock. Wall thickness of frame & sash shall be of 2mm-2.5mm. Maximum possible size 2419mm x 2200mm. (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm6734.06734.039.0FalseNoneNoneFalseNoneFalse262626.00
3995277154595None12.9Providing & fixing of 3-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having an overall size of 108mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm x 75mm with GI reinforcement of 2mm and mesh sash of size 37mm x 58mm. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24 mm. Windows shall be provided with 6mm plain float glass, standard hardware& Multi point locking system with touch lock. Wall thickness of frame & sash shall be of 2mm-2.5mm. Maximum possible size 2419mm x 2200mm. (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm6801.346801.3439.0FalseNoneNoneFalseNoneFalse265252.260
3995278154595None12.9Providing & fixing of 3-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having an overall size of 108mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm x 75mm with GI reinforcement of 2mm and mesh sash of size 37mm x 58mm. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24 mm. Windows shall be provided with 6mm plain float glass, standard hardware& Multi point locking system with touch lock. Wall thickness of frame & sash shall be of 2mm-2.5mm. Maximum possible size 2419mm x 2200mm. (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm6868.686868.683.0FalseNoneNoneFalseNoneFalse20606.040
3995279154595None12.85Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5719.05719.03.0FalseNoneNoneFalseNoneFalse17157.00
3995280154595None12.85Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5776.195776.193.0FalseNoneNoneFalseNoneFalse17328.570
3995281154595None12.85Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5833.385833.381.0FalseNoneNoneFalseNoneFalse5833.380
3995282154595None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs183.0183.0659.0FalseNoneNoneFalseNoneFalse120597.00
3995283154595None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs184.83184.83659.0FalseNoneNoneFalseNoneFalse121802.970
3995284154595None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs186.66186.6642.0FalseNoneNoneFalseNoneFalse7839.720
3995285154595None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2852.02852.080.0FalseNoneNoneFalseNoneFalse228160.00
3995286154595None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2880.522880.5277.0FalseNoneNoneFalseNoneFalse221800.040
3995287154595None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2909.042909.045.0FalseNoneNoneFalseNoneFalse14545.20
3995288154595None9.17.2Providing and laying Vitrified tiles in different sizes (thickness to be specified by manufacturer), with water absorption less than 0.08 % and conforming to I.S. 15622, of approved make, in all colours & shade, over 12 mm thick bed of cement mortar 1:3 (1 cement: 3 coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including grouting the joint with white cement & matching pigments etc. complete. Size of Tile 600x600 mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1175.01175.0308.0FalseNoneNoneFalseNoneFalse361900.00
3995289154595None9.17.2Providing and laying Vitrified tiles in different sizes (thickness to be specified by manufacturer), with water absorption less than 0.08 % and conforming to I.S. 15622, of approved make, in all colours & shade, over 12 mm thick bed of cement mortar 1:3 (1 cement: 3 coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including grouting the joint with white cement & matching pigments etc. complete. Size of Tile 600x600 mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1186.751186.75308.0FalseNoneNoneFalseNoneFalse365519.00
3995290154595None10.1.2Providing and fixing 18 mm thick gang saw cut granite of any color and shade, mirror polished, premoulded and prepolished, machine cut for kitchen platforms, vanity counters, window sills, facias and similar locations of required size, approved shade, colour and texture laid over 20 mm thick base cement mortar 1:4 (1 cement : 4 coarse sand), joints treated with white cement, mixed with matching pigment, epoxy touch up, including rubbing, curing, moulding and polishing to edges to give high gloss finish etc. complete at all levels. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3937.03937.013.0FalseNoneNoneFalseNoneFalse51181.00
3995291154595None10.1.2Providing and fixing 18 mm thick gang saw cut granite of any color and shade, mirror polished, premoulded and prepolished, machine cut for kitchen platforms, vanity counters, window sills, facias and similar locations of required size, approved shade, colour and texture laid over 20 mm thick base cement mortar 1:4 (1 cement : 4 coarse sand), joints treated with white cement, mixed with matching pigment, epoxy touch up, including rubbing, curing, moulding and polishing to edges to give high gloss finish etc. complete at all levels. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3976.373976.3713.0FalseNoneNoneFalseNoneFalse51692.810
3995292154595None9.11Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved make, in all colours, shades, except White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick bed of cement mortar 1:4 (1 Cement : 4 Coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including pointing the joints with white cement and matching pigments etc., complete. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm889.0889.044.0FalseNoneNoneFalseNoneFalse39116.00
3995293154595None9.11Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved make, in all colours, shades, except White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick bed of cement mortar 1:4 (1 Cement : 4 Coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including pointing the joints with white cement and matching pigments etc., complete. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm897.89897.8944.0FalseNoneNoneFalseNoneFalse39507.160
3995294154595None9.39Providing skirting, dadooing, rises of steps with colour glazed tiles 6mm thick on 10mm thick cement plaster 1:3 and jointed with white cement slurry over existing rough plaster surface using glazed tiles of approved make and size including cost of materials, labour, complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1449.01449.0173.0FalseNoneNoneFalseNoneFalse250677.00
3995295154595None9.39Providing skirting, dadooing, rises of steps with colour glazed tiles 6mm thick on 10mm thick cement plaster 1:3 and jointed with white cement slurry over existing rough plaster surface using glazed tiles of approved make and size including cost of materials, labour, complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1463.491463.49172.0FalseNoneNoneFalseNoneFalse251720.280
3995296154595None10.2Providing edge moulding to 18mm thick Granite stone counters, vanities etc including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr328.0328.064.0FalseNoneNoneFalseNoneFalse20992.00
3995297154595None10.2Providing edge moulding to 18mm thick Granite stone counters, vanities etc including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr331.28331.2857.0FalseNoneNoneFalseNoneFalse18882.960
3995298154595None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm295.0295.01030.0FalseNoneNoneFalseNoneFalse303850.00
3995299154595None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm297.95297.951062.0FalseNoneNoneFalseNoneFalse316422.90
3995300154595None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm300.9300.974.0FalseNoneNoneFalseNoneFalse22266.60
3995301154595None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm371.0371.0491.0FalseNoneNoneFalseNoneFalse182161.00
3995302154595None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm374.71374.71489.0FalseNoneNoneFalseNoneFalse183233.190
3995303154595None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm378.42378.42358.0FalseNoneNoneFalseNoneFalse135474.360
3995304154595None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg64.064.074.0FalseNoneNoneFalseNoneFalse4736.00
3995305154595None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg64.6464.6474.0FalseNoneNoneFalseNoneFalse4783.360
3995306154595None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg65.2865.2853.7FalseNoneNoneFalseNoneFalse3505.5360
3995307154595None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm295.0295.0180.0FalseNoneNoneFalseNoneFalse53100.00
3995308154595None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm297.95297.95179.0FalseNoneNoneFalseNoneFalse53333.050
3995309154595None8.16 aProviding lath plaster with cement mortar 1:3, 5cms thick with 6mm dia mild steel bars at 20 cms. c to c both horizontally and vertically fixing chicken mesh for drop chajja, facia, backing to cup boards including cost of all materials, labour, providing and removing form work usage charges, curing complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1238.01238.032.0FalseNoneNoneFalseNoneFalse39616.00
3995310154595None8.16 aProviding lath plaster with cement mortar 1:3, 5cms thick with 6mm dia mild steel bars at 20 cms. c to c both horizontally and vertically fixing chicken mesh for drop chajja, facia, backing to cup boards including cost of all materials, labour, providing and removing form work usage charges, curing complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1250.381250.3832.0FalseNoneNoneFalseNoneFalse40012.160
3995311154595None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm100.0100.01483.335FalseNoneNoneFalseNoneFalse148333.50
3995312154595None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. First floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm101.0101.01515.335FalseNoneNoneFalseNoneFalse153048.8350
3995313154595None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm102.0102.094.13FalseNoneNoneFalseNoneFalse9601.260
3995314154595None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm110.0110.01483.335FalseNoneNoneFalseNoneFalse163166.850
3995315154595None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. First floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm111.1111.11515.335FalseNoneNoneFalseNoneFalse168353.71850
3995316154595None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm112.2112.294.13FalseNoneNoneFalseNoneFalse10561.3860
3995317154595None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.053.01483.335FalseNoneNoneFalseNoneFalse78616.7550
3995318154595None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.5353.531515.335FalseNoneNoneFalseNoneFalse81115.882550
3995319154595None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm54.0654.0694.13FalseNoneNoneFalseNoneFalse5088.66780
3995320154595None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm174.0174.0491.0FalseNoneNoneFalseNoneFalse85434.00
3995321154595None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm175.74175.74489.0FalseNoneNoneFalseNoneFalse85936.860
3995322154595None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm177.48177.48358.0FalseNoneNoneFalseNoneFalse63537.840
3995323154595None8.34.1Applying priming coat: With ready mixed pink or Grey primer of approved brand and manufacture on wood work (hard and soft wood) including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.053.082.0FalseNoneNoneFalseNoneFalse4346.00
3995324154595None8.34.1Applying priming coat: With ready mixed pink or Grey primer of approved brand and manufacture on wood work (hard and soft wood) including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.5353.5382.0FalseNoneNoneFalseNoneFalse4389.460
3995325154595None8.33.2Painting wood work with Deluxe Multi Surface Paint of required shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @0.75 L/10 m² of approved brand and manufacture to give an even shade including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, sand papering and knotting , cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm138.0138.082.0FalseNoneNoneFalseNoneFalse11316.00
3995326154595None8.33.2Painting wood work with Deluxe Multi Surface Paint of required shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @0.75 L/10 m² of approved brand and manufacture to give an even shade including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, sand papering and knotting , cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm139.38139.3882.0FalseNoneNoneFalseNoneFalse11429.160
3995327154595None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @ 0.80 L/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm139.0139.042.0FalseNoneNoneFalseNoneFalse5838.00
3995328154595None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @ 0.80 L/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm140.39140.3942.0FalseNoneNoneFalseNoneFalse5896.380
3995329154595None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @ 0.80 L/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm141.78141.783.0FalseNoneNoneFalseNoneFalse425.340
3995330154595None11.28Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners, stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in- charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.) including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs565.0565.0105.0FalseNoneNoneFalseNoneFalse59325.00
3995331154595None11.28Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners, stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in- charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.) including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs570.65570.65107.0FalseNoneNoneFalseNoneFalse61059.550
3995332154595None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr66.066.0300.0FalseNoneNoneFalseNoneFalse19800.00
3995333154595None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr66.6666.66300.0FalseNoneNoneFalseNoneFalse19998.00
3995334154595None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr67.3267.3241.0FalseNoneNoneFalseNoneFalse2760.120
3995335154595None15.1Polyurethane based Single Component for New Surface Providing and laying water proofing treatment to the Roof with PU based single component elastomeric pure polyurethane based coating on New terrace/Chajjas/Sunken portion of WC:Bathroom, cold applied PU waterproofing membrane that is highly elastic with elongation greater than 400% and tensile strength greater than 2MPa as per ASTM D412. The waterproofing membrane to be applied in 2coats @ 1.6 kg/m2 to achieve final DFT (Dry Film Thickness) of 1mm including prime coat of epoxy primer @150 g/m2 and protection with 120gsm Geo-textile over the waterproofing membrane. The finished cost to include surface preparation, making coving at Junction, Bore Packing, treatment of construction joints completely as per specification. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm833.34833.34327.0FalseNoneNoneFalseNoneFalse272502.180
3995336154595None7.18Providing and laying cinder concrete in cement 1:15 ( 1 cement : 15 cinder of 12.5mm nominal gauge) on terraced roof or sunken slabs, laid to slope compacting, including cost of materials, labour, curing complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum2037.172037.174.0FalseNoneNoneFalseNoneFalse8148.680
3995337154595None15.7Integral Crystalline Water Proofing Admixture Providing and supplying crystalline integral concrete waterproofing admixture that waterproofs concrete by forming crystals deep in the pores, capillaries and microcracks of the concrete, self-seal waterproofing compound to bridge shrinkage cracks upto 0.5mm in width & resist hydro-static pressure upto 16bar for both positive & negative pressure confirming to DIN 1048 part 5 for 56% reduction in depth of penetration against control, resistance to chloride penetration confirming to ASTM C 1202 with 64% improvement against control & protecting steel reinforcement against corrosion mixed @ 1% by weight of cementitious content in concrete. ie., integral crystaline waterproofing admix @ 0.5 kg/bag of cement. (For calculation purpose 320 kg of Cement for M-20 grade of Concrete is considered in the analysis) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm621.15621.1516.0FalseNoneNoneFalseNoneFalse9938.40
3995338154595None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9613.59613.51.9273FalseNoneNoneFalseNoneFalse18528.098550
3995339154595None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9679.89679.83.1153FalseNoneNoneFalseNoneFalse30155.480940
3995340154595None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9746.19746.132.7675FalseNoneNoneFalseNoneFalse319355.331750
3995341154595NoneVOL - 5 7.1.1Providing and fixing MS ladder between landings, 45 cms wide using angle iron of specified sizes, 20mm MS bars at 25 cms. centre to centre, with necessary supports of same angle iron etc. as directed, including hand railing on both sides with 25mm dia. GI pipes with angle iron props at 2 mtrs. intervals and 0.5M heigh, including fixing in ground with CC 1:2:4 and two coats of anticorrosive bituminous paint etc. with all lead and lifts etc. complete with: MS angle of 65 x 65 x 8mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr4464.544464.543.5FalseNoneNoneFalseNoneFalse15625.890
3995342154595None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.038.0193.8FalseNoneNoneFalseNoneFalse7364.40
3995343154595None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.3838.38193.8FalseNoneNoneFalseNoneFalse7438.0440
3995344154595None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.7638.7610.2FalseNoneNoneFalseNoneFalse395.3520
3995345154595None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.038.0206.25FalseNoneNoneFalseNoneFalse7837.50
3995346154595None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.3838.38206.25FalseNoneNoneFalseNoneFalse7915.8750
3995347154595None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.7638.7615.11FalseNoneNoneFalseNoneFalse585.66360
3995348154595None22.15.7Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Tower Bolts 250x10mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos200.0200.048.0FalseNoneNoneFalseNoneFalse9600.00
3995349154595None22.15.7Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Tower Bolts 250x10mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos202.0202.050.0FalseNoneNoneFalseNoneFalse10100.00
3995350154595None22.15.8Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS hinges 125 mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos50.050.088.0FalseNoneNoneFalseNoneFalse4400.00
3995351154595None22.15.8Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS hinges 125 mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos50.550.591.0FalseNoneNoneFalseNoneFalse4595.50
3995352154595None22.15.1Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Handles 200mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos450.0450.048.0FalseNoneNoneFalseNoneFalse21600.00
3995353154595None22.15.1Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Handles 200mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos454.5454.550.0FalseNoneNoneFalseNoneFalse22725.00
3995354154595None22.15.4Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Aldrop 16mm dia, 300mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos375.0375.024.0FalseNoneNoneFalseNoneFalse9000.00
3995355154595None22.15.4Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Aldrop 16mm dia, 300mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos378.75378.7525.0FalseNoneNoneFalseNoneFalse9468.750
3995356154595None22.15.10Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Door stopper 75mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos100.0100.021.0FalseNoneNoneFalseNoneFalse2100.00
3995357154595None22.15.10Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Door stopper 75mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos101.0101.016.0FalseNoneNoneFalseNoneFalse1616.00
17262057300001NoneNoneBuildingsStage Cum Auditorium (Amble)9494474.86
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3995358154596NoneVOL - 3, C - 2 2.1 a (i) MoRT&H 201Cutting of Trees, excluding removal of stumps and roots of trees. (i) Girth from 300 mm to 600 mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each595.0595.0150.0FalseNoneNoneFalseNoneFalse89250.00
3995359154596NoneVOL - 3, C - 2 2.2 b (i) MoRT&H 201Removal of stumps and roots including backfilling with suitable material to required compaction (i) Girth from 300 mm to 600 mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each356.0356.0150.0FalseNoneNoneFalseNoneFalse53400.00
3995360154596None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.045.1415FalseNoneNoneFalseNoneFalse4604.4330
3995361154596None1.15.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In ordinary/soft rock without blasting upto 1.5 m depth ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum363.0363.0180.5661FalseNoneNoneFalseNoneFalse65545.49430
3995362154596None1.9Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum266.0266.02194.6967FalseNoneNoneFalseNoneFalse583789.32220
3995363154596None4.1Providing and injecting chemical emulsion for Pre-constructional Anti-Termite Treatment, creating continuous chemical barrier under and around the column pits, walls, trenches, basement excavation, top surface of the plinth filling, junction of wall and floor, along the external perimeter of building, expansion joints, over the top surface of consolidated earth on which apron is to be laid, surrounding of pipes and conduits with Chlorpyriphos 20% E.C. / Lindane 20% E.C. @ 3.19 l/m2 including cost of chemical, diluting in water to one percent concentration, labour, usage charges of machinery, complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm118.0118.0468.0FalseNoneNoneFalseNoneFalse55224.00
3995364154596None2.1.3Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5989.05989.073.1256FalseNoneNoneFalseNoneFalse437949.21840
3995365154596None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6217.06217.08.5017FalseNoneNoneFalseNoneFalse52855.06890
3995366154596None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor Footing concrete ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6842.886842.8842.9675FalseNoneNoneFalseNoneFalse294021.44640
3995367154596None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Pedastals ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10771.210771.24.5322FalseNoneNoneFalseNoneFalse48817.232640
3995368154596None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Columns Concrete Upto PB ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10771.210771.26.1113FalseNoneNoneFalseNoneFalse65826.034560
3995369154596None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Plinth Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9504.09504.02.8669FalseNoneNoneFalseNoneFalse27247.01760
3995370154596None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Grade Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9504.09504.027.1929FalseNoneNoneFalseNoneFalse258441.32160
3995371154596None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Columns Concrete Up to Roof ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11633.111633.112.1785FalseNoneNoneFalseNoneFalse141673.708350
3995372154596None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10948.810948.86.9759FalseNoneNoneFalseNoneFalse76377.733920
3995373154596None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10264.510264.58.45FalseNoneNoneFalseNoneFalse86735.0250
3995374154596None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Lintel Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10948.810948.810.26FalseNoneNoneFalseNoneFalse112334.6880
3995375154596None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9613.59613.52.0FalseNoneNoneFalseNoneFalse19227.00
3995376154596None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t89457.089457.012.4456FalseNoneNoneFalseNoneFalse1113346.03920
3995377154596None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1310.01310.0323.0FalseNoneNoneFalseNoneFalse423130.00
3995378154596None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1323.11323.139.0FalseNoneNoneFalseNoneFalse51600.90
3995379154596None6.34Providing and constructing load bearing wall with Solid Concrete blocks of size 400x100x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1104.01104.041.0FalseNoneNoneFalseNoneFalse45264.00
3995380154596None12.13.1Providing Salwood frames of doors, windows, clerestory windows, ventilators and other frames, wrought, framed or assembled including making plaster groves (excluding cost of cement concrete and side clamps), but including cost of materials, labour, usage charges complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum98815.098815.00.4FalseNoneNoneFalseNoneFalse39526.00
3995381154596None12.57.3Providing and fixing flush door shutter made out of solid core block board type, well seasoned , chemicaly treated hard wood battens and internal frame with minimum 45 mm wide wooden frame alround door shutters covered with cross bonded wooden sheets (core veneer) hot pressed and fastened on both sides of the door useing liquid phenol formaldehyde resin as per IS specifications 2202 (part-I) 1991. from manufacturer complete as per spcification.-do- 30 mm thick both side commercial ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3005.03005.012.0FalseNoneNoneFalseNoneFalse36060.00
3995382154596None12.51Fixing of door frame in an existing opening including embedding frame in floor and walls after cutting masonry for holdfasts for embedding holdfast in cement concrete 1:3:6 of 20mm and down size granite metal painting two coats of coal tar to sides of frame, making good the damages to walls and floor as required and disposal of the debris with lead upto 50 m. including cost of materials, labour charges, complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1016.01016.08.0FalseNoneNoneFalseNoneFalse8128.00
3995383154596None12.94.1Providing and fixing factory made Green certified, Anti Termite, UV resistant, high water absorbant single extruded WPC (Wood PolymerComposite) solid plain flush door shutter of required size comprising of virgin polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibers (wood powder/rice husk/wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) having minimum density of 650 kg/m3 and screw withdrawal strength of 1800 N (Face) & 900 N (Edge), minimum compressive strength of 50 N/mm2 , modulus of elasticity 850 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixing with stainless steel butt hinges of required size with necessary full body threaded star headed counter sunk S.S screws The cost includes cost of materials, transportation, labour and fixing charges.(Cost of Fixtures to be paid separately) 30 mm thickness ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3485.03485.019.0FalseNoneNoneFalseNoneFalse66215.00
3995384154596None12.93.1Providing and fixing factory made single extruded WPC (Wood Polymer Composite) solid door/window/Clerestory windows & other Frames/ Chowkhat comprising of virgin PVC polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibres (wood powder/rice husk/ wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) fabricated with miter joints after applying PVC solvent cement and screwed with full body threaded star headed SS screws having minimum frame density of 850 kg/m3, screw withdrawal strength of 2200 N (Face) & 1100 N (Edge), minimum compressive strength of 58 N/mm2 , modulus of elasticity 900 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixed in position with M.S hold fast/lugs/SS dash fasteners of required dia and length complete as per direction of Engineer-InCharge. (Fixtures shall be paid for separately) Size 62 x 100mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr702.0702.063.0FalseNoneNoneFalseNoneFalse44226.00
3995385154596None12.88Providing & fixing of 2-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having a overall size of 60mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm X 58mm with GI reinforcement of 1mm for the frame and 1.5 mm for the sash. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24mm. Windows shall be provided with 5mm plain float glass, standard hardware& single point locking system with touch lock. Wall thickness of frame & sash shall be of 2-2.5 mm. Maximum possible size 1819mm x 1819mm (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5390.05390.051.0FalseNoneNoneFalseNoneFalse274890.00
3995386154596None12.85Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5719.05719.03.0FalseNoneNoneFalseNoneFalse17157.00
3995387154596None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs183.0183.0972.0FalseNoneNoneFalseNoneFalse177876.00
3995388154596None9.17.2Providing and laying Vitrified tiles in different sizes (thickness to be specified by manufacturer), with water absorption less than 0.08 % and conforming to I.S. 15622, of approved make, in all colours & shade, over 12 mm thick bed of cement mortar 1:3 (1 cement: 3 coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including grouting the joint with white cement & matching pigments etc. complete. Size of Tile 600x600 mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1175.01175.021.0FalseNoneNoneFalseNoneFalse24675.00
3995389154596None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2852.02852.0492.186FalseNoneNoneFalseNoneFalse1403714.4720
3995390154596None9.11Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved make, in all colours, shades, except White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick bed of cement mortar 1:4 (1 Cement : 4 Coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including pointing the joints with white cement and matching pigments etc., complete. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm889.0889.035.0FalseNoneNoneFalseNoneFalse31115.00
3995391154596None9.39Providing skirting, dadooing, rises of steps with colour glazed tiles 6mm thick on 10mm thick cement plaster 1:3 and jointed with white cement slurry over existing rough plaster surface using glazed tiles of approved make and size including cost of materials, labour, complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1449.01449.0121.0FalseNoneNoneFalseNoneFalse175329.00
3995392154596None10.2Providing edge moulding to 18mm thick Granite stone counters, vanities etc including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr328.0328.011.0FalseNoneNoneFalseNoneFalse3608.00
3995393154596None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm295.0295.0446.0FalseNoneNoneFalseNoneFalse131570.00
3995394154596None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm371.0371.0589.0FalseNoneNoneFalseNoneFalse218519.00
3995395154596None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg64.064.089.0FalseNoneNoneFalseNoneFalse5696.00
3995396154596None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm295.0295.0126.0FalseNoneNoneFalseNoneFalse37170.00
3995397154596None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm100.0100.0513.6FalseNoneNoneFalseNoneFalse51360.00
3995398154596None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm110.0110.0513.6FalseNoneNoneFalseNoneFalse56496.00
3995399154596None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.053.0513.6FalseNoneNoneFalseNoneFalse27220.80
3995400154596None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm174.0174.0589.0FalseNoneNoneFalseNoneFalse102486.00
3995401154596None8.34.1Applying priming coat: With ready mixed pink or Grey primer of approved brand and manufacture on wood work (hard and soft wood) including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.053.028.0FalseNoneNoneFalseNoneFalse1484.00
3995402154596None8.33.2Painting wood work with Deluxe Multi Surface Paint of required shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @0.75 L/10 m² of approved brand and manufacture to give an even shade including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, sand papering and knotting , cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm138.0138.028.0FalseNoneNoneFalseNoneFalse3864.00
3995403154596None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @ 0.80 L/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm139.0139.054.0FalseNoneNoneFalseNoneFalse7506.00
3995404154596None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr66.066.0100.0FalseNoneNoneFalseNoneFalse6600.00
3995405154596None15.1Polyurethane based Single Component for New Surface Providing and laying water proofing treatment to the Roof with PU based single component elastomeric pure polyurethane based coating on New terrace/Chajjas/Sunken portion of WC:Bathroom, cold applied PU waterproofing membrane that is highly elastic with elongation greater than 400% and tensile strength greater than 2MPa as per ASTM D412. The waterproofing membrane to be applied in 2coats @ 1.6 kg/m2 to achieve final DFT (Dry Film Thickness) of 1mm including prime coat of epoxy primer @150 g/m2 and protection with 120gsm Geo-textile over the waterproofing membrane. The finished cost to include surface preparation, making coving at Junction, Bore Packing, treatment of construction joints completely as per specification. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm833.34833.34473.0FalseNoneNoneFalseNoneFalse394169.820
3995406154596NoneVOL -5 7.1.1Providing and fixing MS ladder between landings, 45 cms wide using angle iron of specified sizes, 20mm MS bars at 25 cms. centre to centre, with necessary supports of same angle iron etc. as directed, including hand railing on both sides with 25mm dia. GI pipes with angle iron props at 2 mtrs. intervals and 0.5M heigh, including fixing in ground with CC 1:2:4 and two coats of anticorrosive bituminous paint etc. with all lead and lifts etc. complete with: MS angle of 65 x 65 x 8mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr4420.774420.774.0FalseNoneNoneFalseNoneFalse17683.080
3995407154596NoneVOL -5, 10.14.11Providing and installing at site of work P.V.C. pipes including cost of pipes and specials and labour, including lowering into trenches, laying true to line, level and perfect linking at joints leak proof including jointing of approved type with all labour charges and all lift charges, handling charges including encasing the pipe around to a depth not less than 15 cms with gravel or selected earth available from the excavation etc. complete. 6 Kg/m2: 110mm(weight of pipe -1.894 kg) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m358.0358.020.0FalseNoneNoneFalseNoneFalse7160.00
3995408154596None11.16.1Providing and fixing Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete. Hot finished welded type tubes including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs136.0136.011000.0FalseNoneNoneFalseNoneFalse1496000.00
3995409154596None7.38Providing and fixing precoated galvanised iron profile sheets (size, shape and pitch of corrugation as approved by Engineer-in-charge) 0.50 mm (+ 0.05 %) total coated thickness with zinc coating 120 grams per m2 as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns. Sheet should have protective guard film of 25 microns minimum to avoid scratches during transportation and should be supplied in single length upto 12 m or as desired by Engineer-in-charge. The sheet shall be fixed using self drilling/self tapping screws of size (5.5x 55 mm) with EPDM seal, complete upto any pitch in horizontal/ vertical or curved surfaces, excluding the cost of purlins, rafters and trusses and including cutting to size and shape wherever required. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm568.0568.0765.0FalseNoneNoneFalseNoneFalse434520.00
3995410154596None7.4.1Providing & fixing ridges or hips of width 60 cm overall width plain G.S. sheet fixed with polymer coated J or L hooks, bolts and nuts 8 mm dia G.I. limpet and bitumen washers complete as per design drawings. 0.63 mm thick with zinc coating not less than 275 g/m² ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m639.0639.029.0FalseNoneNoneFalseNoneFalse18531.00
3995411154596None7.6Providing and fixing 15 cm wide, 45 cm overall semi-circular plain G.S. sheet gutter with iron brackets 40x3mm size, bolts, nuts and washers etc., including making necessary connections with rain water pipes complete. (0.63 mm thick with zinc coating not less than 275 g/m²) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m645.0645.058.0FalseNoneNoneFalseNoneFalse37410.00
3995412154596None22.15.7Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Tower Bolts 250x10mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos200.0200.018.0FalseNoneNoneFalseNoneFalse3600.00
3995413154596None22.15.8Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS hinges 125 mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos50.050.054.0FalseNoneNoneFalseNoneFalse2700.00
3995414154596None22.15.1Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Handles 200mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos450.0450.036.0FalseNoneNoneFalseNoneFalse16200.00
3995415154596None22.15.4Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Aldrop 16mm dia, 300mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos375.0375.018.0FalseNoneNoneFalseNoneFalse6750.00
3995416154596None22.15.10Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Door stopper 75mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos100.0100.06.0FalseNoneNoneFalseNoneFalse600.00
17262057300000NoneNoneBuildingsInternal Water Supply Works (Amble)2033669.0
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3995417154597None13.32.3Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply, including all CPVC plain & brass threaded fittings, i/c fixing the pipe with clamps at 1.00 m spacing. This includes jointing of pipes & fittings with one step CPVC solvent cement and the cost of cutting chases and making good the same including testing of joints complete as per direction of Engineer in Charge. Concealed work, including cutting chases and making good the walls etc." ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m477.0477.0670.0FalseNoneNoneFalseNoneFalse319590.00
3995418154597None13.31.4Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply, including all CPVC plain & brass threaded fittings, i/c fixing the pipe with clamps at 1.00 m spacing. This includes jointing of pipes & fittings with one step CPVC solvent cement and the cost of cutting chases and making good the same including testing of joints complete as per direction of Engineer in Charge. Concealed work, including cutting chases and making good the walls etc." 32 mm nominal dia pipes ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m557.0557.071.0FalseNoneNoneFalseNoneFalse39547.00
3995419154597None10.14.2Providing and installing at site of work P.V.C. pipes including cost of pipes and specials and labour, including lowering into trenches, laying true to line, level and perfect linking at joints leak proof including jointing of approved type with all labour charges and all lift charges, handling charges including encasing the pipe around to a depth not less than 15 cms with gravel or selected earth available from the excavation etc. complete. " 75mm(weight of pipe -0.917 kg) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr161.0161.0251.0FalseNoneNoneFalseNoneFalse40411.00
3995420154597None10.14.4Providing and installing at site of work P.V.C. pipes including cost of pipes and specials and labour, including lowering into trenches, laying true to line, level and perfect linking at joints leak proof including jointing of approved type with all labour charges and all lift charges, handling charges including encasing the pipe around to a depth not less than 15 cms with gravel or selected earth available from the excavation etc. complete. " 110mm(weight of pipe -1.894 kg) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr282.0282.0322.0FalseNoneNoneFalseNoneFalse90804.00
3995421154597None14.74-aSANITARY FIXTURES "Providing and fixing Single lever Bib cock Long Nose (Lifting type cold water cartridge) with wall flange made of Stainless steel with all concealed fitting arrangements & all necessary accesories complete - Class" ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1250.01250.0172.0FalseNoneNoneFalseNoneFalse215000.00
3995422154597None14.67-aProviding and fixing Exposed set for concealed stop cock made of Stainless steel with all concealed fitting arrangements & all necessary accesories complete - Class" ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each602.0602.034.0FalseNoneNoneFalseNoneFalse20468.00
3995423154597None14.2.1Providing and fixing white vitreous china pedestal type water closet (European type W.C. pan) with seat and lid, 10 litre low level white P.V.C. flushing cistern, including flush pipe, with manually controlled device (handle lever), conforming to IS : 7231, with all fittings and fixtures complete, including cutting and making good the walls and floors wherever required :" W.C. pan with ISI marked white solid plastic seat and lid ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each4838.04838.027.0FalseNoneNoneFalseNoneFalse130626.00
3995424154597None14.1.1Providing and fixing water closet squatting pan (Indian type W.C. pan ) with 100 mm sand cast Iron P or S trap, 10 litre low level white P.V.C. flushing cistern, including flush pipe, with manually controlled device (handle lever) conforming to IS : 7231, with all fittings and fixtures complete, including cutting and making good the walls and floors wherever required: " "White Vitreous china Orissa pattern W.C. pan of size 580x440 mm with integral type foot rests" ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each4884.04884.079.0FalseNoneNoneFalseNoneFalse385836.00
3995425154597None13.6Providing and fixing PVC (S.W.R) P Trap 10cms x 10cms with all fitting arrangements & all necessary accessories complete ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each309.0309.024.0FalseNoneNoneFalseNoneFalse7416.00
3995426154597None14.4.1Providing and fixing white vitreous china flat back or wall corner type lipped front urinal basin of 430x260x350 mm and 340x410x265 mm sizes respectively with automatic flushing cistern with standard flush pipe and C.P. brass spreaders with brass unions and G.I clamps complete, including painting of fittings and brackets, cutting and making good the walls and floors wherever required :" One urinal basin with 5 litre white P.V.C. automatic flushing cistern ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each4884.04884.018.0FalseNoneNoneFalseNoneFalse87912.00
3995427154597None13.63Providing and fixing PVC (S.W.R) Multi Floor Trap 10.0 cm X 7.5 cm X 5.0 cm X 4.0 cm with all fitting arrangements & all necessary accessories complete" ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each244.0244.094.0FalseNoneNoneFalseNoneFalse22936.00
3995428154597None14.24Providing and fixing white vitreous china squatting plate urinal with integral rim longitudinal flush pipe." ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each2835.02835.06.0FalseNoneNoneFalseNoneFalse17010.00
3995429154597None14.7.1Providing and fixing wash basin with C.I. brackets, 15 mm C.P. brass pillar taps, 32 mm C.P. brass waste of standard pattern, including painting of fittings and brackets, cutting and making good the walls wherever require:" "White Vitreous China Wash basin size 630x450 mm with a pair of 15 mm C.P. brass pillar taps" ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Unit3082.03082.027.0FalseNoneNoneFalseNoneFalse83214.00
3995430154597None14.10.1Providing and fixing Stainless Steel A ISI 304 (18/8) kitchen sink as per IS:13983 with C.I. brackets and stainless steel plug 40 mm, including painting of fittings and brackets, cutting and making good the walls wherever required :" Kitchen sink with drain board ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos5618.05618.010.0FalseNoneNoneFalseNoneFalse56180.00
3995431154597None14.37.1Providing and fixing PTMT Bottle Trap for Wash basin and sink. "Bottle trap 31mm single piece moulded with height of 270 mm, effective length of tail pipe 260 mm from the centre of the waste coupling, 77 mm breadth with 25 mm minimum water seal, weighing not less than 260 g" ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos306.0306.044.0FalseNoneNoneFalseNoneFalse13464.00
3995432154597None14.48Providing and fixing Pillar Cock made of Stainless steel with all concealed fitting arrangements & all necessary accesories complete - Class" ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1223.01223.036.0FalseNoneNoneFalseNoneFalse44028.00
3995433154597None14.78Providing and fixing Single flow hand showers with Anti lime jets with 1.5m PVC tube and holder made of Stainless steel with all concealed fitting arrangements & all necessary accesories complete - Class" ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m887.0887.016.0FalseNoneNoneFalseNoneFalse14192.00
3995434154597None13.48RAIN WATER DISPOSAL SYSTEM "Providing and fixing on wall face unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion, (i) Single socketed pipes 100 mm diameter " M150Y:110mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m291.0291.0385.0FalseNoneNoneFalseNoneFalse112035.00
3995435154597None13.34AProviding and fixing rectangular high density polyethylene water storage loft tank with cover, conforming to ISI : 12701, colour of opaque white or as approved by Engineer-in-charge. The rate includes making necessary holes for inlet, outlet & over flow pipes. The base support i/c fittings & fixtures for tank shall be paid separately." ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Ltr9.09.017000.0FalseNoneNoneFalseNoneFalse153000.00
3995436154597None13.34AProviding and fixing rectangular high density polyethylene water storage loft tank with cover, conforming to ISI : 12701, colour of opaque white or as approved by Engineer-in-charge. The rate includes making necessary holes for inlet, outlet & over flow pipes. The base support i/c fittings & fixtures for tank shall be paid separately." ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Ltr9.09.020000.0FalseNoneNoneFalseNoneFalse180000.00
17262057300000NoneNoneBuildingsExternal Water Supply (Amble)574456.0
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3995437154598None1.6.1Earth work excavation for pipelines/cables by Manual means upto 600 mm trench width, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m. Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering and lift upto 1.5 m including cost of labour, tools, usage& other appurtenances required to complete the work. 1.6.1 In all kinds of soils. Depth upto" In all kinds of soils. Depth upto 1.50m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum242.0242.0510.0FalseNoneNoneFalseNoneFalse123420.00
3995438154598None1.10Refilling available earth around trenches/pipelines, cables in layers not exceeding 20 cm in depth, compacting each deposited layer by ramming after watering with a lead upto 50 m , and lift upto 1.5 m. Including cost of all labour complete as per specifications" Rate as per Item no 1.10 ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum160.0160.0390.0FalseNoneNoneFalseNoneFalse62400.00
3995439154598None13.50.1Providing and fixing Unplasticised Polyvinyl Chloride (uPVC) pipes, for cold water supply including all uPVC plain & brass threaded fittings This includes jointing of pipes & fittings with one step uPVC solvent cement, trenching, refilling & testing of joints complete as per direction of Engineer in Charge. External work External plumbing 32mm pipe outer dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr272.0272.010.0FalseNoneNoneFalseNoneFalse2720.00
3995440154598None13.50.2Providing and fixing Unplasticised Polyvinyl Chloride (uPVC) pipes, for cold water supply including all uPVC plain & brass threaded fittings This includes jointing of pipes & fittings with one step uPVC solvent cement, trenching, refilling & testing of joints complete as per direction of Engineer in Charge. External work External plumbing 40mm pipe outer dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr304.0304.025.0FalseNoneNoneFalseNoneFalse7600.00
3995441154598None13.50.3Providing and fixing Unplasticised Polyvinyl Chloride (uPVC) pipes, for cold water supply including all uPVC plain & brass threaded fittings This includes jointing of pipes & fittings with one step uPVC solvent cement, trenching, refilling & testing of joints complete as per direction of Engineer in Charge. External work External plumbing 50mm pipe outer dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr386.0386.0190.0FalseNoneNoneFalseNoneFalse73340.00
3995442154598None13.50.4Providing and fixing Unplasticised Polyvinyl Chloride (uPVC) pipes, for cold water supply including all uPVC plain & brass threaded fittings This includes jointing of pipes & fittings with one step uPVC solvent cement, trenching, refilling & testing of joints complete as per direction of Engineer in Charge. External work External plumbing 65 mm pipe outer dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr543.0543.0120.0FalseNoneNoneFalseNoneFalse65160.00
3995443154598None13.50.5Providing and fixing Unplasticised Polyvinyl Chloride (uPVC) pipes, for cold water supply including all uPVC plain & brass threaded fittings This includes jointing of pipes & fittings with one step uPVC solvent cement, trenching, refilling & testing of joints complete as per direction of Engineer in Charge. External work External plumbing 80 mm pipe outer dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr674.0674.0190.0FalseNoneNoneFalseNoneFalse128060.00
3995444154598None13.35KSRB13-6.3-6 -Providing and fixing in position brass gate valve with C.I wheel of approved quality ( screwed end ) nominal bore including cost of all materials, labour and HOM of equipments with all leads complete as per specifications. (external domestic water supply) 32 mm dia nominal ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos272.0272.05.0FalseNoneNoneFalseNoneFalse1360.00
3995445154598None13.36KSRB13-6.3-6 -Providing and fixing in position brass gate valve with C.I wheel of approved quality ( screwed end ) nominal bore including cost of all materials, labour and HOM of equipments with all leads complete as per specifications. (external domestic water supply) 40 mm dia nominal ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos304.0304.05.0FalseNoneNoneFalseNoneFalse1520.00
3995446154598None13.38KSRB13-6.3-6 -Providing and fixing in position brass gate valve with C.I wheel of approved quality ( screwed end ) nominal bore including cost of all materials, labour and HOM of equipments with all leads complete as per specifications. Specification (external irrigation ) 63 mm dia nominal ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos536.0536.020.0FalseNoneNoneFalseNoneFalse10720.00
3995447154598None13.39KSRB13-6.3-6 -Providing and fixing in position brass gate valve with C.I wheel of approved quality ( screwed end ) nominal bore including cost of all materials, labour and HOM of equipments with all leads complete as per specifications. Specification (external irrigation ) 80 mm dia nominal ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos781.0781.010.0FalseNoneNoneFalseNoneFalse7810.00
3995448154598None13.40KSRB13-6.3-6 -Providing and fixing in position brass gate valve with C.I wheel of approved quality ( screwed end ) nominal bore including cost of all materials, labour and HOM of equipments with all leads complete as per specifications. Specification (external irrigation ) 100 mm dia nominal ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1333.01333.02.0FalseNoneNoneFalseNoneFalse2666.00
3995449154598None13.67Providing and fixing to wall, ceiling and floor medium density polyethylene pipes 6.00 kgf/sq.cm working pressure outside diameter raising mains & exposed distribution pipes with special flange, compression type fittings, wall clips, making good the wall, ceiling and floor, including cost of all materials, labour charges, HOM of equipments and testing complete as per specifications. Specification No. KBS 13.2.15.1 / 13.9 Page No : 95, Item No :13.66 PWD SR 18-19 (FOR External domestic& Flushing water shaft , terrace piping ) 25 mm dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr224.0224.015.0FalseNoneNoneFalseNoneFalse3360.00
3995450154598None13.68Providing and fixing to wall, ceiling and floor medium density polyethylene pipes 6.00 kgf/sq.cm working pressure outside diameter raising mains & exposed distribution pipes with special flange, compression type fittings, wall clips, making good the wall, ceiling and floor, including cost of all materials, labour charges, HOM of equipments and testing complete as per specifications. Specification No. KBS 13.2.15.1 / 13.9 Page No : 95, Item No :13.66 PWD SR 18-19 (FOR External domestic& Flushing water shaft , terrace piping ) 32 mm dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr272.0272.0310.0FalseNoneNoneFalseNoneFalse84320.00
17262057300000NoneNoneBuildingsExternal Sewage (Amble)1412162.0
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3995451154599None1.6.1Earth work excavation for pipelines/cables by Manual means upto 600 mm trench width, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m. Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering and lift upto 1.5 m including cost of labour, tools, usage& other appurtenances required to complete the work. 1.6.1 In all kinds of soils. Depth upto" In all kinds of soils. Depth upto 1.50m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum242.0242.0440.0FalseNoneNoneFalseNoneFalse106480.00
3995452154599None2.4Refilling available earth around trenches/pipelines, cables in layers not exceeding 20 cm in depth, compacting each deposited layer by ramming after watering with a lead upto 50 m , and lift upto 1.5 m. Including cost of all labour complete as per specifications" Rate as per Item no 1.10 ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum160.0160.0180.0FalseNoneNoneFalseNoneFalse28800.00
3995453154599None2.28.1 Providing and fixing Wafer type single flange Butterfly valve conforming to relevant IS 13099/9991 EN GGG40/50 with latest amendments as detailed below of the following diameter and types with TP set and conveying to work site, loading and unloading, stacking etc. with all lead and lift. The rate is inclusive of the cost of valve, TP set, rubber insertion, bolts and nuts and excluding earth work excavation.For PN 10.0 (Note: TP set should be be considered only for DI pipes estimate. For MS pipes estimates, TP sets cost of corresponding dia shall be deducted from the SR rates of valves and provision for corresponding dia MS flanges should be made in estimate For Valve of PN - 10.0 and 100mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each5849.05849.06.0FalseNoneNoneFalseNoneFalse35094.00
3995454154599None2.33.1Providing and fixing kinetic AIR VALVE of PN 16.0 for automatic discharge of accumulate air during working condition, conforming to IS 14845 / EN 1074-4. Body and bonnet of DI conforming to IS-1865 of grade GGG-40/50, seals are made of approved EPDM, SS 304 float, guide and internals. Flange drilling according to IS-1538 with appurtenances. complete. Body and bonnet shall be coated with electrostatically applied epoxy powder coating with a coating thickness of 250 micron both inside and outside etc. complete" For K Air Valves of 80mm dia. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each26343.026343.06.0FalseNoneNoneFalseNoneFalse158058.00
3995455154599None2.72.2Supply of PPR Ball Valve Plastic (Heavy Body) confirming to IS 15801- PPR Ball Valve Plastic (Heavy Body) 25mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each206.0206.041.0FalseNoneNoneFalseNoneFalse8446.00
3995456154599None13.23.4Providing and fixing PTMT Ball cock of approved quality, colour and makecomplete with Epoxy coated aluminium rod with L.P./ H.P.H.D. plastic ball. 40 mm nominal bore, 206mm long, weighing not less than 690 g ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each725.0725.04.0FalseNoneNoneFalseNoneFalse2900.00
3995457154599None13.23.5Providing and fixing PTMT Ball cock of approved quality, colour and makecomplete with Epoxy coated aluminium rod with L.P./ H.P.H.D. plastic ball. 50 mm nominal bore, 242mm long , weighing not less than 1240 g ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1344.01344.02.0FalseNoneNoneFalseNoneFalse2688.00
3995458154599None7.5.1Providing and fixing DI/CI puddle flanges conforming to IS 7181-1986 with latest ammendments., in position for RCC walls including hoisting and conveying them to work spot with all lead and lifts etc. complete . For DI/CI puddle flanges of 80mm dia. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1580.01580.05.0FalseNoneNoneFalseNoneFalse7900.00
3995459154599None13.40Providing and fixing square-mouth S.W. gully trap class SP-1 complete with C.I. grating brick masonry chamber with water tight C.I. cover 180 x 150 mm size P type & With Non Modular common burnt clay bricks of designation 3.5 & frame of 300 x300 mm size (inside) the weight of cover to be not less than 4.50 kg and frame to be not less than 2.70 kg as per standard design: ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each2686.02686.022.0FalseNoneNoneFalseNoneFalse59092.00
3995460154599None16.3.2Providing S&S RCC SPUN / VIBRATED CAST PIPES (REINFORCED)pipes NP-3 Class conforming to IS:458-1988 with latest amentmentsusing ordinary portland cement, for sanitary works and conveyingto work site, rolling and lowering into trenches, laying true to lineand level including loading and unloading at both destinations andjointing of pipes and specials, perfect linking of joints with jack tocorrect position including cost of jointing materials, i.e, rubber ringsconforming to IS: 5382 for S&S RCC pipes, with all leads and lifts asdirected and giving necessary hydraulic test as per ISS to the required pressure and commissioning etc. complete. (Contractor will make his own arrangements for procuring water for testing). Before the executionof the work, the contractor shall carry out the survey" RCC NP3 Class pipe of 300 mm dia. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m1332.01332.0150.0FalseNoneNoneFalseNoneFalse199800.00
3995461154599None10.7Erection and positioning of RCC Hume pipe pump house/Cistern on size stone masory platform including transportation charges and handling,finishing with all necessary tools ,plants and materials etc.,complete as directed by the Engineer in charge of the work ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.MT1882.01882.030.0FalseNoneNoneFalseNoneFalse56460.00
3995462154599None16.11Constructing brick masonry chamber of internal dimension 450x300mm and depth of 600mm (inner dimensions) with modular bricks of CD 75 in cement mortar 1:6, bed concrete 150mm thick with 1:3:6, plastering 12 mm thick with cement mortar 1:4, CC 1:2:4 coping 75mm thk for fixing CI cover & frame etc. excluding the cost of CI frame and cover. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos3549.03549.012.0FalseNoneNoneFalseNoneFalse42588.00
3995463154599None10.14.6Providing and installing at site of work P.V.C. pipes including cost of pipesand specials and labour, including lowering into trenches, laying trueto line, level and perfect linking at joints leak proof including jointingof approved type with all labour charges and all lift charges, handlingcharges including encasing the pipe around to a depth not less than 15 cms with gravel or selected earth available from the excavation etc. complete." 160mm(weight of pipe -2.753 kg) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m489.0489.0440.0FalseNoneNoneFalseNoneFalse215160.00
3995464154599None16.9Constructing brick masonry chamber of internal dimension 600x600mm and depth of 600mm (inner dimensions) with modular bricks of CD 75 in cement mortar 1:6, bed concrete 150mm thick with 1:3:6, plastering 12 mm thick with cement mortar 1:4, CC 1:2:4 coping 75mm thk for fixing CI cover & frame etc. excluding the cost of CI frame and cover. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos5454.05454.030.0FalseNoneNoneFalseNoneFalse163620.00
3995465154599None16.10Constructing brick masonry chamber of internal dimension 450x450mm and depth of 600mm (inner dimensions) with modular bricks of CD 75 in cement mortar 1:6, bed concrete 150mm thick with 1:3:6, plastering 12 mm thick with cement mortar 1:4, CC 1:2:4 coping 75mm thk for fixing CI cover & frame etc. excluding the cost of CI frame and cover. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos4236.04236.015.0FalseNoneNoneFalseNoneFalse63540.00
3995466154599None13.40.4Supply and delivery of Centrifugal pumpset at site brand new bestmake and with discharge duty confirming to ISI standards and its latestamendments. 12.5 HP, size 100x100 Head 25M, Discharge 1560 LPM(centralized UG sump to centralized OHT tank 2W +1S ) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos38331.038331.02.0FalseNoneNoneFalseNoneFalse76662.00
3995467154599None13.40.3Supply and delivery of Centrifugal pumpset at site brand new bestmake and with discharge duty confirming to ISI standards and its latestamendments. 3 HP, size 50x40 Head 30M, Discharge 198 LPM (IRRIGATION PUMP 1W +1S ) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos18816.018816.02.0FalseNoneNoneFalseNoneFalse37632.00
3995468154599None13.40.3Supply and delivery of Centrifugal pumpset at site brand new bestmake and with discharge duty confirming to ISI standards and its latestamendments. 3 HP, size 50x40 Head 30M, Discharge 198 LPM (STP To Irrigation PUMP 2W +1S ) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos18816.018816.02.0FalseNoneNoneFalseNoneFalse37632.00
3995469154599None13.40.12 HP, Size 65x50 Head 13M, Discharge 462 LPM (For RO PUMP 2W +1S ) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos15610.015610.01.0FalseNoneNoneFalseNoneFalse15610.00
3995470154599None21.1.3Water purification plants: Providing, Installation and Commissioning of automatic Water purification plant (RO+UF) with all accessories piping, product water tank on single phase power supply as per the enclosed detailed Technical Specifications including cost of material, loading and unloading and as directed by the Engineer in charge. (Ref- detailed specification enclosed seperatly). Note:- 1.The above rates mentioned are only for the preparation of estimate purpose. 2. All items are to be of BSI /NFS standards,with BSI / NFS mark . 3. Tenders to be invited for procurement. 4. No direct payment should be made under any situation or condition or on any account. 5. After commissioning of plant necessary testing to be done for the satisfactory of Engineer Incharge. Note : Refer the ANNEXURE : F for Detailed Specification of Each components" 100 LPH : Cabin Type ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos94000.094000.01.0FalseNoneNoneFalseNoneFalse94000.00
17262057300001NoneNoneBuildingsSewage Treatment Plant (Amble)2125586.44
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3995471154600None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.0136.8FalseNoneNoneFalseNoneFalse13953.60
3995472154600None1.15.2Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In ordinary/soft rock without blasting Depth exceeding 1.5 m, but not exceeding 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum425.0425.0188.1FalseNoneNoneFalseNoneFalse79942.50
3995473154600None1.16.1Earth work excavation for FOUNDATION by Mechanical means depth upto 1.50m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including cost of explosives, dressing of excavated surfaces, disposing off or levelling the excavated stuff or sorting & stacking the selected stuff for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, blasting materials, tools, usage of Machinery & all other appurtenaces required to complete the work. In Hard Rock ( requiring blasting) Depth upto 1.50m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum554.0554.017.1FalseNoneNoneFalseNoneFalse9473.40
3995474154600None1.9Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum266.0266.0136.8FalseNoneNoneFalseNoneFalse36388.80
3995475154600None1.18Extra for every additional lift of 1.5 m or part thereof in excavation/ banking excavated or stacked materials. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum87.087.0161.0FalseNoneNoneFalseNoneFalse14007.00
3995476154600None4.1Providing and injecting chemical emulsion for Pre-constructional Anti-Termite Treatment, creating continuous chemical barrier under and around the column pits, walls, trenches, basement excavation, top surface of the plinth filling, junction of wall and floor, along the external perimeter of building, expansion joints, over the top surface of consolidated earth on which apron is to be laid, surrounding of pipes and conduits with Chlorpyriphos 20% E.C. / Lindane 20% E.C. @ 3.19 l/m2 including cost of chemical, diluting in water to one percent concentration, labour, usage charges of machinery, complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum118.0118.098.0FalseNoneNoneFalseNoneFalse11564.00
3995477154600None2.1.3Providing and laying in position plain cement concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machineries, curing, and all the other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement & formwork shall be paid separately) Mix 1:3:6 (M10) Using 40 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5448.05448.020.0FalseNoneNoneFalseNoneFalse108960.00
3995478154600None2.4.2Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6955.36955.375.0FalseNoneNoneFalseNoneFalse521647.50
3995479154600None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Pump Room Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9644.89644.82.098FalseNoneNoneFalseNoneFalse20234.79040
3995480154600None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Pump Room Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9042.09042.06.845FalseNoneNoneFalseNoneFalse61892.490
3995481154600None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Pump Room Columns ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10247.610247.61.987FalseNoneNoneFalseNoneFalse20361.98120
3995482154600None5.4Providing Size Stone masonry with hard stone in foundation & plinth with Cement mortar 1:6 (1 cement : 6 coarse sand) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5315.05315.09.0FalseNoneNoneFalseNoneFalse47835.00
3995483154600None2.5.1Providing and laying in position Reinforced cement concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/ trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement, dowel bars & formwork to be paid separately) M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Chejja ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum8740.68740.61.0FalseNoneNoneFalseNoneFalse8740.60
3995484154600None2.11 hSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. All other type of structures ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Tonne79011.079011.09.4522FalseNoneNoneFalseNoneFalse746827.77420
3995485154600None6.8Providing Brick work with common burnt clay Non Modular bricks of class designation 3.5 in superstructure above plinth level in all shapes and sizes in Cement mortar 1:6 (1 cement : 6 coarse sand) including cost of all materials, labour, scaffolding and usage charges of machinery & other incidental charges complete as per the direction of engineer incharge of work. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6659.06659.022.0FalseNoneNoneFalseNoneFalse146498.00
3995486154600None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings / wooden frames with rawl plugs screws etc. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs154.0154.059.0FalseNoneNoneFalseNoneFalse9086.00
3995487154600None12.88Providing & fixing of 2-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having a overall size of 60mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm X 58mm with GI reinforcement of 1mm for the frame and 1.5 mm for the sash. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24mm. Windows shall be provided with 5mm plain float glass, standard hardware& single point locking system with touch lock. Wall thickness of frame & sash shall be of 2-2.5 mm. Maximum possible size 1819mm x 1819mm (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5390.05390.03.0FalseNoneNoneFalseNoneFalse16170.00
3995488154600None11.5.2Providing and fixing 1mm thick M.S. sheet door with frame of 40x40x6 mm angle iron and 3 mm M.S. gusset plates at the junctions and corners, all necessary fittings complete, including applying a priming coat of approved steel primer. Using flats 30x6mm for diagonal braces and central cross piece including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm4242.04242.02.0FalseNoneNoneFalseNoneFalse8484.00
3995489154600None9.1Providing and laying Cement concrete flooring 40 mm thick with 20 mm nominal size stone aggregate using 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate) finished with a floating coat of neat cement, including cement slurry complete. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm392.0392.040.0FalseNoneNoneFalseNoneFalse15680.00
3995490154600None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm304.0304.0122.0FalseNoneNoneFalseNoneFalse37088.00
3995491154600None8.2.2Providing 15 mm cement plaster on the rough side of single or half brick wall of mix :1:6 (1 cement: 6 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm228.0228.0100.0FalseNoneNoneFalseNoneFalse22800.00
3995492154600None8.1.1Providing 12 mm cement plaster with cement mortar 1:4 (1 cement: 4 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm210.0210.080.0FalseNoneNoneFalseNoneFalse16800.00
3995493154600None8.25Distempering with oil bound washable distemper of approved brand and manufacture to give an even shade :New work (two coats) over and including water thinnable priming coat with cement primer after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm137.0137.0100.0FalseNoneNoneFalseNoneFalse13700.00
3995494154600None8.30Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm174.0174.0122.0FalseNoneNoneFalseNoneFalse21228.00
3995495154600None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90 ltr/10 m² over an under coat of primer applied @ 0.80 ltr/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm139.0139.059.0FalseNoneNoneFalseNoneFalse8201.00
3995496154600NoneVOL - 5, C - 10 10.1.9 Supplying PVC ringtite pipes conforming to IS 4985:2000 with latest amendments and conveying to worksite, rolling and lowering into trenches, laying true to line and level and perfect linking at joints, testing and commissioning, including loading unloading at both destinations and cuts of pipes wherever necessary including jointing of PVC pipes and specials (excluding cost of specials) with jointing of approved type, with all labour with all lead & lift including encasing the pipe alround to a depth of not less than 15 cms. with soft gravel or selected earth available from the excavation etc. complete and giving necessary hydraulic test to the required pressure as per ISS (Contractor will make his own arrangements for procuring water for testing) etc. for: PVC pipes 160mm dia., 6 kg/sqcm & class 3 ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m618.0618.050.0FalseNoneNoneFalseNoneFalse30900.00
3995497154600NoneVOL - 5, 16.9Constructing brick masonry chamber of internal dimension 600x600mm and depth of 600mm (inner dimensions) with modular bricks of CD 75 in cement mortar 1:6, bed concrete 150mm thick with 1:3:6, plastering 12 mm thick with cement mortar 1:4, CC 1:2:4 coping 75mm thk for fixing CI cover & frame etc. excluding the cost of CI frame and cover. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each5454.05454.03.0FalseNoneNoneFalseNoneFalse16362.00
3995498154600NoneVOL - 5, 16.23.1Providing and fixing SFRC frame and cover conforming to IS 12592 (part-I)-1988 and IS 12592 (part-II)- 1991 with latest amendment, including cutting slabs to the required size for the opening and fixing the cover in C.C. 1:2:4 and C.M. 1:3 plastering 20 mm thick to all exposed faces, curing for 10 days with all lead and lift with appurtenances.Complete Medium Duty ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Set1914.01914.03.0FalseNoneNoneFalseNoneFalse5742.00
3995499154600NoneVOL - 5, C - 16 16.15.1 Providing and constructing “WIRE CUT BRICK MACHINEHOLE CHAMBERS” using Portland/Pozzolana cement, conical in shape at top, with CC 1:3:6 foundation using 40mm and down size graded metal of approved quality and with an offset of 0.15M alround the chamber. Construct Brick masonry in CM 1:4, 340 mm thick, with wirecut bricks of approved quality, plaster inside and out side with CM 1:3, 12mm thick, except for the conical surface outside where the plaster thickness shall be 20mm. Slope inside to be 1:6 in the concrete towards central drain and finished smooth. Fixing of pipes in CC 1:2:4 with graded metal of 20mm and down size. Supplying and fixing SFRC Machinehole frame and cover (Heavy Duty) conforming to IS:12592 with latest amendment, in CC 1:2:4. Supplying and fixing footsteps made of 12mm dia. steel bars (Fe-500) with 3mm thick plastic encapsulation (IS-10910). The footsteps shall be fixed 30cms apart and on CC block embeded to masonry wall. The whole works include watering, curing, barricading, danger lighting, pouring tar over MH frame and cover, cost of tar, shoring, strutting, dewatering, engraving Machinehole number with flow direction on the inner conical surface etc. as per the drawing etc. as per technical specifications and for the following diameters and depth etc. for 1.2mm diaCirc. B M.H: Constructing Brick Masonry Circular Machinehole 1.2 m internal dia. , 1.0 M depth & SFRC cover & frame ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each29047.029047.01.0FalseNoneNoneFalseNoneFalse29047.00
3995500154600NoneVOL - 5, 7.3 Providing and fixing MS inspection door of size 60 cms x 60 cms, including MS frame made of 50x50x6mm angle, shutters made of 3mm thick MS sheets, with hinges, locking arrangements at top etc. including painting with anticorrosive approved paint etc. complete including all lead and lifts etc. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each2140.02140.06.0FalseNoneNoneFalseNoneFalse12840.00
3995501154600NoneVOL - 5 7.1.1 Providing and fixing MS ladder between landings, 45 cms wide using angle iron of specified sizes, 20mm MS bars at 25 cms. centre to centre, with necessary supports of same angle iron etc. as directed, including hand railing on both sides with 25mm dia. GI pipes with angle iron props at 2 mtrs. intervals and 0.5M heigh, including fixing in ground with CC 1:2:4 and two coats of anticorrosive bituminous paint etc. with all lead and lifts etc. complete with: MS angle of 65 x 65 x 8mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr4377.04377.03.0FalseNoneNoneFalseNoneFalse13131.00
17262057300000NoneNoneBuildingsAdvanced Sequencing Batch Reactor (Amble)2236551.43
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3995502154601None1.0Design, Engineering, and providing all equipment /machinary at site, installation and commissioning of equipments/ electricals/ piping exclusive of all types of taxes and duties as described inspecification. The approximate capacity of sewage treatment plant is 50KLD Supplying , installing , testing , commissioning of bar screen to exclude the large sized particles with associated set of guide angles in MS flat of 6.0 mm thick and 50 mm wide kept inclined at 45 degree . Size : 600 x 600 ( MS Construction ) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No22982.422982.41.0FalseNoneNoneFalseNoneFalse22982.40
3995503154601None2.0Supplying , installing , testing , commissioning of Raw Sewage Pump (Centrifugal/Submersible).The pump shall be coupled to the adequate HP , electric motor , mounted on a common base frame (1W + 1S) Make: Kirloskar Duty: 10 KLH @ 6-10 M head. (1W+1S) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No60480.060480.02.0FalseNoneNoneFalseNoneFalse120960.00
3995504154601None3.0Supplying , installing , testing , commissioning of Coarse bubble diffusers 90 dia x 800mm long UPVC pipe grid with necessary orifices suitable for 6.0 kg/cm2 pressure rating to provide clog-free oxygen. Make : Scogen ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos7257.67257.68.0FalseNoneNoneFalseNoneFalse58060.80
3995505154601None4.0Supplying , installing , testing , commissioning of Fine bubble diffusers 90 dia x 1000mm long with the membrane from SCOGEN shall consists of set of membranes , SS 304 clips , nylon rope braided hose with all accessories to make it retrievable . Make : Scogen ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos10523.5210523.5212.0FalseNoneNoneFalseNoneFalse126282.240
3995506154601None5.0Supplying , installing , testing , commissioning of approved make Twin Lobe roots type air blower of adequate capacity at 0.5 kg/cm2 capacity of required head comprising of common base frame , suction filter , suction silencer , non return , V belt , safety valve , belt guard , drive and driven pulleys , pressure gauge , inter connection piping , discharge silencer including required motor. Make : KAY International Duty: 160 M3 /hr @ 0.5 KG/CM2 ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No223776.0223776.02.0FalseNoneNoneFalseNoneFalse447552.00
3995507154601None6.0Supplying , installing , testing , commissioning of sludge disposal pumps to pump the sludge from SBR tank to sludge holding tank with wetted parts in CI construction. The pump shall be coupled to the adquate H.P electrical motor , mounted on a base frame Make: Kirloskar . Duty: 10 KLH @10 M head. (1W) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No42336.042336.01.0FalseNoneNoneFalseNoneFalse42336.00
3995508154601None7.0Supplying , installing , testing , commissioning of Filter Feed Pump consisting of Monobloc type filter feed pumps to feed semi treated water to secondary treatment process through the filters.The pump shall be coupled to the adequate HP electrical motor , mounted on a common base frame . Make:Kirloskar Duty: 6 KLH @ 30 M head. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No48384.048384.02.0FalseNoneNoneFalseNoneFalse96768.00
3995509154601None8.0Supplying , installing , testing , commissioning of Chlorine Dosing System consisting of Dosing pump and 100 ltrs Solution Tank having detachable lid with molded inserts for mounting of pump . Capacity :0 - 6lph (1w ) Make : E- Dose ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No31691.5231691.521.0FalseNoneNoneFalseNoneFalse31691.520
3995510154601None9.0Supplying , installing , testing , commissioning of Pressure Sand filter for filtration of treated sewage. The filter shall be made of MS with epoxy painting with first charge of media, frontal face piping and multiport valves Size : 800 mm dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No254016.0254016.01.0FalseNoneNoneFalseNoneFalse254016.00
3995511154601None10.0Supplying , installing , testing , commissioning of Activated Carbon filter for filtration of treated sewage, The filter shall be made of MS with epoxy painting with first charge of media, frontal face piping and multiport valves. Size : 800 mm dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No296352.0296352.01.0FalseNoneNoneFalseNoneFalse296352.00
3995512154601None11.0Supply , fixing , testing & commissioning of fully automatic PLC based decant valve for suitable dia with auto electrical operated with isolation ( butterfly valve ) at suitable time as required opening & Closing automatically cost including all pipes with necessary fittings , electrical connection wiring etc complete. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos90720.090720.01.0FalseNoneNoneFalseNoneFalse90720.00
3995513154601None12.0Plant Piping with UPVC of 10 Kg/sqcm pipes with fittings and approved make valves, gauges, instrumentation etc., for all plumbing lines and MS B Class pipeline with fittings for Blower Air Lines ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Lot243129.6243129.61.0FalseNoneNoneFalseNoneFalse243129.60
3995514154601None13.0Supplying, installing, testing,commissioning of STP Tested Water Transfer Oump . The pump shall be submersible type coupled to the adequate H P Electrical Motor. Make:Kirloskar Duty:KLD @30 M Head. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos43954.4443954.441.0FalseNoneNoneFalseNoneFalse43954.440
3995515154601NoneII.1STP PANEL Supply, installation, testing and commissioning of front operated, front access, totally enclosed, free standing, dust and vermin proof Panel (Indoor non compartmental type) with IP 54 ingress protection, fabricated from 2 mm thick CRCA sheets, with hinged, gasketted and lockable doors including the cost of interconnections, copper crimping lugs, brass glands, bonding to earth and painting, suitable for use at 415 volts, 3 phase 4 wire 50 Hz system with 16 KA rupturing capacity at 415 volts complete. Electrical Motor Control Centre shall be suitable for all equipments connected to the STP with 2 Nos of spare feeders ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Set290304.0290304.01.0FalseNoneNoneFalseNoneFalse290304.00
3995516154601NoneII.2CABLES AND CABLE TERMINATIONS Inter Unit Cabling Inter unit cabling for all equipments with necessary armoured/ unarmoured cables with necessary termination lugs, glands etc complete ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Lot62802.4362802.431.0FalseNoneNoneFalseNoneFalse62802.430
3995517154601NoneIV.1MAINTAINANCE CHARGES AND CONSUMABLES Maintainance Charges including Man power required during maintainance period for 1 shift and Consumables required for functioning and maintainance of 50KLD Sewage Treatment Plant ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Month360.0360.024.0FalseNoneNoneFalseNoneFalse8640.00
17262057300000NoneNoneBuildingsSolar Water Heater (Amble)724472.0
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3995518154602None7.3.1 of Part III Utilization (PWD Electrical)Supplying, installation, testing and commissioning of solar hot water heater comprising of solar flat plate collector of size 2120x1040x100mm and stainless steel hot water storage tank with stainless steel heat exchanger absorber made of copper sheet and copper tube of following capacity aluminium box collector with approximate capacity electrical back up arrangement excluding inlet and out let pipes. As per the directions SS Model with 100mm thick of 48Kg/Meter Cube density Rock wool insulation with 22SWG Aluminium cladding for 200 Liter Capacity for Quarters Block" ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each46914.046914.05.0FalseNoneNoneFalseNoneFalse234570.00
3995519154602None7.3.2 of Part III Utilization (PWD Electrical)Supplying, installation, testing and commissioning of solar hot water heater comprising of solar flat plate collector of size 2120x1040x100mm and stainless steel hot water storage tank with stainless steel heat exchanger absorber made of copper sheet and copper tube of following capacity aluminium box collector with approximate capacity electrical back up arrangement excluding inlet and out let pipes. As per the directions SS Model with 100mm thick of 48Kg/Meter Cube density Rock wool insulation with 22SWG Aluminium cladding for 300 Liters Capacity Dormitory Block " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each69986.069986.07.0FalseNoneNoneFalseNoneFalse489902.00
17262057300000NoneNoneBuildingsBorewell (Amble)956220.0
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3995520154603None12.1.1Sinking borewell of 165mm dia. clear, using super fast hydraulic rig of capacity 300 PSIG & above 1100 CMF and above, in all srata of earth,including over burden upto 20M. Fixing of casing pipes, collars and cap with ncessary cutting, threading and welding including transportation of rig and supporting vehicles, crew charges, cost of consumables,etc,completeincluding yield testing at the final depth with a minimum working of compressor for one hour etc. complete.(Excluding cost of Casing pipes, collars,Cap etc) (Above 450m of drilling add 10% for every 50m depth) - Borewell depth of 0 to 50 Mtrs ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr370.0370.0100.0FalseNoneNoneFalseNoneFalse37000.00
3995521154603None12.1.2Sinking borewell of 165mm dia. clear, using super fast hydraulic rig of capacity 300 PSIG & above 1100 CMF and above, in all srata of earth,including over burden upto 20M. Fixing of casing pipes, collars and cap with ncessary cutting, threading and welding including transportation of rig and supporting vehicles, crew charges, cost of consumables,etc,completeincluding yield testing at the final depth with a minimum working of compressor for one hour etc. complete.(Excluding cost of Casing pipes, collars,Cap etc) (Above 450m of drilling add 10% for every 50m depth) - Borewell depth of 50 to 100 Mtrs ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr464.0464.0100.0FalseNoneNoneFalseNoneFalse46400.00
3995522154603None12.1.3Sinking borewell of 165mm dia. clear, using super fast hydraulic rig of capacity 300 PSIG & above 1100 CMF and above, in all srata of earth,including over burden upto 20M. Fixing of casing pipes, collars and cap with ncessary cutting, threading and welding including transportation of rig and supporting vehicles, crew charges, cost of consumables,etc,completeincluding yield testing at the final depth with a minimum working of compressor for one hour etc. complete.(Excluding cost of Casing pipes, collars,Cap etc) (Above 450m of drilling add 10% for every 50m depth) - Borewell depth of 100 to 150 Mtrs ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr493.0493.0100.0FalseNoneNoneFalseNoneFalse49300.00
3995523154603None12.1.4Sinking borewell of 165mm dia. clear, using super fast hydraulic rig of capacity 300 PSIG & above 1100 CMF and above, in all srata of earth,including over burden upto 20M. Fixing of casing pipes, collars and cap with ncessary cutting, threading and welding including transportation of rig and supporting vehicles, crew charges, cost of consumables,etc,completeincluding yield testing at the final depth with a minimum working of compressor for one hour etc. complete.(Excluding cost of Casing pipes, collars,Cap etc) (Above 450m of drilling add 10% for every 50m depth) - Borewell depth of 150 to 200 Mtrs ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr572.0572.0100.0FalseNoneNoneFalseNoneFalse57200.00
3995524154603None12.1.5Sinking borewell of 165mm dia. clear, using super fast hydraulic rig of capacity 300 PSIG & above 1100 CMF and above, in all srata of earth,including over burden upto 20M. Fixing of casing pipes, collars and cap with ncessary cutting, threading and welding including transportation of rig and supporting vehicles, crew charges, cost of consumables,etc,completeincluding yield testing at the final depth with a minimum working of compressor for one hour etc. complete.(Excluding cost of Casing pipes, collars,Cap etc) (Above 450m of drilling add 10% for every 50m depth) - Borewell depth of 200 to 250 Mtrs ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr671.0671.0100.0FalseNoneNoneFalseNoneFalse67100.00
3995525154603None12.4Geophysical investigation at site for sinking borewells for Providing drinking water to the habitation either through the Hand Pump MWS or P.W.S.S, by vertical electrical sounding by adopting Venner or Schlumbergers's method, including reconnaissance survey of geological formation. Geophysical investigation of existing ground water in the vicinity, its quality, quantity and acceptability of the users, indicating the location of the site, recommended depth of casing pipe required to seal the top unconsolidated formation including an extra depth of 1.0 metre in consolidated formation for proper seating of casing pipe, depth of drilling required to cover full depth of aquifer proposed to be tapped, probable yield and other information required including transportation of instruments and accessories to work site, engaging technical personal and labour required etc. NOTE: 1) Additional rate on item 1&2 is allowed for drilling in over burden and fixing Casing pipes beyond 20 M (for fixing Casing pipes only) a) Above 20 M and upto 30 M - 15%, b) Above 30 M - 30% (Measurement of overburden is restricted to the depth of casing pipe fixed excluding initial depth of 20M and projection above ground level). 2) A sum of Rs. 100/- is to be deducted for Dry Borewell towards yield test. etc. complete. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each BW5288.05288.04.0FalseNoneNoneFalseNoneFalse21152.00
3995526154603None13.16.7Providing Submersible Pump Set of 150mm dia suitable for bore well and confirming to IS 8034-2000;3Phase, SS Bowl & Impeller with Low volt Motor as per specifications, to work site as per necessary ammendments and instructions of engineer incharge of work. For 10.00 HP 10.00 HP - 90 LPM @ 220 m = 20 STG Outlet Dia - 2.00" ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each54612.054612.02.0FalseNoneNoneFalseNoneFalse109224.00
3995527154603None12.32Supply of ISI mark 175mm nominal bore,plain and steel casing pipe grade of steel Fe 410 of wall thickness conforming to IS 4270-2001 and latest ammendments, electrical resistance welded steel tubes, material and conforming to IS 1387-1993 and manufactured by basic open hearth electric or basic oxygen process in andom length of 5-7m both ends.threaded conforming to IS 554-1985 one end fixed with socket conforming to IS 4270-2001 and the other end with screwed pipes all shall be responsibaly free from defects. The tubes shall be responsible straight end should be with ISI marking weighing 25.10kg/m.prices include Collar-Medium duty. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr1933.01933.030.0FalseNoneNoneFalseNoneFalse57990.00
3995528154603None12.34Providing and laying at site of work MS casing cap as per IS 1239 (partII) 1982 with all latest amendments if any for any dia. The thickness of plate used for covering one end shall be 3mm (minimum). The dimensions of caps and colars shall be strictly as per IS 1239 (Part-II) 1982 with all amendments including cost of material and labour charges for fixing, if any etc. complete with all lead and lifts and as directed by the Engineer in charge C ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each164.0164.02.0FalseNoneNoneFalseNoneFalse328.00
3995529154603None13.27.1Supply and delivery of galvanized mild steel tubes of 6mtr standardlength heavy duty (C Class) as per IS 1239 (Part-I) 1990 with latest amendments with ISI Mark (one end fitted with Heavy Duty collar and other end fitted with protective cover) 50mm dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each3050.03050.068.0FalseNoneNoneFalseNoneFalse207400.00
3995530154603None13.29Supply and delivery at site 50mm(2”) dia heavy duty CI adopter setcomplete suitable for uPVC Column pipes for Submersible pumpsets ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Set1550.01550.02.0FalseNoneNoneFalseNoneFalse3100.00
3995531154603None11.3.6Providing, Laying and Fixing of GI pipes conforming to IS 1239:1990 with latest amendments complete with GI fittings (excluding the costof fittings) with cuts and threads wherever necessary, including testingfor water tightness, with all lead and commissioning. (contractor willmake his own arrangements for procuring water for testing) For:Heavy Duty GI Pipe of 50mm dia etc. complete. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr679.0679.010.0FalseNoneNoneFalseNoneFalse6790.00
3995532154603None11.4.6Providing and fixing GI union in existing GI pipe line, cutting and threading the pipe and making long screws including excavation, refillingthe earth or cutting of wall and making good the same complete wherever required etc. complete for: 20.88.6:50mm nominal size ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each660.0660.02.0FalseNoneNoneFalseNoneFalse1320.00
3995533154603None13.24.1Supply and delivery at site of brand new best make gate valve as per IS778/1984 with ISI Mark and as per its latest amendments Size 50mm Gate valve ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1250.01250.02.0FalseNoneNoneFalseNoneFalse2500.00
3995534154603None13.25.1Supply and delivery at site of brand new best make non-return valve as per IS 778/1984 with ISI Mark and as per latest amendmentsits Size 50mm Non-return valve ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1250.01250.02.0FalseNoneNoneFalseNoneFalse2500.00
3995535154603None11.8.6Supply and delivery at site wrought middle steel (galvanized) GI bendconfirming to IS 1239-II, 1991 with latest amendments if any. For 50mm dia GI Bend ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each358.0358.04.0FalseNoneNoneFalseNoneFalse1432.00
3995536154603None13.32Labour charges for Erection, Electrification and commissioning of Pumpsets, including aligning and balancing of all items including supply and erection of two pair of supporting clamps, bore well caps, cable clips and water tight gland cable protectors, bolts, nuts, valve and gauges,tools andequipments etc., involved in the job as per specifications, with necessary tests as per specifications, with testing of as per instructions of engineer incharge of work. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Job6500.06500.02.0FalseNoneNoneFalseNoneFalse13000.00
3995537154603None13.36Providing main connection from pole PVC insulated sheathed steel wire cable in new trench as per IS 1554/ 1988 with latest amendments with ISI mark from KPTCL pole to meter board unit. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr135.0135.0102.0FalseNoneNoneFalseNoneFalse13770.00
3995538154603None13.35.2Labour charges for providing connection using insulated sheathedsteel wire cable as per IS 1554/ 1988 with latest amendments fromKPTCL pole to meter board unit, with all necessary materials ,tools and equipments,as per specificationswith testing of as per instructions of engineer incharge of work. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr160.0160.0100.0FalseNoneNoneFalseNoneFalse16000.00
3995539154603None13.33Labour charges for erection of indoor type panel board and meter board units with all necessary materials and labour, tools and equipments including providing cement concrete foundation bed etc., complete as per specification, with testing of as per instructions of engineer incharge of work. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Job1350.01350.02.0FalseNoneNoneFalseNoneFalse2700.00
3995540154603None13.22Supply and delivery at site Brand new best make PVC insulated cable of Flat 3 core (sheathed) of nominal cross sectional area as per IS 694-1990 with ISI Mark and as per its latest amendments. 1x3x6 Sqm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr185.0185.0556.0FalseNoneNoneFalseNoneFalse102860.00
3995541154603None13.38Providing and fixing suitable for 1.1 KV class UG cable filled with necessary bitumen/insulating compound complete with terminals, clamps,bolts,nuts and washers etc. with necessary materials and labour tools and equipments as per instructions of engineer incharge of work. 1x3x6 Sqm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each375.0375.04.0FalseNoneNoneFalseNoneFalse1500.00
3995542154603None13.39Earthing: Providing and fixing and wiring earth electrode for grounding circuits IC cutouts and other equipments on the meter board in the pit. The pits should be filled up with equal proportion of salt and charcoal 150mm around the pipe to complete depth. The connection from the pipe to the conduits etc. is to established through GI wire of sizes as per clause 7.3.3 of IS 732 using 12mm bolts, nuts, washers and check nuts, the pipe shall have 16 through holes of 12mm dia. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Job3750.03750.04.0FalseNoneNoneFalseNoneFalse15000.00
3995543154603None13.23.3Supply, installing,testing and commissioning COMMON control panel consisting of the following INCOMING:1 No set of Phase indicatinglamps with SFU of suitable rating 1 No, Analog Ammeter, 1 No AnalogVoltmeter 1ni with Phase selector switch, Isolating switch OUTGOINGfor Main Electrical Pump: 1 No. MCB 1 No. DOL of S/D Starter suitablefor respective HP 1 No. Electrcal Protection Like single Phase preventor,under voltage overVolage, under current over current & dry runprotection suitable for the pump described above 1 no Indoor type NOTE: 1) DOL- Direct Online Starter 2) S-D- Star Delta Starter etc. complete. 6 to 15 HP pumps ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each15900.015900.02.0FalseNoneNoneFalseNoneFalse31800.00
3995544154603None9.1.2Providing, laying and jointing HDPE pipes of specified grade and conforming to IS 4984-2016 with latest ammendments and conveying to work site including loading and unloading at both destinations and rolling and lowering into trenches, laying true to line and jointing of pipes and specials with electrofusion welding, giving hydraulic test as per relevant ISS with all lead and lifts including encasing the pipe alround to a depth of not less than 15 cms. with soft gravel or selected earth available from the excation, testing and commissioning. The rate is exclusive of required specials and fittings wherever necessary like saddle Tee, stub ends, flanged sets, bedns, reducers etc. complete Contractor will make his own arrangements for procuring water for testing etc. complete. NOTE: Upto 110mm dia Coil shall be used.For :HDPE PE 80 PN 6.0 HDPE Grade PE80-PN6.0, 63mm dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr189.0189.0200.0FalseNoneNoneFalseNoneFalse37800.00
3995545154603None1.17.1Earth work excavation for pipeline trenches in all kinds of soils by mechanical means as per drawing and technical specifications, including setting out, construction of shoring, strutting, barricading, caution lights, bracing, using sight rails & bonding rods at every 100mm wherever necessary as directed,removal of stumps and other deleterious matter, dressing of sides and levelling the bottom of trench to the extent required , utilising the available excavated earth locally for the work etc and all other appurtenances complete in the following strata. All kinds of soils, depth upto 1.50M ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.cm262.0262.036.0FalseNoneNoneFalseNoneFalse9432.00
3995546154603None1.1Refilling available earth around trenches/pipelines, cables in layers not exceeding 20 cms in depth, compacting each deposited layer by ramming after watering with a lead upto 50 m, and lift upto 1.5 m. Including cost of all labour complete as per specifications ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.cm160.0160.031.6FalseNoneNoneFalseNoneFalse5056.00
3995547154603None10.6RCC hume pipe Circular pump house: Providing precast RCC Circular Hume pipe pump house with M.S door and RCC conical roof as per specification and drawings - Internal dia Mtr. 1200 mm & height of 2.5 Mtr. With Wall thickness 65mm etc. complete. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each16401.016401.02.0FalseNoneNoneFalseNoneFalse32802.00
3995548154603None10.7Erection and positioning of RCC Hume pipe pump house/Cistern onsize stone masory platform including transportation charges andhandling,finishing with all necessary tools ,plants and materials etc.,complete as directed by the Engineer in charge of the work. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1882.01882.02.0FalseNoneNoneFalseNoneFalse3764.00
17262057300000NoneNoneBuildingsSump Tank (Amble)833003.85
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3995549154604None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.047.58FalseNoneNoneFalseNoneFalse4853.160
3995550154604None1.15.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In ordinary/soft rock without blasting upto 1.5 m depth ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum363.0363.0191.0FalseNoneNoneFalseNoneFalse69333.00
3995551154604None1.9Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum266.0266.0107.0FalseNoneNoneFalseNoneFalse28462.00
3995552154604None1.18Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or stacked materials. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum87.087.097.5FalseNoneNoneFalseNoneFalse8482.50
3995553154604None2.1.3Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5448.05448.06.0FalseNoneNoneFalseNoneFalse32688.00
3995554154604None2.4.2Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6955.36955.327.0FalseNoneNoneFalseNoneFalse187793.10
3995555154604None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9644.89644.88.0FalseNoneNoneFalseNoneFalse77158.40
3995556154604None2.11 hSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. All other type of structures ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Tonne79011.079011.03.85FalseNoneNoneFalseNoneFalse304192.350
3995557154604None8.36.1Finishing with Epoxy paint (two coats) at all locations prepared and applied as per manufacturer's specifications including appropriate priming coat, preparation of surface, etc. complete. On steel work including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Enginer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm176.0176.0142.34FalseNoneNoneFalseNoneFalse25051.840
3995558154604None15.1Polyurethane based Single Component for New Surface Providing and laying water proofing treatment to the Roof with PU based single component elastomeric pure polyurethane based coating on New terrace/Chajjas/Sunken portion of WC:Bathroom, cold applied PU waterproofing membrane that is highly elastic with elongation greater than 400% and tensile strength greater than 2MPa as per ASTM D412. The waterproofing membrane to be applied in 2coats @ 1.6 kg/m2 to achieve final DFT (Dry Film Thickness) of 1mm including prime coat of epoxy primer @150 g/m2 and protection with 120gsm Geo-textile over the waterproofing membrane. The finished cost to include surface preparation, making coving at Junction, Bore Packing, treatment of construction joints completely as per specification. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm817.0817.077.5FalseNoneNoneFalseNoneFalse63317.50
3995559154604NoneVOL - 5, 7.3 Providing and fixing MS inspection door of size 60 cms x 60 cms, including MS frame made of 50x50x6mm angle, shutters made of 3mm thick MS sheets, with hinges, locking arrangements at top etc. including painting with anticorrosive approved paint etc. complete including all lead and lifts etc. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each2140.02140.01.0FalseNoneNoneFalseNoneFalse2140.00
3995560154604NoneVOL - 5, 10.6RCC hume pipe Circular pump house: Supplying precast RCC Circular Hume pipe pump house with M.S door and RCC conical roof as per specification and drawings - Internal dia Mtr. 1200 mm & height of 2.5 Mtr. With Wall thickness 65mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each16401.016401.01.0FalseNoneNoneFalseNoneFalse16401.00
3995561154604NoneVOL - 5 7.1.1 Providing and fixing MS ladder between landings, 45 cms wide using angle iron of specified sizes, 20mm MS bars at 25 cms. centre to centre, with necessary supports of same angle iron etc. as directed, including hand railing on both sides with 25mm dia. GI pipes with angle iron props at 2 mtrs. intervals and 0.5M heigh, including fixing in ground with CC 1:2:4 and two coats of anticorrosive bituminous paint etc. with all lead and lifts etc. complete with: MS angle of 65 x 65 x 8mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr4377.04377.03.0FalseNoneNoneFalseNoneFalse13131.00
17262057300000NoneNoneBuildingsInternal Electrical Works (Amble)7240476.72
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3995562154605None1.2.1 of Part III Utilization (PWD Electrical)Concealed Conduit System Supplying 19/20 mm dia 2mm/2.5mm thick heavy gauge PVC conduit pipe with suitable size bends, metal/PVC junction boxes adhesive paste etc., and running before concreting the slab. The conduit should be tied to the reinforcement rods by using binding wires and unused ways of junction boxes and pipe ends should be covered using PVC end enclosures. run with 18SWG GI fish wire wherever necessary. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr66.066.06850.0FalseNoneNoneFalseNoneFalse452100.00
3995563154605None1.1.1 of Part III Utilization (PWD Electrical)Open Conduit System Supplying heavy gauge PVC conduit pipe 19/20mm dia 2mm thick confirming to IS 2509 with suitable size bends, junction boxes, adhesive paste etc., and fixing using inverted wood plugs in case of RCC ceiling and RCC wall / stone structure or rawl plugs in case of brick walls and cement plastering the damaged portion using heavy gauge saddles at an interval of 700mm using NF screws. 19/20mm dia 2mm thick. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr69.069.01250.0FalseNoneNoneFalseNoneFalse86250.00
3995564154605None1.2.2 of Part III Utilization (PWD Electrical)Concealed Conduit System Supplying 25 mm dia 2mm/2.5mm thick heavy gauge PVC conduit pipe with suitable size bends, metal/PVC junction boxes adhesive paste etc., and running before concreting the slab. The conduit should be tied to the reinforcement rods by using binding wires and unused ways of junction boxes and pipe ends should be covered using PVC end enclosures. run with 18SWG GI fish wire wherever necessary. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr78.078.02750.0FalseNoneNoneFalseNoneFalse214500.00
3995565154605None1.3.1 of Part III Utilization (PWD Electrical)Supplying 19/20 dia 2mm/2.5mm thick heavy gauge PVC Conduit Pipe with bends, metal junction boxes adhesive paste etc.,by groove cutting in the wall and fixing by bracing U or J hooks and cement plastering up to the wall surface and run with 18 SWG GI fish wire run throughout the conduit wherever necessary. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr68.068.03725.0FalseNoneNoneFalseNoneFalse253300.00
3995566154605None1.3.2 of Part III Utilization (PWD Electrical)Supplying 25 mm dia 2mm/2.5mm thick heavy gauge PVC Conduit Pipe with bends, metal junction boxes adhesive paste etc.,by groove cutting in the wall and fixing by bracing U or J hooks and cement plastering up to the wall surface and run with 18 SWG GI fish wire run throughout the conduit wherever necessary. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr355.0355.01010.0FalseNoneNoneFalseNoneFalse358550.00
3995567154605None2.1.1 of Part III Utilization (PWD Electrical)Supplying and wiring adopting loop system in existing PVC Conduit /casing capping casing capping using 2x1.5mm (Phase & Neutral) & 1x1.0 mm 2 (Earth wire) FRLS multi strand PVC insulated copper wire (confirming to IS-694: and latest amendments) with a 6A, flush type SP control switch shall be fixed on the existing plastic sheet/ gang box, the other end of the wires shall be terminated with sufficient loose length in a wood/PVC round block. complete for each outlet. - Short point upto 3m from tapping point to out let via switch box ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Point285.0285.074.0FalseNoneNoneFalseNoneFalse21090.00
3995568154605None2.1.2 of Part III Utilization (PWD Electrical)Supplying and wiring adopting loop system in existing PVC Conduit /casing capping casing capping using 2x1.5mm (Phase & Neutral) & 1x1.0 mm 2 (Earth wire) FRLS multi strand PVC insulated copper wire (confirming to IS-694: and latest amendments) with a 6A, flush type SP control switch shall be fixed on the existing plastic sheet/ gang box, the other end of the wires shall be terminated with sufficient loose length in a wood/PVC round block. complete for each outlet. - Medium point above - 3Mtr up to 6Mtr from tapping point to out let via switch ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Point394.0394.093.0FalseNoneNoneFalseNoneFalse36642.00
3995569154605None2.1.3 of Part III Utilization (PWD Electrical)Supplying and wiring adopting loop system in existing PVC Conduit /casing capping casing capping using 2x1.5mm (Phase & Neutral) & 1x1.0 mm 2 (Earth wire) FRLS multi strand PVC insulated copper wire (confirming to IS-694: and latest amendments) with a 6A, flush type SP control switch shall be fixed on the existing plastic sheet/ gang box, the other end of the wires shall be terminated with sufficient loose length in a wood/PVC round block. complete for each outlet. - Long point above 6Mtr up to 10Mtr from tapping point to out let via switch ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Point570.0570.0129.0FalseNoneNoneFalseNoneFalse73530.00
3995570154605None2.1.4 of Part III Utilization (PWD Electrical)Supplying and wiring adopting loop system in existing PVC Conduit /casing capping casing capping using 2x1.5mm (Phase & Neutral) & 1x1.0 mm 2 (Earth wire) FRLS multi strand PVC insulated copper wire (confirming to IS-694: and latest amendments) with a 6A, flush type SP control switch shall be fixed on the existing plastic sheet/ gang box, the other end of the wires shall be terminated with sufficient loose length in a wood/PVC round block. complete for each outlet. - Two outlet in a row, above 3Mtr upto 6Mtr from tapping point to out let via switches. " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Point708.0708.0213.0FalseNoneNoneFalseNoneFalse150804.00
3995571154605None2.1.5 of Part III Utilization (PWD Electrical)Supplying and wiring adopting loop system in existing PVC Conduit /casing capping casing capping using 2x1.5mm (Phase & Neutral) & 1x1.0 mm 2 (Earth wire) FRLS multi strand PVC insulated copper wire (confirming to IS-694: and latest amendments) with a 6A, flush type SP control switch shall be fixed on the existing plastic sheet/ gang box, the other end of the wires shall be terminated with sufficient loose length in a wood/PVC round block. complete for each outlet. - Three outlet in a row, above 6Mts upto 10Mtr from tapping point to out let via switches " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Point1035.01035.0123.0FalseNoneNoneFalseNoneFalse127305.00
3995572154605None3.4.1 of Part III Utilization (PWD Electrical)Supplying and fixing surface/flush mounting powder coated / galvanized metal box suitable for mounting modular switch plates. The box should be firmly flush mounted after due groove cutting in Brick/Stone/C.C wall. 1-3 Way ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each159.0159.0943.0FalseNoneNoneFalseNoneFalse149937.00
3995573154605None3.4.2 of Part III Utilization (PWD Electrical)Supplying and fixing surface/flush mounting powder coated / galvanized metal box suitable for mounting modular switch plates. The box should be firmly flush mounted after due groove cutting in Brick/Stone/C.C wall. 4-5 Way ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each177.0177.0225.0FalseNoneNoneFalseNoneFalse39825.00
3995574154605None3.4.3 of Part III Utilization (PWD Electrical)Supplying and fixing surface/flush mounting powder coated / galvanized metal box suitable for mounting modular switch plates. The box should be firmly flush mounted after due groove cutting in Brick/Stone/C.C wall. 6 Way ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each220.0220.0108.0FalseNoneNoneFalseNoneFalse23760.00
3995575154605None3.4.4 of Part III Utilization (PWD Electrical)Supplying and fixing surface/flush mounting powder coated / galvanized metal box suitable for mounting modular switch plates. The box should be firmly flush mounted after due groove cutting in Brick/Stone/C.C wall. 8 Way ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each261.0261.082.0FalseNoneNoneFalseNoneFalse21402.00
3995576154605None3.4.5 of Part III Utilization (PWD Electrical)Supplying and fixing surface/flush mounting powder coated / galvanized metal box suitable for mounting modular switch plates. The box should be firmly flush mounted after due groove cutting in Brick/Stone/C.C wall. 10-12Way ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each319.0319.068.0FalseNoneNoneFalseNoneFalse21692.00
3995577154605None3.4.6 of Part III Utilization (PWD Electrical)Supplying and fixing surface/flush mounting powder coated / galvanized metal box suitable for mounting modular switch plates. The box should be firmly flush mounted after due groove cutting in Brick/Stone/C.C wall. 16Way ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each363.0363.042.0FalseNoneNoneFalseNoneFalse15246.00
3995578154605None3.5.1 of Part III Utilization (PWD Electrical)Supplying and fixing superior quality modular switch mounting polycarbonate plate with necessary supporting back plate with required nos. of machine screws, bolts nuts etc, complete on the existing metal/PVC box. 1 to 3 Module ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each161.0161.0943.0FalseNoneNoneFalseNoneFalse151823.00
3995579154605None3.5.2 of Part III Utilization (PWD Electrical)Supplying and fixing superior quality modular switch mounting polycarbonate plate with necessary supporting back plate with required nos. of machine screws, bolts nuts etc, complete on the existing metal/PVC box. 4 Module ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each175.0175.0225.0FalseNoneNoneFalseNoneFalse39375.00
3995580154605None3.5.3 of Part III Utilization (PWD Electrical)Supplying and fixing superior quality modular switch mounting polycarbonate plate with necessary supporting back plate with required nos. of machine screws, bolts nuts etc, complete on the existing metal/PVC box. 6 Module ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each234.0234.0108.0FalseNoneNoneFalseNoneFalse25272.00
3995581154605None3.5.4 of Part III Utilization (PWD Electrical)Supplying and fixing superior quality modular switch mounting polycarbonate plate with necessary supporting back plate with required nos. of machine screws, bolts nuts etc, complete on the existing metal/PVC box. 8 Module ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each284.0284.082.0FalseNoneNoneFalseNoneFalse23288.00
3995582154605None3.5.5 of Part III Utilization (PWD Electrical)Supplying and fixing superior quality modular switch mounting polycarbonate plate with necessary supporting back plate with required nos. of machine screws, bolts nuts etc, complete on the existing metal/PVC box. 10 Module ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each344.0344.068.0FalseNoneNoneFalseNoneFalse23392.00
3995583154605None3.5.6 of Part III Utilization (PWD Electrical)Supplying and fixing superior quality modular switch mounting polycarbonate plate with necessary supporting back plate with required nos. of machine screws, bolts nuts etc, complete on the existing metal/PVC box. 12 Module ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each344.0344.068.0FalseNoneNoneFalseNoneFalse23392.00
3995584154605None3.5.7 of Part III Utilization (PWD Electrical)Supplying and fixing superior quality modular switch mounting polycarbonate plate with necessary supporting back plate with required nos. of machine screws, bolts nuts etc, complete on the existing metal/PVC box. 16 Module ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each397.0397.042.0FalseNoneNoneFalseNoneFalse16674.00
3995585154605None3.6.1 of Part III Utilization (PWD Electrical)Supplying and fixing of modular switch/ Socket/Stepped electronic fan regulator/ dimmer / telephone socket etc on existing modular switch plate as per IS 3854 and IS 1293. 6Amps One Way. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each102.0102.0504.0FalseNoneNoneFalseNoneFalse51408.00
3995586154605None3.6.2 of Part III Utilization (PWD Electrical)Supplying and fixing of modular switch/ Socket/Stepped electronic fan regulator/ dimmer / telephone socket etc on existing modular switch plate as per IS 3854 and IS 1293. 6Amps Two Way. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each166.0166.074.0FalseNoneNoneFalseNoneFalse12284.00
3995587154605None3.6.3 of Part III Utilization (PWD Electrical)Supplying and fixing of modular switch/ Socket/Stepped electronic fan regulator/ dimmer / telephone socket etc on existing modular switch plate as per IS 3854 and IS 1293. 6Amps 3way socket. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each171.0171.0504.0FalseNoneNoneFalseNoneFalse86184.00
3995588154605None3.6.4 of Part III Utilization (PWD Electrical)Supplying and fixing of modular switch/ Socket/Stepped electronic fan regulator/ dimmer / telephone socket etc on existing modular switch plate as per IS 3854 and IS 1293. 'Stepped Fan Regulator. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each357.0357.0208.0FalseNoneNoneFalseNoneFalse74256.00
3995589154605None3.6.9 of Part III Utilization (PWD Electrical)Supplying and fixing of modular switch/ Socket/Stepped electronic fan regulator/ dimmer / telephone socket etc on existing modular switch plate as per IS 3854 and IS 1293. 6 Amps Bell Push ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each177.0177.013.0FalseNoneNoneFalseNoneFalse2301.00
3995590154605None3.6.11 of Part III Utilization (PWD Electrical)Supplying and fixing of modular switch/ Socket/Stepped electronic fan regulator/ dimmer / telephone socket etc on existing modular switch plate as per IS 3854 and IS 1293. 6/16Amps Universal Socket ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each236.0236.072.0FalseNoneNoneFalseNoneFalse16992.00
3995591154605None3.6.7 of Part III Utilization (PWD Electrical)Supplying and fixing of modular switch/ Socket/Stepped electronic fan regulator/ dimmer / telephone socket etc on existing modular switch plate as per IS 3854 and IS 1293. 16A One Way Switch " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each180.0180.072.0FalseNoneNoneFalseNoneFalse12960.00
3995592154605None3.6.12 of Part III Utilization (PWD Electrical)Supplying and fixing of modular switch/ Socket/stepped electronic fan regulator/ dimmer/telephone socket etc on existing modular switch plate as per IS 3854 and IS 1293 TV/Telephone socket ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each156.0156.046.0FalseNoneNoneFalseNoneFalse7176.00
3995593154605None3.6.13 of Part III Utilization (PWD Electrical)Supplying and fixing of modular switch/ Socket/stepped electronic fan regulator/ dimmer/telephone socket etc on existing modular switch plate as per IS 3854 and IS 1293 RJ45/I.O Outlet Cat-6 Socket " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each337.0337.022.0FalseNoneNoneFalseNoneFalse7414.00
3995594154605None8.2.2 of Part III Utilization (PWD Electrical)Supplying and drawing PVC flexible two pair telephone unarmoured tinned copper cable. 2 Pair." ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr21.021.01380.0FalseNoneNoneFalseNoneFalse28980.00
3995595154605None8.3 of Part III Utilization (PWD Electrical)Supplying and drawing PVC insulated gas injected physical foam jelly flooded co-axial TV cable.RG- 6 ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr44.044.0920.0FalseNoneNoneFalseNoneFalse40480.00
3995596154605None8.1 of Part III Utilization (PWD Electrical)Supplying and drawing UTP-CAT 6E LAN cable " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr34.034.060.0FalseNoneNoneFalseNoneFalse2040.00
3995597154605None2.3.2 of Part III Utilization (PWD Electrical)Wiring for lighting/power circuit using one of FRLS PVC insulated 1100V grade, multistrand Copper with low conductor resistance single core wire in open or concealed system of wiring. with specified IS-694:1990 & conforming to GTP 1.5 sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr26.026.0570.0FalseNoneNoneFalseNoneFalse14820.00
3995598154605None2.3.3 of Part III Utilization (PWD Electrical)Wiring for lighting/power circuit using one of FRLS PVC insulated 1100V grade, multistrand Copper with low conductor resistance single core wire in open or concealed system of wiring. with specified IS-694:1990 & conforming to GTP 2.5 sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr42.042.01140.0FalseNoneNoneFalseNoneFalse47880.00
3995599154605None2.3.4 of Part III Utilization (PWD Electrical)Wiring for lighting/power circuit using one of FRLS PVC insulated 1100V grade, multistrand Copper with low conductor resistance single core wire in open or concealed system of wiring. with specified IS-694:1990 & conforming to GTP 4 sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr63.063.02350.0FalseNoneNoneFalseNoneFalse148050.00
3995600154605None2.3.5 of Part III Utilization (PWD Electrical)Wiring for lighting/power circuit using one of FRLS PVC insulated 1100V grade, multistrand Copper with low conductor resistance single core wire in open or concealed system of wiring. with specified IS-694:1990 & conforming to GTP 6 sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr92.092.03000.0FalseNoneNoneFalseNoneFalse276000.00
3995601154605None3.10.3 of Part III Utilization (PWD Electrical)Extra for supplying 4mm thick white plastic plate and covering for junction boxes of size 110 mm conduit using necessary machine screws. 110mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos21.021.0616.0FalseNoneNoneFalseNoneFalse12936.00
3995602154605None1.13 of Part III Utilization (PWD Electrical)Supplying and Fixing Metal Fan Box with Round Hook. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos117.0117.0208.0FalseNoneNoneFalseNoneFalse24336.00
3995603154605None12.45 of Part III Utilization (PWD Electrical)Supplying & Fixing of 230 V 20/40 W Fluorescent Lamp holder " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each33.033.01045.0FalseNoneNoneFalseNoneFalse34485.00
3995604154605None11.15 of Part III Utilization (PWD Electrical)Supplying and fixing of LED Bulkhead of 10W with IP65 protection and IK 08 impact resistance suitable for surface and wall mounting applications. " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each842.0842.025.0FalseNoneNoneFalseNoneFalse21050.00
3995605154605None11.11.7 of Part III Utilization (PWD Electrical)Supplying & fixing of retrofit type - LED bulb . W with OPAL acrylic diffuser comprising of LED source with CCT 6500 degree K, CRI 70%. efficacy 80 lumen per W, life 25000 burning hours and Compliance to IS 10322/IEC 60598, LM 79 & LM 80. The LED are driven by HF electronic driver integrated in the system, with PF 0.95, power loss should 5% of lamp Wage., short circuit & open circuit protection to be integrated in the circuit, THD less than 20%, Life as per LM 79. The operating input voltage should be between 130 to 275 V. BIS Approved and Tested by NABL/CPRI accredited laboratory with 2 years Warranty against any manufacturing defect working under standard electrical condition. - 18W, 6500K ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No426.0426.0256.0FalseNoneNoneFalseNoneFalse109056.00
3995606154605None11.11.5 of Part III Utilization (PWD Electrical)Supplying & fixing of retrofit type - LED bulb . W with OPAL acrylic diffuser comprising of LED source with CCT 6500 degree K, CRI 70%. efficacy 80 lumen per W, life 25000 burning hours and Compliance to IS 10322/IEC 60598, LM 79 & LM 80. The LED are driven by HF electronic driver integrated in the system, with PF 0.95, power loss should 5% of lamp Wage., short circuit & open circuit protection to be integrated in the circuit, THD less than 20%, Life as per LM 79. The operating input voltage should be between 130 to 275 V. BIS Approved and Tested by NABL/CPRI accredited laboratory with 2 years Warranty against any manufacturing defect working under standard electrical condition. - 12W, 6500K ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No269.0269.0289.0FalseNoneNoneFalseNoneFalse77741.00
3995607154605None11.2.1 of Part III Utilization (PWD Electrical)Supplying & fixing retrofit type-PL- LED Lamp . W LED linear source with CCT 6500 degree K, CRI 70%. efficacy 80 lumen per W, life 25000 burning hours and Compliance to IS 10322/IEC 60598, LM 79 & LM 80. The LED are driven by HF electronic driver integrated in the system, with PF 0.95, power loss should 5% of lamp Wage., short circuit & open circuit protection to be integrated in the circuit, THD less than 20%, Life as per LM 79. The operating input voltage should be between 130 to275 V. Tested by NABL/CPRI accredited laboratory with 2 years Warranty against any manufacturing defect working under standard electrical condition. - 8-9 W " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No623.0623.054.0FalseNoneNoneFalseNoneFalse33642.00
3995608154605None11.3.32 of Part III Utilization (PWD Electrical)Supplying of .feet -PVC Batten with integrated LED tube . W with high quality diffuser with Life of 25000 burning hours & 70% lumen maintenance with CRI 80. Power Input: 220-240V@ 50/60Hz & Power factor 0.9 along with CE approved. 2 years Warranty against any manufacturing defect working under standard electrical condition. - LED light fitting 1 x 4' - 20/22 W " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each690.0690.0468.0FalseNoneNoneFalseNoneFalse322920.00
3995609154605None11.9.1 of Part III Utilization (PWD Electrical)Supply of LED floodlight luminaire with pressure die cast aluminium housing body for optimal thermal dissipation. Lamp compartment comprising of anti glare clear diffuser with Injection moulded polycarbonate/clear glass material, delivering superior light output Rated life Burning Hrs 50000 hr @ Lumen Maintenance of 70%, CCT 5500K, IP 66 optical and electrical compartment & impact resistance of complete luminaire IK08. Power Factor 0.9 with mains, Surge Protection- Min 5KV along with Over voltage/ Overload, short circuit/ miss-wiring protection. Compatible for pole mauling with outer dia of 40mm to 50mm. Universal voltage driver to operate wide voltage range from 100 V to 270V 50/60Hz application. Compliance to IS 10322/ IEC 60598, LM 79 & LM 80 Adherence with RoHS. UL approved MCPCB. Top access street light with single screw to ensure ease of maintenance at the sight site location with minimized minimal tools. LED Light fixture with . W System Power consumption. LED Efficiency 1301m/w, nominal CRI 75. Luminaire manufacturer should have in- house facility accredited by NABL / CPRI & any Government certified agency & Design & Development facility certified by ISO 9001:2008. Housing with supplier word mark / name shall be Engraved / Embossing on the die cast housing / Body part Warranty of 2 Years against any manufacturing defect working under standard electrical conditions as mentioned above should be given by LED manufacturer & Cree/Nichia/ Lumileds/Osram make LED Source. - LED Floodlight 70W " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each6768.06768.035.0FalseNoneNoneFalseNoneFalse236880.00
3995610154605None6.2.1 of Part III Utilization (PWD Electrical)Supplying of 1440rpm heavy duty exhaust fan bracket blades suitable to operate on 230V 50Hz, AC Supply complete.12"Sweep(300mm) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each2969.02969.0104.0FalseNoneNoneFalseNoneFalse308776.00
3995611154605None13.14 of Part III Utilization (PWD Electrical)Fixing one exhaust fan in the nitch already left in the wall with bolts and nuts and 5 amps ceiling rose with sufficient length of 23 / 0.0076 inch PVC insulated twin core wire of approved make. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each492.0492.0104.0FalseNoneNoneFalseNoneFalse51168.00
3995612154605None6.4.1 of Part III Utilization (PWD Electrical)Supplying of Ceiling Fan with Capacitor rating As per guideline of BEE 5 star rating and IS:374/19 and also comply with IS: 1709/1984 with latest amendment, rated voltage 220 V/50 Hz, Rated power upto 35 W +/- 10 %, Rated current As per IS:374/19, Rated power factor 0.9 lagging(min), Rated speed 350 +/- 10% RPM, rated air delivery 210 +/- 10% Cubic Meter Minimum, Rated service value 6.2 CMM / W, Three Blades of blade leaf 1.05 mm thick Aluminium Alloy sheet, Class B motor insulation, Bearing Two ball bearings, Top 6202, Bottom 6201, as per IS specification, Motor winding. Temp rise Shall not exceed 75 deg C over and ambient of 40 0C by resistance method at 245 V, Insulation resistance Shall not be less than Two Mega Ohms (2M Ohms), Leakage current Should not exceed 210 micro Amp, Power input, W& current, Air Delivery & Fan Speed as per IS:374/2019 with latest amendment, 2year manufacturer Warranty. (BLDC fans) - 48"" Sweep 5 Star (1200 mm) " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each2677.02677.0208.0FalseNoneNoneFalseNoneFalse556816.00
3995613154605None13.10 of Part III Utilization (PWD Electrical)Fixing a ceiling/Wall mounting fan of all capacities and all types to the existing 'S' hook with fan regulator to the existing board together with supplying and fixing a 5 amps, ceiling rose, necessary length of 23 / 0.0076 inch PVC insulated twin twisted copper wire and wiring ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each171.0171.0208.0FalseNoneNoneFalseNoneFalse35568.00
3995614154605None5.6.5 of Part III Utilization (PWD Electrical)Supply and fixing polished wood board made of not less than 15mm thick plank on both sides of not more than 2 pieces and fixing the same to the wall using tapered inverted wooden plugs screws. - 15"" x 12"" x 2"" " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each201.0201.06.0FalseNoneNoneFalseNoneFalse1206.00
3995615154605None5.7.4 of Part III Utilization (PWD Electrical)Supplying & fixing of Porcelain fuse channel with cut out on existing wooden/panel using necessary nuts, bolts and washers. - 100A ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each691.0691.024.0FalseNoneNoneFalseNoneFalse16584.00
3995616154605None5.9.3 of Part III Utilization (PWD Electrical)Supplying and fixing HRC fuse units base on existing switch / panel board - 100 to 300A ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each919.0919.024.0FalseNoneNoneFalseNoneFalse22056.00
3995617154605None5.10.2 of Part III Utilization (PWD Electrical)Supplying and fixing HRC fuse link on existing switch fuse base with W loss as per IS-13703. - Above 63 A to 200 A " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each381.0381.024.0FalseNoneNoneFalseNoneFalse9144.00
3995618154605None5.42.2 of Part III Utilization (PWD Electrical)Fabricating supplying and mounting MS box made out 16 SWG suitable for floor / wall mounting, fully weather proof with provision for better heat dissipation, provided with hinged front cover, equipped with tamper proof locking arrangements, with suitable size clamps with necessary cable entry pipe with gland and box should be finished with 2 coats of red oxide primer paint and finally finished with approved colour enameled metal paint etc., complete. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sq CM0.430.43108000.0FalseNoneNoneFalseNoneFalse46440.00
3995619154605None5.40.1 of Part III Utilization (PWD Electrical)Supplying 100 amps rated 4x30x6mm Alluminium Strips 3phase with neutral bus bar using required capacity electrolytic alluminium strips covered with heat shrinkable coloured PVC sleeve, mounted on phenolic/FRP/DMC insulator which are mounted on powder coated 40x6mm M.S.flat frame work in existing MDB. The bus bar shall have suitable holes for termination of incoming and outgoing cables as per IS specification with necessary botls,nuts and washers etc., complete - 100 A 4 x 30 x 6 mm Aluminium Strips " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr2465.02465.024.0FalseNoneNoneFalseNoneFalse59160.00
3995620154605None3.9 of Part III Utilization (PWD Electrical)Supplying and fixing hylum plastic sheet 3mm thick with necessary nitches for fixing switches, regulators etc., and fixing on existing wood or metal box using N.F screws. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sq CM0.350.3527000.0FalseNoneNoneFalseNoneFalse9450.00
3995621154605None5.38 of Part III Utilization (PWD Electrical)Supplying and fixing of LED type panel board indicating lamp with required colour suitable for 220v A.C. 50 Hz 12/24v D.C. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each515.0515.018.0FalseNoneNoneFalseNoneFalse9270.00
3995622154605None5.31 of Part III Utilization (PWD Electrical)Supplying and fixing Electronic Trivector Meter (ETV) suitable for operation LT operation and -CT operated meter in polycarbonate body in class 0.5 accuracy as per IS 14697 and completely wired. " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each4390.04390.07.0FalseNoneNoneFalseNoneFalse30730.00
3995623154605None5.30 of Part III Utilization (PWD Electrical)Supplying, fixing and wiring Electronic Trivector Meter (ETV) 5 to 20A single phase Class-1 Accuracy with Temper Proof Energy Meter. " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1380.01380.08.0FalseNoneNoneFalseNoneFalse11040.00
3995624154605None5.21 of Part III Utilization (PWD Electrical)Supplying, fixing and wiring earth leakage relay with core balanced current transformer suitable for single phase 50 Hz AC with latest microcontroller based, digital readout of percentage leakage current, programmable delay/auto/ manual reset facility suitable to mount on DIN rail/ flush mounting on panel board. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each9255.09255.06.0FalseNoneNoneFalseNoneFalse55530.00
3995625154605None5.11.2 of Part III Utilization (PWD Electrical)Supplying of on load change over switches 4 poles, AC-23A Duty, 415V, 50Hz, AC Supply. (Open Execution) - 100A ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each7090.07090.05.0FalseNoneNoneFalseNoneFalse35450.00
3995626154605None5.15.9 of Part III Utilization (PWD Electrical)Supplying and fixing Moulded Case Circuit Breaker (MCCB) over the existing wood/panel board using necessary screws, bolts, nuts, necessary phase separators, handle and wiring complete. Protection of Overload and Short circuitwith adjustable thermal magnetic release, Micro processor release shall have Earth Fault as per IS/IEC 60947-2 . (Icu=100% lcs). In 4P MCCB, all Poles should have protection for Short-Cicrcuit/Over Load. For Microprocessor MCCBS Facility for segregating Priority and Non-Priority loads must be available in the MCCB. MCCB shall be provided with double insulation (insulation between front cover and internal power circuits to avoid any accidental contact with live current carrying path with the front cover open). Multi-pole breakers shall be designed to break all the poles simultaneously and they shall have a single mechanism. - 100A, 25kA, 4 Pole ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each8487.08487.06.0FalseNoneNoneFalseNoneFalse50922.00
3995627154605None5.16 of Part III Utilization (PWD Electrical)Supplying and fixing of Shunt trip suitable for MCCB.CBCT " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1703.01703.06.0FalseNoneNoneFalseNoneFalse10218.00
3995628154605None5.34 of Part III Utilization (PWD Electrical)Supplying, fixing and wiring 50/5 to 400/5A 5VA burden Current Transformer Class 0.5 accuracy with Tape Wound. " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each562.0562.033.0FalseNoneNoneFalseNoneFalse18546.00
3995629154605None5.33 of Part III Utilization (PWD Electrical)Supplying of multi function digital meter with three line back light LCD type display for voltage, Current, frequency, Power, power factor, kVA, kWH, kVAR suitable for 3 phase, 4 wire LT network with IP 54 degree of protection and completely wired as required with communication Port and Class 0.5s accuracy ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each9315.09315.06.0FalseNoneNoneFalseNoneFalse55890.00
3995630154605None5.18.9 of Part III Utilization (PWD Electrical)Supplying and fixing miniature circuit breakers on existing MCB distribution boards using necessary fixing materials and 'C' Type curve , indicator ON/OFF, energy cross-3 with Short circuit breaking capacity of 10K and complete wiring as required. c) 63Amps TPN ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each3088.03088.023.0FalseNoneNoneFalseNoneFalse71024.00
3995631154605None5.18.4 of Part III Utilization (PWD Electrical)Supplying and fixing miniature circuit breakers on existing MCB distribution boards using necessary fixing materials and 'C' Type curve , indicator ON/OFF, energy cross-3 with Short circuit breaking capacity of 10K and complete wiring as required. c) 6 - 32Amps DP ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each739.0739.031.0FalseNoneNoneFalseNoneFalse22909.00
3995632154605None5.1 of Part III Utilization (PWD Electrical)Supplying push button operated direct online starter with an antiweld silver cadmium oxide contactor with replaceable fixed and moving contacts and bimetallic thermal overload relay help in anticorrosion treated sheet steel or iron clad enclosure and fixing the same to suitable capacity wires for 230/440 V 1/3 phase motor upto 5 HP. " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1927.01927.011.0FalseNoneNoneFalseNoneFalse21197.00
3995633154605None5.19.13 of Part III Utilization (PWD Electrical)Supplying and fixing regular MCB distribution boards on wall / wood board / flush mounting using required clamps, bolts, nuts etc., with provision for fixing suitable type capacity MCB's single phase / 3 phase / single door with powder coated painting. Made out of 14 SWG MS enclosure. III- Double Door 12way TP & N ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each8735.08735.012.0FalseNoneNoneFalseNoneFalse104820.00
3995634154605None5.19.10 of Part III Utilization (PWD Electrical)Supplying and fixing regular MCB distribution boards on wall / wood board / flush mounting using required clamps, bolts, nuts etc., with provision for fixing suitable type capacity MCB's single phase / 3 phase / single door with powder coated painting. Made out of 14 SWG MS enclosure. III- Double Door 16way SP & N ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each2908.02908.08.0FalseNoneNoneFalseNoneFalse23264.00
3995635154605None5.18.9 of Part III Utilization (PWD Electrical)Supplying and fixing miniature circuit breakers on existing MCB distribution boards using necessary fixing materials and 'C' Type curve, indicator ON/OFF, energy cross-3 with Short circuit breaking capacity of 10K and complete wiring as required. 50-63Amps TPN ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each3088.03088.03.0FalseNoneNoneFalseNoneFalse9264.00
3995636154605None5.18.7 of Part III Utilization (PWD Electrical)Supplying and fixing miniature circuit breakers on existing MCB distribution boards using necessary fixing materials and 'C' Type curve , indicator ON/OFF, energy cross-3 with Short circuit breaking capacity of 10K and complete wiring as required. c) 5-32Amps TPN ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1717.01717.09.0FalseNoneNoneFalseNoneFalse15453.00
3995637154605None5.20.10 of Part III Utilization (PWD Electrical)Supplying, fixing and wiring Earth Leakage Miniature Circuit Breaker [ELMCB] 240/450V up to 300mA sensitivity on existing wood/panel board. - 63 A 4 pole " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each5147.05147.09.0FalseNoneNoneFalseNoneFalse46323.00
3995638154605None5.20.4 of Part III Utilization (PWD Electrical)Supplying, fixing and wiring Earth Leakage Miniature Circuit Breaker [ELMCB] 240/450V up to 300mA sensitivity on existing wood/panel board. - 32 to 40 Amps 2 pole " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each4559.04559.035.0FalseNoneNoneFalseNoneFalse159565.00
3995639154605None5.18.1 of Part III Utilization (PWD Electrical)Supplying and fixing miniature circuit breakers on existing MCB distribution boards using necessary fixing materials and 'C' Type curve , indicator ON/OFF, energy cross-3 with Short circuit breaking capacity of 10K and complete wiring as required. c) 5-32Amps SP ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each415.0415.0384.0FalseNoneNoneFalseNoneFalse159360.00
3995640154605None12.56 of Part III Utilization (PWD Electrical)Supplying, fixing, wiring, earth electrode for grounding conduits, I.C. cutouts and other equipment's on the meter board using 40 mm dia 2.90 mm thick GI pipe 2.5m long buried in a pit . The pit should be filled with equal proportion of salt and charcoal 150 mm all-round the pipe to complete depth. The connection from the pipe to the conduit etc., is to be established through GI wire of size as per lSI specification 7.3.3. of IS 732 using 12 mm dia bolts, nuts, washers and check nuts etc., the pipe shall have 16 through holes of 12 mm dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos3510.03510.012.0FalseNoneNoneFalseNoneFalse42120.00
3995641154605None32.18, of Standard Stock Material (11kV System) - Supplying of 1.1 kV, XLPE or Heat resistant PVC insulated, PVC exutruted Inner Seath Armoured LTUG Cable as per IS-1554 (Part1) or IS-7098 Part-1, Armouring strip thickness and resistivity as per IS-3975 - 3.5 core 240sqmm (2Runs) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr862.67862.67100.0FalseNoneNoneFalseNoneFalse86267.00
3995642154605None32.13, of Standard Stock Material (11kV System) - Supplying of 1.1 kV, XLPE or Heat resistant PVC insulated, PVC exutruted Inner Seath Armoured LTUG Cable as per IS-1554 (Part1) or IS-7098 Part-1, Armouring strip thickness and resistivity as per IS-3975 - 3.5 core 70sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr317.91317.91670.0FalseNoneNoneFalseNoneFalse212999.70
3995643154605None32.07, of Standard Stock Material (11kV System) - Supplying of 1.1 kV, XLPE or Heat resistant PVC insulated, PVC exutruted Inner Seath Armoured LTUG Cable as per IS-1554 (Part1) or IS-7098 Part-1, Armouring strip thickness and resistivity as per IS-3975 - 3.5core 25sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr139.55139.5560.0FalseNoneNoneFalseNoneFalse8373.00
3995644154605None32.03, of Standard Stock Material (11kV System) - Supplying of 1.1 kV, XLPE or Heat resistant PVC insulated, PVC exutruted Inner Seath Armoured LTUG Cable as per IS-1554 (Part1) or IS-7098 Part-1, Armouring strip thickness and resistivity as per IS-3975 4core 10sqmm i)Security Room ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr118.0118.040.0FalseNoneNoneFalseNoneFalse4720.00
3995645154605None21.05, of Labour Charges (11kV System) - Part II DLabour charges for laying of 1.1 KV class UG cable in existing trench GI pipe / stoneware pipe / on wall / on pole as required - In exixting trench/duct. 2.5 sqmm to 25 sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr20.8920.8940.0FalseNoneNoneFalseNoneFalse835.60
3995646154605None21.06, of Labour Charges (11kV System) - Part II DLabour charges for laying of 1.1 KV class UG cable in existing trench GI pipe / stoneware pipe / on wall / on pole as required - In exixting trench/duct. 35 sqmm to 95 sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr31.1431.14670.0FalseNoneNoneFalseNoneFalse20863.80
3995647154605None21.07, of Labour Charges (11kV System) - Part II DLabour charges for laying of 1.1 KV class UG cable in existing trench GI pipe / stoneware pipe / on wall / on pole as required - In exixting trench/duct. 120 to 240 Sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr32.2832.28100.0FalseNoneNoneFalseNoneFalse3228.00
3995648154605None1.6.1Earth work excavation for pipelines/cables by Manual means upto 600 mm trench width, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter, including dressing of excavated surfaces, disposing off or leveling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m. Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering and lift upto 1.5 m including cost of labour, tools, usage& other appurtenances required to complete the work. In all kinds of soils. Depth upto 1.50m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m484.0484.054.0FalseNoneNoneFalseNoneFalse26136.00
3995649154605None11.2.6Providing, Laying and Fixing of GI pipes conforming to IS 1239:1990 with latest amendments complete with GI fittings (excluding the cost of fittings) with cuts and threads wherever necessary, including testing for water tightness, with all lead and commissioning. (contractor will make his own arrangements for procuring water for testing) For:Heavy Duty GI Pipe etc. complete. Medium Duty GI pipe of 50mm dia" ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr584.0584.060.0FalseNoneNoneFalseNoneFalse35040.00
3995650154605None30.12, of Major Work Materials Equipments (Part Supplying and fixing of class B (medium duty) GI pipe of wall thickness not less than 3.25mm on pole/wall/drain crossing with necessary clamping arrangements for UG cable of 1.1 KV class - 100 mm Road Crossing for all buildings ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr1350.01350.0200.0FalseNoneNoneFalseNoneFalse270000.00
3995651154605None35.04, of Standard Stock Material (11kV System) - Supplying and fixing Epoxy Terminating Kit (Pothead) suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 3.5 x 225/240/300 Sqmm " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each588.0588.02.0FalseNoneNoneFalseNoneFalse1176.00
3995652154605None35.02, of Standard Stock Material (11kV System) - Supplying and fixing Epoxy Terminating Kit (Pothead) suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 3.5 x 70/95/120 Sqmm " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each382.0382.012.0FalseNoneNoneFalseNoneFalse4584.00
3995653154605None35.01, of Standard Stock Material (11kV System) - Supplying and fixing Epoxy Terminating Kit (Pothead) suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - Up to 4C x 50 Sqmm " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each324.0324.014.0FalseNoneNoneFalseNoneFalse4536.00
3995654154605None59.10, of Standard Stock Material (11kV System) - Supplying and fixing Heavy Duty Copper Terminal Long Barrel suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 240 Sqmm Copper Terminal, Apprx Wt: 218 Gm " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each355.0355.012.0FalseNoneNoneFalseNoneFalse4260.00
3995655154605None59.06, of Standard Stock Material (11kV System) - Supplying and fixing Heavy Duty Copper Terminal Long Barrel suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 120 Sqmm Copper Terminal, Apprx Wt: 64 Gm " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each140.0140.06.0FalseNoneNoneFalseNoneFalse840.00
3995656154605None59.04, of Standard Stock Material (11kV System) - Supplying and fixing Heavy Duty Copper Terminal Long Barrel suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 70 Sqmm Copper Terminal, Apprx Wt: 38 Gm " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each89.089.036.0FalseNoneNoneFalseNoneFalse3204.00
3995657154605None59.02, of Standard Stock Material (11kV System) - Supplying and fixing Heavy Duty Copper Terminal Long Barrel suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 35 Sqmm Copper Terminal, Apprx Wt: 17 Gm " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each40.040.012.0FalseNoneNoneFalseNoneFalse480.00
3995658154605None59.01, of Standard Stock Material (11kV System) vSupplying and fixing Heavy Duty Copper Terminal Long Barrel suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 25 Sqmm Copper Terminal, Apprx Wt: 11 Gm " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each27.027.048.0FalseNoneNoneFalseNoneFalse1296.00
3995659154605None60.12, of Standard Stock Material (11kV System) - Supplying and fixing Aluminium End Terminal (Lug) suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 240 Sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each61.061.012.0FalseNoneNoneFalseNoneFalse732.00
3995660154605None60.08, of Standard Stock Material (11kV System) - Supplying and fixing Aluminium End Terminal (Lug) suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 120 Sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each20.020.06.0FalseNoneNoneFalseNoneFalse120.00
3995661154605None60.06, of Standard Stock Material (11kV System) - Supplying and fixing Aluminium End Terminal (Lug) suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 70 Sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each13.013.036.0FalseNoneNoneFalseNoneFalse468.00
3995662154605None60.04, of Standard Stock Material (11kV System) - Supplying and fixing Aluminium End Terminal (Lug) suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 35 Sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each4.04.012.0FalseNoneNoneFalseNoneFalse48.00
3995663154605None60.03, of Standard Stock Material (11kV System) - Supplying and fixing Aluminium End Terminal (Lug) suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 25 Sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each3.03.036.0FalseNoneNoneFalseNoneFalse108.00
3995664154605None60.02, of Standard Stock Material (11kV System) - Supplying and fixing Aluminium End Terminal (Lug) suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 16 Sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each2.02.012.0FalseNoneNoneFalseNoneFalse24.00
3995665154605None60.01, of Standard Stock Material (11kV System) - Supplying and fixing Aluminium End Terminal (Lug) suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 10 Sqmm a) Security Room ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each2.02.08.0FalseNoneNoneFalseNoneFalse16.00
3995666154605None63.01, of Standard Stock Material (11kV System) - Supplying and fixing Brass Cable Gland suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 25mm dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each79.079.014.0FalseNoneNoneFalseNoneFalse1106.00
3995667154605None63.03, of Standard Stock Material (11kV System) - Supplying and fixing Brass Cable Gland suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 40mm dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each148.0148.012.0FalseNoneNoneFalseNoneFalse1776.00
3995668154605None63.04, of Standard Stock Material (11kV System) - Supplying and fixing Brass Cable Gland suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 45mm dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each197.0197.04.0FalseNoneNoneFalseNoneFalse788.00
3995669154605None12.58.5 of Part III Utilization (PWD Electrical)Supplying and running of GI/Copper strips for grounding connections, using necessary fixing materials as required. GI Strip 50 x 6 ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr218.0218.0150.0FalseNoneNoneFalseNoneFalse32700.00
3995670154605None12.58.4 of Part III Utilization (PWD Electrical)Supplying and running of GI/Copper strips for grounding connections, using necessary fixing materials as required. GI Strip 40 x 6 ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr181.0181.050.0FalseNoneNoneFalseNoneFalse9050.00
3995671154605None12.58.3 of Part III Utilization (PWD Electrical)Supplying and running of GI/Copper strips for grounding connections, using necessary fixing materials as required. GI Strip 25x6mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr128.0128.0350.0FalseNoneNoneFalseNoneFalse44800.00
3995672154605None12.58.2 of Part III Utilization (PWD Electrical)Supplying and running of GI/Copper strips for grounding connections, using necessary fixing materials as required. GI Strip 25x3mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr82.082.0350.0FalseNoneNoneFalseNoneFalse28700.00
3995673154605None8.02 of Standard Stock Material (11kV System) - PaSupplying and running GI/Copper conductor for grounding and (along with other wires in conduit systm of wiring) using necessary suitable size clamps, nails, guttas/spacers etc. GI Wire 8SWG ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr9.839.83410.0FalseNoneNoneFalseNoneFalse4030.30
3995674154605None19.3, of Major Work Materials Equipments (Part ISupplying and fixing of DANGER / CAUTION board ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos318.0318.06.0FalseNoneNoneFalseNoneFalse1908.00
3995675154605None5.37, of Part III Utilization (PWD Electrical)Suplying fixing and wiring heavy duty low voltage capacitors conforming to IS 2834. 3 phase, 400/400 volts grade, for power factor improvement of roating machinery. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kvar480.0480.027.0FalseNoneNoneFalseNoneFalse12960.00
3995676154605None5.3, of Part III Utilization (PWD Electrical)Supplying and fixing single phase preventer using necessary wires over an existing panel board suitable for motor up to 20HP capacities. k)Sump Tank & RWH ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each904.02904.023.0FalseNoneNoneFalseNoneFalse2712.060
3995677154605None5.6.6, of Part III Utilization (PWD Electrical)Supply and fixing polished wood board made of not less than 15mm thick plank on both sides of not more than 2 pieces and fixing the same to the wall using tapered inverted wooden plugs screws. - 20"x20"x2.5" k)Sump Tank & RWH ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each326.13326.132.0FalseNoneNoneFalseNoneFalse652.260
3995678154605None5.1 of Part III Utilization (PWD Electrical)Supplying push button operated direct online starter with an antiweld silver cadmium oxide contactor with replaceable fixed and moving contacts and bimetallic thermal overload relay help in anticorrosion treated sheet steel or iron clad enclosure and fixing the same to suitable capacity wires for 400/440 volts 3 phase motor/single phase motor upto 5 Hp. k)Sump Tank ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1927.01927.06.0FalseNoneNoneFalseNoneFalse11562.00
3995679154605None15.117 of Part III Utilization (PWD Electrical)Supplying and installation of RUBBER MAT 1mtr x 1mtr -1Omm thick. complete including cost of materials, labour, usage charges of machinery complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1900.01900.023.0FalseNoneNoneFalseNoneFalse43700.00
3995680154605None15.117 of Part III Utilization (PWD Electrical)Supplying and installation of RUBBER MAT 1mtr x 1mtr -1Omm thick. complete including cost of materials, labour, usage charges of machinery complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1900.01900.023.0FalseNoneNoneFalseNoneFalse43700.00
3995681154605None1.Materia l RateMonoblock Pump set 3HP 3Phase 21 Stage 3/2.2 ATALANTA / SUGUNA / C.R.I, KIRLOSKAR and other Equivalent Pumps(XXXXV)" k)Sump Tank ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos16800.016800.03.0FalseNoneNoneFalseNoneFalse50400.00
3995682154605None13.5 of Part III Utilization (PWD Electrical)Fixing halogen/metal halide /SVL/IL/LED floodlight fitting over existing pole / wall ceiling including clamps, bolts, nuts and wiring using suitable capacity wires. " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each162.0162.035.0FalseNoneNoneFalseNoneFalse5670.00
3995683154605None13.7.1 of Part III Utilization (PWD Electrical)Fixing all types and all capacities of fluorescent /false ceiling / spot light / CFL / LED fittings indoor on the wall/ ceiling / rafters / girders using 23/0.0076" twin twisted PVC insulated wires, required Nos of round blocks and clamps. - On wall / celilin / Rafter / Girders ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each122.0122.01092.0FalseNoneNoneFalseNoneFalse133224.00
17262057300000NoneNoneBuildings11KV Line (Amble)481592.5
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3995684154606None21.08, of Standard Stock Material (11kV System) - Supply and erection of Double Pole TC structural set including all hardwares suitable for 100/300 kVA 4/5 Star Rated Transformer on RCC Pole - 9 Mtr Long, 145 Kg WL - GI " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each30694.030694.01.0FalseNoneNoneFalseNoneFalse30694.00
3995685154606None24.07, of Standard Stock Material (11kV System) - Supplying and Fixing H - Frame Set for fixing 11 kV, 200 Amps Single Break GOS - (For DP structure for providing New GOS for sectionalisation) - GI ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each6071.06071.01.0FalseNoneNoneFalseNoneFalse6071.00
3995686154606None24.01, of Standard Stock Material (11kV System) - Supplying and Fixing …. including all Hardwares etc complete as per the standard technical specification.of BESCOM - 11 kV, 200 Amps Single Break GOS ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each9450.09450.01.0FalseNoneNoneFalseNoneFalse9450.00
3995687154606None20.01, of Standard Stock Material (11kV System) - Supplying and Fixing …. including all Hardwares etc complete as per the standard technical specification.of BESCOM - 11 kV, HG Fuse Unit with Solid Core Insulator ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1069.01069.01.0FalseNoneNoneFalseNoneFalse1069.00
3995688154606None19.02, of Standard Stock Material (11kV System) - Supplying and Fixing …. including all Hardwares etc complete as per the standard technical specification of BESCOM. - 10 kV, 5 kA Lightning Arrester Polymeric type with GROUND DISCONNECTOR " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1584.01584.01.0FalseNoneNoneFalseNoneFalse1584.00
3995689154606None1.02, of Standard Stock Material (11kV System) - PSupply and erection of 9 Mtr RCC Pole including earth work etc,. complete as per the standard technical specification of BESCOM. RCC Pole - 9 Mtr Long, 150 Kg WL Sq Section " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each8316.08316.033.0FalseNoneNoneFalseNoneFalse274428.00
3995690154606None2.02, of Standard Stock Material (11kV System) - PSupply and fixing of …….cross arm including all Hardwares complete as per the standard technical specification BESCOM - 11 kV, Horizontal Cross Arm - Galvanised Iron (GI) " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each487.0487.033.0FalseNoneNoneFalseNoneFalse16071.00
3995691154606None2.12, of Standard Stock Material (11kV System) - PSupplying and Fixing …. including all Hardwares etc complete as per the standard technical specification BESCOM - HT ST Support 50x8 mm Flat - GI " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each121.0121.033.0FalseNoneNoneFalseNoneFalse3993.00
3995692154606None2.04, of Standard Stock Material (11kV System) - PSupplying and Fixing …. including all Hardwares etc complete as per the standard technical specification BESCOM - 11 kV, Special 3 Pin Cross Arm - GI " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1151.01151.04.0FalseNoneNoneFalseNoneFalse4604.00
3995693154606None5.02, of Standard Stock Material (11kV System) - PSupplying and Fixing …. including all Hardwares etc complete as per the standard technical specification - RCC Pole Clamp - GI " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each109.0109.033.0FalseNoneNoneFalseNoneFalse3597.00
3995694154606None9.03, of Standard Stock Material (11kV System) - PSupplying and fixing of P.G Clamp inluding all Hardware's etc. complete as per the standard technical specification of BESCOM ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each86.086.033.0FalseNoneNoneFalseNoneFalse2838.00
3995695154606None5.16, of Standard Stock Material (11kV System) - PSupplying and Fixing Strain Clamp, 3 Bolt type for 70/90 kN Disc Insulator including all Hardwares etc complete as per the standard technical specification of BESCOM ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each707.0707.018.0FalseNoneNoneFalseNoneFalse12726.00
3995696154606None6.06, of Standard Stock Material (11kV System) - PSupplying and Fixing ….including all Hardwares etc complete as per the standard technical specification BESCOM - 11 kV, 5 kN Composite/Polymeric Pin Insulator (24 mm dia FRP Rod) " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each205.0205.090.0FalseNoneNoneFalseNoneFalse18450.00
3995697154606None5.10,5.11,5.13,5.15, 5.16 & 8.02 of Standard StockSupplying and Fixing …. including all Hardwares etc complete as per the standard technical specification BESCOM - GUY Set ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1628.451628.4510.0FalseNoneNoneFalseNoneFalse16284.50
3995698154606None2.16, of Labour Charges (11kV System) - Part II DiProviding Spiral Earth Electrode type earthing (without charcoal, salt etc.,) " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each93.093.033.0FalseNoneNoneFalseNoneFalse3069.00
3995699154606None2.06 of Standard Stock Material (11kV System) - PaSupply and fixing of …….cross arm including all Hardwares complete as per the standard technical specification BESCOM - LT 4 Pin Cross Arm - GI " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each379.0379.04.0FalseNoneNoneFalseNoneFalse1516.00
3995700154606None7.02 of Standard Stock Material (11kV System) - PaSupplying and fixing of Rabbit ACSR (6/3.35 mm Al + 1/3.35 mm St), Std Wt: 214 Kg/KM " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr46.2346.231600.0FalseNoneNoneFalseNoneFalse73968.00
3995701154606None6.08 of Standard Stock Material (11kV System) - PaSupplying and Fixing ….including all Hardwares etc complete as per the standard technical specification BESCOM - No. 15 Strain Insulator " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each59.059.020.0FalseNoneNoneFalseNoneFalse1180.00
17262057300000NoneNoneBuildingsEstablishing Sub Station (Amble)1816176.0
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3995702154607None21.08, of Standard Stock Material (11kV System) - Supply and erection of Double Pole TC structural set including all hardwares suitable for 100/300 kVA 4/5 Star Rated Transformer on RCC Pole - 9 Mtr Long, 145 Kg WL - GI " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each30694.030694.01.0FalseNoneNoneFalseNoneFalse30694.00
3995703154607None24.07, of Standard Stock Material (11kV System) - Supplying and Fixing H - Frame Set for fixing 11 kV, 200 Amps Single Break GOS - (For DP structure for providing New GOS for sectionalisation) - GI ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each6071.06071.01.0FalseNoneNoneFalseNoneFalse6071.00
3995704154607None2.12, of Standard Stock Material (11kV System) - PSupplying and Fixing …. including all Hardwares etc complete as per the standard technical specification BESCOM - HT ST Support 50x8 mm Flat - GI " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each121.0121.04.0FalseNoneNoneFalseNoneFalse484.00
3995705154607None2.02, of Standard Stock Material (11kV System) - PSupply and fixing of …….cross arm including all Hardwares complete as per the standard technical specification BESCOM - 11 kV, Horizontal Cross Arm - Galvanised Iron (GI) " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each487.0487.02.0FalseNoneNoneFalseNoneFalse974.00
3995706154607None24.01, of Standard Stock Material (11kV System) - Supplying and Fixing …. including all Hardwares etc complete as per the standard technical specification.of BESCOM - 11 kV, 200 Amps Single Break GOS ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each9450.09450.01.0FalseNoneNoneFalseNoneFalse9450.00
3995707154607None20.01, of Standard Stock Material (11kV System) - Supplying and Fixing …. including all Hardwares etc complete as per the standard technical specification.of BESCOM - 11 kV, HG Fuse Unit with Solid Core Insulator ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1069.01069.01.0FalseNoneNoneFalseNoneFalse1069.00
3995708154607None19.02, of Standard Stock Material (11kV System) - Supplying and Fixing …. including all Hardwares etc complete as per the standard technical specification of BESCOM. - 10 kV, 5 kA Lightning Arrester Polymeric type with GROUND DISCONNECTOR " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1584.01584.01.0FalseNoneNoneFalseNoneFalse1584.00
3995709154607None5.16, of Standard Stock Material (11kV System) - PSupplying and Fixing Strain Clamp, 3 Bolt type for 70/90 kN Disc Insulator including all Hardwares etc complete as per the standard technical specification of BESCOM ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each707.0707.06.0FalseNoneNoneFalseNoneFalse4242.00
3995710154607None6.06, of Standard Stock Material (11kV System) - PSupplying and Fixing ….including all Hardwares etc complete as per the standard technical specification BESCOM - 11 kV, 5 kN Composite/Polymeric Pin Insulator (24 mm dia FRP Rod) " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each205.0205.03.0FalseNoneNoneFalseNoneFalse615.00
3995711154607None1.02, of Standard Stock Material (11kV System) - PSupply and erection of 9 Mtr RCC Pole including earth work etc,. complete as per the standard technical specification of BESCOM. RCC Pole - 9 Mtr Long, 150 Kg WL Sq Section " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each8316.08316.02.0FalseNoneNoneFalseNoneFalse16632.00
3995712154607None5.10,5.11,5.13,5.15, 5.16 & 8.02 of Standard StockSupplying and Fixing …. including all Hardwares etc complete as per the standard technical specification BESCOM - GUY Set ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1628.451628.452.0FalseNoneNoneFalseNoneFalse3256.90
3995713154607None12.57, of Part III Utilization (PWD Electrical)Supplying fixing and wiring earth electrode for grounding of lifts, transformers, DG sets etc. using 40 mm dia 2.9 mm thick 2.5m long GI pipe with GI funnel with mesh and suitable size reducer fixed on the top of the earth electrode.The funnel should be enclosed in a CC chamber of 400x400x400 mm with a cast iron cover. The earth electrode shall have staggered holes of 12 mm dia and the electrode should be covered 150 mm all-round with alternate layers of salt and charcoal from the bottom of the CC chamber. The connection from the electrode is to be established through GI strip using GI bolts and nuts. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos4256.04256.08.0FalseNoneNoneFalseNoneFalse34048.00
3995714154607None30.12, of Major Work Materials Equipments (Part Supplying and fixing of class B GI pipe on pole/wall/drain crossing with necessary clamping arrangements for UG cable of 1.1 KV class - 100 mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr1350.01350.015.0FalseNoneNoneFalseNoneFalse20250.00
3995715154607None25.02, of Standard Stock Material (11kV System) -Supplying and fixing of 11 kV, DOLO Cutout REC Specification(Dwg No. BESCOM/GM/QS&S/20 Dtd 24.11.2018) on pole/wall/drain crossing with necessary clamping arrangements for UG cable of 1.1 KV class ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Set4241.04241.03.0FalseNoneNoneFalseNoneFalse12723.00
3995716154607None45.07, of Standard Stock Material (11kV System) -Supplying and making 11KV (E) Extruded "X" linked for tubing & moulded & cross-linked components using Heat Shrink Stress Control tube having High Permittivity XLPE Terminations- INDOOR & OUTDOOR JOINTING KIT & conforming to th GTP. OUTDOOR 3cx95sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kit4067.04067.02.0FalseNoneNoneFalseNoneFalse8134.00
3995717154607None45.04, of Standard Stock Material (11kV System) -Supplying and making 11KV (E) Extruded "X" linked for tubing & moulded & cross-linked components using Heat Shrink Stress Control tube having High Permittivity XLPE Terminations- INDOOR & OUTDOOR JOINTING KIT & conforming to th GTP.INDOOR 3cx95sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kit3744.03744.02.0FalseNoneNoneFalseNoneFalse7488.00
3995718154607None36.01, of Standard Stock Material (11kV System) -HT Cable - Supplying and laying of high tension 11KV cable, Dry Curing & Dry Cooling with true triple extrusion, simultaneously through a single common head, 3 core under ground XLPE (E) cable having stranded comapact circular aluminium conductor, screened insulated, insulation screened with extruded semiconduting compound in combination with copper tape, core laid up inner sheate of PVC tape GI flat strip armoured and overall PVC sheathed with specified IS 7098/11/85 with latest amendments of conforming to the GTP . 3 Core x 95 Sqmm, (54 GI Wires - 2.5 mm Dia) (2 Runs) " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr889.67889.6750.0FalseNoneNoneFalseNoneFalse44483.50
3995719154607None12.16, of Standard Stock Material (11kV System) -Supply,erection, testing and commissioning of Distribution Transformer - 3 Phase, 11kV/433V - Stacked CRGO Core with Oil as per IS-1180 (Part-1): 2014 tap switch Butchholtz relay winding Temperature indicator, oil temperature indicator, marshalling box with wiring, magnetic oil level indicator with +5% to-10% Steps of 2.5% with HT and LT cable and boxes including all standard accessories as per latest IS Standard Technical Specification. - 100 kVA, Aluminium Wdg, Star 2 (5 Star) with cable entry type " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each225576.0225576.01.0FalseNoneNoneFalseNoneFalse225576.00
3995720154607None11.59Providing and fixing G.I. chain link fabric fencing of required width in mesh size 50x50 mm including strengthening with 2 mm dia wire or nuts, bolts and washers as required complete as per the direction of Engineerin- charge. (Made of G.I. wire of dia. 4 mm, PVC coated to achieve outer dia not less than 5 mm in required colour and shade)" ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm841.0841.093.6FalseNoneNoneFalseNoneFalse78717.60
3995721154607None37.4Providing and fixing M.S.Block pipe of 38mm dia, of heavy guage of 14 including removing the bends, cutting the pipe and fixing pipe in between the existing two verticle poles (M.S rectangular poles) and spot welding the chain link with M.S block pipe including cost of all materials wastage in cutting, and scaffolding wherever necessary with all lead and lifts as directed by the Engineer-in-charge of eork etc.,complete including two coats of approved quality paint over one coat of shop paint.(Top Length 10+8+10+8=36& Bottom Length 10+8+10+8=36=72) (PW,P & IWTD, North Zone, Dharwad Circle 2016-17, Page No 262 , Item No.37.4)" ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m322.0322.072.0FalseNoneNoneFalseNoneFalse23184.00
3995722154607None1, of Civil works - Part IV)Jelly Spreading (20-25 mm) : Supplying and providing jelly in the station yard of uniform thickness of 100 mm including the cost of materials, labour charges, required tools and plants etc., complete. Work shall be carried out as per the instructions of Engineer- in-charge of works as per the standard procedure. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum1773.01773.08.0FalseNoneNoneFalseNoneFalse14184.00
3995723154607None51.5.2, of Major Work Materials Equipments (PartSupplying and installing of CO2 -4-5 Kgs capacity Fire Extinguishers ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each8691.08691.01.0FalseNoneNoneFalseNoneFalse8691.00
3995724154607None15.111 of Part III Utilization (PWD Electrical)Supplying of four bucket stand alongwith buckets. Complete ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1850.01850.01.0FalseNoneNoneFalseNoneFalse1850.00
3995725154607None15.113 of Part III Utilization (PWD Electrical)Supplying of Rubber HAND GLOVES ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Pair975.0975.01.0FalseNoneNoneFalseNoneFalse975.00
3995726154607None15.116 of Part III Utilization (PWD Electrical)Supplying of FIRST AID CHART with lamination. Complete ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each400.0400.01.0FalseNoneNoneFalseNoneFalse400.00
3995727154607None35.50, of Major Work Materials Equipments (Part 11 KV Hickery rod set ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Set5399.05399.01.0FalseNoneNoneFalseNoneFalse5399.00
3995728154607None35.51, of Major Work Materials Equipments (Part Grounding sticks extendable upto 18 ft : 3 nos. of each 6 ft Sticks of 3 phase R, Y, B (3 nos. of 1 set) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Set1755.01755.01.0FalseNoneNoneFalseNoneFalse1755.00
3995729154607None15.114 of Part III Utilization (PWD Electrical)Supplying of first aid box. complete ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each600.0600.01.0FalseNoneNoneFalseNoneFalse600.00
3995730154607None19.3, of Major Work Materials Equipments (Part ISupplying and fixing of DANGER / CAUTION board ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each318.0318.06.0FalseNoneNoneFalseNoneFalse1908.00
3995731154607None15.117 of Part III Utilization (PWD Electrical)Supplying and installation of RUBBER MAT 1mtr x 1mtr -1Omm thick. complete including cost of materials, labour, usage charges of machinery complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1900.01900.02.0FalseNoneNoneFalseNoneFalse3800.00
3995732154607None1.6.1Earth work excavation for pipelines/cables by Manual means upto 600 mm trench width, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter, including dressing of excavated surfaces, disposing off or leveling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m. Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering and lift upto 1.5 m including cost of labour, tools, usage& other appurtenances required to complete the work. In all kinds of soils. Depth upto 1.50m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum484.0484.019.5FalseNoneNoneFalseNoneFalse9438.00
3995733154607None2.16, of Labour Charges (11kV System) - Part II DiProviding Spiral Earth Electrode type earthing (without charcoal, salt etc.,) " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each93.093.04.0FalseNoneNoneFalseNoneFalse372.00
3995734154607None12.58.5 of Part III Utilization (PWD Electrical)Supplying and running of GI/Copper strips for grounding connections, using necessary fixing materials as required. GI Strip 50 x 6 ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr218.0218.0300.0FalseNoneNoneFalseNoneFalse65400.00
3995735154607None40.02, of Standard Stock Material (11kV System) - DAS Specification Compact RMU (VCB/SF6 Type) as per IEC-62271 The DAS RMUs shall have the following in addition to the Standards: DC motors, Numerical Relays, Multifunctional meters, fault passage indicator (FPI), Metering CTs, Protection CTs, Auxiliary transformers, Potential transformer, Batteries, Battery chargers (12 V & 24 V), AC power socket and light for illumination of Control panel. Control cable from each panel shall be wired and terminated to suitable 24 pin connector in the control panel. Suitable space for fixing the Remote Terminal Unit (RTU) and Radio Modem in Control panel. Suitable Clamps for fixing antenna Pipe - 4 Way RMU, 2OD + 2VL (One Incomer + Two Breakers + One Outgoing) 630 Amps with Copper Busbar " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1079188.01079188.01.0FalseNoneNoneFalseNoneFalse1079188.00
3995736154607None18.01, of Standard Stock Material (11kV System) - LT Distribution Box for 100 kVA DTC with MCCB's (Sheet Metal) (Dwg No. BESCOM/GM/QS&S/58 Dtd 24.11.2018) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each22686.022686.01.0FalseNoneNoneFalseNoneFalse22686.00
3995737154607None30.02, of Standard Stock Material (11kV System) - LT Feeder Pillar - 12 Way with Poreclain Rewireable Cutout and & 1 No of 630 Amps Load Break Switch with Copper Busbar asper IS-13947 Part-1&2(Dwg No. BESCOM/GM/QS&S/41 Dtd 24.11.2018) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each62543.062543.01.0FalseNoneNoneFalseNoneFalse62543.00
3995738154607None45.16, of Standard Stock Material (11kV System) - Heat Shrinkable Straight Through Jointing Kit for XLPE Cable with Copper Lug & Al Ferrule - 3x95 Sqmm " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each7311.07311.01.0FalseNoneNoneFalseNoneFalse7311.00
17262057300000NoneNoneBuildingsStreet Lights (Amble)711732.5
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3995739154608None1.03, of Standard Stock Material (11kV System) - PSupply of 8Mtr RCC Pole including earth work etc,. complete as per the standard technical specification BESCOM - b) 8Mtr 115Kg WL ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each5129.05129.025.0FalseNoneNoneFalseNoneFalse128225.00
3995740154608None2.01, of Labour Charges (11kV System) - Part II DiErection of RCC/PSCC Pole of 7.5 to 8 Mtr long in a pit of 1.5 Mtr depth " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each922.0922.025.0FalseNoneNoneFalseNoneFalse23050.00
3995741154608None2.06 of Standard Stock Material (11kV System) - PaSupply and fixing of …….cross arm including all Hardwares complete as per the standard technical specification BESCOM - LT 4 Pin Cross Arm - GI " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each379.0379.025.0FalseNoneNoneFalseNoneFalse9475.00
3995742154608None2.08 of Standard Stock Material (11kV System) - PaSupply and fixing of …….cross arm including all Hardwares complete as per the standard technical specification BESCOM. b) 2 Pin GI" ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each173.0173.025.0FalseNoneNoneFalseNoneFalse4325.00
3995743154608None5.02, of Standard Stock Material (11kV System) - PSupplying and Fixing …. including all Hardwares etc complete as per the standard technical specification - RCC Pole Clamp - GI " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each109.0109.050.0FalseNoneNoneFalseNoneFalse5450.00
3995744154608None5.10,5.11,5.13,5.15, 5.16 & 8.02 of Standard StockSupplying and Fixing …. including all Hardwares etc complete as per the standard technical specification BESCOM - GUY Set ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1628.451628.4510.0FalseNoneNoneFalseNoneFalse16284.50
3995745154608None6.05 of Standard Stock Material (11kV System) - PaSupplying and Fixing ….including all Hardwares etc complete as per the standard technical specification. 1.1 kV Polymeric Pin Insulator " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each87.087.0100.0FalseNoneNoneFalseNoneFalse8700.00
3995746154608None6.07 of Standard Stock Material (11kV System) - PaSupplying and Fixing ….including all Hardwares etc complete as per the standard technical specification BESCOM - No. 8 Strain Insulator " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each27.027.030.0FalseNoneNoneFalseNoneFalse810.00
3995747154608None42.08 of Standard Stock Material (11kV System) - P1.1 kV, LT Aerial Bunched Cable, XLPE insulation confirming to IS-14255: 1995 3x16 + 1x25 + 1x16 Sqmm Street light (Insulated Messenger cum Neutral)" ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr108.77108.771650.0FalseNoneNoneFalseNoneFalse179470.50
3995748154608None2.16, of Labour Charges (11kV System) - Part II DiProviding Spiral Earth Electrode type earthing (without charcoal, salt etc.,) " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each93.093.025.0FalseNoneNoneFalseNoneFalse2325.00
3995749154608None1.1.2 of Part III Utilization (PWD Electrical)Open Conduit System Supplying heavy gauge PVC conduit pipe 25mm dia 2mm thick confirming to IS 2509 with suitable size bends, junction boxes, adhesive paste etc., and fixing using inverted wood plugs in case of RCC ceiling and RCC wall / stone structure or rawl plugs in case of brick walls and cement plastering the damaged portion using heavy gauge saddles at an interval of 700mm using NF screws. 19/20mm dia 2mm thick. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr81.081.0250.0FalseNoneNoneFalseNoneFalse20250.00
3995750154608None2.3.4 of Part III Utilization (PWD Electrical)Wiring for lighting/power circuit using one of FRLS PVC insulated 1100V grade, multistrand Copper with low conductor resistance single core wire in open or concealed system of wiring. with specified IS-694:1990 & conforming to GTP 4 sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr63.063.0750.0FalseNoneNoneFalseNoneFalse47250.00
3995751154608None11.8.3 of Part III Utilization (PWD Electrical)Supply of LED Streetlight luminaire with pressure die cast aluminium housing body for optimal thermal dissipation. Lamp compartment comprising of anti glare clear diffuser with Injection moulded polycarbonate material, delivering superior light output Rated life Burning Hrs 50000 hr @ Lumen Maintenance of 70%, maximum light intensity should be between 60 degrees to 70 degrees. CCT 5500K, IP66 optical and electrical compartment & impact resistance of complete luminaire IK08. Power Factor 0.9 with mains, Surge Protection- Min 5KV along with Over voltage/ Overload, short circuit/ miss-wiring protection. Compatible for pole mounting with outer dia of 40mm to 50mm. Universal Voltage driver to operate wide voltage range from 100V to 270V 50/60Hz application. Compliance to IS 10322/IEC 60598, LM 79 & LM 80 Adherence with RoHS. UL approved MCPCB. Top access street light with single screw to ensure ease of maintenance at the sight site location with minimized minimal tools. LED Light fixture with .W System Power consumption. LED Efficiency1301m/w, nominal CRI 75. Luminaire manufacturer should have in-house facility accredited by NABL/CPRI & any Government certified agency & Design & Development facility certified by ISO 9001:2008. Housing with supplier word mark /name shall be Engraved / Embossing on the die cast housing/ Body part. Warranty of 2 Years against any manufacturing defect working under standard electrical conditions as mentioned above should be given by LED manufacturer & Cree/Nichia/ Lumileds/Osram make LED Source. - LED Streetlight 70W " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each5992.05992.025.0FalseNoneNoneFalseNoneFalse149800.00
3995752154608None32.03, of Standard Stock Material (11kV System) - Supplying of 1.1 kV, XLPE or Heat resistant PVC insulated, PVC exutruted Inner Seath Armoured LTUG Cable as per IS-1554 (Part1) or IS-7098 Part-1, Armouring strip thickness and resistivity as per IS-3975 4core 10sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.MT118.0118.0750.0FalseNoneNoneFalseNoneFalse88500.00
3995753154608None21.05, of Labour Charges (11kV System) - Part II DLabour charges for laying of 1.1 KV class UG cable in existing trench GI pipe / stoneware pipe / on wall / on pole as required - In exixting trench/duct. 2.5 sqmm to 25 sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr20.8920.89750.0FalseNoneNoneFalseNoneFalse15667.50
3995754154608None35.01, of Standard Stock Material (11kV System) - Supplying and fixing Epoxy Terminating Kit (Pothead) suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - Up to 4C x 50 Sqmm " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each324.0324.025.0FalseNoneNoneFalseNoneFalse8100.00
3995755154608None60.01, of Standard Stock Material (11kV System) - Supplying and fixing Aluminium End Terminal (Lug) suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 10 Sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each2.02.050.0FalseNoneNoneFalseNoneFalse100.00
3995756154608None63.01, of Standard Stock Material (11kV System) - Supplying and fixing Brass Cable Gland suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 25mm dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each79.079.050.0FalseNoneNoneFalseNoneFalse3950.00
17262057300000NoneNoneBuildingsLT Line Shifting (Amble)87267.85
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3995757154609None21.08, of Standard Stock Material (11kV System) - Supply and erection of Double Pole TC structural set including all hardwares suitable for 100/300 kVA 4/5 Star Rated Transformer on RCC Pole - 9 Mtr Long, 145 Kg WL - GI " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each30694.030694.01.0FalseNoneNoneFalseNoneFalse30694.00
3995758154609None6.06, of Standard Stock Material (11kV System) - PSupplying and Fixing ….including all Hardwares etc complete as per the standard technical specification BESCOM - 11 kV, 5 kN Composite/Polymeric Pin Insulator (24 mm dia FRP Rod) " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each205.0205.04.0FalseNoneNoneFalseNoneFalse820.00
3995759154609None5.16, of Standard Stock Material (11kV System) - PSupplying and Fixing Strain Clamp, 3 Bolt type for 70/90 kN Disc Insulator including all Hardwares etc complete as per the standard technical specification of BESCOM ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each707.0707.03.0FalseNoneNoneFalseNoneFalse2121.00
3995760154609None2.12, of Standard Stock Material (11kV System) - PSupplying and Fixing …. including all Hardwares etc complete as per the standard technical specification BESCOM - HT ST Support 50x8 mm Flat - GI " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each121.0121.03.0FalseNoneNoneFalseNoneFalse363.00
3995761154609None7.02 of Standard Stock Material (11kV System) - PaSupplying and fixing of Rabbit ACSR (6/3.35 mm Al + 1/3.35 mm St), Std Wt: 214 Kg/KM " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr46.2346.23780.0FalseNoneNoneFalseNoneFalse36059.40
3995762154609None2.02, of Labour Charges (11kV System) - Part II DiErection of RCC/PSCC Pole of 9 to 10 Mtr long in a pit of 1.8 Mtr depth " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1113.01113.01.0FalseNoneNoneFalseNoneFalse1113.00
3995763154609None1.6, of Labour Charges (11kV System) - Part II DisDigging of Pit for providing GI Pipe type Earthing - In hard soil ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos2990.02990.01.0FalseNoneNoneFalseNoneFalse2990.00
3995764154609None5.10,5.11,5.13,5.15, 5.16 & 8.02 of Standard StockSupplying and Fixing …. including all Hardwares etc complete as per the standard technical specification BESCOM - GUY Set ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1628.451628.452.0FalseNoneNoneFalseNoneFalse3256.90
3995765154609None2.02, of Labour Charges (11kV System) - Part II DiRerection of RCC/PSCC poles 9 to 10 mtr long but in a pit of 1.8 mtr depth ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No1113.01113.01.0FalseNoneNoneFalseNoneFalse1113.00
3995766154609None13.12, of Labour Charges (11kV System) - Part II DReleasing and Refixing Insulator of 11 kV Pin Insulator ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No48.048.04.0FalseNoneNoneFalseNoneFalse192.00
3995767154609None13.13, of Labour Charges (11kV System) - Part II DReleasing and Refixing Insulator of 11 kV Dead End Insulator Disc, Strain etc " ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No68.068.03.0FalseNoneNoneFalseNoneFalse204.00
3995768154609None13.12, of Labour Charges (11kV System) - Part II DRefixing of 4 Pin cross arm with insulator and Braces fixing ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each48.048.01.0FalseNoneNoneFalseNoneFalse48.00
3995769154609None13.12, of Labour Charges (11kV System) - Part II DRefixing of 2 Pin cross arm with insulator and Braces fixing ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each48.048.01.0FalseNoneNoneFalseNoneFalse48.00
3995770154609None7.02, of Labour Charges (11kV System) - Part II DiStringing of Conductor (including pin binding, providing jumps, dead ending, etc.,) - Rabbit ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Km5233.05233.00.7FalseNoneNoneFalseNoneFalse3663.10
3995771154609None15.11, of Labour Charges (11kV System) - Part II DReleasing of RCC ploe ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each946.05946.051.0FalseNoneNoneFalseNoneFalse946.050
3995772154609None13.12, of Labour Charges (11kV System) - Part II DRefixing of 4 Pin cross arm with insulator and Braces fixing ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each48.048.04.0FalseNoneNoneFalseNoneFalse192.00
3995773154609None13.12, of Labour Charges (11kV System) - Part II DRefixing of 2 Pin cross arm with insulator and Braces fixing ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each48.048.03.0FalseNoneNoneFalseNoneFalse144.00
3995774154609None7.04, of Labour Charges (11kV System) - Part II DiReleasing of Conductor - Rabbit ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Km4012.04012.00.7FalseNoneNoneFalseNoneFalse2808.40
3995775154609None13.12, of Labour Charges (11kV System) - Part II DRelesing 11KV Pin Insulators ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No48.048.06.0FalseNoneNoneFalseNoneFalse288.00
3995776154609None13.13, of Labour Charges (11kV System) - Part II DReleasing 11KV Dead End Insulators Disc, Strain etc ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No68.068.03.0FalseNoneNoneFalseNoneFalse204.00
17262057300000NoneNoneBuildingsCC Road (Amble)3738241.46
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3995777154610None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.0317.9FalseNoneNoneFalseNoneFalse32425.80
3995778154610None2.1.3Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5448.05448.038.0FalseNoneNoneFalseNoneFalse207024.00
3995779154610None2.4.2Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6955.36955.336.0FalseNoneNoneFalseNoneFalse250390.80
3995780154610None6.33Providing and constructing load bearing wall with Solid Concrete blocks of size 400x150x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1058.01058.0770.0FalseNoneNoneFalseNoneFalse814660.00
3995781154610None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm304.0304.01144.0FalseNoneNoneFalseNoneFalse347776.00
3995782154610None1.9Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum266.0266.044.0FalseNoneNoneFalseNoneFalse11704.00
3995783154610None2.11 hSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. All other type of structures ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Tonne79011.079011.02.351FalseNoneNoneFalseNoneFalse185754.8610
3995784154610NoneVOL - 3, C - 3 3.7 MoRT&H 305.3.4Compacting original ground supporting embankment Loosening, leveling and Compacting original ground supporting embankment to facilitate placement of first layer of embankment, scarified to a depth of 150 mm, mixed with water at OMC and then compacted by rolling so as to achieve minimum dry density as given in Table 300-2 for embankment construction. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum105.0105.0462.0FalseNoneNoneFalseNoneFalse48510.00
3995785154610NoneVOL - 3, C - 4 4.17 MoRT&H 406A.Wet Mix Macadam (Plant mix method) Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver/grader in sub-base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum2559.02559.0124.0FalseNoneNoneFalseNoneFalse317316.00
3995786154610NoneVOL - 3, C - 6 6.5 Pavement Quality M30 grade Concrete (RMC) with OPC & GGBS laid using Paver Construction of M30 Grade un-reinforced, dowel jointed, plain cement concrete pavement over a prepared sub base with OPC @ 270 kg/m3 and GGBS@ 90 kg/m3, coarse and fine aggregate conforming to IS 383:2016, maximum size of coarse aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per approved mix design transported to site, laid with a paver finisher, spread, compacted and finished in a continuous operation including provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane, sealant primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures, curing compound, steel channels, finishing to lines and grades as per drawing. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7839.07839.0165.0FalseNoneNoneFalseNoneFalse1293435.00
3995787154610NoneVOL - 3, C - 3 3.6 MoRT&H 305Construction of Subgrade and Earthen Shoulders Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2 ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum493.0493.0465.0FalseNoneNoneFalseNoneFalse229245.00
17262057300000NoneNoneBuildingsCompound Wall - 400 Mtrs Barbed Wire Fencing - 240 Mtrs (Amble)4923587.2
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3995788154611NoneVOL - 3, C - 2 2.5 (ii) b MoRT&H 201Clearing and Grubbing Road Land. Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness. (ii) By Mechanical Means using Dozer B. In area of thorny jungle ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.100 Sqm484.0484.032.0FalseNoneNoneFalseNoneFalse15488.00
3995789154611None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.0125.0FalseNoneNoneFalseNoneFalse12750.00
3995790154611None1.15.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In ordinary/soft rock without blasting upto 1.5 m depth ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum363.0363.0186.6FalseNoneNoneFalseNoneFalse67735.80
3995791154611None1.9Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum266.0266.0186.31FalseNoneNoneFalseNoneFalse49558.460
3995792154611None2.1.3Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5448.05448.043.0FalseNoneNoneFalseNoneFalse234264.00
3995793154611None2.5.1Providing and laying in position Reinforced cement concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/ trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement, dowel bars & formwork to be paid separately) M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9042.09042.021.0FalseNoneNoneFalseNoneFalse189882.00
3995794154611None2.4.2Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Plinth Beam ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9484.59484.528.31FalseNoneNoneFalseNoneFalse268506.1950
3995795154611None2.4.2Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Footings ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6828.846828.8464.3FalseNoneNoneFalseNoneFalse439094.4120
3995796154611None2.4.2Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Columns Below Plinth ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10749.110749.112.32FalseNoneNoneFalseNoneFalse132428.9120
3995797154611None2.5.1Providing and laying in position Reinforced cement concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/ trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement, dowel bars & formwork to be paid separately) M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10247.610247.623.909FalseNoneNoneFalseNoneFalse245009.86840
3995798154611None2.11 hSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. All other type of structures ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Tonne79011.079011.015.05FalseNoneNoneFalseNoneFalse1189115.550
3995799154611None6.33Providing and constructing load bearing wall with Solid Concrete blocks of size 400x150x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Compound Wall ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1058.01058.0599.0FalseNoneNoneFalseNoneFalse633742.00
3995800154611None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1192.01192.0218.0FalseNoneNoneFalseNoneFalse259856.00
3995801154611None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm304.0304.01761.0FalseNoneNoneFalseNoneFalse535344.00
3995802154611None11.57.1Fencing with G.I. barbed wire Angle iron post placed at required distance embedded in cement concrete blocks, every 15th post, last but one end post and corner post shall be strutted on both sides and end post on one side only and provided with horizontal lines and two diagonals interwoven with horizontal wires, of barbed wire weighing 9.38 kg per 100 m (minimum), between the two posts fitted and fixed with G.I. staples, turn buckles etc. complete. (Cost of posts, struts, earth work and concrete work to be paid for separately). Payment to be made per metre cost of total length of barbed wire used.With G.I. barbed wire ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m18.018.05520.0FalseNoneNoneFalseNoneFalse99360.00
3995803154611None11.25.2Providing and fixing Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs118.0118.01341.0FalseNoneNoneFalseNoneFalse158238.00
3995804154611None11.62Providing and fixing RCC precast fencing pole of size 0.15mx0.15mx2.0m casted in M 20 with 20mm down size aggregates making holes for drawing barbed wire at 30 cm c/c using 8 mm dia vertical 4 TMT steel rods and 6 mm dia stirups at 15 cm c/c fixed 1.5 m above Ground level using steel moulding , curing , transportation to work spot including excavation in all types of soil, fixing in plain cement concrete M15 using 20 mm downsize aggregate including aligning to plumb and line providing including cost of all materials, labour,usage charges of machinery complete. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1085.01085.080.0FalseNoneNoneFalseNoneFalse86800.00
3995805154611None8.30Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm174.0174.01761.0FalseNoneNoneFalseNoneFalse306414.00
17262057300001NoneNoneBuildingsEntrance Arch (Amble)887455.22
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3995806154612None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m Exacavation For Footings Foundation ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.08.0FalseNoneNoneFalseNoneFalse816.00
3995807154612None1.15.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In ordinary/soft rock without blasting upto 1.5 m depth ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum363.0363.030.84FalseNoneNoneFalseNoneFalse11194.920
3995808154612None1.9Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum266.0266.027.13FalseNoneNoneFalseNoneFalse7216.580
3995809154612None2.1.3Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5448.05448.04.0FalseNoneNoneFalseNoneFalse21792.00
3995810154612None5.4Providing Size Stone masonry with hard stone in foundation & plinth with Cement mortar 1:6 (1 cement : 6 coarse sand) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5315.05315.04.0FalseNoneNoneFalseNoneFalse21260.00
3995811154612None2.4.2Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates REINFORCED CEMENT CONCRETE Footing concrete ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6828.846828.847.56FalseNoneNoneFalseNoneFalse51626.03040
3995812154612None2.4.2Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates REINFORCED CEMENT CONCRETE For Columns Concrete Upto PB ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10749.1110749.110.896FalseNoneNoneFalseNoneFalse9631.202560
3995813154612None2.4.2Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates REINFORCED CEMENT CONCRETE For Plinth Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9484.59484.51.756FalseNoneNoneFalseNoneFalse16654.7820
3995814154612None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Columns Concrete Up to Roof Beam Bottom ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10237.410237.44.11FalseNoneNoneFalseNoneFalse42075.7140
3995815154612None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9635.29635.212.19FalseNoneNoneFalseNoneFalse117453.0880
3995816154612None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9033.09033.01.08FalseNoneNoneFalseNoneFalse9755.640
3995817154612None2.11 hSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. All other type of structures STEEL ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Tonne79011.079011.02.76FalseNoneNoneFalseNoneFalse218070.360
3995818154612None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1192.01192.067.0FalseNoneNoneFalseNoneFalse79864.00
3995819154612None12.13.1Providing Salwood frames of doors, windows, clerestory windows, ventilators and other frames, wrought, framed or assembled including making plaster groves (excluding cost of cement concrete and side clamps), but including cost of materials, labour, usage charges complete as per specifications. DOORS ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum98815.098815.00.06FalseNoneNoneFalseNoneFalse5928.90
3995820154612None12.57.3Providing and fixing flush door shutter made out of solid core block board type, well seasoned , chemicaly treated hard wood battens and internal frame with minimum 45 mm wide wooden frame alround door shutters covered with cross bonded wooden sheets (core veneer) hot pressed and fastened on both sides of the door useing liquid phenol formaldehyde resin as per IS specifications 2202 (part-I) 1991. from manufacturer complete as per spcification.-do- 30 mm thick both side commercial ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3005.03005.02.0FalseNoneNoneFalseNoneFalse6010.00
3995821154612None12.88Providing & fixing of 2-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having a overall size of 60mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm X 58mm with GI reinforcement of 1mm for the frame and 1.5 mm for the sash. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24mm. Windows shall be provided with 5mm plain float glass, standard hardware& single point locking system with touch lock. Wall thickness of frame & sash shall be of 2-2.5 mm. Maximum possible size 1819mm x 1819mm (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5390.05390.04.0FalseNoneNoneFalseNoneFalse21560.00
3995822154612None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs154.0154.065.0FalseNoneNoneFalseNoneFalse10010.00
3995823154612None9.17.2Providing and laying Vitrified tiles with thickness 9-10 mm in different sizes with water absorption less than 0.08 % and conforming to I.S. 15622, of approved make, in all colours & shade, over 12 mm thick bed of cement mortar 1:3 (1 cement: 3 coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including grouting the joint with white cement & matching pigments etc. complete. Size of Tile 600x600 mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1097.01097.09.0FalseNoneNoneFalseNoneFalse9873.00
3995824154612None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm244.0244.029.0FalseNoneNoneFalseNoneFalse7076.00
3995825154612None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. External Plastering ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm304.0304.0374.0FalseNoneNoneFalseNoneFalse113696.00
3995826154612None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg64.064.057.0FalseNoneNoneFalseNoneFalse3648.00
3995827154612None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm100.0100.036.2FalseNoneNoneFalseNoneFalse3620.00
3995828154612None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm110.0110.036.2FalseNoneNoneFalseNoneFalse3982.00
3995829154612None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.053.036.2FalseNoneNoneFalseNoneFalse1918.60
3995830154612None8.25Distempering with oil bound washable distemper of approved brand and manufacture to give an even shade :New work (two coats) over and including water thinnable priming coat with cement primer after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm137.0137.07.2FalseNoneNoneFalseNoneFalse986.40
3995831154612None8.30Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.053.0374.0FalseNoneNoneFalseNoneFalse19822.00
3995832154612None8.34.1Applying priming coat: With ready mixed pink or Grey primer of approved brand and manufacture on wood work (hard and soft wood) including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.053.05.0FalseNoneNoneFalseNoneFalse265.00
3995833154612None8.33.2Painting wood work with Deluxe Multi Surface Paint of required shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @0.75 L/10 m² of approved brand and manufacture to give an even shade including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, sand papering and knotting , cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm138.0138.05.0FalseNoneNoneFalseNoneFalse690.00
3995834154612None8.34.3Applying priming coat: With ready mixed red oxide zinc chromate primer of approved brand and manufacture on steel galvanised iron/ steel works including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm50.050.018.0FalseNoneNoneFalseNoneFalse900.00
3995835154612None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90 ltr/10 m² over an under coat of primer applied @ 0.80 ltr/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm139.0139.018.0FalseNoneNoneFalseNoneFalse2502.00
3995836154612None12.51Fixing of door frame in an existing opening including embedding frame in floor and walls after cutting masonry for holdfasts for embedding holdfast in cement concrete 1:3:6 of 20mm and down size granite metal painting two coats of coal tar to sides of frame, making good the damages to walls and floor as required and disposal of the debris with lead upto 50 m. including cost of materials, labour charges, complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1477.01477.01.0FalseNoneNoneFalseNoneFalse1477.00
3995837154612None11.25.2Providing and fixing Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs118.0118.0560.0FalseNoneNoneFalseNoneFalse66080.00
17262057300000NoneNoneBuildingsBasket Ball Court (Amble)1607418.27
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3995838154613None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.0309.88FalseNoneNoneFalseNoneFalse31607.760
3995839154613None2.1.3Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5448.05448.00.39FalseNoneNoneFalseNoneFalse2124.720
3995840154613None2.4.2Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6828.846828.84122.82FalseNoneNoneFalseNoneFalse838718.12880
3995841154613None2.5.1Providing and laying in position Reinforced cement concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/ trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement, dowel bars & formwork to be paid separately) M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10247.610247.60.75FalseNoneNoneFalseNoneFalse7685.70
3995842154613NoneVOL - 3, C - 4 4.17 MoRT&H 406A.Wet Mix Macadam (Plant mix method) Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver/grader in sub-base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum2559.02559.091.2FalseNoneNoneFalseNoneFalse233380.80
3995843154613None8.6.2Providing 20 mm cement plaster with cement mortar 1:3 (1 cement: 3 coarse sand) finished with a floating coat of neat cement to brick/stone masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm361.0361.0608.0FalseNoneNoneFalseNoneFalse219488.00
3995844154613None2.11 hSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. All other type of structures ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Tonne79011.079011.02.56FalseNoneNoneFalseNoneFalse202268.160
3995845154613NoneVOL - 3, C - 8 8.10 MoRT&H 803Painting Two Coats on New Concrete Surfaces Providing and applying two coats of ready mix paint of approved brand on steel surface after thorough cleaning of surface to give an even shade" ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm109.0109.0120.0FalseNoneNoneFalseNoneFalse13080.00
3995846154613NoneVOL - 3, C-17C MoRT&H 602.6.3Cutting transverse contraction joints 3 to 4 mm wide and depth 60mm in concrete slab using concrete cutting machine with diamond studded saw within 48 hours of casting of bay / slab etc. complete including subsequent widening of the groove 8 to 10 mm. wide at top having depth of 15 mm. as directed by Engineer incharge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm70.070.0242.0FalseNoneNoneFalseNoneFalse16940.00
3995847154613NoneVOL - 3, C-16 16.15.aProviding and Laying Reinforced Cement Concrete Pipe NP3 as per design in Single Row Providing and laying reinforced cement concrete pipe NP3 for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls and parapets Clause 1101.6. 1200 mm dia" ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m8425.08425.05.0FalseNoneNoneFalseNoneFalse42125.00
17262057300000NoneNoneBuildingsVolley ball Court (Amble)18620.64
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3995848154614None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.080.36FalseNoneNoneFalseNoneFalse8196.720
3995849154614NoneVOL - 3, C - 3 3.7 MoRT&H 305.3.4Compacting original ground supporting embankment Loosening, leveling and Compacting original ground supporting embankment to facilitate placement of first layer of embankment, scarified to a depth of 150 mm, mixed with water at OMC and then compacted by rolling so as to achieve minimum dry density as given in Table 300-2 for embankment construction. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum105.0105.080.0FalseNoneNoneFalseNoneFalse8400.00
3995850154614None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5622.05622.00.36FalseNoneNoneFalseNoneFalse2023.920
17262057300000NoneNoneBuildingsKho-Kho Court (Amble)145436.84
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3995851154615None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.0171.36FalseNoneNoneFalseNoneFalse17478.720
3995852154615NoneVOL - 3, C - 3 3.7 MoRT&H 305.3.4Compacting original ground supporting embankment Loosening, leveling and Compacting original ground supporting embankment to facilitate placement of first layer of embankment, scarified to a depth of 150 mm, mixed with water at OMC and then compacted by rolling so as to achieve minimum dry density as given in Table 300-2 for embankment construction. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum105.0105.0171.0FalseNoneNoneFalseNoneFalse17955.00
3995853154615None1.11Supplying and filling in plinth with sand under floors, foundation of Bridges including watering, ramming, consolidating and dressing complete. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum2177.02177.049.6FalseNoneNoneFalseNoneFalse107979.20
3995854154615None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5622.05622.00.36FalseNoneNoneFalseNoneFalse2023.920
17262057300000NoneNoneBuildingsKabadi Court (Amble)35009.0
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3995855154616None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.039.0FalseNoneNoneFalseNoneFalse3978.00
3995856154616NoneVOL - 3, C - 3 3.7 MoRT&H 305.3.4Compacting original ground supporting embankment Loosening, leveling and Compacting original ground supporting embankment to facilitate placement of first layer of embankment, scarified to a depth of 150 mm, mixed with water at OMC and then compacted by rolling so as to achieve minimum dry density as given in Table 300-2 for embankment construction. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum105.0105.026.0FalseNoneNoneFalseNoneFalse2730.00
3995857154616None1.11Supplying and filling in plinth with sand under floors, foundation of Bridges including watering, ramming, consolidating and dressing complete. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum2177.02177.013.0FalseNoneNoneFalseNoneFalse28301.00
17262057300000NoneNoneBuildingsBall Badminton Court (Amble)42243.29
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3995858154617None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.045.14FalseNoneNoneFalseNoneFalse4604.280
3995859154617NoneVOL - 3, C - 3 3.7 MoRT&H 305.3.4Compacting original ground supporting embankment Loosening, leveling and Compacting original ground supporting embankment to facilitate placement of first layer of embankment, scarified to a depth of 150 mm, mixed with water at OMC and then compacted by rolling so as to achieve minimum dry density as given in Table 300-2 for embankment construction. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum105.0105.029.85FalseNoneNoneFalseNoneFalse3134.250
3995860154617None1.11Supplying and filling in plinth with sand under floors, foundation of Bridges including watering, ramming, consolidating and dressing complete. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum2177.02177.014.92FalseNoneNoneFalseNoneFalse32480.840
3995861154617None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5622.05622.00.36FalseNoneNoneFalseNoneFalse2023.920
17262057300000NoneNoneBuildingsLong Jump (Amble)42294.0
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3995862154618None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.094.5FalseNoneNoneFalseNoneFalse9639.00
3995863154618None1.11Supplying and filling in plinth with sand under floors, foundation of Bridges including watering, ramming, consolidating and dressing complete. Long jump court Filling ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum2177.02177.015.0FalseNoneNoneFalseNoneFalse32655.00
17262057300000NoneNoneBuildingsHigh Jump (Amble)74067.5
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3995864154619None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.032.5FalseNoneNoneFalseNoneFalse3315.00
3995865154619None1.11Supplying and filling in plinth with sand under floors, foundation of Bridges including watering, ramming, consolidating and dressing complete. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum2177.02177.032.5FalseNoneNoneFalseNoneFalse70752.50
17262057300000NoneNoneBuildingsWashing Platform (Amble)1855512.27
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3995866154620None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.023.0FalseNoneNoneFalseNoneFalse2346.00
3995867154620None1.15.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In ordinary/soft rock without blasting upto 1.5 m depth ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum363.0363.091.11FalseNoneNoneFalseNoneFalse33072.930
3995868154620None1.9Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum266.0266.0113.89FalseNoneNoneFalseNoneFalse30294.740
3995869154620None1.8Construction of Embankment by excavating the available approved Gravel/Murrum deposited at a place or borrow pits during or prior excavation with all lifts and lead, transportation to site, spreading, grading to required slope and compacting to meet the requirement complete as per specifications, including cost of labour,rolling,water,all materials,usage& all other appurtenaces required to complete the work. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum474.0474.011.0FalseNoneNoneFalseNoneFalse5214.00
3995870154620None2.1.3Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5448.05448.039.0FalseNoneNoneFalseNoneFalse212472.00
3995871154620None2.4.2Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Footing Concrete ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6828.846828.844.8FalseNoneNoneFalseNoneFalse32778.4320
3995872154620None2.4.2Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Drains Concrete ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6639.156639.152.898FalseNoneNoneFalseNoneFalse19240.25670
3995873154620None2.4.2Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Pedastal Concrete ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10749.110749.11.0FalseNoneNoneFalseNoneFalse10749.10
3995874154620None2.11 hSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. All other type of structures ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Tonne79011.079011.00.783FalseNoneNoneFalseNoneFalse61865.6130
3995875154620None5.4Providing Size Stone masonry with hard stone in foundation & plinth with Cement mortar 1:6 (1 cement : 6 coarse sand) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5315.05315.03.0FalseNoneNoneFalseNoneFalse15945.00
3995876154620None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1192.01192.010.0FalseNoneNoneFalseNoneFalse11920.00
3995877154620None6.34Providing and constructing load bearing wall with Solid Concrete blocks of size 400x100x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm937.0937.021.0FalseNoneNoneFalseNoneFalse19677.00
3995878154620None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5622.05622.02.0FalseNoneNoneFalseNoneFalse11244.00
3995879154620None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm304.0304.0148.0FalseNoneNoneFalseNoneFalse44992.00
3995880154620None13.31.6Providing and fixing Chorinated Poly Venyl Chloride (CPVC) pipes, having thermal stability for hot and cold water supply including all CPVC plain and brass threaded fittings including fixing the pipe with clamp at 1.00 mtr spacing. This includes jointing of pipes and fittings with one step CPVC solvent cement and testing of joints complete. (internal work exposed on wall) - 50mm nominal OD pipes ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m781.0781.040.0FalseNoneNoneFalseNoneFalse31240.00
3995881154620None13.2.2Providing and fixing brass bib cock of approved quality : 20 mm nominal bore ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos305.0305.024.0FalseNoneNoneFalseNoneFalse7320.00
3995882154620None11.16.1Providing and fixing Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete. Hot finished welded type tubes including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg136.0136.07432.0FalseNoneNoneFalseNoneFalse1010752.00
3995883154620None7.38Providing and fixing precoated galvanised iron profile sheets (size, shape and pitch of corrugation as approved by Engineer-in-charge) 0.50 mm (+ 0.05 %) total coated thickness with zinc coating 120 grams per m2 as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns. Sheet should have protective guard film of 25 microns minimum to avoid scratches during transportation and should be supplied in single length upto 12 m or as desired by Engineer-in-charge. The sheet shall be fixed using self drilling/self tapping screws of size (5.5x 55 mm) with EPDM seal, complete upto any pitch in horizontal/ vertical or curved surfaces, excluding the cost of purlins, rafters and trusses and including cutting to size and shape wherever required. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm568.0568.0292.4FalseNoneNoneFalseNoneFalse166083.20
3995884154620None7.4.1Providing & fixing ridges or hips of width 60 cm overall width plain G.S. sheet fixed with polymer coated J or L hooks, bolts and nuts 8 mm dia G.I. limpet and bitumen washers complete as per design drawings. 0.63 mm thick with zinc coating not less than 275 g/m² ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m639.0639.034.0FalseNoneNoneFalseNoneFalse21726.00
3995885154620None7.6Providing and fixing 15 cm wide, 45 cm overall semi-circular plain G.S. sheet gutter with iron brackets 40x3mm size, bolts, nuts and washers etc., including making necessary connections with rain water pipes complete. (0.63 mm thick with zinc coating not less than 275 g/m²) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m645.0645.068.0FalseNoneNoneFalseNoneFalse43860.00
3995886154620None9.1Providing and laying Cement concrete flooring 40 mm thick with 20 mm nominal size stone aggregate using 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate) finished with a floating coat of neat cement, including cement slurry complete. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm392.0392.0160.0FalseNoneNoneFalseNoneFalse62720.00
17262057300001NoneNoneBuildingsBox Culvert (Amble)495930.37
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3995887154621None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.029.0FalseNoneNoneFalseNoneFalse2958.00
3995888154621None1.15.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In ordinary/soft rock without blasting upto 1.5 m depth ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum363.0363.0115.0FalseNoneNoneFalseNoneFalse41745.00
3995889154621None2.1.3Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5448.05448.05.0FalseNoneNoneFalseNoneFalse27240.00
3995890154621None2.4.2Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6828.846828.8422.0FalseNoneNoneFalseNoneFalse150234.480
3995891154621None2.5.1Providing and laying in position Reinforced cement concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/ trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement, dowel bars & formwork to be paid separately) M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9042.09042.03.002FalseNoneNoneFalseNoneFalse27144.0840
3995892154621None2.11 hSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. All other type of structures ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Tonne79011.079011.03.0002FalseNoneNoneFalseNoneFalse237048.80220
3995893154621NoneVOL - 3, C - 14 14.4 A MoRT&H 2504Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in front of toe of embankment complete as per drawing and Technical specifications. Stone/Boulder ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum1912.01912.05.0FalseNoneNoneFalseNoneFalse9560.00
17262057300000NoneNoneBuildingsFlagpost (Amble)135805.5
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3995894154622None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.06.06FalseNoneNoneFalseNoneFalse618.120
3995895154622None1.9Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum266.0266.00.58FalseNoneNoneFalseNoneFalse154.280
3995896154622None2.1.3Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates a)For Foundation Bed ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5448.05448.01.7277FalseNoneNoneFalseNoneFalse9412.50960
3995897154622None2.4.2Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6828.846828.841.457FalseNoneNoneFalseNoneFalse9949.619880
3995898154622None2.11 hSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. All other type of structures ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Tonne79011.079011.00.1167FalseNoneNoneFalseNoneFalse9220.58370
3995899154622None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1192.01192.018.18FalseNoneNoneFalseNoneFalse21670.560
3995900154622None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm304.0304.031.11FalseNoneNoneFalseNoneFalse9457.440
3995901154622None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2864.02864.010.567FalseNoneNoneFalseNoneFalse30263.8880
3995902154622None10.2Providing edge moulding to 18mm thick Granite stone counters, vanities etc including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr328.0328.018.0FalseNoneNoneFalseNoneFalse5904.00
3995903154622None11.28Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners, stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in- charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.) including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs565.0565.069.3FalseNoneNoneFalseNoneFalse39154.50
17262057300000NoneNoneBuildingsProcurement Of Furnitures, Kitchen Equipments, Furnishing, Computers, Cctv & Internet Connect Etc, (Amble)9930529.0
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3995904154623NoneDATA RATETwo tier cot to MDRS/KRCRS / P U MDRS Size: 1980L X 760W X 1980mmH. The verticals shall be made out of 38mm square MS tubes of 16G thick on all the four corners & 19mm square MS tubes in-between. A single CRCA sheet of 14G thick and uniformly bent on all sides vertically and further inside and with one lengthwise rib of 18G in the middle underneath for both the cots shall be provided. For the upper cot 25mm dia pipe to be bent and fixed in the middle on either sides as obstacle to avoid dropping of the person while sleeping to the side. The height for bottom tier from the floor shall be 460mm. The distance between bottom tier and top tier shall be 1000mm. The ladder shall be provided on one side to enable the person to climb to upper tier. Curtain hooks at the top corners for both the cots shall be welded for tying mosquito curtains. Strong rubber bushes shall be fixed for the verticals at the bottom. The entire cot shall be neatly de rusted, powder coated with epoxy polyesterpowder. Name of the institution i.e., KREIS Should be embossed on the material. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos14950.014950.0125.0FalseNoneNoneFalseNoneFalse1868750.00
3995905154623NoneDATA RATEDesk cum Bench Dimensions: Size : 1800 (L) * 787 (W) * 787mm (H) Specification: Made using 25mm*25mm & 25mm*50mm 16g MS ERW tubular section frame & book shelf of 20 swg CRCA sheet, fitted with 25mm thick PLPB & 2mm thick PVC edge binding for all the exposed edges for sitting & writing planks & 18mm thick PLPB for back rest planks respectively. The desk frame shall be epoxy powder coated upto 40microns with siemens grey colour. Part Details:- 1) Writing Plank: Size: 1800 Mm(L) * 355mm(W)*25mm(T) 2) Sitting Plank: Size: 1800 Mm(L) * 305mm(W)*25mm(T) 3) Backrest Plank: Size: 1800 Mm(L) * 203mm(W)*18mm(T) 4) Book Shelve: Made Out Of MS 20swg. Name of the institution i.e, KREIS Should be embossed on the material. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos12600.012600.062.0FalseNoneNoneFalseNoneFalse781200.00
3995906154623NoneDATA RATESteel Almirah plain with shelves &Door 6.6 Feet with 20 Guage doors & 22 Guage body. Size : 198cm H x 915cm W x 48cm D (including leg of 15.24cm) , fitted with four fixed shelves making five compartments with double door with three way locking device and duplicate keys, all joints outside and inside should be spot or co2 welded and neatly finished by sandering. The outside corners should be rounded off to give good appearance. The edges of doors and shelves should be properly bent to U shape of 25mm width to ensure good strength and the outer edge of U bent of the door length wise should be double folded and neatly finished. The shelves front side should be bent to U shape neatly and finished to avoid any possible cuts to fingers and hand when handled. Longitudinal rib of 15.24cm wide including bent to required shape should be provided and fixed to each door at its centre. The breadth of the shelf in the Almirah should be to the entire width leaving above 12mm gap from the shutter when it is closed. Locking Device: Three ways locking device with 10 Gauge M.S. sheet for locking and lever plate, and with locking rod of 10mm dia with strong bracket at top and bottom to hold the locking rod with six lever lock should be provided. 65mm size 6 lever strong lock to be fixed. Handle should be made out of cast alloy with nickel chrome plated. The entire almirah shall be derusted, powder coated with epoxy polyester powder Name of the institution i.e, KREIS should be embossed on the material. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos21823.021823.012.0FalseNoneNoneFalseNoneFalse261876.00
3995907154623NoneDATA RATES Type continuous armrest chair: SEAT/BACK ASSEMBLY: The seat and back are made from well seasoned& polished wood. CANE FOR SEAT/BACK: Cane is made from mix of LDPE+HDPE MIX material. The caning used for seat/back shall have high tensile strength. ARMREST TUBE: The armrest tube is made of MS ERW tube of dia.2.54cm x 16G thick and powder coated. The armrest is gas-assisted injection moulded from black polypropylene. Name of the institution i.e, KREIS should be embossed on the material. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos3492.03492.025.0FalseNoneNoneFalseNoneFalse87300.00
3995908154623NoneDATA RATEStaff Table Size: 1365mm W X 680mm D X 750mm H the Table Top work surface to be manufactured using 25mm thick pre laminated particle board (PLPB). All work surface edges are to be duly sealed with 2mm thick PVC edge banding. The understructure C- frame to be made using CRCA MS sheet 20 gauge Thick and Tubular Frame to be made using MS ERW Square Tube with dia 25.4 mm X 1.2mm Thick. The MS ERW Square Tubes: 25.4 mm X 25.4mm X 1.2mm Thickness. The modesty panel is to be made using 20 gauge thick CRCA MS sheet. The table should contain 1 drawer & cupboard unit to the left hand side and 3 drawer units on the right hand side of the table. The metal drawer unit with shell made out of 0.5mm thick CRCA sheet and MS Drawer Tray made out of 0.5mm Thick CRCA MS sheet and the drawer facia to be made out of 22 gauge Thick CRCA sheet. The drawer to be provided with MS Lock with 10 Lever Cam Lock. The handles to be fixed made out of Built in Plastic. The table should have connecting leg rest made out of MS tube. The entire table shall be neatly derusted, powder coated with epoxy polyester powder Name of the institution i.e., KREIS Should be embossed on the material. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos12990.012990.012.0FalseNoneNoneFalseNoneFalse155880.00
3995909154623NoneDATA RATEShoe Cabinet: Shoe racks with shelves 8.1ft with uniformly welded 18 gauge pipes for verticals & 16 gauge sheet folded L angles for horizontals and covered with 20guage thick CRCA sheet on top, sides and back. Size 1371H,2463W,381D fitted with pipes consisting of 30 shelvesof size 203H & 381 W in inclined position to stock footwear. The rack will be provided with 4 castors. The entire rack will be derusted, powder coated with epoxy polyster power. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos16810.016810.012.0FalseNoneNoneFalseNoneFalse201720.00
3995910154623NoneDATA RATEClass Room Tables: Under structure: C frame shall be made up of 0.9 +/- 0.09mm thick powder coated 50 microns (+/- 10) CRCA MS. Tubular frame is made up of Sq. 25.4 (+/- 0.3mm) X 1.2 (+/- 0.096mm) Thick MS ERW tube. The modesty panel is made up from 1.0 (+/- 0.09mm) thick powder coated 50 microns (+/- 10mm) CRCA MS. The work surface shall be made up of 18 (+/-0.5mm ) thick pre laminated particle board as per with 2 mm thick PVC edge banding on all sides. Shell of the storage unit shall be made up of 0.5 (+/-0.07mm) thick CRCA steel. The drawer tray shall be made up of 0.5 (+/-0.07mm) thick CRCA steel. Drawer front shall be made up of 0.8 (+/- 0.1mm ) thick CRCA steel. Lock shall be of 10 lever cam lock. Handles shall be of plastic handle. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos10480.010480.08.0FalseNoneNoneFalseNoneFalse83840.00
3995911154623NoneDATA RATELibrary Racks: a Product Size: Width 900mm, Height: 1850mm, Depth: 300mm (DMX Drg. - PL13-A4-20825 R0) b. Construction: Rigid Knockdown construction. c. Material: CRCA 0.8mm Thickness d Finish: Epoxy Polyester Powder coated to the thickness of 50 microns (+/-1) e. Number of Adjustable shelf: Five adjustable shelves (Total 6 Loading levels). Uniformly Distributed Load Capacity per each shelf shall be 80 Kg maximum. f. Shelf back stiffener At the rear side of the shelves back stiffeners are provided. These act as separators between front & rear books. g. Label holder & range indicator Label Holder & Range indicator on each main unit for inserting labels. h. Accessories: Optional stand of 125 mm Height with levelling screws. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos15416.015416.010.0FalseNoneNoneFalseNoneFalse154160.00
3995912154623NoneDATA RATEPLATE & TUMBLER STAND: 125 plates Supply of plate & tumbler stand with heavy duty wheels of size 8ft W x 2ft D x 6ft H to stack plates in five rows and tumblers in two rows as per Drawing. MS powder coated to60 microns welded main frame 25mmx50mmx2mm rectangular tubes vertically and horizontally with 6mm rod spaced 1.5” vertically to stack plates individually. Tumbler stand made of 2mm thick MS sheet powder coated to 60 microns on either side with holes to insert tumblers all as directed by the engineer in charge and sample to be approved before supply. The entire stand shall be neatly derusted, powder coated with epoxy polyester powder. Name of the institution i.e., KREIS Should be embossed on the material. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos15000.015000.02.0FalseNoneNoneFalseNoneFalse30000.00
3995913154623NoneDATA RATESmart Class Projector with Integrated Computer and other accessories with 1 year Onsite Service Warranty Video Conferencing Software for the above integrated Computer system Virtual Classroom Software for the integrated Computer system Ceiling mount kit for the Projector system USB extenders with 5 meter cable length for fixing to Projector system Antiglare White Board Server System Content Access Software and 3D Virtual Interactive experiments Desktops for students (15 1 Locations) Headsets Audio Splitter USB Keyboard and Optical Mouse Installation charges of all equipment s, including fixing the white board and ceiling mount kit, Internal wiring of LAN, Networking of computers, projector and server system Warranty of 1 year onsite, comprehensive end to end AMC for the hardware’s and software’s with visit to schools every 3 months with successful utilization report from vendor Training Cost 2 days divisional level hands on and assignment based training for 2 teachers Providing Onsite Warranty and AMC Support for all the hardware and software with visit to schools every 3 months with successful utilization report from vendor 4 years Portable Electronic equipment insurance as per the specification for 1 Year Renewal charges of Portable Electronic equipment insurance for Server System 1 No., Desktop Computer system 15 Nos., provided for usage by students, Projector System with integrated PC 1 No. including Physical loss theft for a period of 4 Years Name Boards and Instruction sheet for E Learning Centre Supplying and drawing of UTP 6 E LAN cable Computer Table for E learning centre Computer chair with armrest for E learning centre Supplying and fixing of 2 meters Cat 6 Patch cable 272 85 Supplying and fixing of 9 U with 650 mm depth switch mounting rack with power manager and cable manager as standard specification Supplying and fixing of I O socket with back box Supplying and fixing of Network switches 24 port Supplying and fixing of Patch panel for LAN cabling 24 port ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Set2646000.02646000.01.0FalseNoneNoneFalseNoneFalse2646000.00
3995914154623NoneDATA RATEMattress type : Pocket Spring Mattresses 1. Mattress Size 189 x 67 x 15 cm (29099 Numbers) & 176 x 74 x 15 cm (3275 Numbers) 2. Coil Count 189 x 67 x 15 cm= 28X 10 176 x 74 x 15 cm =26X 9 3. Construction a) 120mm high pocket spring (dia) core covered with 5mm cotton felt & plastic mesh from top & bottom b) Entire pocket spring core surrounded by border of 75mm shorter side and 84 mmlonger side made out of 28 density hard foam c) Above this core 10mm or 12mm (thickness) 28 density P.U foam pasted on top. d) Above final carcass covered with 20 to 24mm 18density P.U foam quilted fabric from top and bottom 4. Raw Material Specification 1. Spring Coil with 1.8mm dia 5 turns, dia of the spring 55 mm, Flexibility 2.7, Hardness IS 4454 grade part- 2,2003. Spring Material carbonised steel of grade IS-4453 part-1, 2001 & the centre to centre distance of spring 60mm. 2.Spring Coil is pocketed with 80 GSM white Non woven fabric. Fabric type - 130 GSM Knitted Cotton felt - (1000 GSM) Air Vents - 4 nos. individually packed and sealed with LDPE 80 microns Corner fitments - 3 Ply corrugated corner guards to prevent any transit damage Tensile strength 170kg/sq mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos5000.05000.0250.0FalseNoneNoneFalseNoneFalse1250000.00
3995915154623NoneDATA RATEPillow Specification Fibers 50:50 recycled & hollow Fiber Weight 500 Grm Fabric Peach polyester 85Gsm and one cotton pillow cover Packing LDPE 250 Gauge Size 17''x27'' recorn pack of 1 pillow ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos400.0400.0250.0FalseNoneNoneFalseNoneFalse100000.00
3995916154623NoneDATA RATEZamkana Width 91 CMs+/- 2cms Color fatness to washing 2-3 or better Weight/piece 1000 Grm+/-5% Count warp 2/30 to 2/34s +/ -10% Weft 25 to 6s +/-10% Composition Polyster,viscose,cotton Length 198 Cms +/- 2 cm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos315.0315.0250.0FalseNoneNoneFalseNoneFalse78750.00
3995917154623NoneDATA RATEBed Spread Width 147 CMs+/- 2cms Color fatness to washing 2-3 or better Weight/piece 600 Grm+/-5% Count warp 8s to 12s +/ -10% Weft 2s to 6s +/-10% Composition Polyster,viscose,cotton Length 198 Cms +/- 2 cm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos147.0147.0250.0FalseNoneNoneFalseNoneFalse36750.00
3995918154623NoneDATA RATEBed Sheet Width 147 CMs+/- 2cms Color fatness to washing 2-3 or better Weight/piece 1000 Grm +/-5% Count warp 2/18s to 2/20s +/ -10% Weft 6s to 10s +/-10% Composition Polyster,viscose,cotton Length 223Cms +/- 2 cm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos420.0420.0250.0FalseNoneNoneFalseNoneFalse105000.00
3995919154623NoneDATA RATESuppying & Installing reputed brand 55 inch LED TV with android supports. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos75000.075000.02.0FalseNoneNoneFalseNoneFalse150000.00
3995920154623NoneDATA RATEMosquito net GSM-min 28, colour-white,Typing loop-6 loops,polyolefin 100, Tolerance limit+-10% for all above parameters ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos582.0582.0250.0FalseNoneNoneFalseNoneFalse145500.00
3995921154623None10.1.3 of Part III Utilization (PWD Electrical)Supply and installation of 25 KVA Diesel Generator Set, 3Phase, 1500 RPM DG Set: Diesel engine and alternator of the same make shall be close coupled and mounted on a base plate of robust construction with standard accessories. 1) DIESEL ENGINE: a) Diesel Engine shall be air cooled, electric start, developing required B.H.P at 1500 RPM with Class G-2 Governing or better for alternator to deliver specified continuous 25 KVA output as per IS/ISO 8528. b) The Diesel Engine should be capable of providing 10% overload for one hour for every 12 hours continuous running at full load. c) Naturally aspirated engines shall conform to IS: 10000-2/81 d) The Diesel Engine shall be complete with the following standard accessories: i) Fuel tank with capacity for 12 hours continuous running at full load. ii) Exhaust silencer of Residential type. iii) 12V or 24V starting system complete with starter motor, charging alternator with Cutout. iv) Lead Acid Battery/ies of suitable ratings with connecting cables. The battery/ies shall be supplied in charged condition and shall conform to relevant IS Specification. v) Standard set of tools consisting of a set of 3 spanners, one screw driver, one standard plier and one nose plier of appropriate size shall be provided along with DG sets free of cost for each of DG sets. 2) ALTERNATOR: a) The Alternator shall be self excited and self regulated of specified KVA rating in three phase at 415 Volt, 50 Hz, 1500 RPM and 0.8 power factor and shall conform to latest IS/ISO Specification and Standards. The alternators shall be of brush less type with VG-1 Grade of voltage regulation. b) The alternators shall be screen-protected drip proof with Min.IP-21 degree of protection as per latest IS/ISO Specification and Standards. The class of insulation of the Alternator would be 'H'. The rated voltage of Alternator will be 415 V, three phase. 3) MANUAL CONTROL PANEL/INTEGRATED DIGITAL CONTROLLER: a) The Control Panel shall be fabricated from steel/metal sheet of 1.5 mm thickness minimum duly pretreated and aesthetically finished or integrated with the DG set in the form of Digital Controller. b) The Control Panel shall be totally enclosed, dust and vermin proof, floor mounted or wall mounted/skid mounted or integral type with IP-53 degree of protection as per latest IS/ISO Specification and Standards. c) The Control Panel shall have the instrumentation/indicators for speed status, current status, voltage status, Load status, Oil Pressure, low fuel indicator and other operational/safety controls. 4) OPERATION: Manual On-off Push Button Switch on DG set and Change over Switch 5) ACCOUSTIC ENCLOSER a) DG sets shall be provided with integrated acoustic enclosure which shall conform to norms of Central Pollution Control Board (CPCB) as per updated provision. b) The acoustic enclosure supplied shall be in accordance with as per latest IS/ISO or equivalent IEC code for conformity to noise norms. This aspect shall also be verified at the time of delivery. 6) PRE-DESPATCH TESTING a) Supplier shall furnish complete & satisfactory TTC(Type test certificate) for engines, alternators complete with enclosure to be used by them for this rating of DG sets clearly indicating make, model and ratings of the DG sets tested at the time of delivery of the DG set. The TTC of three phase alternators shall cover ‘unbalanced load test’ as per latest IS/ISO Specification and Standards as applicable. However the engine models/rating shall need relevant certifications as per norms. b) Either of the following types of TTC shall be acceptable: i) Type Test Certificate issued by recognized Government Lab. Type Test Certificate issued by recognized Government Lab irrespective of whether engines and alternators were tested at firm’s lab or some other lab, but witnessed by Government representative. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Set451101.0451101.01.0FalseNoneNoneFalseNoneFalse451101.00
3995922154623NoneDATA RATENetwork Video Recorder: Up to 16 channel IP camera input ,H.265/H.264/MJPEG dual codec decoding, Max 256Mbps incoming bandwidth, Up to 8ch@1080P(4ch@H.265+4ch@H.264) real-time live-view Up to 12Mp resolution preview playback, HDMI/VGA simultaneous video output, 8/16 channel synchronous real-time playback, GRID interface Support Multi-brand network cameras, ONVIF Version 2.4 conformance 3D intelligent positioning, Support 2 SATA HDDs up to 12TB, 2 USB(1 USB3.0), Support IPC UPnP, 8PoE ports Support P2P, QR code scan & add Multiple network monitoring: Web viewer. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos11200.011200.01.0FalseNoneNoneFalseNoneFalse11200.00
3995923154623NoneDATA RATEIR Dome camera (Indoor) 2 Megapixel progressive scan CMOS, varifocal lenses 3.312MM or better H 264 MJPEG dualstream encoding, Min 20fps 1080P1920 1080 Minimum WDR, Day Night ICR DNR AWB AGC BLC,Multiplenetwork monitoring: Web viewer, Flexible cropping On camera real time motion detection and privacy mask with 1024 detection zones;Backlight compensation privacy masking Max IR LEDs Length20m IP66 PoE ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos8700.08700.05.0FalseNoneNoneFalseNoneFalse43500.00
3995924154623NoneDATA RATE18.5 Inch Display Monitor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos9450.09450.01.0FalseNoneNoneFalseNoneFalse9450.00
3995925154623NoneDATA RATESTORAGE Hard disk 4 TB Surveillance Hard Drives - Surveillance Storage is built for 24/7 always-on surveillance in high-definition security systems for the Videos Footages generated by all the Cameras installed within the network for a period of 3 months in case of Boys' Residential Schools and for a period of 6 months in case of Girls' /Co-education Residential Schools. Off-line Backup: The system should capable of compressing the video footages stored beyond the capacity of online storage capacity of the NVR, and upload the same to Private Cloud Servers via network. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos11800.011800.01.0FalseNoneNoneFalseNoneFalse11800.00
3995926154623NoneDATA RATE6 u server rack with 500 depth wall mounted 1 fan ,1 self and spike card 6 output ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos3500.03500.01.0FalseNoneNoneFalseNoneFalse3500.00
3995927154623NoneDATA RATE8 port 10/100 switch with 4 port POE with more than 50 watts POE budget or 8 port 10/100 switch with 4 port POE with more than 40 watts POE budget ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos9450.09450.01.0FalseNoneNoneFalseNoneFalse9450.00
3995928154623NoneDATA RATERJ 45 Connectors with 4X4" Boxes for Cameras. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos729.0729.08.0FalseNoneNoneFalseNoneFalse5832.00
3995929154623NoneDATA RATEPower variation controller unit ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos13500.013500.01.0FalseNoneNoneFalseNoneFalse13500.00
3995930154623NoneDATA RATECAT Cable with Including 25 mm Round Pvc White Conduit ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos340.0340.0100.0FalseNoneNoneFalseNoneFalse34000.00
3995931154623NoneDATA RATEElectrical cable to connect all equipments ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos334.0334.0100.0FalseNoneNoneFalseNoneFalse33400.00
3995932154623NoneDATA RATEDining table: 6 seater The overall dimensions of the table should be 1800mm(W) X 800mm(D) X750mm(H).The table top should be made of SS-204 grade 1mm thick brush finish stainless steel. The top frame assembly should be rectangular tube of dimensions 50.8mm X 25.4mm X 1.6mm thick MS ERW and cylindrical socket which are welded and powder coated. The side frame assembly should be fixed to the top with screws. The side frame assembly should be made of combination of circular and rectangular tubes of MS ERW. The circular tube should be of diameter 38.1mm and thickness 1.6mm.The rectangular tube should be of dimensions 50.8mm X 25.4mm and thickness 1.6mm.Circular and rectangular tubes should be welded together to form the assembly. Side frame assembly should be fixed to top frame assembly. The stool top should be made SS-204 grade 1mm thick brush finish stainless steel with MS Ribs for strength. The stool top should have an height of 450mm and the diameter of the stool top should be 300mm.The stool assembly should be foldable above the side frame. Cross members should be provided between side frame assembly. Cross members should be made of 50.8mm X 25.4mm X 1.6mm thick MS ERW of 1.6mm thickness and should be powder coated. Finish should be epoxy polyester powder coated of 40-60 micron thickness. Shoe should be provided at the bottom. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos13000.013000.032.0FalseNoneNoneFalseNoneFalse416000.00
3995933154623NoneDATA RATEGalvanized Iron Storage Trunks The GI Steel trunk shall be as per IS 72571973 Reaffirmed 2006 as per the drawing enclosed. The body of the steel trunk shall be made in three panel construction viz. front, bottom and back in one piece and the two sides in two separate pieces. The top portion of the box Lid cover is in one piece construction. Metal Galvanized Iron Sheet Thicknes 0 80 mm. Dimension in mm 675 L X370 W 330 D Padlock Front 1 No. Side Handles: 2 Nos. Front Handle: 1 No. 1. All joints shall be double seamed. 2. All dimensions in mm. 3. Tolerance L = 5mm, H =+/- 5mm, All other tolerance as per relevant IS. 4. Method of component fixing By riveting. 5. Hasp & Staple size 150mm as per IS 3631993 (Reaffirmed 2003), type II. 6. Material: GI Sheet 0.80 mm thick to Class 3 of IS 2771969 2nd revision for Body, Lid, Cover, Pocket Channels. 7. Trunk weight Min 11.2 Kgs. 8. Steel Trunk shall be properly cleaned degreased, pickled. 9 Name of the institution i e KREIS should be embossed on the material ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1700.01700.0250.0FalseNoneNoneFalseNoneFalse425000.00
3995934154623None10.3.2Supplying, erecting, testing & commissioning of ON-LINE UPS system suitable for operation on 230V, 50Hz, A/C supply, with isolation transformer all accessories complete and Excluding batteries and wiring complete ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each42480.042480.02.0FalseNoneNoneFalseNoneFalse84960.00
3995935154623None10.5.9Supplying, installation, testing & commissioning of 12V DC, AH batteries in poly propylene container for U.P.S. Sealed maintenance free batteries. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each14100.014100.012.0FalseNoneNoneFalseNoneFalse169200.00
3995936154623NoneDATA RATEProviding & fixing AD 12 Yellow ACP with Red, Blue White Acrylic combined 2D Board with 3 years warranty. LED Modules & 25mmx50mmx18SWG MS frame. IP65 Power supply 400watts, Installation Outdoor type, 9000 Lumen, White (exact colour will be confirmed in the work order) Colour, Protection class IP65, Rated life of LEDs 40000 hrs, Working voltage of 230 V, single phase AC, 50 Hz, Height of Characters as per enclosed design, ambient temperature up to 55 degree celsius, letters in Kannada, English Font size shall be as per Govt of Karnataka order. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sft850.0850.054.6FalseNoneNoneFalseNoneFalse46410.00
3995937154623NoneDATA RATEIR Bullet camera (Outdoor - Entrance) 2Megapixel progressive scan CMOS, varifocal lenses 3.6 12MM or better, H.264&MJPEG dual-stream encoding, Min20fp 1080P(19201080), Minimum WDR, Day/Night(ICR), 3DNR,AWB,AGC,BLC ,Multiple network monitoring: Web viewer, Flexible cropping, On-camera real-time motion detection and privacy mask with 1024 detection zones; Backlight compensation, privacy masking Max. IR LEDs Length20m, IP66, PoE ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos8500.08500.03.0FalseNoneNoneFalseNoneFalse25500.00
17262057300000NoneNoneBuildingsLevelling For Playgrounds (Amble)403720.22
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3995938154624None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.044.0FalseNoneNoneFalseNoneFalse4488.00
3995939154624None1.15.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In ordinary/soft rock without blasting upto 1.5 m depth ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum363.0363.0249.0FalseNoneNoneFalseNoneFalse90387.00
3995940154624None1.9Earth work excavation for FOUNDATION by Mechanical means depth upto 1.50m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including cost of explosives, dressing of excavated surfaces, disposing off or levelling the excavated stuff or sorting & stacking the selected stuff for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, blasting materials, tools, usage of Machinery & all other appurtenaces required to complete the work. In Hard Rock ( requiring blasting) Depth upto 1.50m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum266.0266.0205.0FalseNoneNoneFalseNoneFalse54530.00
3995941154624None1.8Earth work excavation for FOUNDATION by Mechanical means depth upto 1.50m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including cost of explosives, dressing of excavated surfaces, disposing off or levelling the excavated stuff or sorting & stacking the selected stuff for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, blasting materials, tools, usage of Machinery & all other appurtenaces required to complete the work. In Hard Rock ( requiring blasting) Depth upto 1.50m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum474.0474.0536.53FalseNoneNoneFalseNoneFalse254315.220
17262057300001NoneNoneBuildingsAcademic Block (Shivani)27800073.03
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3995942154625NoneVOL -3, C-2 2.5 (ii) b MoRT&H 201Clearing and Grubbing Road Land. Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness. (ii) By Mechanical Means using Dozer B. In area of thorny jungle ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.100 Sqm484.0484.0300.0FalseNoneNoneFalseNoneFalse145200.00
3995943154625None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.01434.2165FalseNoneNoneFalseNoneFalse146290.0830
3995944154625None1.15.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In ordinary/soft rock without blasting upto 1.5 m depth ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum363.0363.0406.6698FalseNoneNoneFalseNoneFalse147621.13740
3995945154625None1.16.1Earth work excavation for Foundation by Mechanical means depth upto 1.50m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including cost of explosives, dressing of excavated surfaces, disposing off or levelling the excavated stuff or sorting & stacking the selected stuff for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, blasting materials, tools, usage of Machinery & all other appurtenaces required to complete the work. In Hard Rock ( requiring blasting) Depth upto 1.50m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum554.0554.033.8891FalseNoneNoneFalseNoneFalse18774.56140
3995946154625None1.9Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum266.0266.0830.6136FalseNoneNoneFalseNoneFalse220943.21760
3995947154625None4.1Providing and injecting chemical emulsion for Pre-constructional Anti-Termite Treatment, creating continuous chemical barrier under and around the column pits, walls, trenches, basement excavation, top surface of the plinth filling, junction of wall and floor, along the external perimeter of building, expansion joints, over the top surface of consolidated earth on which apron is to be laid, surrounding of pipes and conduits with Chlorpyriphos 20% E.C. / Lindane 20% E.C. @ 3.19 l/m2 including cost of chemical, diluting in water to one percent concentration, labour, usage charges of machinery, complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm118.0118.0810.0FalseNoneNoneFalseNoneFalse95580.00
3995948154625None2.1.3Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5989.05989.0133.0FalseNoneNoneFalseNoneFalse796537.00
3995949154625None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6217.06217.06.855FalseNoneNoneFalseNoneFalse42617.5350
3995950154625None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7460.47460.42.3721FalseNoneNoneFalseNoneFalse17696.814840
3995951154625None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7522.577522.572.1FalseNoneNoneFalseNoneFalse15797.3970
3995952154625None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7584.747584.743.1FalseNoneNoneFalseNoneFalse23512.6940
3995953154625None2.1.6Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:2:4 Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6243.06243.04.0FalseNoneNoneFalseNoneFalse24972.00
3995954154625None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Footing concrete ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6842.886842.88193.0207FalseNoneNoneFalseNoneFalse1320817.4876160
3995955154625None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Pedastals ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10771.210771.211.1846FalseNoneNoneFalseNoneFalse120471.563520
3995956154625None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Columns Concrete Upto PB ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10771.210771.25.3634FalseNoneNoneFalseNoneFalse57770.254080
3995957154625None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Plinth Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9504.09504.021.7339FalseNoneNoneFalseNoneFalse206558.98560
3995958154625None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Grade Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9504.09504.037.0723FalseNoneNoneFalseNoneFalse352335.13920
3995959154625None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Columns Concrete Up to Roof ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11633.111633.125.6793FalseNoneNoneFalseNoneFalse298729.864830
3995960154625None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10948.810948.837.2586FalseNoneNoneFalseNoneFalse407936.959680
3995961154625None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10264.510264.5123.1868FalseNoneNoneFalseNoneFalse1264450.90860
3995962154625None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Lintel Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10948.810948.89.4446FalseNoneNoneFalseNoneFalse103407.036480
3995963154625None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Staircase ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10264.510264.57.77FalseNoneNoneFalseNoneFalse79755.1650
3995964154625None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor For Columns Concrete Up to Roof ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11749.4311749.4324.3432FalseNoneNoneFalseNoneFalse286018.7243760
3995965154625None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11058.2811058.2831.1038FalseNoneNoneFalseNoneFalse343954.5294640
3995966154625None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10367.1410367.1497.1454FalseNoneNoneFalseNoneFalse1007119.9621560
3995967154625None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor For Lintel Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11058.2811058.287.9935FalseNoneNoneFalseNoneFalse88394.361180
3995968154625None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor For Staircase ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10367.1410367.143.885FalseNoneNoneFalseNoneFalse40276.33890
3995969154625None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor For Columns ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11865.7611865.761.6767FalseNoneNoneFalseNoneFalse19895.3197920
3995970154625None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11167.7711167.779.0838FalseNoneNoneFalseNoneFalse101445.7891260
3995971154625None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10469.7910469.798.7956FalseNoneNoneFalseNoneFalse92088.0849240
3995972154625None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10780.2710780.274.0FalseNoneNoneFalseNoneFalse43121.080
3995973154625None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t89457.089457.035.7215FalseNoneNoneFalseNoneFalse3195538.22550
3995974154625None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t90351.5790351.5714.2637FalseNoneNoneFalseNoneFalse1288747.6890090
3995975154625None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t91246.1491246.142.3241FalseNoneNoneFalseNoneFalse212065.1539740
3995976154625None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1310.01310.0813.0FalseNoneNoneFalseNoneFalse1065030.00
3995977154625None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1323.11323.1650.0FalseNoneNoneFalseNoneFalse860015.00
3995978154625None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1336.21336.2191.0FalseNoneNoneFalseNoneFalse255214.20
3995979154625None6.34Providing and constructing load bearing wall with Solid Concrete blocks of size 400x100x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1104.01104.0128.0FalseNoneNoneFalseNoneFalse141312.00
3995980154625None6.34Providing and constructing load bearing wall with Solid Concrete blocks of size 400x100x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1115.041115.0498.0FalseNoneNoneFalseNoneFalse109273.920
3995981154625None12.13.1Providing Salwood frames of doors, windows, clerestory windows, ventilators and other frames, wrought, framed or assembled including making plaster groves (excluding cost of cement concrete and side clamps), but including cost of materials, labour, usage charges complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum98815.098815.00.9FalseNoneNoneFalseNoneFalse88933.50
3995982154625None12.13.1Providing Salwood frames of doors, windows, clerestory windows, ventilators and other frames, wrought, framed or assembled including making plaster groves (excluding cost of cement concrete and side clamps), but including cost of materials, labour, usage charges complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum99803.1599803.150.8FalseNoneNoneFalseNoneFalse79842.520
3995983154625None12.17Providing and fixing in position fully panelled Honne wood shutters for doors with , stiles and rails of 35mm. thick with bottom and lock rails 180mm wide top rail and stiles 100mm wide as per drawing and panels of 25mm thick including cost of materials, labour, usage charges complete as per specifications. (excluding cost of fixtures) Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm7085.07085.05.0FalseNoneNoneFalseNoneFalse35425.00
3995984154625None12.57.3Providing and fixing flush door shutter made out of solid core block board type, well seasoned , chemicaly treated hard wood battens and internal frame with minimum 45 mm wide wooden frame alround door shutters covered with cross bonded wooden sheets (core veneer) hot pressed and fastened on both sides of the door useing liquid phenol formaldehyde resin as per IS specifications 2202 (part-I) 1991. from manufacturer complete as per spcification.-do- 30 mm thick both side commercial Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3005.03005.026.0FalseNoneNoneFalseNoneFalse78130.00
3995985154625None12.57.3Providing and fixing flush door shutter made out of solid core block board type, well seasoned , chemicaly treated hard wood battens and internal frame with minimum 45 mm wide wooden frame alround door shutters covered with cross bonded wooden sheets (core veneer) hot pressed and fastened on both sides of the door useing liquid phenol formaldehyde resin as per IS specifications 2202 (part-I) 1991. from manufacturer complete as per spcification.-do- 30 mm thick both side commercial First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3035.053035.0526.0FalseNoneNoneFalseNoneFalse78911.30
3995986154625None12.51Fixing of door frame in an existing opening including embedding frame in floor and walls after cutting masonry for holdfasts for embedding holdfast in cement concrete 1:3:6 of 20mm and down size granite metal painting two coats of coal tar to sides of frame, making good the damages to walls and floor as required and disposal of the debris with lead upto 50 m. including cost of materials, labour charges, complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1016.01016.010.0FalseNoneNoneFalseNoneFalse10160.00
3995987154625None12.51Fixing of door frame in an existing opening including embedding frame in floor and walls after cutting masonry for holdfasts for embedding holdfast in cement concrete 1:3:6 of 20mm and down size granite metal painting two coats of coal tar to sides of frame, making good the damages to walls and floor as required and disposal of the debris with lead upto 50 m. including cost of materials, labour charges, complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1026.161026.169.0FalseNoneNoneFalseNoneFalse9235.440
3995988154625None12.93.1Providing and fixing factory made single extruded WPC (Wood Polymer Composite) solid door/window/Clerestory windows & other Frames/ Chowkhat comprising of virgin PVC polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibres (wood powder/rice husk/ wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) fabricated with miter joints after applying PVC solvent cement and screwed with full body threaded star headed SS screws having minimum frame density of 850 kg/m3, screw withdrawal strength of 2200 N (Face) & 1100 N (Edge), minimum compressive strength of 58 N/mm2 , modulus of elasticity 900 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixed in position with M.S hold fast/lugs/SS dash fasteners of required dia and length complete as per direction of Engineer-InCharge. (Fixtures shall be paid for separately) Size 62 x 100mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr702.0702.0101.0FalseNoneNoneFalseNoneFalse70902.00
3995989154625None12.93.1Providing and fixing factory made single extruded WPC (Wood Polymer Composite) solid door/window/Clerestory windows & other Frames/ Chowkhat comprising of virgin PVC polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibres (wood powder/rice husk/ wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) fabricated with miter joints after applying PVC solvent cement and screwed with full body threaded star headed SS screws having minimum frame density of 850 kg/m3, screw withdrawal strength of 2200 N (Face) & 1100 N (Edge), minimum compressive strength of 58 N/mm2 , modulus of elasticity 900 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixed in position with M.S hold fast/lugs/SS dash fasteners of required dia and length complete as per direction of Engineer-InCharge. (Fixtures shall be paid for separately) Size 62 x 100mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr709.02709.0291.0FalseNoneNoneFalseNoneFalse64520.820
3995990154625None12.94.1Providing and fixing factory made Green certified, Anti Termite, UV resistant, high water absorbant single extruded WPC (Wood PolymerComposite) solid plain flush door shutter of required size comprising of virgin polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibers (wood powder/rice husk/wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) having minimum density of 650 kg/m3 and screw withdrawal strength of 1800 N (Face) & 900 N (Edge), minimum compressive strength of 50 N/mm2 , modulus of elasticity 850 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixing with stainless steel butt hinges of required size with necessary full body threaded star headed counter sunk S.S screws The cost includes cost of materials, transportation, labour and fixing charges.(Cost of Fixtures to be paid separately) 30 mm thickness Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3485.03485.033.0FalseNoneNoneFalseNoneFalse115005.00
3995991154625None12.94.1Providing and fixing factory made Green certified, Anti Termite, UV resistant, high water absorbant single extruded WPC (Wood PolymerComposite) solid plain flush door shutter of required size comprising of virgin polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibers (wood powder/rice husk/wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) having minimum density of 650 kg/m3 and screw withdrawal strength of 1800 N (Face) & 900 N (Edge), minimum compressive strength of 50 N/mm2 , modulus of elasticity 850 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixing with stainless steel butt hinges of required size with necessary full body threaded star headed counter sunk S.S screws The cost includes cost of materials, transportation, labour and fixing charges.(Cost of Fixtures to be paid separately) 30 mm thickness First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3519.853519.8529.0FalseNoneNoneFalseNoneFalse102075.650
3995992154625None12.88Providing & fixing of 2-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having a overall size of 60mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm X 58mm with GI reinforcement of 1mm for the frame and 1.5 mm for the sash. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24mm. Windows shall be provided with 5mm plain float glass, standard hardware& single point locking system with touch lock. Wall thickness of frame & sash shall be of 2-2.5 mm. Maximum possible size 1819mm x 1819mm (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5390.05390.098.0FalseNoneNoneFalseNoneFalse528220.00
3995993154625None12.88Providing & fixing of 2-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having a overall size of 60mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm X 58mm with GI reinforcement of 1mm for the frame and 1.5 mm for the sash. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24mm. Windows shall be provided with 5mm plain float glass, standard hardware& single point locking system with touch lock. Wall thickness of frame & sash shall be of 2-2.5 mm. Maximum possible size 1819mm x 1819mm (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5443.95443.985.0FalseNoneNoneFalseNoneFalse462731.50
3995994154625None12.88Providing & fixing of 2-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having a overall size of 60mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm X 58mm with GI reinforcement of 1mm for the frame and 1.5 mm for the sash. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24mm. Windows shall be provided with 5mm plain float glass, standard hardware& single point locking system with touch lock. Wall thickness of frame & sash shall be of 2-2.5 mm. Maximum possible size 1819mm x 1819mm (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5497.85497.82.0FalseNoneNoneFalseNoneFalse10995.60
3995995154625None12.85Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5719.05719.057.0FalseNoneNoneFalseNoneFalse325983.00
3995996154625None12.85Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5776.195776.1952.0FalseNoneNoneFalseNoneFalse300361.880
3995997154625None12.85Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5833.385833.381.0FalseNoneNoneFalseNoneFalse5833.380
3995998154625None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs183.0183.02457.0FalseNoneNoneFalseNoneFalse449631.00
3995999154625None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs184.83184.832175.0FalseNoneNoneFalseNoneFalse402005.250
3996000154625None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs186.66186.6644.0FalseNoneNoneFalseNoneFalse8213.040
3996001154625None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2852.02852.0775.0FalseNoneNoneFalseNoneFalse2210300.00
3996002154625None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2880.522880.52523.0FalseNoneNoneFalseNoneFalse1506511.960
3996003154625None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2909.042909.045.0FalseNoneNoneFalseNoneFalse14545.20
3996004154625None9.11Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved make, in all colours, shades, except White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick bed of cement mortar 1:4 (1 Cement : 4 Coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including pointing the joints with white cement and matching pigments etc., complete. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm889.0889.056.0FalseNoneNoneFalseNoneFalse49784.00
3996005154625None9.11Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved make, in all colours, shades, except White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick bed of cement mortar 1:4 (1 Cement : 4 Coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including pointing the joints with white cement and matching pigments etc., complete. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm897.89897.8947.0FalseNoneNoneFalseNoneFalse42200.830
3996006154625None9.39Providing skirting, dadooing, rises of steps with colour glazed tiles 6mm thick on 10mm thick cement plaster 1:3 and jointed with white cement slurry over existing rough plaster surface using glazed tiles of approved make and size including cost of materials, labour, complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1449.01449.0252.0FalseNoneNoneFalseNoneFalse365148.00
3996007154625None9.39Providing skirting, dadooing, rises of steps with colour glazed tiles 6mm thick on 10mm thick cement plaster 1:3 and jointed with white cement slurry over existing rough plaster surface using glazed tiles of approved make and size including cost of materials, labour, complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1463.491463.49169.0FalseNoneNoneFalseNoneFalse247329.810
3996008154625None10.2Providing edge moulding to 18mm thick Granite stone counters, vanities etc including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr328.0328.0157.0FalseNoneNoneFalseNoneFalse51496.00
3996009154625None10.2Providing edge moulding to 18mm thick Granite stone counters, vanities etc including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr331.28331.2866.0FalseNoneNoneFalseNoneFalse21864.480
3996010154625None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm295.0295.01629.0FalseNoneNoneFalseNoneFalse480555.00
3996011154625None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm297.95297.951298.0FalseNoneNoneFalseNoneFalse386739.10
3996012154625None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm300.9300.946.0FalseNoneNoneFalseNoneFalse13841.40
3996013154625None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm371.0371.0669.0FalseNoneNoneFalseNoneFalse248199.00
3996014154625None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm374.71374.71826.0FalseNoneNoneFalseNoneFalse309510.460
3996015154625None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm378.42378.42452.0FalseNoneNoneFalseNoneFalse171045.840
3996016154625None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg64.064.0101.0FalseNoneNoneFalseNoneFalse6464.00
3996017154625None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg64.6464.64124.0FalseNoneNoneFalseNoneFalse8015.360
3996018154625None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg65.2865.2867.8FalseNoneNoneFalseNoneFalse4425.9840
3996019154625None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm295.0295.0261.0FalseNoneNoneFalseNoneFalse76995.00
3996020154625None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm297.95297.95178.0FalseNoneNoneFalseNoneFalse53035.10
3996021154625None8.16 aProviding lath plaster with cement mortar 1:3, 5cms thick with 6mm dia mild steel bars at 20 cms. c to c both horizontally and vertically fixing chicken mesh for drop chajja, facia, backing to cup boards including cost of all materials, labour, providing and removing form work usage charges, curing complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1238.01238.05.0FalseNoneNoneFalseNoneFalse6190.00
3996022154625None8.16 aProviding lath plaster with cement mortar 1:3, 5cms thick with 6mm dia mild steel bars at 20 cms. c to c both horizontally and vertically fixing chicken mesh for drop chajja, facia, backing to cup boards including cost of all materials, labour, providing and removing form work usage charges, curing complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1250.381250.385.0FalseNoneNoneFalseNoneFalse6251.90
3996023154625None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm100.0100.02459.2034FalseNoneNoneFalseNoneFalse245920.340
3996024154625None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. First floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm101.0101.01928.4572FalseNoneNoneFalseNoneFalse194774.17720
3996025154625None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm102.0102.069.1128FalseNoneNoneFalseNoneFalse7049.50560
3996026154625None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm110.0110.02220.0284FalseNoneNoneFalseNoneFalse244203.1240
3996027154625None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. First floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm111.1111.11710.5622FalseNoneNoneFalseNoneFalse190043.460420
3996028154625None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm112.2112.269.1128FalseNoneNoneFalseNoneFalse7754.456160
3996029154625None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.053.02459.2034FalseNoneNoneFalseNoneFalse130337.78020
3996030154625None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.5353.531928.4572FalseNoneNoneFalseNoneFalse103230.3139160
3996031154625None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. TerraceFloor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm54.0654.0669.1128FalseNoneNoneFalseNoneFalse3736.2379680
3996032154625None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm174.0174.0669.0FalseNoneNoneFalseNoneFalse116406.00
3996033154625None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm175.74175.74826.0FalseNoneNoneFalseNoneFalse145161.240
3996034154625None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm177.48177.48452.0FalseNoneNoneFalseNoneFalse80220.960
3996035154625None8.34.1Applying priming coat: With ready mixed pink or Grey primer of approved brand and manufacture on wood work (hard and soft wood) including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.053.072.0FalseNoneNoneFalseNoneFalse3816.00
3996036154625None8.34.1Applying priming coat: With ready mixed pink or Grey primer of approved brand and manufacture on wood work (hard and soft wood) including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.5353.5362.0FalseNoneNoneFalseNoneFalse3318.860
3996037154625None8.33.2Painting wood work with Deluxe Multi Surface Paint of required shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @0.75 L/10 m² of approved brand and manufacture to give an even shade including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, sand papering and knotting , cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm138.0138.072.0FalseNoneNoneFalseNoneFalse9936.00
3996038154625None8.33.2Painting wood work with Deluxe Multi Surface Paint of required shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @0.75 L/10 m² of approved brand and manufacture to give an even shade including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, sand papering and knotting , cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm139.38139.3862.0FalseNoneNoneFalseNoneFalse8641.560
3996039154625None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @ 0.80 L/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm139.0139.0154.0FalseNoneNoneFalseNoneFalse21406.00
3996040154625None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @ 0.80 L/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm140.39140.39136.0FalseNoneNoneFalseNoneFalse19093.040
3996041154625None8.4Painting with synthetic enamel paint of approved brand and manufacture to give an even shade :Two coats on new work after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm115.0115.0239.175FalseNoneNoneFalseNoneFalse27505.1250
3996042154625None8.4Painting with synthetic enamel paint of approved brand and manufacture to give an even shade :Two coats on new work after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm116.15116.15217.895FalseNoneNoneFalseNoneFalse25308.504250
3996043154625None11.28Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners, stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in- charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.) including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs565.0565.0296.0FalseNoneNoneFalseNoneFalse167240.00
3996044154625None11.28Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners, stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in- charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.) including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs570.65570.6558.0FalseNoneNoneFalseNoneFalse33097.70
3996045154625None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr66.066.0382.0FalseNoneNoneFalseNoneFalse25212.00
3996046154625None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr66.6666.66348.0FalseNoneNoneFalseNoneFalse23197.680
3996047154625None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr67.3267.3241.0FalseNoneNoneFalseNoneFalse2760.120
3996048154625None7.18Providing and laying cinder concrete in cement 1:15 ( 1 cement : 15 cinder of 12.5mm nominal gauge) on terraced roof or sunken slabs, laid to slope compacting, including cost of materials, labour, curing complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum2037.172037.1725.0FalseNoneNoneFalseNoneFalse50929.250
3996049154625None15.7Integral Crystalline Water Proofing Admixture Providing and supplying crystalline integral concrete waterproofing admixture that waterproofs concrete by forming crystals deep in the pores, capillaries and microcracks of the concrete, self-seal waterproofing compound to bridge shrinkage cracks upto 0.5mm in width & resist hydro-static pressure upto 16bar for both positive & negative pressure confirming to DIN 1048 part 5 for 56% reduction in depth of penetration against control, resistance to chloride penetration confirming to ASTM C 1202 with 64% improvement against control & protecting steel reinforcement against corrosion mixed @ 1% by weight of cementitious content in concrete. ie., integral crystaline waterproofing admix @ 0.5 kg/bag of cement. (For calculation purpose 320 kg of Cement for M-20 grade of Concrete is considered in the analysis) First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm621.15621.1580.0FalseNoneNoneFalseNoneFalse49692.00
3996050154625None9.25Providing and laying 60mm thick factory made cement concrete paver block of approved shape and colour of M -30 grade made of C&D waste by block making machine with vibratory compaction laid in required pattern and including over 50mm thick compacted bed of coarse sand, filling the joints with fine sand etc. all complete as per the direction of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm800.0800.044.58FalseNoneNoneFalseNoneFalse35664.00
3996051154625None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9613.59613.54.0515FalseNoneNoneFalseNoneFalse38949.095250
3996052154625None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9679.89679.83.7672FalseNoneNoneFalseNoneFalse36465.742560
3996053154625None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9746.19746.148.0FalseNoneNoneFalseNoneFalse467812.80
3996054154625NoneVOL - 5 7.1.1Providing and fixing MS ladder between landings, 45 cms wide using angle iron of specified sizes, 20mm MS bars at 25 cms. centre to centre, with necessary supports of same angle iron etc. as directed, including hand railing on both sides with 25mm dia. GI pipes with angle iron props at 2 mtrs. intervals and 0.5M heigh, including fixing in ground with CC 1:2:4 and two coats of anticorrosive bituminous paint etc. with all lead and lifts etc. complete with: MS angle of 65 x 65 x 8mm Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr4464.544464.544.5FalseNoneNoneFalseNoneFalse20090.430
3996055154625None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.038.0378.0FalseNoneNoneFalseNoneFalse14364.00
3996056154625None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.3838.38309.6FalseNoneNoneFalseNoneFalse11882.4480
3996057154625None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.7638.7614.4FalseNoneNoneFalseNoneFalse558.1440
3996058154625None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.038.0429.56FalseNoneNoneFalseNoneFalse16323.280
3996059154625None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.3838.38358.02FalseNoneNoneFalseNoneFalse13740.80760
3996060154625None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.7638.7618.0FalseNoneNoneFalseNoneFalse697.680
3996061154625None22.15.7Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Tower Bolts 250x10mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos200.0200.030.0FalseNoneNoneFalseNoneFalse6000.00
3996062154625None22.15.7Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Tower Bolts 250x10mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos202.0202.026.0FalseNoneNoneFalseNoneFalse5252.00
3996063154625None22.15.8Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS hinges 125 mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos50.050.0101.0FalseNoneNoneFalseNoneFalse5050.00
3996064154625None22.15.8Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS hinges 125 mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos50.550.587.0FalseNoneNoneFalseNoneFalse4393.50
3996065154625None22.15.1Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Handles 200mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos450.0450.060.0FalseNoneNoneFalseNoneFalse27000.00
3996066154625None22.15.1Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Handles 200mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos454.5454.552.0FalseNoneNoneFalseNoneFalse23634.00
3996067154625None22.15.4Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Aldrop 16mm dia, 300mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos375.0375.029.0FalseNoneNoneFalseNoneFalse10875.00
3996068154625None22.15.4Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Aldrop 16mm dia, 300mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos378.75378.7526.0FalseNoneNoneFalseNoneFalse9847.50
3996069154625None22.15.10Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Door stopper 75mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos100.0100.010.0FalseNoneNoneFalseNoneFalse1000.00
3996070154625None22.15.10Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Door stopper 75mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos101.0101.09.0FalseNoneNoneFalseNoneFalse909.00
3996071154625None15.1Providing and laying water proofing treatment to the Roof with PU based single component elastomeric pure polyurethane based coating on New rrace/Chajjas/Sunken portion of WC:Bathroom, cold applied PU waterproofing membrane that is highly elastic with elongation greater than 400% and tensile strength greater than 2MPa as per ASTM D412. The waterproofing membrane to be applied in 2coats @ 1.6kg per m2 to achieve final DFT (dry film thickness) of 1mm including prime coat of epoxy primer @150 g per m2 and protection with 120gsm Geo-textile over the waterproofing membrane. The finished cost to include surface preparation, making coving at Junction, Bore Packing, treatment of construction joints completely as per specification & with a 10 years warranty on product & work from certified manufacturers as per the direction of the Engineer In charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm833.34833.34640.759FalseNoneNoneFalseNoneFalse533970.105060
3996072154625None20.107Providing and fixing plain rolled glass 4mm thick with teakwood beading of 10mm thick. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1147.01147.04.965FalseNoneNoneFalseNoneFalse5694.8550
3996073154625None20.107Providing and fixing plain rolled glass 4mm thick with teakwood beading of 10mm thick. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1158.471158.474.365FalseNoneNoneFalseNoneFalse5056.721550
17262057300000NoneNoneBuildingsGirls Dormitory-1 (Shivani)24982185.71
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3996074154626None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.01450.1766FalseNoneNoneFalseNoneFalse147918.01320
3996075154626None1.15.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In ordinary/soft rock without blasting upto 1.5 m depth ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum363.0363.0369.607FalseNoneNoneFalseNoneFalse134167.3410
3996076154626None1.16.1Earth work excavation for FOUNDATION by Mechanical means depth upto 1.50m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including cost of explosives, dressing of excavated surfaces, disposing off or levelling the excavated stuff or sorting & stacking the selected stuff for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, blasting materials, tools, usage of Machinery & all other appurtenaces required to complete the work. In Hard Rock ( requiring blasting) Depth upto 1.50m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum554.0554.030.8005FalseNoneNoneFalseNoneFalse17063.4770
3996077154626None1.9Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum266.0266.0762.3514FalseNoneNoneFalseNoneFalse202785.47240
3996078154626None4.1Providing and injecting chemical emulsion for Pre-constructional Anti-Termite Treatment, creating continuous chemical barrier under and around the column pits, walls, trenches, basement excavation, top surface of the plinth filling, junction of wall and floor, along the external perimeter of building, expansion joints, over the top surface of consolidated earth on which apron is to be laid, surrounding of pipes and conduits with Chlorpyriphos 20% E.C. / Lindane 20% E.C. @ 3.19 l/m2 including cost of chemical, diluting in water to one percent concentration, labour, usage charges of machinery, complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm118.0118.0404.0FalseNoneNoneFalseNoneFalse47672.00
3996079154626None2.1.3Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5989.05989.085.0FalseNoneNoneFalseNoneFalse509065.00
3996080154626None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6217.06217.05.0FalseNoneNoneFalseNoneFalse31085.00
3996081154626None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7460.47460.40.9929FalseNoneNoneFalseNoneFalse7407.431160
3996082154626None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7522.577522.571.1201FalseNoneNoneFalseNoneFalse8426.0306570
3996083154626None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7584.747584.741.1278FalseNoneNoneFalseNoneFalse8554.0697720
3996084154626None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7646.917646.911.9FalseNoneNoneFalseNoneFalse14529.1290
3996085154626None2.1.6Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:2:4 Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6243.06243.04.0FalseNoneNoneFalseNoneFalse24972.00
3996086154626None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Footing concrete ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6842.886842.88152.2742FalseNoneNoneFalseNoneFalse1041994.0776960
3996087154626None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Pedastals ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10771.210771.27.9922FalseNoneNoneFalseNoneFalse86085.584640
3996088154626None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Columns Concrete Upto PB ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10771.210771.23.6855FalseNoneNoneFalseNoneFalse39697.25760
3996089154626None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Plinth Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9504.09504.016.1598FalseNoneNoneFalseNoneFalse153582.73920
3996090154626None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Grade Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9504.09504.030.7629FalseNoneNoneFalseNoneFalse292370.60160
3996091154626None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Columns Concrete Up to Roof ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11633.111633.119.0496FalseNoneNoneFalseNoneFalse221605.901760
3996092154626None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10948.810948.824.0478FalseNoneNoneFalseNoneFalse263294.552640
3996093154626None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10264.510264.568.8187FalseNoneNoneFalseNoneFalse706389.546150
3996094154626None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Lintel Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10948.810948.86.3535FalseNoneNoneFalseNoneFalse69563.20080
3996095154626None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Staircase ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10264.510264.58.0469FalseNoneNoneFalseNoneFalse82597.405050
3996096154626None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor For Columns Concrete Up to Roof ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11749.4311749.4318.3816FalseNoneNoneFalseNoneFalse215973.3224880
3996097154626None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11058.2811058.2824.1333FalseNoneNoneFalseNoneFalse266872.7887240
3996098154626None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10367.1410367.1461.8004FalseNoneNoneFalseNoneFalse640693.3988560
3996099154626None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor For Lintel Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11058.2811058.286.1206FalseNoneNoneFalseNoneFalse67683.3085680
3996100154626None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor For Staircase ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10367.1410367.148.0469FalseNoneNoneFalseNoneFalse83423.3388660
3996101154626None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Second Floor For Columns Concrete Up to Roof ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11865.7611865.7614.7798FalseNoneNoneFalseNoneFalse175373.5596480
3996102154626None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Second Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11167.7711167.7718.3455FalseNoneNoneFalseNoneFalse204878.3245350
3996103154626None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Second Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10469.7910469.7939.1743FalseNoneNoneFalseNoneFalse410146.6943970
3996104154626None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Second Floor For Lintel Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11167.7711167.774.2021FalseNoneNoneFalseNoneFalse46928.0863170
3996105154626None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Second Floor For Staircase ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10469.7910469.794.0234FalseNoneNoneFalseNoneFalse42124.1530860
3996106154626None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor For Columns ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11982.0911982.093.205FalseNoneNoneFalseNoneFalse38402.598450
3996107154626None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11277.2611277.2612.52FalseNoneNoneFalseNoneFalse141191.29520
3996108154626None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10572.4310572.4311.9266FalseNoneNoneFalseNoneFalse126093.1436380
3996109154626None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10885.9610885.964.0FalseNoneNoneFalseNoneFalse43543.840
3996110154626None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t89457.089457.029.8125FalseNoneNoneFalseNoneFalse2666936.81250
3996111154626None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t90351.5790351.5712.7707FalseNoneNoneFalseNoneFalse1153852.7949990
3996112154626None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t91246.1491246.148.8672FalseNoneNoneFalseNoneFalse809097.7726080
3996113154626None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t92140.7192140.713.6145FalseNoneNoneFalseNoneFalse333042.5962950
3996114154626None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1310.01310.0612.0FalseNoneNoneFalseNoneFalse801720.00
3996115154626None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1323.11323.1553.0FalseNoneNoneFalseNoneFalse731674.30
3996116154626None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1336.21336.2382.0FalseNoneNoneFalseNoneFalse510428.40
3996117154626None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1349.31349.3117.0FalseNoneNoneFalseNoneFalse157868.10
3996118154626None6.34Providing and constructing load bearing wall with Solid Concrete blocks of size 400x100x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1104.01104.0110.0FalseNoneNoneFalseNoneFalse121440.00
3996119154626None6.34Providing and constructing load bearing wall with Solid Concrete blocks of size 400x100x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1115.041115.0480.0FalseNoneNoneFalseNoneFalse89203.20
3996120154626None6.34Providing and constructing load bearing wall with Solid Concrete blocks of size 400x100x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1126.081126.0853.0FalseNoneNoneFalseNoneFalse59682.240
3996121154626None12.13.1Providing Salwood frames of doors, windows, clerestory windows, ventilators and other frames, wrought, framed or assembled including making plaster groves (excluding cost of cement concrete and side clamps), but including cost of materials, labour, usage charges complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum98815.098815.00.6FalseNoneNoneFalseNoneFalse59289.00
3996122154626None12.13.1Providing Salwood frames of doors, windows, clerestory windows, ventilators and other frames, wrought, framed or assembled including making plaster groves (excluding cost of cement concrete and side clamps), but including cost of materials, labour, usage charges complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum99803.1599803.150.4FalseNoneNoneFalseNoneFalse39921.260
3996123154626None12.13.1Providing Salwood frames of doors, windows, clerestory windows, ventilators and other frames, wrought, framed or assembled including making plaster groves (excluding cost of cement concrete and side clamps), but including cost of materials, labour, usage charges complete as per specifications. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum100791.3100791.30.4FalseNoneNoneFalseNoneFalse40316.520
3996124154626None12.17Providing and fixing in position fully panelled Honne wood shutters for doors with , stiles and rails of 35mm. thick with bottom and lock rails 180mm wide top rail and stiles 100mm wide as per drawing and panels of 25mm thick including cost of materials, labour, usage charges complete as per specifications. (excluding cost of fixtures) Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm7085.07085.03.8FalseNoneNoneFalseNoneFalse26923.00
3996125154626None12.57.3Providing and fixing flush door shutter made out of solid core block board type, well seasoned , chemicaly treated hard wood battens and internal frame with minimum 45 mm wide wooden frame alround door shutters covered with cross bonded wooden sheets (core veneer) hot pressed and fastened on both sides of the door useing liquid phenol formaldehyde resin as per IS specifications 2202 (part-I) 1991. from manufacturer complete as per spcification.-do- 30 mm thick both side commercial Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3005.03005.013.3FalseNoneNoneFalseNoneFalse39966.50
3996126154626None12.57.3Providing and fixing flush door shutter made out of solid core block board type, well seasoned , chemicaly treated hard wood battens and internal frame with minimum 45 mm wide wooden frame alround door shutters covered with cross bonded wooden sheets (core veneer) hot pressed and fastened on both sides of the door useing liquid phenol formaldehyde resin as per IS specifications 2202 (part-I) 1991. from manufacturer complete as per spcification.-do- 30 mm thick both side commercial First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3035.053035.0512.0FalseNoneNoneFalseNoneFalse36420.60
3996127154626None12.57.3Providing and fixing flush door shutter made out of solid core block board type, well seasoned , chemicaly treated hard wood battens and internal frame with minimum 45 mm wide wooden frame alround door shutters covered with cross bonded wooden sheets (core veneer) hot pressed and fastened on both sides of the door useing liquid phenol formaldehyde resin as per IS specifications 2202 (part-I) 1991. from manufacturer complete as per spcification.-do- 30 mm thick both side commercial Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3065.13065.110.1FalseNoneNoneFalseNoneFalse30957.510
3996128154626None12.51Fixing of door frame in an existing opening including embedding frame in floor and walls after cutting masonry for holdfasts for embedding holdfast in cement concrete 1:3:6 of 20mm and down size granite metal painting two coats of coal tar to sides of frame, making good the damages to walls and floor as required and disposal of the debris with lead upto 50 m. including cost of materials, labour charges, complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1016.01016.07.0FalseNoneNoneFalseNoneFalse7112.00
3996129154626None12.51Fixing of door frame in an existing opening including embedding frame in floor and walls after cutting masonry for holdfasts for embedding holdfast in cement concrete 1:3:6 of 20mm and down size granite metal painting two coats of coal tar to sides of frame, making good the damages to walls and floor as required and disposal of the debris with lead upto 50 m. including cost of materials, labour charges, complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1026.161026.165.0FalseNoneNoneFalseNoneFalse5130.80
3996130154626None12.51Fixing of door frame in an existing opening including embedding frame in floor and walls after cutting masonry for holdfasts for embedding holdfast in cement concrete 1:3:6 of 20mm and down size granite metal painting two coats of coal tar to sides of frame, making good the damages to walls and floor as required and disposal of the debris with lead upto 50 m. including cost of materials, labour charges, complete as per specifications. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1036.321036.324.0FalseNoneNoneFalseNoneFalse4145.280
3996131154626None12.93.1Providing and fixing factory made single extruded WPC (Wood Polymer Composite) solid door/window/Clerestory windows & other Frames/ Chowkhat comprising of virgin PVC polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibres (wood powder/rice husk/ wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) fabricated with miter joints after applying PVC solvent cement and screwed with full body threaded star headed SS screws having minimum frame density of 850 kg/m3, screw withdrawal strength of 2200 N (Face) & 1100 N (Edge), minimum compressive strength of 58 N/mm2 , modulus of elasticity 900 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixed in position with M.S hold fast/lugs/SS dash fasteners of required dia and length complete as per direction of Engineer-InCharge. (Fixtures shall be paid for separately) Size 62 x 100mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr702.0702.0110.4FalseNoneNoneFalseNoneFalse77500.80
3996132154626None12.93.1Providing and fixing factory made single extruded WPC (Wood Polymer Composite) solid door/window/Clerestory windows & other Frames/ Chowkhat comprising of virgin PVC polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibres (wood powder/rice husk/ wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) fabricated with miter joints after applying PVC solvent cement and screwed with full body threaded star headed SS screws having minimum frame density of 850 kg/m3, screw withdrawal strength of 2200 N (Face) & 1100 N (Edge), minimum compressive strength of 58 N/mm2 , modulus of elasticity 900 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixed in position with M.S hold fast/lugs/SS dash fasteners of required dia and length complete as per direction of Engineer-InCharge. (Fixtures shall be paid for separately) Size 62 x 100mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr709.02709.02105.0FalseNoneNoneFalseNoneFalse74447.10
3996133154626None12.93.1Providing and fixing factory made single extruded WPC (Wood Polymer Composite) solid door/window/Clerestory windows & other Frames/ Chowkhat comprising of virgin PVC polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibres (wood powder/rice husk/ wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) fabricated with miter joints after applying PVC solvent cement and screwed with full body threaded star headed SS screws having minimum frame density of 850 kg/m3, screw withdrawal strength of 2200 N (Face) & 1100 N (Edge), minimum compressive strength of 58 N/mm2 , modulus of elasticity 900 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixed in position with M.S hold fast/lugs/SS dash fasteners of required dia and length complete as per direction of Engineer-InCharge. (Fixtures shall be paid for separately) Size 62 x 100mm Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr716.04716.0447.4FalseNoneNoneFalseNoneFalse33940.2960
3996134154626None12.94.1Providing and fixing factory made Green certified, Anti Termite, UV resistant, high water absorbant single extruded WPC (Wood PolymerComposite) solid plain flush door shutter of required size comprising of virgin polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibers (wood powder/rice husk/wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) having minimum density of 650 kg/m3 and screw withdrawal strength of 1800 N (Face) & 900 N (Edge), minimum compressive strength of 50 N/mm2 , modulus of elasticity 850 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixing with stainless steel butt hinges of required size with necessary full body threaded star headed counter sunk S.S screws The cost includes cost of materials, transportation, labour and fixing charges.(Cost of Fixtures to be paid separately) 30 mm thickness Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3485.03485.033.4FalseNoneNoneFalseNoneFalse116399.00
3996135154626None12.94.1Providing and fixing factory made Green certified, Anti Termite, UV resistant, high water absorbant single extruded WPC (Wood PolymerComposite) solid plain flush door shutter of required size comprising of virgin polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibers (wood powder/rice husk/wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) having minimum density of 650 kg/m3 and screw withdrawal strength of 1800 N (Face) & 900 N (Edge), minimum compressive strength of 50 N/mm2 , modulus of elasticity 850 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixing with stainless steel butt hinges of required size with necessary full body threaded star headed counter sunk S.S screws The cost includes cost of materials, transportation, labour and fixing charges.(Cost of Fixtures to be paid separately) 30 mm thickness First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3519.853519.8531.5FalseNoneNoneFalseNoneFalse110875.2750
3996136154626None12.94.1Providing and fixing factory made Green certified, Anti Termite, UV resistant, high water absorbant single extruded WPC (Wood PolymerComposite) solid plain flush door shutter of required size comprising of virgin polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibers (wood powder/rice husk/wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) having minimum density of 650 kg/m3 and screw withdrawal strength of 1800 N (Face) & 900 N (Edge), minimum compressive strength of 50 N/mm2 , modulus of elasticity 850 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixing with stainless steel butt hinges of required size with necessary full body threaded star headed counter sunk S.S screws The cost includes cost of materials, transportation, labour and fixing charges.(Cost of Fixtures to be paid separately) 30 mm thickness Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3554.73554.714.5FalseNoneNoneFalseNoneFalse51543.150
3996137154626None12.9Providing & fixing of 3-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having an overall size of 108mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm x 75mm with GI reinforcement of 2mm and mesh sash of size 37mm x 58mm. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24 mm. Windows shall be provided with 6mm plain float glass, standard hardware& Multi point locking system with touch lock. Wall thickness of frame & sash shall be of 2mm-2.5mm. Maximum possible size 2419mm x 2200mm. (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm6734.06734.030.0FalseNoneNoneFalseNoneFalse202020.00
3996138154626None12.9Providing & fixing of 3-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having an overall size of 108mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm x 75mm with GI reinforcement of 2mm and mesh sash of size 37mm x 58mm. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24 mm. Windows shall be provided with 6mm plain float glass, standard hardware& Multi point locking system with touch lock. Wall thickness of frame & sash shall be of 2mm-2.5mm. Maximum possible size 2419mm x 2200mm. (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm6801.346801.3432.0FalseNoneNoneFalseNoneFalse217642.880
3996139154626None12.9Providing & fixing of 3-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having an overall size of 108mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm x 75mm with GI reinforcement of 2mm and mesh sash of size 37mm x 58mm. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24 mm. Windows shall be provided with 6mm plain float glass, standard hardware& Multi point locking system with touch lock. Wall thickness of frame & sash shall be of 2mm-2.5mm. Maximum possible size 2419mm x 2200mm. (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm6868.686868.6837.0FalseNoneNoneFalseNoneFalse254141.160
3996140154626None12.9Providing & fixing of 3-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having an overall size of 108mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm x 75mm with GI reinforcement of 2mm and mesh sash of size 37mm x 58mm. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24 mm. Windows shall be provided with 6mm plain float glass, standard hardware& Multi point locking system with touch lock. Wall thickness of frame & sash shall be of 2mm-2.5mm. Maximum possible size 2419mm x 2200mm. (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm6936.026936.023.0FalseNoneNoneFalseNoneFalse20808.060
3996141154626None12.85Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5719.05719.024.0FalseNoneNoneFalseNoneFalse137256.00
3996142154626None12.85Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5776.195776.1919.0FalseNoneNoneFalseNoneFalse109747.610
3996143154626None12.85Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5833.385833.3820.0FalseNoneNoneFalseNoneFalse116667.60
3996144154626None12.85Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5890.575890.572.0FalseNoneNoneFalseNoneFalse11781.140
3996145154626None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs183.0183.0961.0FalseNoneNoneFalseNoneFalse175863.00
3996146154626None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs184.83184.83896.0FalseNoneNoneFalseNoneFalse165607.680
3996147154626None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs186.66186.661013.0FalseNoneNoneFalseNoneFalse189086.580
3996148154626None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs188.49188.4959.0FalseNoneNoneFalseNoneFalse11120.910
3996149154626None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2852.02852.0411.0FalseNoneNoneFalseNoneFalse1172172.00
3996150154626None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2880.522880.52364.0FalseNoneNoneFalseNoneFalse1048509.280
3996151154626None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2909.042909.04232.0FalseNoneNoneFalseNoneFalse674897.280
3996152154626None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2937.562937.568.0FalseNoneNoneFalseNoneFalse23500.480
3996153154626None9.11Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved make, in all colours, shades, except White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick bed of cement mortar 1:4 (1 Cement : 4 Coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including pointing the joints with white cement and matching pigments etc., complete. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm889.0889.072.0FalseNoneNoneFalseNoneFalse64008.00
3996154154626None9.11Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved make, in all colours, shades, except White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick bed of cement mortar 1:4 (1 Cement : 4 Coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including pointing the joints with white cement and matching pigments etc., complete. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm897.89897.8969.0FalseNoneNoneFalseNoneFalse61954.410
3996155154626None9.11Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved make, in all colours, shades, except White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick bed of cement mortar 1:4 (1 Cement : 4 Coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including pointing the joints with white cement and matching pigments etc., complete. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm906.78906.7831.0FalseNoneNoneFalseNoneFalse28110.180
3996156154626None9.39Providing skirting, dadooing, rises of steps with colour glazed tiles 6mm thick on 10mm thick cement plaster 1:3 and jointed with white cement slurry over existing rough plaster surface using glazed tiles of approved make and size including cost of materials, labour, complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1449.01449.0262.0FalseNoneNoneFalseNoneFalse379638.00
3996157154626None9.39Providing skirting, dadooing, rises of steps with colour glazed tiles 6mm thick on 10mm thick cement plaster 1:3 and jointed with white cement slurry over existing rough plaster surface using glazed tiles of approved make and size including cost of materials, labour, complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1463.491463.49240.0FalseNoneNoneFalseNoneFalse351237.60
3996158154626None9.39Providing skirting, dadooing, rises of steps with colour glazed tiles 6mm thick on 10mm thick cement plaster 1:3 and jointed with white cement slurry over existing rough plaster surface using glazed tiles of approved make and size including cost of materials, labour, complete as per specifications. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1477.981477.9892.0FalseNoneNoneFalseNoneFalse135974.160
3996159154626None10.2Providing edge moulding to 18mm thick Granite stone counters, vanities etc including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr328.0328.086.0FalseNoneNoneFalseNoneFalse28208.00
3996160154626None10.2Providing edge moulding to 18mm thick Granite stone counters, vanities etc including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr331.28331.2867.0FalseNoneNoneFalseNoneFalse22195.760
3996161154626None10.2Providing edge moulding to 18mm thick Granite stone counters, vanities etc including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineer-in-charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr334.56334.5634.0FalseNoneNoneFalseNoneFalse11375.040
3996162154626None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm295.0295.01105.0FalseNoneNoneFalseNoneFalse325975.00
3996163154626None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm297.95297.951048.0FalseNoneNoneFalseNoneFalse312251.60
3996164154626None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm300.9300.9626.0FalseNoneNoneFalseNoneFalse188363.40
3996165154626None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm303.85303.8574.0FalseNoneNoneFalseNoneFalse22484.90
3996166154626None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm371.0371.0510.0FalseNoneNoneFalseNoneFalse189210.00
3996167154626None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm374.71374.71516.0FalseNoneNoneFalseNoneFalse193350.360
3996168154626None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm378.42378.42497.0FalseNoneNoneFalseNoneFalse188074.740
3996169154626None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm382.13382.13311.0FalseNoneNoneFalseNoneFalse118842.430
3996170154626None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg64.064.077.0FalseNoneNoneFalseNoneFalse4928.00
3996171154626None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg64.6464.6478.0FalseNoneNoneFalseNoneFalse5041.920
3996172154626None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg65.2865.2874.55FalseNoneNoneFalseNoneFalse4866.6240
3996173154626None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg65.9265.9246.65FalseNoneNoneFalseNoneFalse3075.1680
3996174154626None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm295.0295.0279.0FalseNoneNoneFalseNoneFalse82305.00
3996175154626None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm297.95297.95255.0FalseNoneNoneFalseNoneFalse75977.250
3996176154626None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm300.9300.999.0FalseNoneNoneFalseNoneFalse29789.10
3996177154626None8.16 aProviding lath plaster with cement mortar 1:3, 5cms thick with 6mm dia mild steel bars at 20 cms. c to c both horizontally and vertically fixing chicken mesh for drop chajja, facia, backing to cup boards including cost of all materials, labour, providing and removing form work usage charges, curing complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1238.01238.03.0FalseNoneNoneFalseNoneFalse3714.00
3996178154626None8.16 aProviding lath plaster with cement mortar 1:3, 5cms thick with 6mm dia mild steel bars at 20 cms. c to c both horizontally and vertically fixing chicken mesh for drop chajja, facia, backing to cup boards including cost of all materials, labour, providing and removing form work usage charges, curing complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1250.381250.383.0FalseNoneNoneFalseNoneFalse3751.140
3996179154626None8.16 aProviding lath plaster with cement mortar 1:3, 5cms thick with 6mm dia mild steel bars at 20 cms. c to c both horizontally and vertically fixing chicken mesh for drop chajja, facia, backing to cup boards including cost of all materials, labour, providing and removing form work usage charges, curing complete as per specifications. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1262.761262.763.0FalseNoneNoneFalseNoneFalse3788.280
3996180154626None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm100.0100.01574.0067FalseNoneNoneFalseNoneFalse157400.670
3996181154626None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. First floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm101.0101.01468.5176FalseNoneNoneFalseNoneFalse148320.27760
3996182154626None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm102.0102.0895.6766FalseNoneNoneFalseNoneFalse91359.01320
3996183154626None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm103.0103.0123.8334FalseNoneNoneFalseNoneFalse12754.84020
3996184154626None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm110.0110.01425.5917FalseNoneNoneFalseNoneFalse156815.0870
3996185154626None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. First floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm111.1111.11319.5626FalseNoneNoneFalseNoneFalse146603.404860
3996186154626None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm112.2112.2748.3416FalseNoneNoneFalseNoneFalse83963.927520
3996187154626None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm113.3113.3123.8334FalseNoneNoneFalseNoneFalse14030.324220
3996188154626None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.053.01574.0067FalseNoneNoneFalseNoneFalse83422.35510
3996189154626None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.5353.531468.5176FalseNoneNoneFalseNoneFalse78609.7471280
3996190154626None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm54.0654.06895.6766FalseNoneNoneFalseNoneFalse48420.2769960
3996191154626None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm54.5954.59123.8334FalseNoneNoneFalseNoneFalse6760.0653060
3996192154626None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm174.0174.0510.0FalseNoneNoneFalseNoneFalse88740.00
3996193154626None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm175.74175.74516.0FalseNoneNoneFalseNoneFalse90681.840
3996194154626None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Second floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm177.48177.48497.0FalseNoneNoneFalseNoneFalse88207.560
3996195154626None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm179.22179.22311.0FalseNoneNoneFalseNoneFalse55737.420
3996196154626None8.34.1Applying priming coat: With ready mixed pink or Grey primer of approved brand and manufacture on wood work (hard and soft wood) including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.053.041.0FalseNoneNoneFalseNoneFalse2173.00
3996197154626None8.34.1Applying priming coat: With ready mixed pink or Grey primer of approved brand and manufacture on wood work (hard and soft wood) including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.5353.5325.0FalseNoneNoneFalseNoneFalse1338.250
3996198154626None8.34.1Applying priming coat: With ready mixed pink or Grey primer of approved brand and manufacture on wood work (hard and soft wood) including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm54.0654.0625.0FalseNoneNoneFalseNoneFalse1351.50
3996199154626None8.33.2Painting wood work with Deluxe Multi Surface Paint of required shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @0.75 L/10 m² of approved brand and manufacture to give an even shade including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, sand papering and knotting , cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm138.0138.041.0FalseNoneNoneFalseNoneFalse5658.00
3996200154626None8.33.2Painting wood work with Deluxe Multi Surface Paint of required shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @0.75 L/10 m² of approved brand and manufacture to give an even shade including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, sand papering and knotting , cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm139.38139.3825.0FalseNoneNoneFalseNoneFalse3484.50
3996201154626None8.33.2Painting wood work with Deluxe Multi Surface Paint of required shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @0.75 L/10 m² of approved brand and manufacture to give an even shade including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, sand papering and knotting , cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm140.76140.7625.0FalseNoneNoneFalseNoneFalse3519.00
3996202154626None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @ 0.80 L/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm139.0139.054.0FalseNoneNoneFalseNoneFalse7506.00
3996203154626None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @ 0.80 L/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm140.39140.3950.0FalseNoneNoneFalseNoneFalse7019.50
3996204154626None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @ 0.80 L/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm141.78141.7857.0FalseNoneNoneFalseNoneFalse8081.460
3996205154626None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @ 0.80 L/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm143.17143.174.0FalseNoneNoneFalseNoneFalse572.680
3996206154626None8.4Painting with synthetic enamel paint of approved brand and manufacture to give an even shade :Two coats on new work after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm115.0115.0148.415FalseNoneNoneFalseNoneFalse17067.7250
3996207154626None8.4Painting with synthetic enamel paint of approved brand and manufacture to give an even shade :Two coats on new work after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm116.15116.15148.955FalseNoneNoneFalseNoneFalse17301.123250
3996208154626None8.4Painting with synthetic enamel paint of approved brand and manufacture to give an even shade :Two coats on new work after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm117.3117.3147.335FalseNoneNoneFalseNoneFalse17282.39550
3996209154626None11.28Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners, stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in- charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.) including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs565.0565.0298.0FalseNoneNoneFalseNoneFalse168370.00
3996210154626None11.28Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners, stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in- charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.) including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs570.65570.65130.0FalseNoneNoneFalseNoneFalse74184.50
3996211154626None11.28Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners, stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in- charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.) including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. Second floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs576.3576.365.0FalseNoneNoneFalseNoneFalse37459.50
3996212154626None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr66.066.0201.0FalseNoneNoneFalseNoneFalse13266.00
3996213154626None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr66.6666.66201.0FalseNoneNoneFalseNoneFalse13398.660
3996214154626None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr67.3267.32237.0FalseNoneNoneFalseNoneFalse15954.840
3996215154626None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr67.9867.9841.0FalseNoneNoneFalseNoneFalse2787.180
3996216154626None7.18Providing and laying cinder concrete in cement 1:15 ( 1 cement : 15 cinder of 12.5mm nominal gauge) on terraced roof or sunken slabs, laid to slope compacting, including cost of materials, labour, curing complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum2037.172037.1716.0FalseNoneNoneFalseNoneFalse32594.720
3996217154626None7.18Providing and laying cinder concrete in cement 1:15 ( 1 cement : 15 cinder of 12.5mm nominal gauge) on terraced roof or sunken slabs, laid to slope compacting, including cost of materials, labour, curing complete as per specifications. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum2057.342057.3411.0FalseNoneNoneFalseNoneFalse22630.740
3996218154626None15.7Integral Crystalline Water Proofing Admixture Providing and supplying crystalline integral concrete waterproofing admixture that waterproofs concrete by forming crystals deep in the pores, capillaries and microcracks of the concrete, self-seal waterproofing compound to bridge shrinkage cracks upto 0.5mm in width & resist hydro-static pressure upto 16bar for both positive & negative pressure confirming to DIN 1048 part 5 for 56% reduction in depth of penetration against control, resistance to chloride penetration confirming to ASTM C 1202 with 64% improvement against control & protecting steel reinforcement against corrosion mixed @ 1% by weight of cementitious content in concrete. ie., integral crystaline waterproofing admix @ 0.5 kg/bag of cement. (For calculation purpose 320 kg of Cement for M-20 grade of Concrete is considered in the analysis) First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm621.15621.1566.0FalseNoneNoneFalseNoneFalse40995.90
3996219154626None15.7Integral Crystalline Water Proofing Admixture Providing and supplying crystalline integral concrete waterproofing admixture that waterproofs concrete by forming crystals deep in the pores, capillaries and microcracks of the concrete, self-seal waterproofing compound to bridge shrinkage cracks upto 0.5mm in width & resist hydro-static pressure upto 16bar for both positive & negative pressure confirming to DIN 1048 part 5 for 56% reduction in depth of penetration against control, resistance to chloride penetration confirming to ASTM C 1202 with 64% improvement against control & protecting steel reinforcement against corrosion mixed @ 1% by weight of cementitious content in concrete. ie., integral crystaline waterproofing admix @ 0.5 kg/bag of cement. (For calculation purpose 320 kg of Cement for M-20 grade of Concrete is considered in the analysis) Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm627.3627.335.0FalseNoneNoneFalseNoneFalse21955.50
3996220154626None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9613.59613.53.4015FalseNoneNoneFalseNoneFalse32700.320250
3996221154626None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9679.89679.84.2669FalseNoneNoneFalseNoneFalse41302.738620
3996222154626None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9746.19746.12.0155FalseNoneNoneFalseNoneFalse19643.264550
3996223154626None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9812.49812.434.5701FalseNoneNoneFalseNoneFalse339215.649240
3996224154626None9.25Providing and laying 60mm thick factory made cement concrete paver block of approved shape and colour of M -30 grade made of C&D waste by block making machine with vibratory compaction laid in required pattern and including over 50mm thick compacted bed of coarse sand, filling the joints with fine sand etc. all complete as per the direction of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm800.0800.025.0FalseNoneNoneFalseNoneFalse20000.00
3996225154626NoneVOL -5 7.1.1Providing and fixing MS ladder between landings, 45 cms wide using angle iron of specified sizes, 20mm MS bars at 25 cms. centre to centre, with necessary supports of same angle iron etc. as directed, including hand railing on both sides with 25mm dia. GI pipes with angle iron props at 2 mtrs. intervals and 0.5M heigh, including fixing in ground with CC 1:2:4 and two coats of anticorrosive bituminous paint etc. with all lead and lifts etc. complete with: MS angle of 65 x 65 x 8mm Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr4508.314508.314.5FalseNoneNoneFalseNoneFalse20287.3950
3996226154626None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.038.0241.2FalseNoneNoneFalseNoneFalse9165.60
3996227154626None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.3838.38165.6FalseNoneNoneFalseNoneFalse6355.7280
3996228154626None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.7638.76165.6FalseNoneNoneFalseNoneFalse6418.6560
3996229154626None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr39.1439.147.65FalseNoneNoneFalseNoneFalse299.4210
3996230154626None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.038.0243.69FalseNoneNoneFalseNoneFalse9260.220
3996231154626None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.3838.38232.09FalseNoneNoneFalseNoneFalse8907.61420
3996232154626None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.7638.76151.23FalseNoneNoneFalseNoneFalse5861.67480
3996233154626None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr39.1439.1415.11FalseNoneNoneFalseNoneFalse591.40540
3996234154626None22.15.7Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Tower Bolts 250x10mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos200.0200.029.0FalseNoneNoneFalseNoneFalse5800.00
3996235154626None22.15.7Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Tower Bolts 250x10mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos202.0202.025.0FalseNoneNoneFalseNoneFalse5050.00
3996236154626None22.15.7Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Tower Bolts 250x10mm Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos204.0204.013.0FalseNoneNoneFalseNoneFalse2652.00
3996237154626None22.15.8Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS hinges 125 mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos50.050.095.0FalseNoneNoneFalseNoneFalse4750.00
3996238154626None22.15.8Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS hinges 125 mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos50.550.580.0FalseNoneNoneFalseNoneFalse4040.00
3996239154626None22.15.8Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS hinges 125 mm Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos51.051.043.0FalseNoneNoneFalseNoneFalse2193.00
3996240154626None22.15.1Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Handles 200mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos450.0450.058.0FalseNoneNoneFalseNoneFalse26100.00
3996241154626None22.15.1Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Handles 200mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos454.5454.550.0FalseNoneNoneFalseNoneFalse22725.00
3996242154626None22.15.1Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Handles 200mm Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos459.0459.026.0FalseNoneNoneFalseNoneFalse11934.00
3996243154626None22.15.4Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Aldrop 16mm dia, 300mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos375.0375.028.0FalseNoneNoneFalseNoneFalse10500.00
3996244154626None22.15.4Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Aldrop 16mm dia, 300mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos378.75378.7525.0FalseNoneNoneFalseNoneFalse9468.750
3996245154626None22.15.4Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Aldrop 16mm dia, 300mm Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos382.5382.513.0FalseNoneNoneFalseNoneFalse4972.50
3996246154626None22.15.10Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Door stopper 75mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos100.0100.08.0FalseNoneNoneFalseNoneFalse800.00
3996247154626None22.15.10Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Door stopper 75mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos101.0101.05.0FalseNoneNoneFalseNoneFalse505.00
3996248154626None22.15.10Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Door stopper 75mm Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos102.0102.04.0FalseNoneNoneFalseNoneFalse408.00
3996249154626None15.1Providing and laying water proofing treatment to the Roof with PU based single component elastomeric pure polyurethane based coating on New rrace/Chajjas/Sunken portion of WC:Bathroom, cold applied PU waterproofing membrane that is highly elastic with elongation greater than 400% and tensile strength greater than 2MPa as per ASTM D412. The waterproofing membrane to be applied in 2coats @ 1.6kg per m2 to achieve final DFT (dry film thickness) of 1mm including prime coat of epoxy primer @150 g per m2 and protection with 120gsm Geo-textile over the waterproofing membrane. The finished cost to include surface preparation, making coving at Junction, Bore Packing, treatment of construction joints completely as per specification & with a 10 years warranty on product & work from certified manufacturers as per the direction of the Engineer In charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm841.51841.51338.0FalseNoneNoneFalseNoneFalse284430.380
3996250154626None20.107Providing and fixing plain rolled glass 4mm thick with teakwood beading of 10mm thick. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1147.01147.02.43FalseNoneNoneFalseNoneFalse2787.210
3996251154626None20.107Providing and fixing plain rolled glass 4mm thick with teakwood beading of 10mm thick. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1158.471158.471.71FalseNoneNoneFalseNoneFalse1980.98370
17262057300001NoneNoneBuildingsGirls Dormitory-2 (Shivani)25203578.49
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3996252154627None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.03620.6941FalseNoneNoneFalseNoneFalse369310.79820
3996253154627None1.15.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In ordinary/soft rock without blasting upto 1.5 m depth ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum363.0363.0369.607FalseNoneNoneFalseNoneFalse134167.3410
3996254154627None1.16.1Earth work excavation for FOUNDATION by Mechanical means depth upto 1.50m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including cost of explosives, dressing of excavated surfaces, disposing off or levelling the excavated stuff or sorting & stacking the selected stuff for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, blasting materials, tools, usage of Machinery & all other appurtenaces required to complete the work. In Hard Rock ( requiring blasting) Depth upto 1.50m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum554.0554.030.8005FalseNoneNoneFalseNoneFalse17063.4770
3996255154627None1.9Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum266.0266.0762.3514FalseNoneNoneFalseNoneFalse202785.47240
3996256154627None4.1Providing and injecting chemical emulsion for Pre-constructional Anti-Termite Treatment, creating continuous chemical barrier under and around the column pits, walls, trenches, basement excavation, top surface of the plinth filling, junction of wall and floor, along the external perimeter of building, expansion joints, over the top surface of consolidated earth on which apron is to be laid, surrounding of pipes and conduits with Chlorpyriphos 20% E.C. / Lindane 20% E.C. @ 3.19 l/m2 including cost of chemical, diluting in water to one percent concentration, labour, usage charges of machinery, complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm118.0118.0404.0FalseNoneNoneFalseNoneFalse47672.00
3996257154627None2.1.3Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5989.05989.085.0FalseNoneNoneFalseNoneFalse509065.00
3996258154627None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6217.06217.05.0FalseNoneNoneFalseNoneFalse31085.00
3996259154627None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7460.47460.40.9929FalseNoneNoneFalseNoneFalse7407.431160
3996260154627None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7522.577522.571.1201FalseNoneNoneFalseNoneFalse8426.0306570
3996261154627None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7584.747584.741.1278FalseNoneNoneFalseNoneFalse8554.0697720
3996262154627None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7646.917646.911.9FalseNoneNoneFalseNoneFalse14529.1290
3996263154627None2.1.6Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:2:4 Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6243.06243.04.0FalseNoneNoneFalseNoneFalse24972.00
3996264154627None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Footing concrete ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6842.886842.88152.2742FalseNoneNoneFalseNoneFalse1041994.0776960
3996265154627None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Pedastals ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10771.210771.27.9922FalseNoneNoneFalseNoneFalse86085.584640
3996266154627None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Columns Concrete Upto PB ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10771.210771.23.6855FalseNoneNoneFalseNoneFalse39697.25760
3996267154627None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Plinth Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9504.09504.016.1598FalseNoneNoneFalseNoneFalse153582.73920
3996268154627None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Grade Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9504.09504.030.7629FalseNoneNoneFalseNoneFalse292370.60160
3996269154627None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Columns Concrete Up to Roof ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11633.111633.119.0496FalseNoneNoneFalseNoneFalse221605.901760
3996270154627None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10948.810948.824.0478FalseNoneNoneFalseNoneFalse263294.552640
3996271154627None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10264.510264.568.8187FalseNoneNoneFalseNoneFalse706389.546150
3996272154627None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Lintel Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10948.810948.86.3535FalseNoneNoneFalseNoneFalse69563.20080
3996273154627None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Staircase ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10264.510264.58.0469FalseNoneNoneFalseNoneFalse82597.405050
3996274154627None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor For Columns Concrete Up to Roof ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11749.4311749.4318.3816FalseNoneNoneFalseNoneFalse215973.3224880
3996275154627None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11058.2811058.2824.1333FalseNoneNoneFalseNoneFalse266872.7887240
3996276154627None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10367.1410367.1461.8004FalseNoneNoneFalseNoneFalse640693.3988560
3996277154627None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor For Lintel Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11058.2811058.286.1206FalseNoneNoneFalseNoneFalse67683.3085680
3996278154627None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor For Staircase ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10367.1410367.148.0469FalseNoneNoneFalseNoneFalse83423.3388660
3996279154627None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Second Floor For Columns Concrete Up to Roof ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11865.7611865.7614.7798FalseNoneNoneFalseNoneFalse175373.5596480
3996280154627None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Second Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11167.7711167.7718.3455FalseNoneNoneFalseNoneFalse204878.3245350
3996281154627None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Second Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10469.7910469.7939.1743FalseNoneNoneFalseNoneFalse410146.6943970
3996282154627None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Second Floor For Lintel Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11167.7711167.774.2021FalseNoneNoneFalseNoneFalse46928.0863170
3996283154627None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Second Floor For Staircase ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10469.7910469.794.0234FalseNoneNoneFalseNoneFalse42124.1530860
3996284154627None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor For Columns ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11982.0911982.093.205FalseNoneNoneFalseNoneFalse38402.598450
3996285154627None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11277.2611277.2612.52FalseNoneNoneFalseNoneFalse141191.29520
3996286154627None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10572.4310572.4311.9266FalseNoneNoneFalseNoneFalse126093.1436380
3996287154627None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10885.9610885.964.0FalseNoneNoneFalseNoneFalse43543.840
3996288154627None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t89457.089457.029.8125FalseNoneNoneFalseNoneFalse2666936.81250
3996289154627None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t90351.5790351.5712.7707FalseNoneNoneFalseNoneFalse1153852.7949990
3996290154627None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t91246.1491246.148.8672FalseNoneNoneFalseNoneFalse809097.7726080
3996291154627None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t92140.7192140.713.6145FalseNoneNoneFalseNoneFalse333042.5962950
3996292154627None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1310.01310.0612.0FalseNoneNoneFalseNoneFalse801720.00
3996293154627None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1323.11323.1553.0FalseNoneNoneFalseNoneFalse731674.30
3996294154627None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1336.21336.2382.0FalseNoneNoneFalseNoneFalse510428.40
3996295154627None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1349.31349.3117.0FalseNoneNoneFalseNoneFalse157868.10
3996296154627None6.34Providing and constructing load bearing wall with Solid Concrete blocks of size 400x100x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1104.01104.0110.0FalseNoneNoneFalseNoneFalse121440.00
3996297154627None6.34Providing and constructing load bearing wall with Solid Concrete blocks of size 400x100x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1115.041115.0480.0FalseNoneNoneFalseNoneFalse89203.20
3996298154627None6.34Providing and constructing load bearing wall with Solid Concrete blocks of size 400x100x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1126.081126.0853.0FalseNoneNoneFalseNoneFalse59682.240
3996299154627None12.13.1Providing Salwood frames of doors, windows, clerestory windows, ventilators and other frames, wrought, framed or assembled including making plaster groves (excluding cost of cement concrete and side clamps), but including cost of materials, labour, usage charges complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum98815.098815.00.6FalseNoneNoneFalseNoneFalse59289.00
3996300154627None12.13.1Providing Salwood frames of doors, windows, clerestory windows, ventilators and other frames, wrought, framed or assembled including making plaster groves (excluding cost of cement concrete and side clamps), but including cost of materials, labour, usage charges complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum99803.1599803.150.4FalseNoneNoneFalseNoneFalse39921.260
3996301154627None12.13.1Providing Salwood frames of doors, windows, clerestory windows, ventilators and other frames, wrought, framed or assembled including making plaster groves (excluding cost of cement concrete and side clamps), but including cost of materials, labour, usage charges complete as per specifications. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum100791.3100791.30.4FalseNoneNoneFalseNoneFalse40316.520
3996302154627None12.17Providing and fixing in position fully panelled Honne wood shutters for doors with , stiles and rails of 35mm. thick with bottom and lock rails 180mm wide top rail and stiles 100mm wide as per drawing and panels of 25mm thick including cost of materials, labour, usage charges complete as per specifications. (excluding cost of fixtures) Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm7085.07085.03.8FalseNoneNoneFalseNoneFalse26923.00
3996303154627None12.57.3Providing and fixing flush door shutter made out of solid core block board type, well seasoned , chemicaly treated hard wood battens and internal frame with minimum 45 mm wide wooden frame alround door shutters covered with cross bonded wooden sheets (core veneer) hot pressed and fastened on both sides of the door useing liquid phenol formaldehyde resin as per IS specifications 2202 (part-I) 1991. from manufacturer complete as per spcification.-do- 30 mm thick both side commercial Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3005.03005.013.3FalseNoneNoneFalseNoneFalse39966.50
3996304154627None12.57.3Providing and fixing flush door shutter made out of solid core block board type, well seasoned , chemicaly treated hard wood battens and internal frame with minimum 45 mm wide wooden frame alround door shutters covered with cross bonded wooden sheets (core veneer) hot pressed and fastened on both sides of the door useing liquid phenol formaldehyde resin as per IS specifications 2202 (part-I) 1991. from manufacturer complete as per spcification.-do- 30 mm thick both side commercial First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3035.053035.0512.0FalseNoneNoneFalseNoneFalse36420.60
3996305154627None12.57.3Providing and fixing flush door shutter made out of solid core block board type, well seasoned , chemicaly treated hard wood battens and internal frame with minimum 45 mm wide wooden frame alround door shutters covered with cross bonded wooden sheets (core veneer) hot pressed and fastened on both sides of the door useing liquid phenol formaldehyde resin as per IS specifications 2202 (part-I) 1991. from manufacturer complete as per spcification.-do- 30 mm thick both side commercial Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3065.13065.110.1FalseNoneNoneFalseNoneFalse30957.510
3996306154627None12.51Fixing of door frame in an existing opening including embedding frame in floor and walls after cutting masonry for holdfasts for embedding holdfast in cement concrete 1:3:6 of 20mm and down size granite metal painting two coats of coal tar to sides of frame, making good the damages to walls and floor as required and disposal of the debris with lead upto 50 m. including cost of materials, labour charges, complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1016.01016.07.0FalseNoneNoneFalseNoneFalse7112.00
3996307154627None12.51Fixing of door frame in an existing opening including embedding frame in floor and walls after cutting masonry for holdfasts for embedding holdfast in cement concrete 1:3:6 of 20mm and down size granite metal painting two coats of coal tar to sides of frame, making good the damages to walls and floor as required and disposal of the debris with lead upto 50 m. including cost of materials, labour charges, complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1026.161026.165.0FalseNoneNoneFalseNoneFalse5130.80
3996308154627None12.51Fixing of door frame in an existing opening including embedding frame in floor and walls after cutting masonry for holdfasts for embedding holdfast in cement concrete 1:3:6 of 20mm and down size granite metal painting two coats of coal tar to sides of frame, making good the damages to walls and floor as required and disposal of the debris with lead upto 50 m. including cost of materials, labour charges, complete as per specifications. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1036.321036.324.0FalseNoneNoneFalseNoneFalse4145.280
3996309154627None12.93.1Providing and fixing factory made single extruded WPC (Wood Polymer Composite) solid door/window/Clerestory windows & other Frames/ Chowkhat comprising of virgin PVC polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibres (wood powder/rice husk/ wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) fabricated with miter joints after applying PVC solvent cement and screwed with full body threaded star headed SS screws having minimum frame density of 850 kg/m3, screw withdrawal strength of 2200 N (Face) & 1100 N (Edge), minimum compressive strength of 58 N/mm2 , modulus of elasticity 900 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixed in position with M.S hold fast/lugs/SS dash fasteners of required dia and length complete as per direction of Engineer-InCharge. (Fixtures shall be paid for separately) Size 62 x 100mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr702.0702.0110.4FalseNoneNoneFalseNoneFalse77500.80
3996310154627None12.93.1Providing and fixing factory made single extruded WPC (Wood Polymer Composite) solid door/window/Clerestory windows & other Frames/ Chowkhat comprising of virgin PVC polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibres (wood powder/rice husk/ wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) fabricated with miter joints after applying PVC solvent cement and screwed with full body threaded star headed SS screws having minimum frame density of 850 kg/m3, screw withdrawal strength of 2200 N (Face) & 1100 N (Edge), minimum compressive strength of 58 N/mm2 , modulus of elasticity 900 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixed in position with M.S hold fast/lugs/SS dash fasteners of required dia and length complete as per direction of Engineer-InCharge. (Fixtures shall be paid for separately) Size 62 x 100mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr709.02709.02105.0FalseNoneNoneFalseNoneFalse74447.10
3996311154627None12.93.1Providing and fixing factory made single extruded WPC (Wood Polymer Composite) solid door/window/Clerestory windows & other Frames/ Chowkhat comprising of virgin PVC polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibres (wood powder/rice husk/ wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) fabricated with miter joints after applying PVC solvent cement and screwed with full body threaded star headed SS screws having minimum frame density of 850 kg/m3, screw withdrawal strength of 2200 N (Face) & 1100 N (Edge), minimum compressive strength of 58 N/mm2 , modulus of elasticity 900 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixed in position with M.S hold fast/lugs/SS dash fasteners of required dia and length complete as per direction of Engineer-InCharge. (Fixtures shall be paid for separately) Size 62 x 100mm Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr716.04716.0447.4FalseNoneNoneFalseNoneFalse33940.2960
3996312154627None12.94.1Providing and fixing factory made Green certified, Anti Termite, UV resistant, high water absorbant single extruded WPC (Wood PolymerComposite) solid plain flush door shutter of required size comprising of virgin polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibers (wood powder/rice husk/wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) having minimum density of 650 kg/m3 and screw withdrawal strength of 1800 N (Face) & 900 N (Edge), minimum compressive strength of 50 N/mm2 , modulus of elasticity 850 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixing with stainless steel butt hinges of required size with necessary full body threaded star headed counter sunk S.S screws The cost includes cost of materials, transportation, labour and fixing charges.(Cost of Fixtures to be paid separately) 30 mm thickness Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3485.03485.033.4FalseNoneNoneFalseNoneFalse116399.00
3996313154627None12.94.1Providing and fixing factory made Green certified, Anti Termite, UV resistant, high water absorbant single extruded WPC (Wood PolymerComposite) solid plain flush door shutter of required size comprising of virgin polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibers (wood powder/rice husk/wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) having minimum density of 650 kg/m3 and screw withdrawal strength of 1800 N (Face) & 900 N (Edge), minimum compressive strength of 50 N/mm2 , modulus of elasticity 850 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixing with stainless steel butt hinges of required size with necessary full body threaded star headed counter sunk S.S screws The cost includes cost of materials, transportation, labour and fixing charges.(Cost of Fixtures to be paid separately) 30 mm thickness First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3519.853519.8531.5FalseNoneNoneFalseNoneFalse110875.2750
3996314154627None12.94.1Providing and fixing factory made Green certified, Anti Termite, UV resistant, high water absorbant single extruded WPC (Wood PolymerComposite) solid plain flush door shutter of required size comprising of virgin polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibers (wood powder/rice husk/wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) having minimum density of 650 kg/m3 and screw withdrawal strength of 1800 N (Face) & 900 N (Edge), minimum compressive strength of 50 N/mm2 , modulus of elasticity 850 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixing with stainless steel butt hinges of required size with necessary full body threaded star headed counter sunk S.S screws The cost includes cost of materials, transportation, labour and fixing charges.(Cost of Fixtures to be paid separately) 30 mm thickness Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3554.73554.714.5FalseNoneNoneFalseNoneFalse51543.150
3996315154627None12.9Providing & fixing of 3-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having an overall size of 108mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm x 75mm with GI reinforcement of 2mm and mesh sash of size 37mm x 58mm. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24 mm. Windows shall be provided with 6mm plain float glass, standard hardware& Multi point locking system with touch lock. Wall thickness of frame & sash shall be of 2mm-2.5mm. Maximum possible size 2419mm x 2200mm. (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm6734.06734.030.0FalseNoneNoneFalseNoneFalse202020.00
3996316154627None12.9Providing & fixing of 3-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having an overall size of 108mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm x 75mm with GI reinforcement of 2mm and mesh sash of size 37mm x 58mm. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24 mm. Windows shall be provided with 6mm plain float glass, standard hardware& Multi point locking system with touch lock. Wall thickness of frame & sash shall be of 2mm-2.5mm. Maximum possible size 2419mm x 2200mm. (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm6801.346801.3432.0FalseNoneNoneFalseNoneFalse217642.880
3996317154627None12.9Providing & fixing of 3-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having an overall size of 108mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm x 75mm with GI reinforcement of 2mm and mesh sash of size 37mm x 58mm. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24 mm. Windows shall be provided with 6mm plain float glass, standard hardware& Multi point locking system with touch lock. Wall thickness of frame & sash shall be of 2mm-2.5mm. Maximum possible size 2419mm x 2200mm. (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm6868.686868.6837.0FalseNoneNoneFalseNoneFalse254141.160
3996318154627None12.9Providing & fixing of 3-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having an overall size of 108mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm x 75mm with GI reinforcement of 2mm and mesh sash of size 37mm x 58mm. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24 mm. Windows shall be provided with 6mm plain float glass, standard hardware& Multi point locking system with touch lock. Wall thickness of frame & sash shall be of 2mm-2.5mm. Maximum possible size 2419mm x 2200mm. (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm6936.026936.023.0FalseNoneNoneFalseNoneFalse20808.060
3996319154627None12.85Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5719.05719.024.0FalseNoneNoneFalseNoneFalse137256.00
3996320154627None12.85Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5776.195776.1919.0FalseNoneNoneFalseNoneFalse109747.610
3996321154627None12.85Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5833.385833.3820.0FalseNoneNoneFalseNoneFalse116667.60
3996322154627None12.85Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5890.575890.572.0FalseNoneNoneFalseNoneFalse11781.140
3996323154627None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs183.0183.0961.0FalseNoneNoneFalseNoneFalse175863.00
3996324154627None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs184.83184.83896.0FalseNoneNoneFalseNoneFalse165607.680
3996325154627None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs186.66186.661013.0FalseNoneNoneFalseNoneFalse189086.580
3996326154627None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs188.49188.4959.0FalseNoneNoneFalseNoneFalse11120.910
3996327154627None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2852.02852.0411.0FalseNoneNoneFalseNoneFalse1172172.00
3996328154627None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2880.522880.52364.0FalseNoneNoneFalseNoneFalse1048509.280
3996329154627None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2909.042909.04232.0FalseNoneNoneFalseNoneFalse674897.280
3996330154627None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2937.562937.568.0FalseNoneNoneFalseNoneFalse23500.480
3996331154627None9.11Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved make, in all colours, shades, except White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick bed of cement mortar 1:4 (1 Cement : 4 Coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including pointing the joints with white cement and matching pigments etc., complete. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm889.0889.072.0FalseNoneNoneFalseNoneFalse64008.00
3996332154627None9.11Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved make, in all colours, shades, except White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick bed of cement mortar 1:4 (1 Cement : 4 Coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including pointing the joints with white cement and matching pigments etc., complete. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm897.89897.8969.0FalseNoneNoneFalseNoneFalse61954.410
3996333154627None9.11Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved make, in all colours, shades, except White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick bed of cement mortar 1:4 (1 Cement : 4 Coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including pointing the joints with white cement and matching pigments etc., complete. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm906.78906.7831.0FalseNoneNoneFalseNoneFalse28110.180
3996334154627None9.39Providing skirting, dadooing, rises of steps with colour glazed tiles 6mm thick on 10mm thick cement plaster 1:3 and jointed with white cement slurry over existing rough plaster surface using glazed tiles of approved make and size including cost of materials, labour, complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1449.01449.0262.0FalseNoneNoneFalseNoneFalse379638.00
3996335154627None9.39Providing skirting, dadooing, rises of steps with colour glazed tiles 6mm thick on 10mm thick cement plaster 1:3 and jointed with white cement slurry over existing rough plaster surface using glazed tiles of approved make and size including cost of materials, labour, complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1463.491463.49240.0FalseNoneNoneFalseNoneFalse351237.60
3996336154627None9.39Providing skirting, dadooing, rises of steps with colour glazed tiles 6mm thick on 10mm thick cement plaster 1:3 and jointed with white cement slurry over existing rough plaster surface using glazed tiles of approved make and size including cost of materials, labour, complete as per specifications. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1477.981477.9892.0FalseNoneNoneFalseNoneFalse135974.160
3996337154627None10.2Providing edge moulding to 18mm thick Granite stone counters, vanities etc including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr328.0328.086.0FalseNoneNoneFalseNoneFalse28208.00
3996338154627None10.2Providing edge moulding to 18mm thick Granite stone counters, vanities etc including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr331.28331.2867.0FalseNoneNoneFalseNoneFalse22195.760
3996339154627None10.2Providing edge moulding to 18mm thick Granite stone counters, vanities etc including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineer-in-charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr334.56334.5634.0FalseNoneNoneFalseNoneFalse11375.040
3996340154627None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm295.0295.01105.0FalseNoneNoneFalseNoneFalse325975.00
3996341154627None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm297.95297.951048.0FalseNoneNoneFalseNoneFalse312251.60
3996342154627None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm300.9300.9626.0FalseNoneNoneFalseNoneFalse188363.40
3996343154627None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm303.85303.8574.0FalseNoneNoneFalseNoneFalse22484.90
3996344154627None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm371.0371.0510.0FalseNoneNoneFalseNoneFalse189210.00
3996345154627None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm374.71374.71516.0FalseNoneNoneFalseNoneFalse193350.360
3996346154627None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm378.42378.42497.0FalseNoneNoneFalseNoneFalse188074.740
3996347154627None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm382.13382.13311.0FalseNoneNoneFalseNoneFalse118842.430
3996348154627None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg64.064.077.0FalseNoneNoneFalseNoneFalse4928.00
3996349154627None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg64.6464.6478.0FalseNoneNoneFalseNoneFalse5041.920
3996350154627None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg65.2865.2874.55FalseNoneNoneFalseNoneFalse4866.6240
3996351154627None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg65.9265.9246.65FalseNoneNoneFalseNoneFalse3075.1680
3996352154627None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm295.0295.0279.0FalseNoneNoneFalseNoneFalse82305.00
3996353154627None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm297.95297.95255.0FalseNoneNoneFalseNoneFalse75977.250
3996354154627None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm300.9300.999.0FalseNoneNoneFalseNoneFalse29789.10
3996355154627None8.16 aProviding lath plaster with cement mortar 1:3, 5cms thick with 6mm dia mild steel bars at 20 cms. c to c both horizontally and vertically fixing chicken mesh for drop chajja, facia, backing to cup boards including cost of all materials, labour, providing and removing form work usage charges, curing complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1238.01238.03.0FalseNoneNoneFalseNoneFalse3714.00
3996356154627None8.16 aProviding lath plaster with cement mortar 1:3, 5cms thick with 6mm dia mild steel bars at 20 cms. c to c both horizontally and vertically fixing chicken mesh for drop chajja, facia, backing to cup boards including cost of all materials, labour, providing and removing form work usage charges, curing complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1250.381250.383.0FalseNoneNoneFalseNoneFalse3751.140
3996357154627None8.16 aProviding lath plaster with cement mortar 1:3, 5cms thick with 6mm dia mild steel bars at 20 cms. c to c both horizontally and vertically fixing chicken mesh for drop chajja, facia, backing to cup boards including cost of all materials, labour, providing and removing form work usage charges, curing complete as per specifications. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1262.761262.763.0FalseNoneNoneFalseNoneFalse3788.280
3996358154627None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm100.0100.01574.0067FalseNoneNoneFalseNoneFalse157400.670
3996359154627None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. First floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm101.0101.01468.5176FalseNoneNoneFalseNoneFalse148320.27760
3996360154627None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm102.0102.0895.6766FalseNoneNoneFalseNoneFalse91359.01320
3996361154627None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm103.0103.0123.8334FalseNoneNoneFalseNoneFalse12754.84020
3996362154627None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm110.0110.01425.5917FalseNoneNoneFalseNoneFalse156815.0870
3996363154627None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. First floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm111.1111.11319.5626FalseNoneNoneFalseNoneFalse146603.404860
3996364154627None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm112.2112.2748.3416FalseNoneNoneFalseNoneFalse83963.927520
3996365154627None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm113.3113.3123.8334FalseNoneNoneFalseNoneFalse14030.324220
3996366154627None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.053.01574.0067FalseNoneNoneFalseNoneFalse83422.35510
3996367154627None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.5353.531468.5176FalseNoneNoneFalseNoneFalse78609.7471280
3996368154627None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm54.0654.06895.6766FalseNoneNoneFalseNoneFalse48420.2769960
3996369154627None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm54.5954.59123.8334FalseNoneNoneFalseNoneFalse6760.0653060
3996370154627None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm174.0174.0510.0FalseNoneNoneFalseNoneFalse88740.00
3996371154627None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm175.74175.74516.0FalseNoneNoneFalseNoneFalse90681.840
3996372154627None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Second floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm177.48177.48497.0FalseNoneNoneFalseNoneFalse88207.560
3996373154627None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm179.22179.22311.0FalseNoneNoneFalseNoneFalse55737.420
3996374154627None8.34.1Applying priming coat: With ready mixed pink or Grey primer of approved brand and manufacture on wood work (hard and soft wood) including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.053.041.0FalseNoneNoneFalseNoneFalse2173.00
3996375154627None8.34.1Applying priming coat: With ready mixed pink or Grey primer of approved brand and manufacture on wood work (hard and soft wood) including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.5353.5325.0FalseNoneNoneFalseNoneFalse1338.250
3996376154627None8.34.1Applying priming coat: With ready mixed pink or Grey primer of approved brand and manufacture on wood work (hard and soft wood) including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm54.0654.0625.0FalseNoneNoneFalseNoneFalse1351.50
3996377154627None8.33.2Painting wood work with Deluxe Multi Surface Paint of required shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @0.75 L/10 m² of approved brand and manufacture to give an even shade including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, sand papering and knotting , cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm138.0138.041.0FalseNoneNoneFalseNoneFalse5658.00
3996378154627None8.33.2Painting wood work with Deluxe Multi Surface Paint of required shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @0.75 L/10 m² of approved brand and manufacture to give an even shade including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, sand papering and knotting , cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm139.38139.3825.0FalseNoneNoneFalseNoneFalse3484.50
3996379154627None8.33.2Painting wood work with Deluxe Multi Surface Paint of required shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @0.75 L/10 m² of approved brand and manufacture to give an even shade including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, sand papering and knotting , cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm140.76140.7625.0FalseNoneNoneFalseNoneFalse3519.00
3996380154627None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @ 0.80 L/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm139.0139.054.0FalseNoneNoneFalseNoneFalse7506.00
3996381154627None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @ 0.80 L/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm140.39140.3950.0FalseNoneNoneFalseNoneFalse7019.50
3996382154627None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @ 0.80 L/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm141.78141.7857.0FalseNoneNoneFalseNoneFalse8081.460
3996383154627None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @ 0.80 L/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm143.17143.174.0FalseNoneNoneFalseNoneFalse572.680
3996384154627None8.4Painting with synthetic enamel paint of approved brand and manufacture to give an even shade :Two coats on new work after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm115.0115.0148.415FalseNoneNoneFalseNoneFalse17067.7250
3996385154627None8.4Painting with synthetic enamel paint of approved brand and manufacture to give an even shade :Two coats on new work after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm116.15116.15148.955FalseNoneNoneFalseNoneFalse17301.123250
3996386154627None8.4Painting with synthetic enamel paint of approved brand and manufacture to give an even shade :Two coats on new work after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm117.3117.3147.335FalseNoneNoneFalseNoneFalse17282.39550
3996387154627None11.28Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners, stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in- charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.) including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs565.0565.0298.0FalseNoneNoneFalseNoneFalse168370.00
3996388154627None11.28Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners, stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in- charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.) including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs570.65570.65130.0FalseNoneNoneFalseNoneFalse74184.50
3996389154627None11.28Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners, stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in- charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.) including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. Second floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs576.3576.365.0FalseNoneNoneFalseNoneFalse37459.50
3996390154627None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr66.066.0201.0FalseNoneNoneFalseNoneFalse13266.00
3996391154627None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr66.6666.66201.0FalseNoneNoneFalseNoneFalse13398.660
3996392154627None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr67.3267.32237.0FalseNoneNoneFalseNoneFalse15954.840
3996393154627None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr67.9867.9841.0FalseNoneNoneFalseNoneFalse2787.180
3996394154627None7.18Providing and laying cinder concrete in cement 1:15 ( 1 cement : 15 cinder of 12.5mm nominal gauge) on terraced roof or sunken slabs, laid to slope compacting, including cost of materials, labour, curing complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum2037.172037.1716.0FalseNoneNoneFalseNoneFalse32594.720
3996395154627None7.18Providing and laying cinder concrete in cement 1:15 ( 1 cement : 15 cinder of 12.5mm nominal gauge) on terraced roof or sunken slabs, laid to slope compacting, including cost of materials, labour, curing complete as per specifications. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum2057.342057.3411.0FalseNoneNoneFalseNoneFalse22630.740
3996396154627None15.7Integral Crystalline Water Proofing Admixture Providing and supplying crystalline integral concrete waterproofing admixture that waterproofs concrete by forming crystals deep in the pores, capillaries and microcracks of the concrete, self-seal waterproofing compound to bridge shrinkage cracks upto 0.5mm in width & resist hydro-static pressure upto 16bar for both positive & negative pressure confirming to DIN 1048 part 5 for 56% reduction in depth of penetration against control, resistance to chloride penetration confirming to ASTM C 1202 with 64% improvement against control & protecting steel reinforcement against corrosion mixed @ 1% by weight of cementitious content in concrete. ie., integral crystaline waterproofing admix @ 0.5 kg/bag of cement. (For calculation purpose 320 kg of Cement for M-20 grade of Concrete is considered in the analysis) First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm621.15621.1566.0FalseNoneNoneFalseNoneFalse40995.90
3996397154627None15.7Integral Crystalline Water Proofing Admixture Providing and supplying crystalline integral concrete waterproofing admixture that waterproofs concrete by forming crystals deep in the pores, capillaries and microcracks of the concrete, self-seal waterproofing compound to bridge shrinkage cracks upto 0.5mm in width & resist hydro-static pressure upto 16bar for both positive & negative pressure confirming to DIN 1048 part 5 for 56% reduction in depth of penetration against control, resistance to chloride penetration confirming to ASTM C 1202 with 64% improvement against control & protecting steel reinforcement against corrosion mixed @ 1% by weight of cementitious content in concrete. ie., integral crystaline waterproofing admix @ 0.5 kg/bag of cement. (For calculation purpose 320 kg of Cement for M-20 grade of Concrete is considered in the analysis) Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm627.3627.335.0FalseNoneNoneFalseNoneFalse21955.50
3996398154627None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9613.59613.53.4015FalseNoneNoneFalseNoneFalse32700.320250
3996399154627None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9679.89679.84.2669FalseNoneNoneFalseNoneFalse41302.738620
3996400154627None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9746.19746.12.0155FalseNoneNoneFalseNoneFalse19643.264550
3996401154627None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9812.49812.434.5701FalseNoneNoneFalseNoneFalse339215.649240
3996402154627None9.25Providing and laying 60mm thick factory made cement concrete paver block of approved shape and colour of M -30 grade made of C&D waste by block making machine with vibratory compaction laid in required pattern and including over 50mm thick compacted bed of coarse sand, filling the joints with fine sand etc. all complete as per the direction of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm800.0800.025.0FalseNoneNoneFalseNoneFalse20000.00
3996403154627NoneVOL -5 7.1.1Providing and fixing MS ladder between landings, 45 cms wide using angle iron of specified sizes, 20mm MS bars at 25 cms. centre to centre, with necessary supports of same angle iron etc. as directed, including hand railing on both sides with 25mm dia. GI pipes with angle iron props at 2 mtrs. intervals and 0.5M heigh, including fixing in ground with CC 1:2:4 and two coats of anticorrosive bituminous paint etc. with all lead and lifts etc. complete with: MS angle of 65 x 65 x 8mm Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr4508.314508.314.5FalseNoneNoneFalseNoneFalse20287.3950
3996404154627None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.038.0241.2FalseNoneNoneFalseNoneFalse9165.60
3996405154627None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.3838.38165.6FalseNoneNoneFalseNoneFalse6355.7280
3996406154627None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.7638.76165.6FalseNoneNoneFalseNoneFalse6418.6560
3996407154627None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr39.1439.147.65FalseNoneNoneFalseNoneFalse299.4210
3996408154627None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.038.0243.69FalseNoneNoneFalseNoneFalse9260.220
3996409154627None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.3838.38232.09FalseNoneNoneFalseNoneFalse8907.61420
3996410154627None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.7638.76151.23FalseNoneNoneFalseNoneFalse5861.67480
3996411154627None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr39.1439.1415.11FalseNoneNoneFalseNoneFalse591.40540
3996412154627None22.15.7Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Tower Bolts 250x10mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos200.0200.029.0FalseNoneNoneFalseNoneFalse5800.00
3996413154627None22.15.7Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Tower Bolts 250x10mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos202.0202.025.0FalseNoneNoneFalseNoneFalse5050.00
3996414154627None22.15.7Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Tower Bolts 250x10mm Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos204.0204.013.0FalseNoneNoneFalseNoneFalse2652.00
3996415154627None22.15.8Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS hinges 125 mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos50.050.095.0FalseNoneNoneFalseNoneFalse4750.00
3996416154627None22.15.8Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS hinges 125 mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos50.550.580.0FalseNoneNoneFalseNoneFalse4040.00
3996417154627None22.15.8Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS hinges 125 mm Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos51.051.043.0FalseNoneNoneFalseNoneFalse2193.00
3996418154627None22.15.1Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Handles 200mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos450.0450.058.0FalseNoneNoneFalseNoneFalse26100.00
3996419154627None22.15.1Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Handles 200mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos454.5454.550.0FalseNoneNoneFalseNoneFalse22725.00
3996420154627None22.15.1Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Handles 200mm Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos459.0459.026.0FalseNoneNoneFalseNoneFalse11934.00
3996421154627None22.15.4Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Aldrop 16mm dia, 300mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos375.0375.028.0FalseNoneNoneFalseNoneFalse10500.00
3996422154627None22.15.4Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Aldrop 16mm dia, 300mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos378.75378.7525.0FalseNoneNoneFalseNoneFalse9468.750
3996423154627None22.15.4Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Aldrop 16mm dia, 300mm Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos382.5382.513.0FalseNoneNoneFalseNoneFalse4972.50
3996424154627None22.15.10Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Door stopper 75mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos100.0100.08.0FalseNoneNoneFalseNoneFalse800.00
3996425154627None22.15.10Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Door stopper 75mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos101.0101.05.0FalseNoneNoneFalseNoneFalse505.00
3996426154627None22.15.10Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Door stopper 75mm Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos102.0102.04.0FalseNoneNoneFalseNoneFalse408.00
3996427154627None15.1Providing and laying water proofing treatment to the Roof with PU based single component elastomeric pure polyurethane based coating on New rrace/Chajjas/Sunken portion of WC:Bathroom, cold applied PU waterproofing membrane that is highly elastic with elongation greater than 400% and tensile strength greater than 2MPa as per ASTM D412. The waterproofing membrane to be applied in 2coats @ 1.6kg per m2 to achieve final DFT (dry film thickness) of 1mm including prime coat of epoxy primer @150 g per m2 and protection with 120gsm Geo-textile over the waterproofing membrane. The finished cost to include surface preparation, making coving at Junction, Bore Packing, treatment of construction joints completely as per specification & with a 10 years warranty on product & work from certified manufacturers as per the direction of the Engineer In charge. Second Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm841.51841.51338.0FalseNoneNoneFalseNoneFalse284430.380
3996428154627None20.107Providing and fixing plain rolled glass 4mm thick with teakwood beading of 10mm thick. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1147.01147.02.43FalseNoneNoneFalseNoneFalse2787.210
3996429154627None20.107Providing and fixing plain rolled glass 4mm thick with teakwood beading of 10mm thick. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1158.471158.471.71FalseNoneNoneFalseNoneFalse1980.98370
17262057300000NoneNoneBuildingsKitchen & Dining (Shivani)10040980.72
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3996430154628None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.01290.109FalseNoneNoneFalseNoneFalse131591.1180
3996431154628None1.15.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In ordinary/soft rock without blasting upto 1.5 m depth ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum363.0363.0204.4698FalseNoneNoneFalseNoneFalse74222.53740
3996432154628None1.16.1Earth work excavation for Foundation by Mechanical means depth upto 1.50m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including cost of explosives, dressing of excavated surfaces, disposing off or levelling the excavated stuff or sorting & stacking the selected stuff for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, blasting materials, tools, usage of Machinery & all other appurtenaces required to complete the work. In Hard Rock ( requiring blasting) Depth upto 1.50m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum554.0554.017.0391FalseNoneNoneFalseNoneFalse9439.66140
3996433154628None1.9Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum266.0266.0458.7476FalseNoneNoneFalseNoneFalse122026.86160
3996434154628None4.1Providing and injecting chemical emulsion for Pre-constructional Anti-Termite Treatment, creating continuous chemical barrier under and around the column pits, walls, trenches, basement excavation, top surface of the plinth filling, junction of wall and floor, along the external perimeter of building, expansion joints, over the top surface of consolidated earth on which apron is to be laid, surrounding of pipes and conduits with Chlorpyriphos 20% E.C. / Lindane 20% E.C. @ 3.19 l/m2 including cost of chemical, diluting in water to one percent concentration, labour, usage charges of machinery, complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm118.0118.0446.0FalseNoneNoneFalseNoneFalse52628.00
3996435154628None2.1.3Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5989.05989.074.0FalseNoneNoneFalseNoneFalse443186.00
3996436154628None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6217.06217.04.5FalseNoneNoneFalseNoneFalse27976.50
3996437154628None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7460.47460.41.0FalseNoneNoneFalseNoneFalse7460.40
3996438154628None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7522.577522.572.1FalseNoneNoneFalseNoneFalse15797.3970
3996439154628None2.1.6Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:2:4 Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6243.06243.04.0FalseNoneNoneFalseNoneFalse24972.00
3996440154628None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Footing concrete ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6842.886842.8889.1533FalseNoneNoneFalseNoneFalse610065.3335040
3996441154628None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Pedastals ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10771.210771.27.198FalseNoneNoneFalseNoneFalse77531.09760
3996442154628None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Columns Concrete Upto PB ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10771.210771.23.0482FalseNoneNoneFalseNoneFalse32832.771840
3996443154628None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Plinth Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9504.09504.09.712FalseNoneNoneFalseNoneFalse92302.8480
3996444154628None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Grade Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9504.09504.022.808FalseNoneNoneFalseNoneFalse216767.2320
3996445154628None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Columns Concrete Up to Roof ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11633.111633.115.8675FalseNoneNoneFalseNoneFalse184588.214250
3996446154628None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10948.810948.824.961FalseNoneNoneFalseNoneFalse273292.99680
3996447154628None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10264.510264.566.7308FalseNoneNoneFalseNoneFalse684958.29660
3996448154628None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Lintel Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10948.810948.84.1886FalseNoneNoneFalseNoneFalse45860.143680
3996449154628None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Staircase ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10264.510264.52.495FalseNoneNoneFalseNoneFalse25609.92750
3996450154628None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor For Columns ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11749.4311749.430.978FalseNoneNoneFalseNoneFalse11490.942540
3996451154628None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11058.2811058.281.5649FalseNoneNoneFalseNoneFalse17305.1023720
3996452154628None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10367.1410367.142.0928FalseNoneNoneFalseNoneFalse21696.3505920
3996453154628None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10674.5810674.584.0FalseNoneNoneFalseNoneFalse42698.320
3996454154628None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t89457.089457.021.0228FalseNoneNoneFalseNoneFalse1880636.61960
3996455154628None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t90351.5790351.570.987FalseNoneNoneFalseNoneFalse89176.999590
3996456154628None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1310.01310.0406.0FalseNoneNoneFalseNoneFalse531860.00
3996457154628None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1323.11323.1142.0FalseNoneNoneFalseNoneFalse187880.20
3996458154628None6.34Providing and constructing load bearing wall with Solid Concrete blocks of size 400x100x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1104.01104.027.0FalseNoneNoneFalseNoneFalse29808.00
3996459154628None12.13.1Providing Salwood frames of doors, windows, clerestory windows, ventilators and other frames, wrought, framed or assembled including making plaster groves (excluding cost of cement concrete and side clamps), but including cost of materials, labour, usage charges complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum98815.098815.00.5FalseNoneNoneFalseNoneFalse49407.50
3996460154628None12.17Providing and fixing in position fully panelled Honne wood shutters for doors with , stiles and rails of 35mm. thick with bottom and lock rails 180mm wide top rail and stiles 100mm wide as per drawing and panels of 25mm thick including cost of materials, labour, usage charges complete as per specifications. (excluding cost of fixtures) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm7085.07085.03.8FalseNoneNoneFalseNoneFalse26923.00
3996461154628None12.57.3Providing and fixing flush door shutter made out of solid core block board type, well seasoned , chemicaly treated hard wood battens and internal frame with minimum 45 mm wide wooden frame alround door shutters covered with cross bonded wooden sheets (core veneer) hot pressed and fastened on both sides of the door useing liquid phenol formaldehyde resin as per IS specifications 2202 (part-I) 1991. from manufacturer complete as per spcification.-do- 30 mm thick both side commercial Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3005.03005.011.4FalseNoneNoneFalseNoneFalse34257.00
3996462154628None12.51Fixing of door frame in an existing opening including embedding frame in floor and walls after cutting masonry for holdfasts for embedding holdfast in cement concrete 1:3:6 of 20mm and down size granite metal painting two coats of coal tar to sides of frame, making good the damages to walls and floor as required and disposal of the debris with lead upto 50 m. including cost of materials, labour charges, complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1016.01016.07.0FalseNoneNoneFalseNoneFalse7112.00
3996463154628None12.93.1Providing and fixing factory made single extruded WPC (Wood Polymer Composite) solid door/window/Clerestory windows & other Frames/ Chowkhat comprising of virgin PVC polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibres (wood powder/rice husk/ wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) fabricated with miter joints after applying PVC solvent cement and screwed with full body threaded star headed SS screws having minimum frame density of 850 kg/m3, screw withdrawal strength of 2200 N (Face) & 1100 N (Edge), minimum compressive strength of 58 N/mm2 , modulus of elasticity 900 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixed in position with M.S hold fast/lugs/SS dash fasteners of required dia and length complete as per direction of Engineer-InCharge. (Fixtures shall be paid for separately) Size 62 x 100mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr702.0702.010.7FalseNoneNoneFalseNoneFalse7511.40
3996464154628None12.94.1Providing and fixing factory made Green certified, Anti Termite, UV resistant, high water absorbant single extruded WPC (Wood PolymerComposite) solid plain flush door shutter of required size comprising of virgin polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibers (wood powder/rice husk/wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) having minimum density of 650 kg/m3 and screw withdrawal strength of 1800 N (Face) & 900 N (Edge), minimum compressive strength of 50 N/mm2 , modulus of elasticity 850 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixing with stainless steel butt hinges of required size with necessary full body threaded star headed counter sunk S.S screws The cost includes cost of materials, transportation, labour and fixing charges.(Cost of Fixtures to be paid separately) 30 mm thickness ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3485.03485.03.5FalseNoneNoneFalseNoneFalse12197.50
3996465154628None12.88Providing & fixing of 2-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having a overall size of 60mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm X 58mm with GI reinforcement of 1mm for the frame and 1.5 mm for the sash. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24mm. Windows shall be provided with 5mm plain float glass, standard hardware& single point locking system with touch lock. Wall thickness of frame & sash shall be of 2-2.5 mm. Maximum possible size 1819mm x 1819mm (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5390.05390.040.0FalseNoneNoneFalseNoneFalse215600.00
3996466154628None12.85Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5719.05719.023.0FalseNoneNoneFalseNoneFalse131537.00
3996467154628None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs183.0183.01096.0FalseNoneNoneFalseNoneFalse200568.00
3996468154628None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2852.02852.0427.0FalseNoneNoneFalseNoneFalse1217804.00
3996469154628None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2880.522880.523.0FalseNoneNoneFalseNoneFalse8641.560
3996470154628None9.11Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved make, in all colours, shades, except White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick bed of cement mortar 1:4 (1 Cement : 4 Coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including pointing the joints with white cement and matching pigments etc., complete. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm889.0889.035.0FalseNoneNoneFalseNoneFalse31115.00
3996471154628None9.39Providing skirting, dadooing, rises of steps with colour glazed tiles 6mm thick on 10mm thick cement plaster 1:3 and jointed with white cement slurry over existing rough plaster surface using glazed tiles of approved make and size including cost of materials, labour, complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1449.01449.067.0FalseNoneNoneFalseNoneFalse97083.00
3996472154628None10.18Providing and fixing of wall cladding using 20mm thick gang saw water cut Shiva gold granite, grey granite in CM 1:3 (1 cement : 3 coarse sand) proportion cut to required shape, pattern with paper joints, finished with cement mortal using white cement and colour pigments to match the colour of slab making through jointing with sealant, making holes 25mmx12mm grooves in joints including cost of all materials, mortar, labour, curing etc., complete. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3359.03359.084.8255FalseNoneNoneFalseNoneFalse284928.85450
3996473154628None10.2Providing edge moulding to 18mm thick Granite stone counters, vanities etc including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr328.0328.080.0FalseNoneNoneFalseNoneFalse26240.00
3996474154628None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm295.0295.0582.1745FalseNoneNoneFalseNoneFalse171741.47750
3996475154628None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm297.95297.9545.0FalseNoneNoneFalseNoneFalse13407.750
3996476154628None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm371.0371.0320.0FalseNoneNoneFalseNoneFalse118720.00
3996477154628None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm374.71374.71282.92FalseNoneNoneFalseNoneFalse106012.95320
3996478154628None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg64.064.048.0FalseNoneNoneFalseNoneFalse3072.00
3996479154628None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg64.6464.6443.0FalseNoneNoneFalseNoneFalse2779.520
3996480154628None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm295.0295.0161.0FalseNoneNoneFalseNoneFalse47495.00
3996481154628None8.16 aProviding lath plaster with cement mortar 1:3, 5cms thick with 6mm dia mild steel bars at 20 cms. c to c both horizontally and vertically fixing chicken mesh for drop chajja, facia, backing to cup boards including cost of all materials, labour, providing and removing form work usage charges, curing complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1238.01238.015.0FalseNoneNoneFalseNoneFalse18570.00
3996482154628None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm100.0100.01127.4867FalseNoneNoneFalseNoneFalse112748.670
3996483154628None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm101.0101.058.952FalseNoneNoneFalseNoneFalse5954.1520
3996484154628None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm110.0110.01127.4867FalseNoneNoneFalseNoneFalse124023.5370
3996485154628None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm111.1111.158.952FalseNoneNoneFalseNoneFalse6549.56720
3996486154628None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.053.01127.4867FalseNoneNoneFalseNoneFalse59756.79510
3996487154628None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.5353.5358.952FalseNoneNoneFalseNoneFalse3155.700560
3996488154628None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm174.0174.0320.0FalseNoneNoneFalseNoneFalse55680.00
3996489154628None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm175.74175.74283.0FalseNoneNoneFalseNoneFalse49734.420
3996490154628None8.34.1Applying priming coat: With ready mixed pink or Grey primer of approved brand and manufacture on wood work (hard and soft wood) including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.053.037.0FalseNoneNoneFalseNoneFalse1961.00
3996491154628None8.33.2Painting wood work with Deluxe Multi Surface Paint of required shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @0.75 L/10 m² of approved brand and manufacture to give an even shade including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, sand papering and knotting , cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm138.0138.037.0FalseNoneNoneFalseNoneFalse5106.00
3996492154628None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @ 0.80 L/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm139.0139.069.0FalseNoneNoneFalseNoneFalse9591.00
3996493154628None11.28Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners, stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in- charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.) including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs565.0565.0216.0FalseNoneNoneFalseNoneFalse122040.00
3996494154628None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr66.066.0180.0FalseNoneNoneFalseNoneFalse11880.00
3996495154628None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr66.6666.6647.0FalseNoneNoneFalseNoneFalse3133.020
3996496154628None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9613.59613.51.8943FalseNoneNoneFalseNoneFalse18210.853050
3996497154628None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9679.89679.832.8658FalseNoneNoneFalseNoneFalse318134.370840
3996498154628None9.25Providing and laying heavy duty cobble stones 60mm thick interlock pavers, using cement and course sand for manufacture of blocks of approved size, shape and colour with a minimum compressive strength of 281 kg per m2 over 50mm thick sand bed ( average thickness ) and compacting with plate vibrator having 3 tons compaction force thereby forcing part of sand underneath to come up in between joints, final compaction of paver surface joints into its final level , including cost of materials, labour and Usage charges of machinery complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm800.0800.042.0FalseNoneNoneFalseNoneFalse33600.00
3996499154628None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.038.0133.2FalseNoneNoneFalseNoneFalse5061.60
3996500154628None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.038.0181.33FalseNoneNoneFalseNoneFalse6890.540
3996501154628None22.15.7Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Tower Bolts 250x10mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos200.0200.010.0FalseNoneNoneFalseNoneFalse2000.00
3996502154628None22.15.8Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS hinges 125 mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos50.050.038.0FalseNoneNoneFalseNoneFalse1900.00
3996503154628None22.15.1Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Handles 200mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos450.0450.020.0FalseNoneNoneFalseNoneFalse9000.00
3996504154628None22.15.4Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Aldrop 16mm dia, 300mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos375.0375.09.0FalseNoneNoneFalseNoneFalse3375.00
3996505154628None22.15.10Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Door stopper 75mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos100.0100.08.0FalseNoneNoneFalseNoneFalse800.00
3996506154628None15.1Providing and laying water proofing treatment to the Roof with PU based single component elastomeric pure polyurethane based coating on New rrace/Chajjas/Sunken portion of WC:Bathroom, cold applied PU waterproofing membrane that is highly elastic with elongation greater than 400% and tensile strength greater than 2MPa as per ASTM D412. The waterproofing membrane to be applied in 2coats @ 1.6kg per m2 to achieve final DFT (dry film thickness) of 1mm including prime coat of epoxy primer @150 g per m2 and protection with 120gsm Geo-textile over the waterproofing membrane. The finished cost to include surface preparation, making coving at Junction, Bore Packing, treatment of construction joints completely as per specification & with a 10 years warranty on product & work from certified manufacturers as per the direction of the Engineer In charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm825.17825.17327.0FalseNoneNoneFalseNoneFalse269830.590
3996507154628None20.107Providing and fixing plain rolled glass 4mm thick with teakwood beading of 10mm thick. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1147.01147.02.16FalseNoneNoneFalseNoneFalse2477.520
17262057300001NoneNoneBuildingsStaff Quarters (Shivani)17409495.72
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3996508154629None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.01922.5195FalseNoneNoneFalseNoneFalse196096.9890
3996509154629None1.15.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In ordinary/soft rock without blasting upto 1.5 m depth ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum363.0363.0301.062FalseNoneNoneFalseNoneFalse109285.5060
3996510154629None1.16.1Earth work excavation for FOUNDATION by Mechanical means depth upto 1.50m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including cost of explosives, dressing of excavated surfaces, disposing off or levelling the excavated stuff or sorting & stacking the selected stuff for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, blasting materials, tools, usage of Machinery & all other appurtenaces required to complete the work. In Hard Rock ( requiring blasting) Depth upto 1.50m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum554.0554.025.0885FalseNoneNoneFalseNoneFalse13899.0290
3996511154629None1.9Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum266.0266.0562.4664FalseNoneNoneFalseNoneFalse149616.06240
3996512154629None4.1Providing and injecting chemical emulsion for Pre-constructional Anti-Termite Treatment, creating continuous chemical barrier under and around the column pits, walls, trenches, basement excavation, top surface of the plinth filling, junction of wall and floor, along the external perimeter of building, expansion joints, over the top surface of consolidated earth on which apron is to be laid, surrounding of pipes and conduits with Chlorpyriphos 20% E.C. / Lindane 20% E.C. @ 3.19 l/m2 including cost of chemical, diluting in water to one percent concentration, labour, usage charges of machinery, complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm118.0118.0418.0FalseNoneNoneFalseNoneFalse49324.00
3996513154629None2.1.3Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5989.05989.081.0FalseNoneNoneFalseNoneFalse485109.00
3996514154629None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6217.06217.05.0FalseNoneNoneFalseNoneFalse31085.00
3996515154629None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7460.47460.40.9101FalseNoneNoneFalseNoneFalse6789.710040
3996516154629None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7522.577522.570.9101FalseNoneNoneFalseNoneFalse6846.2909570
3996517154629None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7584.747584.742.8FalseNoneNoneFalseNoneFalse21237.2720
3996518154629None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor Footing concrete ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6842.886842.88126.8392FalseNoneNoneFalseNoneFalse867945.4248960
3996519154629None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Pedastals ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10771.210771.29.0429FalseNoneNoneFalseNoneFalse97402.884480
3996520154629None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Columns Concrete Upto PB ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10771.210771.23.7674FalseNoneNoneFalseNoneFalse40579.418880
3996521154629None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Plinth Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9504.09504.011.8093FalseNoneNoneFalseNoneFalse112235.58720
3996522154629None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Grade Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9504.09504.033.9921FalseNoneNoneFalseNoneFalse323060.91840
3996523154629None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Columns Concrete Up to Roof ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11633.111633.116.9533FalseNoneNoneFalseNoneFalse197219.434230
3996524154629None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10948.810948.827.4896FalseNoneNoneFalseNoneFalse300978.132480
3996525154629None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10264.510264.568.0002FalseNoneNoneFalseNoneFalse697988.05290
3996526154629None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Lintel Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10948.810948.87.719FalseNoneNoneFalseNoneFalse84513.78720
3996527154629None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Staircase ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10264.510264.54.0431FalseNoneNoneFalseNoneFalse41500.399950
3996528154629None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor For Columns Concrete Up to Roof ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11749.4311749.4316.9533FalseNoneNoneFalseNoneFalse199191.6116190
3996529154629None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11058.2811058.2827.4896FalseNoneNoneFalseNoneFalse303987.6938880
3996530154629None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10367.1410367.1468.0002FalseNoneNoneFalseNoneFalse704967.5934280
3996531154629None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor For Lintel Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11058.2811058.287.719FalseNoneNoneFalseNoneFalse85358.863320
3996532154629None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor For Staircase ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10367.1410367.144.0431FalseNoneNoneFalseNoneFalse41915.3837340
3996533154629None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor For Columns ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11865.7611865.761.3041FalseNoneNoneFalseNoneFalse15474.1376160
3996534154629None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11167.7711167.771.3248FalseNoneNoneFalseNoneFalse14795.0616960
3996535154629None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10469.7910469.793.0195FalseNoneNoneFalseNoneFalse31613.5309050
3996536154629None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10780.2710780.274.6368FalseNoneNoneFalseNoneFalse49985.9559360
3996537154629None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t89457.089457.024.0046FalseNoneNoneFalseNoneFalse2147379.50220
3996538154629None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t90351.5790351.5711.1348FalseNoneNoneFalseNoneFalse1006046.6616360
3996539154629None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t91246.1491246.141.0681FalseNoneNoneFalseNoneFalse97460.0021340
3996540154629None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1310.01310.0661.0FalseNoneNoneFalseNoneFalse865910.00
3996541154629None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1323.11323.1784.0FalseNoneNoneFalseNoneFalse1037310.40
3996542154629None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1336.21336.2169.0FalseNoneNoneFalseNoneFalse225817.80
3996543154629None6.34Providing and constructing load bearing wall with Solid Concrete blocks of size 400x100x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1104.01104.04.0FalseNoneNoneFalseNoneFalse4416.00
3996544154629None6.34Providing and constructing load bearing wall with Solid Concrete blocks of size 400x100x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1115.041115.042.0FalseNoneNoneFalseNoneFalse2230.080
3996545154629None12.13.1Providing Salwood frames of doors, windows, clerestory windows, ventilators and other frames, wrought, framed or assembled including making plaster groves (excluding cost of cement concrete and side clamps), but including cost of materials, labour, usage charges complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum98815.098815.00.9FalseNoneNoneFalseNoneFalse88933.50
3996546154629None12.13.1Providing Salwood frames of doors, windows, clerestory windows, ventilators and other frames, wrought, framed or assembled including making plaster groves (excluding cost of cement concrete and side clamps), but including cost of materials, labour, usage charges complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum99803.1599803.151.0FalseNoneNoneFalseNoneFalse99803.150
3996547154629None12.57.3Providing and fixing flush door shutter made out of solid core block board type, well seasoned , chemicaly treated hard wood battens and internal frame with minimum 45 mm wide wooden frame alround door shutters covered with cross bonded wooden sheets (core veneer) hot pressed and fastened on both sides of the door useing liquid phenol formaldehyde resin as per IS specifications 2202 (part-I) 1991. from manufacturer complete as per spcification.-do- 30 mm thick both side commercial Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3005.03005.034.1FalseNoneNoneFalseNoneFalse102470.50
3996548154629None12.57.3Providing and fixing flush door shutter made out of solid core block board type, well seasoned , chemicaly treated hard wood battens and internal frame with minimum 45 mm wide wooden frame alround door shutters covered with cross bonded wooden sheets (core veneer) hot pressed and fastened on both sides of the door useing liquid phenol formaldehyde resin as per IS specifications 2202 (part-I) 1991. from manufacturer complete as per spcification.-do- 30 mm thick both side commercial First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3035.053035.0534.1FalseNoneNoneFalseNoneFalse103495.2050
3996549154629None12.51Fixing of door frame in an existing opening including embedding frame in floor and walls after cutting masonry for holdfasts for embedding holdfast in cement concrete 1:3:6 of 20mm and down size granite metal painting two coats of coal tar to sides of frame, making good the damages to walls and floor as required and disposal of the debris with lead upto 50 m. including cost of materials, labour charges, complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1016.01016.016.0FalseNoneNoneFalseNoneFalse16256.00
3996550154629None12.51Fixing of door frame in an existing opening including embedding frame in floor and walls after cutting masonry for holdfasts for embedding holdfast in cement concrete 1:3:6 of 20mm and down size granite metal painting two coats of coal tar to sides of frame, making good the damages to walls and floor as required and disposal of the debris with lead upto 50 m. including cost of materials, labour charges, complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1026.161026.1616.0FalseNoneNoneFalseNoneFalse16418.560
3996551154629None12.93.1Providing and fixing factory made single extruded WPC (Wood Polymer Composite) solid door/window/Clerestory windows & other Frames/ Chowkhat comprising of virgin PVC polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibres (wood powder/rice husk/ wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) fabricated with miter joints after applying PVC solvent cement and screwed with full body threaded star headed SS screws having minimum frame density of 850 kg/m3, screw withdrawal strength of 2200 N (Face) & 1100 N (Edge), minimum compressive strength of 58 N/mm2 , modulus of elasticity 900 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixed in position with M.S hold fast/lugs/SS dash fasteners of required dia and length complete as per direction of Engineer-InCharge. (Fixtures shall be paid for separately) Size 62 x 100mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr702.0702.042.0FalseNoneNoneFalseNoneFalse29484.00
3996552154629None12.93.1Providing and fixing factory made single extruded WPC (Wood Polymer Composite) solid door/window/Clerestory windows & other Frames/ Chowkhat comprising of virgin PVC polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibres (wood powder/rice husk/ wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) fabricated with miter joints after applying PVC solvent cement and screwed with full body threaded star headed SS screws having minimum frame density of 850 kg/m3, screw withdrawal strength of 2200 N (Face) & 1100 N (Edge), minimum compressive strength of 58 N/mm2 , modulus of elasticity 900 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixed in position with M.S hold fast/lugs/SS dash fasteners of required dia and length complete as per direction of Engineer-InCharge. (Fixtures shall be paid for separately) Size 62 x 100mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr709.02709.0247.4FalseNoneNoneFalseNoneFalse33607.5480
3996553154629None12.94.1Providing and fixing factory made Green certified, Anti Termite, UV resistant, high water absorbant single extruded WPC (Wood PolymerComposite) solid plain flush door shutter of required size comprising of virgin polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibers (wood powder/rice husk/wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) having minimum density of 650 kg/m3 and screw withdrawal strength of 1800 N (Face) & 900 N (Edge), minimum compressive strength of 50 N/mm2 , modulus of elasticity 850 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixing with stainless steel butt hinges of required size with necessary full body threaded star headed counter sunk S.S screws The cost includes cost of materials, transportation, labour and fixing charges.(Cost of Fixtures to be paid separately) 30 mm thickness Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3485.03485.012.6FalseNoneNoneFalseNoneFalse43911.00
3996554154629None12.94.1Providing and fixing factory made Green certified, Anti Termite, UV resistant, high water absorbant single extruded WPC (Wood PolymerComposite) solid plain flush door shutter of required size comprising of virgin polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibers (wood powder/rice husk/wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) having minimum density of 650 kg/m3 and screw withdrawal strength of 1800 N (Face) & 900 N (Edge), minimum compressive strength of 50 N/mm2 , modulus of elasticity 850 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixing with stainless steel butt hinges of required size with necessary full body threaded star headed counter sunk S.S screws The cost includes cost of materials, transportation, labour and fixing charges.(Cost of Fixtures to be paid separately) 30 mm thickness First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3519.853519.8514.5FalseNoneNoneFalseNoneFalse51037.8250
3996555154629None12.9Providing & fixing of 3-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having an overall size of 108mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm x 75mm with GI reinforcement of 2mm and mesh sash of size 37mm x 58mm. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24 mm. Windows shall be provided with 6mm plain float glass, standard hardware& Multi point locking system with touch lock. Wall thickness of frame & sash shall be of 2mm-2.5mm. Maximum possible size 2419mm x 2200mm. (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm6734.06734.039.0FalseNoneNoneFalseNoneFalse262626.00
3996556154629None12.9Providing & fixing of 3-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having an overall size of 108mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm x 75mm with GI reinforcement of 2mm and mesh sash of size 37mm x 58mm. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24 mm. Windows shall be provided with 6mm plain float glass, standard hardware& Multi point locking system with touch lock. Wall thickness of frame & sash shall be of 2mm-2.5mm. Maximum possible size 2419mm x 2200mm. (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm6801.346801.3439.0FalseNoneNoneFalseNoneFalse265252.260
3996557154629None12.9Providing & fixing of 3-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having an overall size of 108mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm x 75mm with GI reinforcement of 2mm and mesh sash of size 37mm x 58mm. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24 mm. Windows shall be provided with 6mm plain float glass, standard hardware& Multi point locking system with touch lock. Wall thickness of frame & sash shall be of 2mm-2.5mm. Maximum possible size 2419mm x 2200mm. (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm6868.686868.683.0FalseNoneNoneFalseNoneFalse20606.040
3996558154629None12.85Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5719.05719.03.0FalseNoneNoneFalseNoneFalse17157.00
3996559154629None12.85Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5776.195776.193.0FalseNoneNoneFalseNoneFalse17328.570
3996560154629None12.85Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5833.385833.381.0FalseNoneNoneFalseNoneFalse5833.380
3996561154629None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs183.0183.0659.0FalseNoneNoneFalseNoneFalse120597.00
3996562154629None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs184.83184.83659.0FalseNoneNoneFalseNoneFalse121802.970
3996563154629None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs186.66186.6642.0FalseNoneNoneFalseNoneFalse7839.720
3996564154629None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2852.02852.080.0FalseNoneNoneFalseNoneFalse228160.00
3996565154629None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2880.522880.5277.0FalseNoneNoneFalseNoneFalse221800.040
3996566154629None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2909.042909.045.0FalseNoneNoneFalseNoneFalse14545.20
3996567154629None9.17.2Providing and laying Vitrified tiles in different sizes (thickness to be specified by manufacturer), with water absorption less than 0.08 % and conforming to I.S. 15622, of approved make, in all colours & shade, over 12 mm thick bed of cement mortar 1:3 (1 cement: 3 coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including grouting the joint with white cement & matching pigments etc. complete. Size of Tile 600x600 mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1175.01175.0308.0FalseNoneNoneFalseNoneFalse361900.00
3996568154629None9.17.2Providing and laying Vitrified tiles in different sizes (thickness to be specified by manufacturer), with water absorption less than 0.08 % and conforming to I.S. 15622, of approved make, in all colours & shade, over 12 mm thick bed of cement mortar 1:3 (1 cement: 3 coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including grouting the joint with white cement & matching pigments etc. complete. Size of Tile 600x600 mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1186.751186.75308.0FalseNoneNoneFalseNoneFalse365519.00
3996569154629None10.1.2Providing and fixing 18 mm thick gang saw cut granite of any color and shade, mirror polished, premoulded and prepolished, machine cut for kitchen platforms, vanity counters, window sills, facias and similar locations of required size, approved shade, colour and texture laid over 20 mm thick base cement mortar 1:4 (1 cement : 4 coarse sand), joints treated with white cement, mixed with matching pigment, epoxy touch up, including rubbing, curing, moulding and polishing to edges to give high gloss finish etc. complete at all levels. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3937.03937.013.0FalseNoneNoneFalseNoneFalse51181.00
3996570154629None10.1.2Providing and fixing 18 mm thick gang saw cut granite of any color and shade, mirror polished, premoulded and prepolished, machine cut for kitchen platforms, vanity counters, window sills, facias and similar locations of required size, approved shade, colour and texture laid over 20 mm thick base cement mortar 1:4 (1 cement : 4 coarse sand), joints treated with white cement, mixed with matching pigment, epoxy touch up, including rubbing, curing, moulding and polishing to edges to give high gloss finish etc. complete at all levels. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3976.373976.3713.0FalseNoneNoneFalseNoneFalse51692.810
3996571154629None9.11Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved make, in all colours, shades, except White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick bed of cement mortar 1:4 (1 Cement : 4 Coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including pointing the joints with white cement and matching pigments etc., complete. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm889.0889.044.0FalseNoneNoneFalseNoneFalse39116.00
3996572154629None9.11Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved make, in all colours, shades, except White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick bed of cement mortar 1:4 (1 Cement : 4 Coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including pointing the joints with white cement and matching pigments etc., complete. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm897.89897.8944.0FalseNoneNoneFalseNoneFalse39507.160
3996573154629None9.39Providing skirting, dadooing, rises of steps with colour glazed tiles 6mm thick on 10mm thick cement plaster 1:3 and jointed with white cement slurry over existing rough plaster surface using glazed tiles of approved make and size including cost of materials, labour, complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1449.01449.0173.0FalseNoneNoneFalseNoneFalse250677.00
3996574154629None9.39Providing skirting, dadooing, rises of steps with colour glazed tiles 6mm thick on 10mm thick cement plaster 1:3 and jointed with white cement slurry over existing rough plaster surface using glazed tiles of approved make and size including cost of materials, labour, complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1463.491463.49172.0FalseNoneNoneFalseNoneFalse251720.280
3996575154629None10.2Providing edge moulding to 18mm thick Granite stone counters, vanities etc including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr328.0328.064.0FalseNoneNoneFalseNoneFalse20992.00
3996576154629None10.2Providing edge moulding to 18mm thick Granite stone counters, vanities etc including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr331.28331.2857.0FalseNoneNoneFalseNoneFalse18882.960
3996577154629None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm295.0295.01030.0FalseNoneNoneFalseNoneFalse303850.00
3996578154629None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm297.95297.951062.0FalseNoneNoneFalseNoneFalse316422.90
3996579154629None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm300.9300.974.0FalseNoneNoneFalseNoneFalse22266.60
3996580154629None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm371.0371.0491.0FalseNoneNoneFalseNoneFalse182161.00
3996581154629None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm374.71374.71489.0FalseNoneNoneFalseNoneFalse183233.190
3996582154629None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm378.42378.42358.0FalseNoneNoneFalseNoneFalse135474.360
3996583154629None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg64.064.074.0FalseNoneNoneFalseNoneFalse4736.00
3996584154629None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg64.6464.6474.0FalseNoneNoneFalseNoneFalse4783.360
3996585154629None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg65.2865.2853.7FalseNoneNoneFalseNoneFalse3505.5360
3996586154629None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm295.0295.0180.0FalseNoneNoneFalseNoneFalse53100.00
3996587154629None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm297.95297.95179.0FalseNoneNoneFalseNoneFalse53333.050
3996588154629None8.16 aProviding lath plaster with cement mortar 1:3, 5cms thick with 6mm dia mild steel bars at 20 cms. c to c both horizontally and vertically fixing chicken mesh for drop chajja, facia, backing to cup boards including cost of all materials, labour, providing and removing form work usage charges, curing complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1238.01238.032.0FalseNoneNoneFalseNoneFalse39616.00
3996589154629None8.16 aProviding lath plaster with cement mortar 1:3, 5cms thick with 6mm dia mild steel bars at 20 cms. c to c both horizontally and vertically fixing chicken mesh for drop chajja, facia, backing to cup boards including cost of all materials, labour, providing and removing form work usage charges, curing complete as per specifications. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1250.381250.3832.0FalseNoneNoneFalseNoneFalse40012.160
3996590154629None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm100.0100.01483.335FalseNoneNoneFalseNoneFalse148333.50
3996591154629None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. First floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm101.0101.01515.335FalseNoneNoneFalseNoneFalse153048.8350
3996592154629None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm102.0102.094.13FalseNoneNoneFalseNoneFalse9601.260
3996593154629None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm110.0110.01483.335FalseNoneNoneFalseNoneFalse163166.850
3996594154629None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. First floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm111.1111.11515.335FalseNoneNoneFalseNoneFalse168353.71850
3996595154629None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm112.2112.294.13FalseNoneNoneFalseNoneFalse10561.3860
3996596154629None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.053.01483.335FalseNoneNoneFalseNoneFalse78616.7550
3996597154629None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.5353.531515.335FalseNoneNoneFalseNoneFalse81115.882550
3996598154629None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm54.0654.0694.13FalseNoneNoneFalseNoneFalse5088.66780
3996599154629None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm174.0174.0491.0FalseNoneNoneFalseNoneFalse85434.00
3996600154629None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm175.74175.74489.0FalseNoneNoneFalseNoneFalse85936.860
3996601154629None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm177.48177.48358.0FalseNoneNoneFalseNoneFalse63537.840
3996602154629None8.34.1Applying priming coat: With ready mixed pink or Grey primer of approved brand and manufacture on wood work (hard and soft wood) including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.053.082.0FalseNoneNoneFalseNoneFalse4346.00
3996603154629None8.34.1Applying priming coat: With ready mixed pink or Grey primer of approved brand and manufacture on wood work (hard and soft wood) including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.5353.5382.0FalseNoneNoneFalseNoneFalse4389.460
3996604154629None8.33.2Painting wood work with Deluxe Multi Surface Paint of required shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @0.75 L/10 m² of approved brand and manufacture to give an even shade including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, sand papering and knotting , cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm138.0138.082.0FalseNoneNoneFalseNoneFalse11316.00
3996605154629None8.33.2Painting wood work with Deluxe Multi Surface Paint of required shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @0.75 L/10 m² of approved brand and manufacture to give an even shade including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, sand papering and knotting , cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm139.38139.3882.0FalseNoneNoneFalseNoneFalse11429.160
3996606154629None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @ 0.80 L/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm139.0139.042.0FalseNoneNoneFalseNoneFalse5838.00
3996607154629None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @ 0.80 L/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm140.39140.3942.0FalseNoneNoneFalseNoneFalse5896.380
3996608154629None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @ 0.80 L/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm141.78141.783.0FalseNoneNoneFalseNoneFalse425.340
3996609154629None11.28Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners, stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in- charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.) including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs565.0565.0105.0FalseNoneNoneFalseNoneFalse59325.00
3996610154629None11.28Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners, stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in- charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.) including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs570.65570.65107.0FalseNoneNoneFalseNoneFalse61059.550
3996611154629None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr66.066.0300.0FalseNoneNoneFalseNoneFalse19800.00
3996612154629None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr66.6666.66300.0FalseNoneNoneFalseNoneFalse19998.00
3996613154629None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr67.3267.3241.0FalseNoneNoneFalseNoneFalse2760.120
3996614154629None15.1Polyurethane based Single Component for New Surface Providing and laying water proofing treatment to the Roof with PU based single component elastomeric pure polyurethane based coating on New terrace/Chajjas/Sunken portion of WC:Bathroom, cold applied PU waterproofing membrane that is highly elastic with elongation greater than 400% and tensile strength greater than 2MPa as per ASTM D412. The waterproofing membrane to be applied in 2coats @ 1.6 kg/m2 to achieve final DFT (Dry Film Thickness) of 1mm including prime coat of epoxy primer @150 g/m2 and protection with 120gsm Geo-textile over the waterproofing membrane. The finished cost to include surface preparation, making coving at Junction, Bore Packing, treatment of construction joints completely as per specification. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm833.34833.34327.0FalseNoneNoneFalseNoneFalse272502.180
3996615154629None7.18Providing and laying cinder concrete in cement 1:15 ( 1 cement : 15 cinder of 12.5mm nominal gauge) on terraced roof or sunken slabs, laid to slope compacting, including cost of materials, labour, curing complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum2037.172037.174.0FalseNoneNoneFalseNoneFalse8148.680
3996616154629None15.7Integral Crystalline Water Proofing Admixture Providing and supplying crystalline integral concrete waterproofing admixture that waterproofs concrete by forming crystals deep in the pores, capillaries and microcracks of the concrete, self-seal waterproofing compound to bridge shrinkage cracks upto 0.5mm in width & resist hydro-static pressure upto 16bar for both positive & negative pressure confirming to DIN 1048 part 5 for 56% reduction in depth of penetration against control, resistance to chloride penetration confirming to ASTM C 1202 with 64% improvement against control & protecting steel reinforcement against corrosion mixed @ 1% by weight of cementitious content in concrete. ie., integral crystaline waterproofing admix @ 0.5 kg/bag of cement. (For calculation purpose 320 kg of Cement for M-20 grade of Concrete is considered in the analysis) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm621.15621.1516.0FalseNoneNoneFalseNoneFalse9938.40
3996617154629None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9613.59613.51.9273FalseNoneNoneFalseNoneFalse18528.098550
3996618154629None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9679.89679.83.1153FalseNoneNoneFalseNoneFalse30155.480940
3996619154629None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9746.19746.132.7675FalseNoneNoneFalseNoneFalse319355.331750
3996620154629NoneVOL - 5 7.1.1Providing and fixing MS ladder between landings, 45 cms wide using angle iron of specified sizes, 20mm MS bars at 25 cms. centre to centre, with necessary supports of same angle iron etc. as directed, including hand railing on both sides with 25mm dia. GI pipes with angle iron props at 2 mtrs. intervals and 0.5M heigh, including fixing in ground with CC 1:2:4 and two coats of anticorrosive bituminous paint etc. with all lead and lifts etc. complete with: MS angle of 65 x 65 x 8mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr4464.544464.543.5FalseNoneNoneFalseNoneFalse15625.890
3996621154629None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.038.0193.8FalseNoneNoneFalseNoneFalse7364.40
3996622154629None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.3838.38193.8FalseNoneNoneFalseNoneFalse7438.0440
3996623154629None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.7638.7610.2FalseNoneNoneFalseNoneFalse395.3520
3996624154629None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.038.0206.25FalseNoneNoneFalseNoneFalse7837.50
3996625154629None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.3838.38206.25FalseNoneNoneFalseNoneFalse7915.8750
3996626154629None8.16.2Providing and fixing suitable plaster mesh 100mm wide manufactured out of hot dipped galvanised iron of nominal thickness 0.35mm with a zinc coating of 120g/m2 width, along route of walls chipped for services, junction between RCC and brick walls including cost of materials, labour for fixing complete as per specifications. ( length of mesh only be measured for payment Plaster mesh 150mm wide Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr38.7638.7615.11FalseNoneNoneFalseNoneFalse585.66360
3996627154629None22.15.7Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Tower Bolts 250x10mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos200.0200.048.0FalseNoneNoneFalseNoneFalse9600.00
3996628154629None22.15.7Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Tower Bolts 250x10mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos202.0202.050.0FalseNoneNoneFalseNoneFalse10100.00
3996629154629None22.15.8Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS hinges 125 mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos50.050.088.0FalseNoneNoneFalseNoneFalse4400.00
3996630154629None22.15.8Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS hinges 125 mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos50.550.591.0FalseNoneNoneFalseNoneFalse4595.50
3996631154629None22.15.1Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Handles 200mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos450.0450.048.0FalseNoneNoneFalseNoneFalse21600.00
3996632154629None22.15.1Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Handles 200mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos454.5454.550.0FalseNoneNoneFalseNoneFalse22725.00
3996633154629None22.15.4Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Aldrop 16mm dia, 300mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos375.0375.024.0FalseNoneNoneFalseNoneFalse9000.00
3996634154629None22.15.4Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Aldrop 16mm dia, 300mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos378.75378.7525.0FalseNoneNoneFalseNoneFalse9468.750
3996635154629None22.15.10Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Door stopper 75mm Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos100.0100.020.0FalseNoneNoneFalseNoneFalse2000.00
3996636154629None22.15.10Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Door stopper 75mm First Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos101.0101.016.0FalseNoneNoneFalseNoneFalse1616.00
17262057300000NoneNoneBuildingsStage Cum Auditorium (Shivani)8884907.09
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3996637154630NoneVOL - 3, C - 2 2.1 a (i) MoRT&H 201Cutting of Trees, excluding removal of stumps and roots of trees. (i) Girth from 300 mm to 600 mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each595.0595.050.0FalseNoneNoneFalseNoneFalse29750.00
3996638154630NoneVOL - 3, C - 2 2.2 b (i) MoRT&H 201Removal of stumps and roots including backfilling with suitable material to required compaction (i) Girth from 300 mm to 600 mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each356.0356.050.0FalseNoneNoneFalseNoneFalse17800.00
3996639154630None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.01245.8705FalseNoneNoneFalseNoneFalse127078.7910
3996640154630None1.15.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In ordinary/soft rock without blasting upto 1.5 m depth ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum363.0363.0135.4246FalseNoneNoneFalseNoneFalse49159.12980
3996641154630None1.9Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum266.0266.0521.1111FalseNoneNoneFalseNoneFalse138615.55260
3996642154630None4.1Providing and injecting chemical emulsion for Pre-constructional Anti-Termite Treatment, creating continuous chemical barrier under and around the column pits, walls, trenches, basement excavation, top surface of the plinth filling, junction of wall and floor, along the external perimeter of building, expansion joints, over the top surface of consolidated earth on which apron is to be laid, surrounding of pipes and conduits with Chlorpyriphos 20% E.C. / Lindane 20% E.C. @ 3.19 l/m2 including cost of chemical, diluting in water to one percent concentration, labour, usage charges of machinery, complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm118.0118.0468.0FalseNoneNoneFalseNoneFalse55224.00
3996643154630None2.1.3Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5989.05989.073.1256FalseNoneNoneFalseNoneFalse437949.21840
3996644154630None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6217.06217.08.5017FalseNoneNoneFalseNoneFalse52855.06890
3996645154630None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor Footing concrete ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6842.886842.8842.9675FalseNoneNoneFalseNoneFalse294021.44640
3996646154630None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Pedastals ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10771.210771.24.5322FalseNoneNoneFalseNoneFalse48817.232640
3996647154630None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Columns Concrete Upto PB ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10771.210771.21.7595FalseNoneNoneFalseNoneFalse18951.92640
3996648154630None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Plinth Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9504.09504.02.8669FalseNoneNoneFalseNoneFalse27247.01760
3996649154630None2.2.3Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Grade Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9504.09504.027.1929FalseNoneNoneFalseNoneFalse258441.32160
3996650154630None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Columns Concrete Up to Roof ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum11633.111633.112.1785FalseNoneNoneFalseNoneFalse141673.708350
3996651154630None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10948.810948.86.9759FalseNoneNoneFalseNoneFalse76377.733920
3996652154630None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10264.510264.58.45FalseNoneNoneFalseNoneFalse86735.0250
3996653154630None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Ground Floor For Lintel Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10948.810948.810.26FalseNoneNoneFalseNoneFalse112334.6880
3996654154630None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9613.59613.52.0FalseNoneNoneFalseNoneFalse19227.00
3996655154630None2.11 aSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. Buildings ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.t89457.089457.011.1254FalseNoneNoneFalseNoneFalse995244.90780
3996656154630None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Ground Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1310.01310.0323.0FalseNoneNoneFalseNoneFalse423130.00
3996657154630None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Terrace Floor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1323.11323.139.0FalseNoneNoneFalseNoneFalse51600.90
3996658154630None6.34Providing and constructing load bearing wall with Solid Concrete blocks of size 400x100x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1104.01104.041.0FalseNoneNoneFalseNoneFalse45264.00
3996659154630None12.13.1Providing Salwood frames of doors, windows, clerestory windows, ventilators and other frames, wrought, framed or assembled including making plaster groves (excluding cost of cement concrete and side clamps), but including cost of materials, labour, usage charges complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum98815.098815.00.4FalseNoneNoneFalseNoneFalse39526.00
3996660154630None12.57.3Providing and fixing flush door shutter made out of solid core block board type, well seasoned , chemicaly treated hard wood battens and internal frame with minimum 45 mm wide wooden frame alround door shutters covered with cross bonded wooden sheets (core veneer) hot pressed and fastened on both sides of the door useing liquid phenol formaldehyde resin as per IS specifications 2202 (part-I) 1991. from manufacturer complete as per spcification.-do- 30 mm thick both side commercial ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3005.03005.012.0FalseNoneNoneFalseNoneFalse36060.00
3996661154630None12.51Fixing of door frame in an existing opening including embedding frame in floor and walls after cutting masonry for holdfasts for embedding holdfast in cement concrete 1:3:6 of 20mm and down size granite metal painting two coats of coal tar to sides of frame, making good the damages to walls and floor as required and disposal of the debris with lead upto 50 m. including cost of materials, labour charges, complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1016.01016.08.0FalseNoneNoneFalseNoneFalse8128.00
3996662154630None12.94.1Providing and fixing factory made Green certified, Anti Termite, UV resistant, high water absorbant single extruded WPC (Wood PolymerComposite) solid plain flush door shutter of required size comprising of virgin polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibers (wood powder/rice husk/wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) having minimum density of 650 kg/m3 and screw withdrawal strength of 1800 N (Face) & 900 N (Edge), minimum compressive strength of 50 N/mm2 , modulus of elasticity 850 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixing with stainless steel butt hinges of required size with necessary full body threaded star headed counter sunk S.S screws The cost includes cost of materials, transportation, labour and fixing charges.(Cost of Fixtures to be paid separately) 30 mm thickness ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3485.03485.019.0FalseNoneNoneFalseNoneFalse66215.00
3996663154630None12.93.1Providing and fixing factory made single extruded WPC (Wood Polymer Composite) solid door/window/Clerestory windows & other Frames/ Chowkhat comprising of virgin PVC polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibres (wood powder/rice husk/ wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 g) fabricated with miter joints after applying PVC solvent cement and screwed with full body threaded star headed SS screws having minimum frame density of 850 kg/m3, screw withdrawal strength of 2200 N (Face) & 1100 N (Edge), minimum compressive strength of 58 N/mm2 , modulus of elasticity 900 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixed in position with M.S hold fast/lugs/SS dash fasteners of required dia and length complete as per direction of Engineer-InCharge. (Fixtures shall be paid for separately) Size 62 x 100mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr702.0702.063.0FalseNoneNoneFalseNoneFalse44226.00
3996664154630None12.88Providing & fixing of 2-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having a overall size of 60mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm X 58mm with GI reinforcement of 1mm for the frame and 1.5 mm for the sash. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24mm. Windows shall be provided with 5mm plain float glass, standard hardware& single point locking system with touch lock. Wall thickness of frame & sash shall be of 2-2.5 mm. Maximum possible size 1819mm x 1819mm (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5390.05390.051.0FalseNoneNoneFalseNoneFalse274890.00
3996665154630None12.85Providing & fixing of louvered ventilator made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free with gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the ventilator frame. The frame having overall size of 39mm x 39mm with GI reinforcement of 1mm thickness. Louver clip in Aluminium (powder coated in white) will be used on the frame along with plastic parts for fixing the 4 mm pin head glass. Wall thickness of frame shall be 2mm.Maximum possible size 1000mm x 1000mm.(The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5719.05719.03.0FalseNoneNoneFalseNoneFalse17157.00
3996666154630None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs183.0183.0972.0FalseNoneNoneFalseNoneFalse177876.00
3996667154630None9.17.2Providing and laying Vitrified tiles in different sizes (thickness to be specified by manufacturer), with water absorption less than 0.08 % and conforming to I.S. 15622, of approved make, in all colours & shade, over 12 mm thick bed of cement mortar 1:3 (1 cement: 3 coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including grouting the joint with white cement & matching pigments etc. complete. Size of Tile 600x600 mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1175.01175.021.0FalseNoneNoneFalseNoneFalse24675.00
3996668154630None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2852.02852.0492.186FalseNoneNoneFalseNoneFalse1403714.4720
3996669154630None9.11Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved make, in all colours, shades, except White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick bed of cement mortar 1:4 (1 Cement : 4 Coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including pointing the joints with white cement and matching pigments etc., complete. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm889.0889.035.0FalseNoneNoneFalseNoneFalse31115.00
3996670154630None9.39Providing skirting, dadooing, rises of steps with colour glazed tiles 6mm thick on 10mm thick cement plaster 1:3 and jointed with white cement slurry over existing rough plaster surface using glazed tiles of approved make and size including cost of materials, labour, complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1449.01449.0121.0FalseNoneNoneFalseNoneFalse175329.00
3996671154630None10.2Providing edge moulding to 18mm thick Granite stone counters, vanities etc including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr328.0328.011.0FalseNoneNoneFalseNoneFalse3608.00
3996672154630None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm295.0295.0446.0FalseNoneNoneFalseNoneFalse131570.00
3996673154630None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm371.0371.0589.0FalseNoneNoneFalseNoneFalse218519.00
3996674154630None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg64.064.089.0FalseNoneNoneFalseNoneFalse5696.00
3996675154630None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm295.0295.0126.0FalseNoneNoneFalseNoneFalse37170.00
3996676154630None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm100.0100.0513.6FalseNoneNoneFalseNoneFalse51360.00
3996677154630None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm110.0110.0513.6FalseNoneNoneFalseNoneFalse56496.00
3996678154630None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.053.0513.6FalseNoneNoneFalseNoneFalse27220.80
3996679154630None8.3Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm174.0174.0589.0FalseNoneNoneFalseNoneFalse102486.00
3996680154630None8.34.1Applying priming coat: With ready mixed pink or Grey primer of approved brand and manufacture on wood work (hard and soft wood) including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.053.028.0FalseNoneNoneFalseNoneFalse1484.00
3996681154630None8.33.2Painting wood work with Deluxe Multi Surface Paint of required shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @0.75 L/10 m² of approved brand and manufacture to give an even shade including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, sand papering and knotting , cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm138.0138.028.0FalseNoneNoneFalseNoneFalse3864.00
3996682154630None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @ 0.80 L/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm139.0139.054.0FalseNoneNoneFalseNoneFalse7506.00
3996683154630None8.8Forming groove of uniform size in the top layer of plaster as per approved pattern including repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge: 20 mm to 25 mm wide to required depth. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr66.066.0100.0FalseNoneNoneFalseNoneFalse6600.00
3996684154630None15.1Polyurethane based Single Component for New Surface Providing and laying water proofing treatment to the Roof with PU based single component elastomeric pure polyurethane based coating on New terrace/Chajjas/Sunken portion of WC:Bathroom, cold applied PU waterproofing membrane that is highly elastic with elongation greater than 400% and tensile strength greater than 2MPa as per ASTM D412. The waterproofing membrane to be applied in 2coats @ 1.6 kg/m2 to achieve final DFT (Dry Film Thickness) of 1mm including prime coat of epoxy primer @150 g/m2 and protection with 120gsm Geo-textile over the waterproofing membrane. The finished cost to include surface preparation, making coving at Junction, Bore Packing, treatment of construction joints completely as per specification. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm833.34833.34460.512FalseNoneNoneFalseNoneFalse383763.070080
3996685154630NoneVOL -5 7.1.1Providing and fixing MS ladder between landings, 45 cms wide using angle iron of specified sizes, 20mm MS bars at 25 cms. centre to centre, with necessary supports of same angle iron etc. as directed, including hand railing on both sides with 25mm dia. GI pipes with angle iron props at 2 mtrs. intervals and 0.5M heigh, including fixing in ground with CC 1:2:4 and two coats of anticorrosive bituminous paint etc. with all lead and lifts etc. complete with: MS angle of 65 x 65 x 8mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr4420.774420.774.0FalseNoneNoneFalseNoneFalse17683.080
3996686154630NoneVOL -5, 10.14.11Providing and installing at site of work P.V.C. pipes including cost of pipes and specials and labour, including lowering into trenches, laying true to line, level and perfect linking at joints leak proof including jointing of approved type with all labour charges and all lift charges, handling charges including encasing the pipe around to a depth not less than 15 cms with gravel or selected earth available from the excavation etc. complete. 6 Kg/m2: 110mm(weight of pipe -1.894 kg) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m358.0358.020.0FalseNoneNoneFalseNoneFalse7160.00
3996687154630None11.16.1Providing and fixing Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete. Hot finished welded type tubes including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs136.0136.011000.0FalseNoneNoneFalseNoneFalse1496000.00
3996688154630None7.38Providing and fixing precoated galvanised iron profile sheets (size, shape and pitch of corrugation as approved by Engineer-in-charge) 0.50 mm (+ 0.05 %) total coated thickness with zinc coating 120 grams per m2 as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns. Sheet should have protective guard film of 25 microns minimum to avoid scratches during transportation and should be supplied in single length upto 12 m or as desired by Engineer-in-charge. The sheet shall be fixed using self drilling/self tapping screws of size (5.5x 55 mm) with EPDM seal, complete upto any pitch in horizontal/ vertical or curved surfaces, excluding the cost of purlins, rafters and trusses and including cutting to size and shape wherever required. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm568.0568.0765.0FalseNoneNoneFalseNoneFalse434520.00
3996689154630None7.4.1Providing & fixing ridges or hips of width 60 cm overall width plain G.S. sheet fixed with polymer coated J or L hooks, bolts and nuts 8 mm dia G.I. limpet and bitumen washers complete as per design drawings. 0.63 mm thick with zinc coating not less than 275 g/m² ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m639.0639.029.0FalseNoneNoneFalseNoneFalse18531.00
3996690154630None7.6Providing and fixing 15 cm wide, 45 cm overall semi-circular plain G.S. sheet gutter with iron brackets 40x3mm size, bolts, nuts and washers etc., including making necessary connections with rain water pipes complete. (0.63 mm thick with zinc coating not less than 275 g/m²) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m645.0645.058.0FalseNoneNoneFalseNoneFalse37410.00
3996691154630None22.15.7Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Tower Bolts 250x10mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos200.0200.018.0FalseNoneNoneFalseNoneFalse3600.00
3996692154630None22.15.8Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS hinges 125 mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos50.050.054.0FalseNoneNoneFalseNoneFalse2700.00
3996693154630None22.15.1Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Handles 200mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos450.0450.036.0FalseNoneNoneFalseNoneFalse16200.00
3996694154630None22.15.4Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Aldrop 16mm dia, 300mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos375.0375.018.0FalseNoneNoneFalseNoneFalse6750.00
3996695154630None22.15.10Providing and fixing Stainless Steel Fixtures conforming to 304 graded steel as per direction of engineer in charge. SS Door stopper 75mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos100.0100.06.0FalseNoneNoneFalseNoneFalse600.00
17262057300000NoneNoneBuildingsInternal Water Supply Works (Shivani)2033669.0
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3996696154631None13.32.3Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply, including all CPVC plain & brass threaded fittings, i/c fixing the pipe with clamps at 1.00 m spacing. This includes jointing of pipes & fittings with one step CPVC solvent cement and the cost of cutting chases and making good the same including testing of joints complete as per direction of Engineer in Charge. Concealed work, including cutting chases and making good the walls etc. 25 mm nominal dia pipes ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m477.0477.0670.0FalseNoneNoneFalseNoneFalse319590.00
3996697154631None13.31.432 mm nominal dia pipes ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m557.0557.071.0FalseNoneNoneFalseNoneFalse39547.00
3996698154631None10.14.2SANITARY PIPING Providing and installing at site of work P.V.C. pipes including cost of pipes and specials and labour, including lowering into trenches, laying true to line, level and perfect linking at joints leak proof including jointing of approved type with all labour charges and all lift charges, handling charges including encasing the pipe around to a depth not less than 15 cms with gravel or selected earth available from the excavation etc. complete. 75mm(weight of pipe -0.917 kg) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr161.0161.0251.0FalseNoneNoneFalseNoneFalse40411.00
3996699154631None10.14.4110mm(weight of pipe -1.894 kg) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr282.0282.0322.0FalseNoneNoneFalseNoneFalse90804.00
3996700154631None14.74-aSANITARY FIXTURES Providing and fixing Single lever Bib cock Long Nose (Lifting type cold water cartridge) with wall flange made of Stainless steel with all concealed fitting arrangements & all necessary accesories complete - Class ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1250.01250.0172.0FalseNoneNoneFalseNoneFalse215000.00
3996701154631None14.67-aProviding and fixing Exposed set for concealed stop cock made of Stainless steel with all concealed fitting arrangements & all necessary accesories complete - Class ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each602.0602.034.0FalseNoneNoneFalseNoneFalse20468.00
3996702154631None14.2.1Providing and fixing white vitreous china pedestal type water closet (European type W.C. pan) with seat and lid, 10 litre low level white P.V.C. flushing cistern, including flush pipe, with manually controlled device (handle lever), conforming to IS : 7231, with all fittings and fixtures complete, including cutting and making good the walls and floors wherever required : W.C. pan with ISI marked white solid plastic seat and lid ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each4838.04838.027.0FalseNoneNoneFalseNoneFalse130626.00
3996703154631None14.1.1Providing and fixing water closet squatting pan (Indian type W.C. pan ) with 100 mm sand cast Iron P or S trap, 10 litre low level white P.V.C. flushing cistern, including flush pipe, with manually controlled device (handle lever) conforming to IS : 7231, with all fittings and fixtures complete, including cutting and making good the walls and floors wherever required: White Vitreous china Orissa pattern W.C. pan of size 580x440 mm with integral type foot rests ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each4884.04884.079.0FalseNoneNoneFalseNoneFalse385836.00
3996704154631None13.6Providing and fixing PVC (S.W.R) P Trap 10cms x 10cms with all fitting arrangements & all necessary accessories complete ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each309.0309.024.0FalseNoneNoneFalseNoneFalse7416.00
3996705154631None14.4.1Providing and fixing white vitreous china flat back or wall corner type lipped front urinal basin of 430x260x350 mm and 340x410x265 mm sizes respectively with automatic flushing cistern with standard flush pipe and C.P. brass spreaders with brass unions and G.I clamps complete, including painting of fittings and brackets, cutting and making good the walls and floors wherever required : One urinal basin with 5 litre white P.V.C. automatic flushing cistern ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each4884.04884.018.0FalseNoneNoneFalseNoneFalse87912.00
3996706154631None13.63Providing and fixing PVC (S.W.R) Multi Floor Trap 10.0 cm X 7.5 cm X 5.0 cm X 4.0 cm with all fitting arrangements & all necessary accessories complete ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each244.0244.094.0FalseNoneNoneFalseNoneFalse22936.00
3996707154631None14.24Providing and fixing white vitreous china squatting plate urinal with integral rim longitudinal flush pipe. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each2835.02835.06.0FalseNoneNoneFalseNoneFalse17010.00
3996708154631None14.7.1Providing and fixing wash basin with C.I. brackets, 15 mm C.P. brass pillar taps, 32 mm C.P. brass waste of standard pattern, including painting of fittings and brackets, cutting and making good the walls wherever require: White Vitreous China Wash basin size 630x450 mm with a pair of 15 mm C.P. brass pillar taps ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Unit3082.03082.027.0FalseNoneNoneFalseNoneFalse83214.00
3996709154631None14.10.1Providing and fixing Stainless Steel A ISI 304 (18/8) kitchen sink as per IS:13983 with C.I. brackets and stainless steel plug 40 mm, including painting of fittings and brackets, cutting and making good the walls wherever required : Kitchen sink with drain board ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos5618.05618.010.0FalseNoneNoneFalseNoneFalse56180.00
3996710154631None14.37.1Providing and fixing PTMT Bottle Trap for Wash basin and sink. Bottle trap 31mm single piece moulded with height of 270 mm, effective length of tail pipe 260 mm from the centre of the waste coupling, 77 mm breadth with 25 mm minimum water seal, weighing not less than 260 g ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos306.0306.044.0FalseNoneNoneFalseNoneFalse13464.00
3996711154631None14.48Providing and fixing Pillar Cock made of Stainless steel with all concealed fitting arrangements & all necessary accesories complete - Class ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1223.01223.036.0FalseNoneNoneFalseNoneFalse44028.00
3996712154631None14.78Providing and fixing Single flow hand showers with Anti lime jets with 1.5m PVC tube and holder made of Stainless steel with all concealed fitting arrangements & all necessary accesories complete - Class ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m887.0887.016.0FalseNoneNoneFalseNoneFalse14192.00
3996713154631None13.48 M150YRAIN WATER DISPOSAL SYSTEM Providing and fixing on wall face unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion, (i) Single socketed pipes 100 mm diameter 110mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m291.0291.0385.0FalseNoneNoneFalseNoneFalse112035.00
3996714154631None13.34AProviding and fixing rectangular high density polyethylene water storage loft tank with cover, conforming to ISI : 12701, colour of opaque white or as approved by Engineer-in-charge. The rate includes making necessary holes for inlet, outlet & over flow pipes. The base support i/c fittings & fixtures for tank shall be paid separately. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Ltr9.09.017000.0FalseNoneNoneFalseNoneFalse153000.00
3996715154631None13.34AProviding and fixing rectangular high density polyethylene water storage loft tank with cover, conforming to ISI : 12701, colour of opaque white or as approved by Engineer-in-charge. The rate includes making necessary holes for inlet, outlet & over flow pipes. The base support i/c fittings & fixtures for tank shall be paid separately. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Ltr9.09.020000.0FalseNoneNoneFalseNoneFalse180000.00
17262057300000NoneNoneBuildingsExternal Water Supply (Shivani)574456.0
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3996716154632None1.6Earth work excavation for pipelines/cables by Manual means upto 600 mm trench width, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m. Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering and lift upto 1.5 m including cost of labour, tools, usage& other appurtenances required to complete the work. 1.6.1 In all kinds of soils. Depth upto ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm242.0242.0510.0FalseNoneNoneFalseNoneFalse123420.00
3996717154632None1.10Refilling available earth around trenches/pipelines, cables in layers not exceeding 20 cm in depth, compacting each deposited layer by ramming after watering with a lead upto 50 m , and lift upto 1.5 m. Including cost of all labour complete as per specifications ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm160.0160.0390.0FalseNoneNoneFalseNoneFalse62400.00
3996718154632None13.50.1Providing and fixing Unplasticised Polyvinyl Chloride (uPVC) pipes, for cold water supply including all uPVC plain & brass threaded fittings This includes jointing of pipes & fittings with one step uPVC solvent cement, trenching, refilling & testing of joints complete as per direction of Engineer in Charge. External work External plumbing 32mm pipe outer dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr272.0272.010.0FalseNoneNoneFalseNoneFalse2720.00
3996719154632None13.50.240mm pipe outer dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr304.0304.025.0FalseNoneNoneFalseNoneFalse7600.00
3996720154632None13.50.350mm pipe outer dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr386.0386.0190.0FalseNoneNoneFalseNoneFalse73340.00
3996721154632None13.50.465 mm pipe outer dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr543.0543.0120.0FalseNoneNoneFalseNoneFalse65160.00
3996722154632None13.50.580 mm pipe outer dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr674.0674.0190.0FalseNoneNoneFalseNoneFalse128060.00
3996723154632None13.32 13.35KSRB13-6.3-6 -Providing and fixing in position brass gate valve with C.I wheel of approved quality ( screwed end ) nominal bore including cost of all materials, labour and HOM of equipments with all leads complete as per specifications. (external domestic water supply) 32 mm dia nominal ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos272.0272.05.0FalseNoneNoneFalseNoneFalse1360.00
3996724154632None13.3640 mm dia nominal ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos304.0304.05.0FalseNoneNoneFalseNoneFalse1520.00
3996725154632None13.32 13.38KSRB13-6.3-6 -Providing and fixing in position brass gate valve with C.I wheel of approved quality ( screwed end ) nominal bore including cost of all materials, labour and HOM of equipments with all leads complete as per specifications. Specification (external irrigation ) 63 mm dia nominal ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos536.0536.020.0FalseNoneNoneFalseNoneFalse10720.00
3996726154632None13.3980 mm dia nominal ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos781.0781.010.0FalseNoneNoneFalseNoneFalse7810.00
3996727154632None13.40100 mm dia nominal ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1333.01333.02.0FalseNoneNoneFalseNoneFalse2666.00
3996728154632None13.66Providing and fixing to wall, ceiling and floor medium density polyethylene pipes 6.00 kgf/sq.cm working pressure outside diameter raising mains & exposed distribution pipes with special flange, compression type fittings, wall clips, making good the wall, ceiling and floor, including cost of all materials, labour charges, HOM of equipments and testing complete as per specifications. Specification No. KBS 13.2.15.1 / 13.9 Page No : 95, Item No :13.66 PWD SR 18-19 (FOR External domestic& Flushing water shaft , terrace piping ) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr224.0224.015.0FalseNoneNoneFalseNoneFalse3360.00
3996729154632None13.6832 mm dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr272.0272.0310.0FalseNoneNoneFalseNoneFalse84320.00
17262057300000NoneNoneBuildingsExternal Sewage (Shivani)1412162.0
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3996730154633None1.6.1Earth work excavation for pipelines/cables by Manual means upto 600 mm trench width, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m. Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering and lift upto 1.5 m including cost of labour, tools, usage& other appurtenances required to complete the work. 1.6.1 In all kinds of soils. Depth upto 1.50m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm242.0242.0440.0FalseNoneNoneFalseNoneFalse106480.00
3996731154633None2.4Refilling available earth around trenches/pipelines, cables in layers not exceeding 20 cm in depth, compacting each deposited layer by ramming after watering with a lead upto 50 m , and lift upto 1.5 m. Including cost of all labour complete as per specifications Rate as per Item no 1.10 ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm160.0160.0180.0FalseNoneNoneFalseNoneFalse28800.00
3996732154633None2.28.1 Providing and fixing Wafer type single flange Butterfly valve conforming to relevant IS 13099/9991 EN GGG40/50 with latest amendments as detailed below of the following diameter and types with TP set and conveying to work site, loading and unloading, stacking etc. with all lead and lift. The rate is inclusive of the cost of valve, TP set, rubber insertion, bolts and nuts and excluding earth work excavation.For PN 10.0 (Note: TP set should be be considered only for DI pipes estimate. For MS pipes estimates, TP sets cost of corresponding dia shall be deducted from the SR rates of valves and provision for corresponding dia MS flanges should be made in estimate For Valve of PN - 10.0 and 100mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each5849.05849.06.0FalseNoneNoneFalseNoneFalse35094.00
3996733154633None2.33.1Providing and fixing kinetic AIR VALVE of PN 16.0 for automatic discharge of accumulate air during working condition, conforming to IS 14845 / EN 1074-4. Body and bonnet of DI conforming to IS-1865 of grade GGG-40/50, seals are made of approved EPDM, SS 304 float, guide and internals. Flange drilling according to IS-1538 with appurtenances. complete. Body and bonnet shall be coated with electrostatically applied epoxy powder coating with a coating thickness of 250 micron both inside and outside etc. complete For K Air Valves of 80mm dia. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each26343.026343.06.0FalseNoneNoneFalseNoneFalse158058.00
3996734154633None2.72.2Supply of PPR Ball Valve Plastic (Heavy Body) confirming to IS 15801- PPR Ball Valve Plastic (Heavy Body) 25mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each206.0206.041.0FalseNoneNoneFalseNoneFalse8446.00
3996735154633None13.23.4Providing and fixing PTMT Ball cock of approved quality, colour and makecomplete with Epoxy coated aluminium rod with L.P./ H.P.H.D. plastic ball. 40 mm nominal bore, 206mm long, weighing not less than 690 g ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each725.0725.04.0FalseNoneNoneFalseNoneFalse2900.00
3996736154633None13.23.550 mm nominal bore, 242mm long , weighing not less than 1240 g ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1344.01344.02.0FalseNoneNoneFalseNoneFalse2688.00
3996737154633None7.5.1Providing and fixing DI/CI puddle flanges conforming to IS 7181-1986 with latest ammendments., in position for RCC walls including hoisting and conveying them to work spot with all lead and lifts etc. complete . For DI/CI puddle flanges of 80mm dia. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1580.01580.05.0FalseNoneNoneFalseNoneFalse7900.00
3996738154633None13.40Providing and fixing square-mouth S.W. gully trap class SP-1 complete with C.I. grating brick masonry chamber with water tight C.I. cover 180 x 150 mm size P type & With Non Modular common burnt clay bricks of designation 3.5 & frame of 300 x300 mm size (inside) the weight of cover to be not less than 4.50 kg and frame to be not less than 2.70 kg as per standard design: ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each2686.02686.022.0FalseNoneNoneFalseNoneFalse59092.00
3996739154633None16.3.2Providing S&S RCC SPUN / VIBRATED CAST PIPES (REINFORCED)pipes NP-3 Class conforming to IS:458-1988 with latest amentmentsusing ordinary portland cement, for sanitary works and conveyingto work site, rolling and lowering into trenches, laying true to lineand level including loading and unloading at both destinations andjointing of pipes and specials, perfect linking of joints with jack tocorrect position including cost of jointing materials, i.e, rubber ringsconforming to IS: 5382 for S&S RCC pipes, with all leads and lifts asdirected and giving necessary hydraulic test as per ISS to the required pressure and commissioning etc. complete. (Contractor will make his own arrangements for procuring water for testing). Before the executionof the work, the contractor shall carry out the survey RCC NP3 Class pipe of 300 mm dia. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m1332.01332.0150.0FalseNoneNoneFalseNoneFalse199800.00
3996740154633None10.7Erection and positioning of RCC Hume pipe pump house/Cistern on size stone masory platform including transportation charges and handling,finishing with all necessary tools ,plants and materials etc.,complete as directed by the Engineer in charge of the work ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m1882.01882.030.0FalseNoneNoneFalseNoneFalse56460.00
3996741154633None16.11Constructing brick masonry chamber of internal dimension 450x300mm and depth of 600mm (inner dimensions) with modular bricks of CD 75 in cement mortar 1:6, bed concrete 150mm thick with 1:3:6, plastering 12 mm thick with cement mortar 1:4, CC 1:2:4 coping 75mm thk for fixing CI cover & frame etc. excluding the cost of CI frame and cover. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos3549.03549.012.0FalseNoneNoneFalseNoneFalse42588.00
3996742154633None10.14.6Providing and installing at site of work P.V.C. pipes including cost of pipesand specials and labour, including lowering into trenches, laying trueto line, level and perfect linking at joints leak proof including jointingof approved type with all labour charges and all lift charges, handlingcharges including encasing the pipe around to a depth not less than 15 cms with gravel or selected earth available from the excavation etc. complete. 160mm(weight of pipe -2.753 kg) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m489.0489.0440.0FalseNoneNoneFalseNoneFalse215160.00
3996743154633None16.9Constructing brick masonry chamber of internal dimension 600x600mm and depth of 600mm (inner dimensions) with modular bricks of CD 75 in cement mortar 1:6, bed concrete 150mm thick with 1:3:6, plastering 12 mm thick with cement mortar 1:4, CC 1:2:4 coping 75mm thk for fixing CI cover & frame etc. excluding the cost of CI frame and cover. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos5454.05454.030.0FalseNoneNoneFalseNoneFalse163620.00
3996744154633None16.10Constructing brick masonry chamber of internal dimension 450x450mm and depth of 600mm (inner dimensions) with modular bricks of CD 75 in cement mortar 1:6, bed concrete 150mm thick with 1:3:6, plastering 12 mm thick with cement mortar 1:4, CC 1:2:4 coping 75mm thk for fixing CI cover & frame etc. excluding the cost of CI frame and cover. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos4236.04236.015.0FalseNoneNoneFalseNoneFalse63540.00
3996745154633None13.40.4Supply and delivery of Centrifugal pumpset at site brand new bestmake and with discharge duty confirming to ISI standards and its latestamendments. 12.5 HP, size 100x100 Head 25M, Discharge 1560 LPM(centralized UG sump to centralized OHT tank 2W +1S ) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos38331.038331.02.0FalseNoneNoneFalseNoneFalse76662.00
3996746154633None13.40.33 HP, size 50x40 Head 30M, Discharge 198 LPM (IRRIGATION PUMP 1W +1S ) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos18816.018816.02.0FalseNoneNoneFalseNoneFalse37632.00
3996747154633None13.40.33 HP, size 50x40 Head 30M, Discharge 198 LPM (STP To Irrigation PUMP 2W +1S ) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos18816.018816.02.0FalseNoneNoneFalseNoneFalse37632.00
3996748154633None13.40.12 HP, Size 65x50 Head 13M, Discharge 462 LPM (For RO PUMP 2W +1S ) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos15610.015610.01.0FalseNoneNoneFalseNoneFalse15610.00
3996749154633None21.1.3Water purification plants: Providing, Installation and Commissioning of automatic Water purification plant (RO+UF) with all accessories piping, product water tank on single phase power supply as per the enclosed detailed Technical Specifications including cost of material, loading and unloading and as directed by the Engineer in charge. (Ref- detailed specification enclosed seperatly). Note:- 1.The above rates mentioned are only for the preparation of estimate purpose. 2. All items are to be of BSI /NFS standards,with BSI / NFS mark . 3. Tenders to be invited for procurement. 4. No direct payment should be made under any situation or condition or on any account. 5. After commissioning of plant necessary testing to be done for the satisfactory of Engineer Incharge. Note : Refer the ANNEXURE : F for Detailed Specification of Each components 100 LPH : Cabin Type ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No.94000.094000.01.0FalseNoneNoneFalseNoneFalse94000.00
17262057300000NoneNoneBuildingsSewage Treatment Plant (Shivani)2125603.25
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3996750154634None1.14.1Sewage Treatment Plant Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.0136.8FalseNoneNoneFalseNoneFalse13953.60
3996751154634None1.15.2Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In ordinary/soft rock without blasting Depth exceeding 1.5 m, but not exceeding 3 m Soft Rock 55% ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum425.0425.0188.1FalseNoneNoneFalseNoneFalse79942.50
3996752154634None1.16.1Earth work excavation for FOUNDATION by Mechanical means depth upto 1.50m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including cost of explosives, dressing of excavated surfaces, disposing off or levelling the excavated stuff or sorting & stacking the selected stuff for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, blasting materials, tools, usage of Machinery & all other appurtenaces required to complete the work. In Hard Rock ( requiring blasting) Depth upto 1.50m Hard Rock 5% ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum554.0554.017.1FalseNoneNoneFalseNoneFalse9473.40
3996753154634None1.9Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum266.0266.0136.8FalseNoneNoneFalseNoneFalse36388.80
3996754154634None1.18Extra for every additional lift of 1.5 m or part thereof in excavation/ banking excavated or stacked materials. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum87.087.0161.0FalseNoneNoneFalseNoneFalse14007.00
3996755154634None4.1Providing and injecting chemical emulsion for Pre-constructional Anti-Termite Treatment, creating continuous chemical barrier under and around the column pits, walls, trenches, basement excavation, top surface of the plinth filling, junction of wall and floor, along the external perimeter of building, expansion joints, over the top surface of consolidated earth on which apron is to be laid, surrounding of pipes and conduits with Chlorpyriphos 20% E.C. / Lindane 20% E.C. @ 3.19 l/m2 including cost of chemical, diluting in water to one percent concentration, labour, usage charges of machinery, complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum118.0118.098.0FalseNoneNoneFalseNoneFalse11564.00
3996756154634None2.1.3Providing and laying in position plain cement concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machineries, curing, and all the other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement & formwork shall be paid separately) Mix 1:3:6 (M10) Using 40 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5448.05448.020.0FalseNoneNoneFalseNoneFalse108960.00
3996757154634None2.4.2Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6955.36955.375.0FalseNoneNoneFalseNoneFalse521647.50
3996758154634None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Pump Room Roof Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9644.89644.82.1FalseNoneNoneFalseNoneFalse20254.080
3996759154634None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Pump Room Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9042.09042.06.8445FalseNoneNoneFalseNoneFalse61887.9690
3996760154634None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Pump Room Columns ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10247.610247.61.9872FalseNoneNoneFalseNoneFalse20364.030720
3996761154634None5.4Providing Size Stone masonry with hard stone in foundation & plinth with Cement mortar 1:6 (1 cement : 6 coarse sand) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5315.05315.09.0FalseNoneNoneFalseNoneFalse47835.00
3996762154634None2.5.1Providing and laying in position Reinforced cement concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/ trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement, dowel bars & formwork to be paid separately) M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum8740.68740.61.0FalseNoneNoneFalseNoneFalse8740.60
3996763154634None2.11 hSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. All other type of structures ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Tonne79011.079011.09.4522FalseNoneNoneFalseNoneFalse746827.77420
3996764154634None6.8Providing Brick work with common burnt clay Non Modular bricks of class designation 3.5 in superstructure above plinth level in all shapes and sizes in Cement mortar 1:6 (1 cement : 6 coarse sand) including cost of all materials, labour, scaffolding and usage charges of machinery & other incidental charges complete as per the direction of engineer incharge of work. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6659.06659.022.0FalseNoneNoneFalseNoneFalse146498.00
3996765154634None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings / wooden frames with rawl plugs screws etc. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs154.0154.059.0FalseNoneNoneFalseNoneFalse9086.00
3996766154634None12.88Providing & fixing of 2-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having a overall size of 60mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm X 58mm with GI reinforcement of 1mm for the frame and 1.5 mm for the sash. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24mm. Windows shall be provided with 5mm plain float glass, standard hardware& single point locking system with touch lock. Wall thickness of frame & sash shall be of 2-2.5 mm. Maximum possible size - 1819mm x 1819mm (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5390.05390.03.0FalseNoneNoneFalseNoneFalse16170.00
3996767154634None11.5.2Providing and fixing 1mm thick M.S. sheet door with frame of 40x40x6 mm angle iron and 3 mm M.S. gusset plates at the junctions and corners, all necessary fittings complete, including applying a priming coat of approved steel primer. Using flats 30x6mm for diagonal braces and central cross piece including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm4242.04242.02.0FalseNoneNoneFalseNoneFalse8484.00
3996768154634None9.1Providing and laying Cement concrete flooring 40 mm thick with 20 mm nominal size stone aggregate using 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate) finished with a floating coat of neat cement, including cement slurry complete. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm392.0392.040.0FalseNoneNoneFalseNoneFalse15680.00
3996769154634None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm304.0304.0122.0FalseNoneNoneFalseNoneFalse37088.00
3996770154634None8.2.2Providing 15 mm cement plaster on the rough side of single or half brick wall of mix :1:6 (1 cement: 6 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm228.0228.0100.0FalseNoneNoneFalseNoneFalse22800.00
3996771154634None8.1.1Providing 12 mm cement plaster with cement mortar 1:4 (1 cement: 4 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm210.0210.080.0FalseNoneNoneFalseNoneFalse16800.00
3996772154634None8.25Distempering with oil bound washable distemper of approved brand and manufacture to give an even shade :New work (two coats) over and including water thinnable priming coat with cement primer after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. Internal Plastering qty of control room ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm137.0137.0100.0FalseNoneNoneFalseNoneFalse13700.00
3996773154634None8.30Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. External Plastering ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm174.0174.0122.0FalseNoneNoneFalseNoneFalse21228.00
3996774154634None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90 ltr/10 m² over an under coat of primer applied @ 0.80 ltr/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm139.0139.059.0FalseNoneNoneFalseNoneFalse8201.00
3996775154634NoneVOL - 5, C - 10 10.1.9 Supplying PVC ringtite pipes conforming to IS 4985:2000 with latest amendments and conveying to worksite, rolling and lowering into trenches, laying true to line and level and perfect linking at joints, testing and commissioning, including loading unloading at both destinations and cuts of pipes wherever necessary including jointing of PVC pipes and specials (excluding cost of specials) with jointing of approved type, with all labour with all lead & lift including encasing the pipe alround to a depth of not less than 15 cms. with soft gravel or selected earth available from the excavation etc. complete and giving necessary hydraulic test to the required pressure as per ISS (Contractor will make his own arrangements for procuring water for testing) etc. for: PVC pipes 160mm dia., 6 kg/sqcm & class 3 ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m618.0618.050.0FalseNoneNoneFalseNoneFalse30900.00
3996776154634NoneVOL - 5, 16.9Constructing brick masonry chamber of internal dimension 600x600mm and depth of 600mm (inner dimensions) with modular bricks of CD 75 in cement mortar 1:6, bed concrete 150mm thick with 1:3:6, plastering 12 mm thick with cement mortar 1:4, CC 1:2:4 coping 75mm thk for fixing CI cover & frame etc. excluding the cost of CI frame and cover. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each5454.05454.03.0FalseNoneNoneFalseNoneFalse16362.00
3996777154634NoneVOL - 5, 16.23.1Providing and fixing SFRC frame and cover conforming to IS 12592 (part-I)-1988 and IS 12592 (part-II)- 1991 with latest amendment, including cutting slabs to the required size for the opening and fixing the cover in C.C. 1:2:4 and C.M. 1:3 plastering 20 mm thick to all exposed faces, curing for 10 days with all lead and lift with appurtenances.Complete Medium Duty ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Set1914.01914.03.0FalseNoneNoneFalseNoneFalse5742.00
3996778154634NoneVOL - 5, C - 16 16.15.1 Providing and constructing “WIRE CUT BRICK MACHINEHOLE CHAMBERS” using Portland/Pozzolana cement, conical in shape at top, with CC 1:3:6 foundation using 40mm and down size graded metal of approved quality and with an offset of 0.15M alround the chamber. Construct Brick masonry in CM 1:4, 340 mm thick, with wirecut bricks of approved quality, plaster inside and out side with CM 1:3, 12mm thick, except for the conical surface outside where the plaster thickness shall be 20mm. Slope inside to be 1:6 in the concrete towards central drain and finished smooth. Fixing of pipes in CC 1:2:4 with graded metal of 20mm and down size. Supplying and fixing SFRC Machinehole frame and cover (Heavy Duty) conforming to IS:12592 with latest amendment, in CC 1:2:4. Supplying and fixing footsteps made of 12mm dia. steel bars (Fe-500) with 3mm thick plastic encapsulation (IS-10910). The footsteps shall be fixed 30cms apart and on CC block embeded to masonry wall. The whole works include watering, curing, barricading, danger lighting, pouring tar over MH frame and cover, cost of tar, shoring, strutting, dewatering, engraving Machinehole number with flow direction on the inner conical surface etc. as per the drawing etc. as per technical specifications and for the following diameters and depth etc. for 1.2mm diaCirc. B M.H: Constructing Brick Masonry Circular Machinehole 1.2 m internal dia. , 1.0 M depth & SFRC cover & frame. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each29047.029047.01.0FalseNoneNoneFalseNoneFalse29047.00
3996779154634NoneVOL - 5, 7.3 Providing and fixing MS inspection door of size 60 cms x 60 cms, including MS frame made of 50x50x6mm angle, shutters made of 3mm thick MS sheets, with hinges, locking arrangements at top etc. including painting with anticorrosive approved paint etc. complete including all lead and lifts etc. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each2140.02140.06.0FalseNoneNoneFalseNoneFalse12840.00
3996780154634NoneVOL - 5 7.1.1 Providing and fixing MS ladder between landings, 45 cms wide using angle iron of specified sizes, 20mm MS bars at 25 cms. centre to centre, with necessary supports of same angle iron etc. as directed, including hand railing on both sides with 25mm dia. GI pipes with angle iron props at 2 mtrs. intervals and 0.5M heigh, including fixing in ground with CC 1:2:4 and two coats of anticorrosive bituminous paint etc. with all lead and lifts etc. complete with: MS angle of 65 x 65 x 8mm. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr4377.04377.03.0FalseNoneNoneFalseNoneFalse13131.00
17262057300000NoneNoneBuildingsAdvanced Sequencing Batch Reactor (Shivani)2236551.43
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3996781154635NoneI. 1ELECTROMECHANICAL EQUIPMENTS Design, Engineering, and providing all equipment /machinary at site, installation and commissioning of equipments/ electricals/ piping exclusive of all types of taxes and duties as described inspecification. The approximate capacity of sewage treatment plant is 50KLD Supplying , installing , testing , commissioning of bar screen to exclude the large sized particles with associated set of guide angles in MS flat of 6.0 mm thick and 50 mm wide kept inclined at 45 degree . Size : 600 x 600 ( MS Construction ) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No22982.422982.41.0FalseNoneNoneFalseNoneFalse22982.40
3996782154635None2. Supplying , installing , testing , commissioning of Raw Sewage Pump (Centrifugal/Submersible).The pump shall be coupled to the adequate HP , electric motor , mounted on a common base frame (1W + 1S) Make: Kirloskar Duty: 10 KLH @ 6-10 M head. (1W+1S) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No60480.060480.02.0FalseNoneNoneFalseNoneFalse120960.00
3996783154635None3. Supplying , installing , testing , commissioning of Coarse bubble diffusers 90 dia x 800mm long UPVC pipe grid with necessary orifices suitable for 6.0 kg/cm2 pressure rating to provide clog-free oxygen. Make : Scogen ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos7257.67257.68.0FalseNoneNoneFalseNoneFalse58060.80
3996784154635None4. Supplying , installing , testing , commissioning of Fine bubble diffusers 90 dia x 1000mm long with the membrane from SCOGEN shall consists of set of membranes , SS 304 clips , nylon rope braided hose with all accessories to make it retrievable . Make : Scogen ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos10523.5210523.5212.0FalseNoneNoneFalseNoneFalse126282.240
3996785154635None5. Supplying , installing , testing , commissioning of approved make Twin Lobe roots type air blower of adequate capacity at 0.5 kg/cm2 capacity of required head comprising of common base frame , suction filter , suction silencer , non return , V belt , safety valve , belt guard , drive and driven pulleys , pressure gauge , inter connection piping , discharge silencer including required motor. Make : KAY International Duty: 160 M3 /hr @ 0.5 KG/CM2 ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No223776.0223776.02.0FalseNoneNoneFalseNoneFalse447552.00
3996786154635None6. Supplying , installing , testing , commissioning of sludge disposal pumps to pump the sludge from SBR tank to sludge holding tank with wetted parts in CI construction. The pump shall be coupled to the adquate H.P electrical motor , mounted on a base frame . Make: Kirloskar Duty: 10 KLH @10 M head. (1W) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No42336.042336.01.0FalseNoneNoneFalseNoneFalse42336.00
3996787154635None7. Supplying , installing , testing , commissioning of Filter Feed Pump consisting of Monobloc type filter feed pumps to feed semi treated water to secondary treatment process through the filters.The pump shall be coupled to the adequate HP electrical motor , mounted on a common base frame . Make:Kirloskar Duty: 6 KLH @ 30 M head. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No48384.048384.02.0FalseNoneNoneFalseNoneFalse96768.00
3996788154635None8. Supplying , installing , testing , commissioning of Chlorine Dosing System consisting of Dosing pump and 100 ltrs Solution Tank having detachable lid with molded inserts for mounting of pump . Capacity :0 - 6lph (1w ) Make : E- Dose ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No31691.5231691.521.0FalseNoneNoneFalseNoneFalse31691.520
3996789154635None9. Supplying , installing , testing , commissioning of Pressure Sand filter for filtration of treated sewage. The filter shall be made of MS with epoxy painting with first charge of media, frontal face piping and multiport valves Size : 800 mm dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No254016.0254016.01.0FalseNoneNoneFalseNoneFalse254016.00
3996790154635None10. Supplying , installing , testing , commissioning of Activated Carbon filter for filtration of treated sewage, The filter shall be made of MS with epoxy painting with first charge of media, frontal face piping and multiport valves. Size : 800 mm dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No296352.0296352.01.0FalseNoneNoneFalseNoneFalse296352.00
3996791154635None11.Supply , fixing , testing & commissioning of fully automatic PLC based decant valve for suitable dia with auto electrical operated with isolation ( butterfly valve ) at suitable time as required opening & Closing automatically cost including all pipes with necessary fittings , electrical connection wiring etc complete. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No90720.090720.01.0FalseNoneNoneFalseNoneFalse90720.00
3996792154635None12.Plant Piping with UPVC of 10 Kg/sqcm pipes with fittings and approved make valves, gauges, instrumentation etc., for all plumbing lines and MS B Class pipeline with fittings for Blower Air Lines ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Lot243129.6243129.61.0FalseNoneNoneFalseNoneFalse243129.60
3996793154635None13.Supplying, installing, testing,commissioning of STP Tested Water Transfer Oump . The pump shall be submersible type coupled to the adequate H P Electrical Motor. Make:Kirloskar Duty:- KLD at30 M Head. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No43954.4443954.441.0FalseNoneNoneFalseNoneFalse43954.440
3996794154635NoneII. 1STP PANEL Supply, installation, testing and commissioning of front operated, front access, totally enclosed, free standing, dust and vermin proof Panel (Indoor non compartmental type) with IP 54 ingress protection, fabricated from 2 mm thick CRCA sheets, with hinged, gasketted and lockable doors including the cost of interconnections, copper crimping lugs, brass glands, bonding to earth and painting, suitable for use at 415 volts, 3 phase 4 wire 50 Hz system with 16 KA rupturing capacity at 415 volts complete. Electrical Motor Control Centre shall be suitable for all equipments connected to the STP with 2 Nos of spare feeders ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Set290304.0290304.01.0FalseNoneNoneFalseNoneFalse290304.00
3996795154635None2. CABLES AND CABLE TERMINATIONS Inter Unit Cabling Inter unit cabling for all equipments with necessary armoured/ unarmoured cables with necessary termination lugs, glands etc complete ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Lot62802.4362802.431.0FalseNoneNoneFalseNoneFalse62802.430
3996796154635NoneIV.MAINTAINANCE CHARGES AND CONSUMABLES Maintainance Charges including Man power required during maintainance period for 1 shift and Consumables required for functioning and maintainance of 50KLD Sewage Treatment Plant ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Month360.0360.024.0FalseNoneNoneFalseNoneFalse8640.00
17262057300000NoneNoneBuildingsSolar Water Heater (Shivani)724472.0
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3996797154636None7.3.1 of Part III Utilization (PWD Electrical)Supplying, installation, testing and commissioning of solar hot water heater comprising of solar flat plate collector of size 2120x1040x100mm and stainless steel hot water storage tank with stainless steel heat exchanger absorber made of copper sheet and copper tube of following capacity aluminium box collector with approximate capacity electrical back up arrangement excluding inlet and out let pipes. As per the directions SS Model with 100mm thick of 48Kg/Meter Cube density Rock wool insulation with 22SWG Aluminium cladding for 200 Liter Capacity for Quarters Block ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each46914.046914.05.0FalseNoneNoneFalseNoneFalse234570.00
3996798154636None7.3.2 of Part III Utilization (PWD Electrical)Supplying, installation, testing and commissioning of solar hot water heater comprising of solar flat plate collector of size 2120x1040x100mm and stainless steel hot water storage tank with stainless steel heat exchanger absorber made of copper sheet and copper tube of following capacity aluminium box collector with approximate capacity electrical back up arrangement excluding inlet and out let pipes. As per the directions SS Model with 100mm thick of 48Kg/Meter Cube density Rock wool insulation with 22SWG Aluminium cladding for 300 Liters Capacity Dormitory Block ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each69986.069986.07.0FalseNoneNoneFalseNoneFalse489902.00
17262057300000NoneNoneBuildingsBorewell (Shivani)956220.0
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3996799154637None12.1.1Sinking borewell of 165mm dia. clear, using super fast hydraulic rig of capacity 300 PSIG & above 1100 CMF and above, in all srata of earth,including over burden upto 20M. Fixing of casing pipes, collars and cap with ncessary cutting, threading and welding including transportation of rig and supporting vehicles, crew charges, cost of consumables,etc,completeincluding yield testing at the final depth with a minimum working of compressor for one hour etc. complete.(Excluding cost of Casing pipes, collars,Cap etc) (Above 450m of drilling add 10% for every 50m depth) - Borewell depth of 0 to 50 Mtrs ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr370.0370.0100.0FalseNoneNoneFalseNoneFalse37000.00
3996800154637None12.1.2Sinking borewell of 165mm dia. clear, using super fast hydraulic rig of capacity 300 PSIG & above 1100 CMF and above, in all srata of earth,including over burden upto 20M. Fixing of casing pipes, collars and cap with ncessary cutting, threading and welding including transportation of rig and supporting vehicles, crew charges, cost of consumables,etc,completeincluding yield testing at the final depth with a minimum working of compressor for one hour etc. complete.(Excluding cost of Casing pipes, collars,Cap etc) (Above 450m of drilling add 10% for every 50m depth) - Borewell depth of 50 to 100 Mtrs ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr464.0464.0100.0FalseNoneNoneFalseNoneFalse46400.00
3996801154637None12.1.3Sinking borewell of 165mm dia. clear, using super fast hydraulic rig of capacity 300 PSIG & above 1100 CMF and above, in all srata of earth,including over burden upto 20M. Fixing of casing pipes, collars and cap with ncessary cutting, threading and welding including transportation of rig and supporting vehicles, crew charges, cost of consumables,etc,completeincluding yield testing at the final depth with a minimum working of compressor for one hour etc. complete.(Excluding cost of Casing pipes, collars,Cap etc) (Above 450m of drilling add 10% for every 50m depth) - Borewell depth of 100 to 150 Mtrs ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr493.0493.0100.0FalseNoneNoneFalseNoneFalse49300.00
3996802154637None12.1.4Sinking borewell of 165mm dia. clear, using super fast hydraulic rig of capacity 300 PSIG & above 1100 CMF and above, in all srata of earth,including over burden upto 20M. Fixing of casing pipes, collars and cap with ncessary cutting, threading and welding including transportation of rig and supporting vehicles, crew charges, cost of consumables,etc,completeincluding yield testing at the final depth with a minimum working of compressor for one hour etc. complete.(Excluding cost of Casing pipes, collars,Cap etc) (Above 450m of drilling add 10% for every 50m depth) - Borewell depth of 150 to 200 Mtrs ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr572.0572.0100.0FalseNoneNoneFalseNoneFalse57200.00
3996803154637None12.1.5Sinking borewell of 165mm dia. clear, using super fast hydraulic rig of capacity 300 PSIG & above 1100 CMF and above, in all srata of earth,including over burden upto 20M. Fixing of casing pipes, collars and cap with ncessary cutting, threading and welding including transportation of rig and supporting vehicles, crew charges, cost of consumables,etc,completeincluding yield testing at the final depth with a minimum working of compressor for one hour etc. complete.(Excluding cost of Casing pipes, collars,Cap etc) (Above 450m of drilling add 10% for every 50m depth) - Borewell depth of 200 to 250 Mtrs ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr671.0671.0100.0FalseNoneNoneFalseNoneFalse67100.00
3996804154637None12.4Geophysical investigation at site for sinking borewells for Providing drinking water to the habitation either through the Hand Pump MWS or P.W.S.S, by vertical electrical sounding by adopting Venner or Schlumbergers's method, including reconnaissance survey of geological formation. Geophysical investigation of existing ground water in the vicinity, its quality, quantity and acceptability of the users, indicating the location of the site, recommended depth of casing pipe required to seal the top unconsolidated formation including an extra depth of 1.0 metre in consolidated formation for proper seating of casing pipe, depth of drilling required to cover full depth of aquifer proposed to be tapped, probable yield and other information required including transportation of instruments and accessories to work site, engaging technical personal and labour required etc. NOTE: 1) Additional rate on item 1&2 is allowed for drilling in over burden and fixing Casing pipes beyond 20 M (for fixing Casing pipes only) a) Above 20 M and upto 30 M - 15%, b) Above 30 M - 30% (Measurement of overburden is restricted to the depth of casing pipe fixed excluding initial depth of 20M and projection above ground level). 2) A sum of Rs. 100/- is to be deducted for Dry Borewell towards yield test. etc. complete. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each BW5288.05288.04.0FalseNoneNoneFalseNoneFalse21152.00
3996805154637None13.16.7Providing Submersible Pump Set of 150mm dia suitable for bore well and confirming to IS 8034-2000;3Phase, SS Bowl & Impeller with Low volt Motor as per specifications, to work site as per necessary ammendments and instructions of engineer incharge of work. For 10.00 HP 10.00 HP - 90 LPM @ 220 m = 20 STG Outlet Dia - 2.00" ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each54612.054612.02.0FalseNoneNoneFalseNoneFalse109224.00
3996806154637None12.32Supply of ISI mark 175mm nominal bore,plain and steel casing pipe grade of steel Fe 410 of wall thickness conforming to IS 4270-2001 and latest ammendments, electrical resistance welded steel tubes, material and conforming to IS 1387-1993 and manufactured by basic open hearth electric or basic oxygen process in andom length of 5-7m both ends.threaded conforming to IS 554-1985 one end fixed with socket conforming to IS 4270-2001 and the other end with screwed pipes all shall be responsibaly free from defects. The tubes shall be responsible straight end should be with ISI marking weighing 25.10kg/m.prices include Collar-Medium duty. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr1933.01933.030.0FalseNoneNoneFalseNoneFalse57990.00
3996807154637None12.34Providing and laying at site of work MS casing cap as per IS 1239 (partII) 1982 with all latest amendments if any for any dia. The thickness of plate used for covering one end shall be 3mm (minimum). The dimensions of caps and colars shall be strictly as per IS 1239 (Part-II) 1982 with all amendments including cost of material and labour charges for fixing, if any etc. complete with all lead and lifts and as directed by the Engineer in charge C ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each164.0164.02.0FalseNoneNoneFalseNoneFalse328.00
3996808154637None13.27.1Supply and delivery of galvanized mild steel tubes of 6mtr standardlength heavy duty (C Class) as per IS 1239 (Part-I) 1990 with latest amendments with ISI Mark (one end fitted with Heavy Duty collar and other end fitted with protective cover) 50mm dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each3050.03050.068.0FalseNoneNoneFalseNoneFalse207400.00
3996809154637None13.29Supply and delivery at site 50mm(2”) dia heavy duty CI adopter setcomplete suitable for uPVC Column pipes for Submersible pumpsets ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Set1550.01550.02.0FalseNoneNoneFalseNoneFalse3100.00
3996810154637None11.3.6Providing, Laying and Fixing of GI pipes conforming to IS 1239:1990 with latest amendments complete with GI fittings (excluding the costof fittings) with cuts and threads wherever necessary, including testingfor water tightness, with all lead and commissioning. (contractor willmake his own arrangements for procuring water for testing) For:Heavy Duty GI Pipe of 50mm dia etc. complete. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr679.0679.010.0FalseNoneNoneFalseNoneFalse6790.00
3996811154637None11.4.6Providing and fixing GI union in existing GI pipe line, cutting and threading the pipe and making long screws including excavation, refillingthe earth or cutting of wall and making good the same complete wherever required etc. complete for: 20.88.6:50mm nominal size ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each660.0660.02.0FalseNoneNoneFalseNoneFalse1320.00
3996812154637None13.24.1Supply and delivery at site of brand new best make gate valve as per IS778/1984 with ISI Mark and as per its latest amendments Size 50mm Gate valve ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1250.01250.02.0FalseNoneNoneFalseNoneFalse2500.00
3996813154637None13.25.1Supply and delivery at site of brand new best make non-return valve as per IS 778/1984 with ISI Mark and as per latest amendmentsits Size 50mm Non-return valve ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1250.01250.02.0FalseNoneNoneFalseNoneFalse2500.00
3996814154637None11.8.6Supply and delivery at site wrought middle steel (galvanized) GI bendconfirming to IS 1239-II, 1991 with latest amendments if any. For 50mm dia GI Bend ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each358.0358.04.0FalseNoneNoneFalseNoneFalse1432.00
3996815154637None13.32Labour charges for Erection, Electrification and commissioning of Pumpsets, including aligning and balancing of all items including supply and erection of two pair of supporting clamps, bore well caps, cable clips and water tight gland cable protectors, bolts, nuts, valve and gauges,tools andequipments etc., involved in the job as per specifications, with necessary tests as per specifications, with testing of as per instructions of engineer incharge of work. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Job6500.06500.02.0FalseNoneNoneFalseNoneFalse13000.00
3996816154637None13.36Providing main connection from pole PVC insulated sheathed steel wire cable in new trench as per IS 1554/ 1988 with latest amendments with ISI mark from KPTCL pole to meter board unit. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr135.0135.0102.0FalseNoneNoneFalseNoneFalse13770.00
3996817154637None13.35.2Labour charges for providing connection using insulated sheathedsteel wire cable as per IS 1554/ 1988 with latest amendments fromKPTCL pole to meter board unit, with all necessary materials ,tools and equipments,as per specificationswith testing of as per instructions of engineer incharge of work. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr160.0160.0100.0FalseNoneNoneFalseNoneFalse16000.00
3996818154637None13.33Labour charges for erection of indoor type panel board and meter board units with all necessary materials and labour, tools and equipments including providing cement concrete foundation bed etc., complete as per specification, with testing of as per instructions of engineer incharge of work. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Job1350.01350.02.0FalseNoneNoneFalseNoneFalse2700.00
3996819154637None13.22Supply and delivery at site Brand new best make PVC insulated cable of Flat 3 core (sheathed) of nominal cross sectional area as per IS 694-1990 with ISI Mark and as per its latest amendments. 1x3x6 Sqm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr185.0185.0556.0FalseNoneNoneFalseNoneFalse102860.00
3996820154637None13.38Providing and fixing suitable for 1.1 KV class UG cable filled with necessary bitumen/insulating compound complete with terminals, clamps,bolts,nuts and washers etc. with necessary materials and labour tools and equipments as per instructions of engineer incharge of work. 1x3x6 Sqm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each375.0375.04.0FalseNoneNoneFalseNoneFalse1500.00
3996821154637None13.39Earthing: Providing and fixing and wiring earth electrode for grounding circuits IC cutouts and other equipments on the meter board in the pit. The pits should be filled up with equal proportion of salt and charcoal 150mm around the pipe to complete depth. The connection from the pipe to the conduits etc. is to established through GI wire of sizes as per clause 7.3.3 of IS 732 using 12mm bolts, nuts, washers and check nuts, the pipe shall have 16 through holes of 12mm dia. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Job3750.03750.04.0FalseNoneNoneFalseNoneFalse15000.00
3996822154637None13.23.3Supply, installing,testing and commissioning COMMON control panel consisting of the following INCOMING:1 No set of Phase indicatinglamps with SFU of suitable rating 1 No, Analog Ammeter, 1 No AnalogVoltmeter 1ni with Phase selector switch, Isolating switch OUTGOINGfor Main Electrical Pump: 1 No. MCB 1 No. DOL of S/D Starter suitablefor respective HP 1 No. Electrcal Protection Like single Phase preventor,under voltage overVolage, under current over current & dry runprotection suitable for the pump described above 1 no Indoor type NOTE: 1) DOL- Direct Online Starter 2) S-D- Star Delta Starter etc. complete. 6 to 15 HP pumps ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each15900.015900.02.0FalseNoneNoneFalseNoneFalse31800.00
3996823154637None9.1.2Providing, laying and jointing HDPE pipes of specified grade and conforming to IS 4984-2016 with latest ammendments and conveying to work site including loading and unloading at both destinations and rolling and lowering into trenches, laying true to line and jointing of pipes and specials with electrofusion welding, giving hydraulic test as per relevant ISS with all lead and lifts including encasing the pipe alround to a depth of not less than 15 cms. with soft gravel or selected earth available from the excation, testing and commissioning. The rate is exclusive of required specials and fittings wherever necessary like saddle Tee, stub ends, flanged sets, bedns, reducers etc. complete Contractor will make his own arrangements for procuring water for testing etc. complete. NOTE: Upto 110mm dia Coil shall be used.For :HDPE PE 80 PN 6.0 HDPE Grade PE80-PN6.0, 63mm dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr189.0189.0200.0FalseNoneNoneFalseNoneFalse37800.00
3996824154637None1.17.1Earth work excavation for pipeline trenches in all kinds of soils by mechanical means as per drawing and technical specifications, including setting out, construction of shoring, strutting, barricading, caution lights, bracing, using sight rails & bonding rods at every 100mm wherever necessary as directed,removal of stumps and other deleterious matter, dressing of sides and levelling the bottom of trench to the extent required , utilising the available excavated earth locally for the work etc and all other appurtenances complete in the following strata. All kinds of soils, depth upto 1.50M ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.cm262.0262.036.0FalseNoneNoneFalseNoneFalse9432.00
3996825154637None1.1Refilling available earth around trenches/pipelines, cables in layers not exceeding 20 cms in depth, compacting each deposited layer by ramming after watering with a lead upto 50 m, and lift upto 1.5 m. Including cost of all labour complete as per specifications ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.cm160.0160.031.6FalseNoneNoneFalseNoneFalse5056.00
3996826154637None10.6RCC hume pipe Circular pump house: Providing precast RCC Circular Hume pipe pump house with M.S door and RCC conical roof as per specification and drawings - Internal dia Mtr. 1200 mm & height of 2.5 Mtr. With Wall thickness 65mm etc. complete. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each16401.016401.02.0FalseNoneNoneFalseNoneFalse32802.00
3996827154637None10.7Erection and positioning of RCC Hume pipe pump house/Cistern onsize stone masory platform including transportation charges andhandling,finishing with all necessary tools ,plants and materials etc.,complete as directed by the Engineer in charge of the work. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1882.01882.02.0FalseNoneNoneFalseNoneFalse3764.00
17262057300000NoneNoneBuildingsSump Tank (Shivani)833004.13
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3996828154638None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.047.58FalseNoneNoneFalseNoneFalse4853.160
3996829154638None1.15.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In ordinary/soft rock without blasting upto 1.5 m depth Soft Rock 80% ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum363.0363.0191.0FalseNoneNoneFalseNoneFalse69333.00
3996830154638None1.9Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum266.0266.0107.0FalseNoneNoneFalseNoneFalse28462.00
3996831154638None1.18Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or stacked materials. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum87.087.097.5FalseNoneNoneFalseNoneFalse8482.50
3996832154638None2.1.3Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5448.05448.06.0FalseNoneNoneFalseNoneFalse32688.00
3996833154638None2.4.2Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6955.36955.327.0FalseNoneNoneFalseNoneFalse187793.10
3996834154638None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9644.89644.88.0FalseNoneNoneFalseNoneFalse77158.40
3996835154638None2.11 hSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. All other type of structures. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Tonne79011.079011.03.85FalseNoneNoneFalseNoneFalse304192.350
3996836154638None8.36.1Finishing with Epoxy paint (two coats) at all locations prepared and applied as per manufacturer's specifications including appropriate priming coat, preparation of surface, etc. complete. On steel work including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Enginer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm176.0176.0142.3416FalseNoneNoneFalseNoneFalse25052.12160
3996837154638None15.1Polyurethane based Single Component for New Surface Providing and laying water proofing treatment to the Roof with PU based single component elastomeric pure polyurethane based coating on New terrace/Chajjas/Sunken portion of WC:Bathroom, cold applied PU waterproofing membrane that is highly elastic with elongation greater than 400% and tensile strength greater than 2MPa as per ASTM D412. The waterproofing membrane to be applied in 2coats @ 1.6 kg/m2 to achieve final DFT (Dry Film Thickness) of 1mm including prime coat of epoxy primer @150 g/m2 and protection with 120gsm Geo-textile over the waterproofing membrane. The finished cost to include surface preparation, making coving at Junction, Bore Packing, treatment of construction joints completely as per specification. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm817.0817.077.5FalseNoneNoneFalseNoneFalse63317.50
3996838154638NoneVOL - 5, 7.3 Providing and fixing MS inspection door of size 60 cms x 60 cms, including MS frame made of 50x50x6mm angle, shutters made of 3mm thick MS sheets, with hinges, locking arrangements at top etc. including painting with anticorrosive approved paint etc. complete including all lead and lifts etc. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each2140.02140.01.0FalseNoneNoneFalseNoneFalse2140.00
3996839154638NoneVOL - 5, 10.6RCC hume pipe Circular pump house: Supplying precast RCC Circular Hume pipe pump house with M.S door and RCC conical roof as per specification and drawings - Internal dia Mtr. 1200 mm & height of 2.5 Mtr. With Wall thickness 65mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each16401.016401.01.0FalseNoneNoneFalseNoneFalse16401.00
3996840154638NoneVOL - 5 7.1.1 Providing and fixing MS ladder between landings, 45 cms wide using angle iron of specified sizes, 20mm MS bars at 25 cms. centre to centre, with necessary supports of same angle iron etc. as directed, including hand railing on both sides with 25mm dia. GI pipes with angle iron props at 2 mtrs. intervals and 0.5M heigh, including fixing in ground with CC 1:2:4 and two coats of anticorrosive bituminous paint etc. with all lead and lifts etc. complete with: MS angle of 65 x 65 x 8mm. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr4377.04377.03.0FalseNoneNoneFalseNoneFalse13131.00
17262057300000NoneNoneBuildingsInternal Electrical Works (Shivani)7232726.72
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3996841154639None1.2.1 of Part III Utilization (PWD Electrical)Concealed Conduit System Supplying 19/20 mm dia 2mm/2.5mm thick heavy gauge PVC conduit pipe with suitable size bends, metal/PVC junction boxes adhesive paste etc., and running before concreting the slab. The conduit should be tied to the reinforcement rods by using binding wires and unused ways of junction boxes and pipe ends should be covered using PVC end enclosures. run with 18SWG GI fish wire wherever necessary. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr66.066.06850.0FalseNoneNoneFalseNoneFalse452100.00
3996842154639None1.1.1 of Part III Utilization (PWD Electrical)Open Conduit System Supplying heavy gauge PVC conduit pipe 19/20mm dia 2mm thick confirming to IS 2509 with suitable size bends, junction boxes, adhesive paste etc., and fixing using inverted wood plugs in case of RCC ceiling and RCC wall / stone structure or rawl plugs in case of brick walls and cement plastering the damaged portion using heavy gauge saddles at an interval of 700mm using NF screws. 19/20mm dia 2mm thick. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr69.069.01250.0FalseNoneNoneFalseNoneFalse86250.00
3996843154639None1.2.2 of Part III Utilization (PWD Electrical)Concealed Conduit System Supplying 25 mm dia 2mm/2.5mm thick heavy gauge PVC conduit pipe with suitable size bends, metal/PVC junction boxes adhesive paste etc., and running before concreting the slab. The conduit should be tied to the reinforcement rods by using binding wires and unused ways of junction boxes and pipe ends should be covered using PVC end enclosures. run with 18SWG GI fish wire wherever necessary. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr78.078.02750.0FalseNoneNoneFalseNoneFalse214500.00
3996844154639None1.3.1 of Part III Utilization (PWD Electrical)Supplying 19/20 dia 2mm/2.5mm thick heavy gauge PVC Conduit Pipe with bends, metal junction boxes adhesive paste etc.,by groove cutting in the wall and fixing by bracing U or J hooks and cement plastering up to the wall surface and run with 18 SWG GI fish wire run throughout the conduit wherever necessary. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr68.068.03725.0FalseNoneNoneFalseNoneFalse253300.00
3996845154639None1.3.2 of Part III Utilization (PWD Electrical)Supplying 25 mm dia 2mm/2.5mm thick heavy gauge PVC Conduit Pipe with bends, metal junction boxes adhesive paste etc.,by groove cutting in the wall and fixing by bracing U or J hooks and cement plastering up to the wall surface and run with 18 SWG GI fish wire run throughout the conduit wherever necessary. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr355.0355.01010.0FalseNoneNoneFalseNoneFalse358550.00
3996846154639None2.1.1 of Part III Utilization (PWD Electrical)Supplying and wiring adopting loop system in existing PVC Conduit /casing capping casing capping using 2x1.5mm (Phase & Neutral) & 1x1.0 mm 2 (Earth wire) FRLS multi strand PVC insulated copper wire (confirming to IS-694: and latest amendments) with a 6A, flush type SP control switch shall be fixed on the existing plastic sheet/ gang box, the other end of the wires shall be terminated with sufficient loose length in a wood/PVC round block. complete for each outlet. - Short point upto 3m from tapping point to out let via switch box ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Point285.0285.074.0FalseNoneNoneFalseNoneFalse21090.00
3996847154639None2.1.2 of Part III Utilization (PWD Electrical)Supplying and wiring adopting loop system in existing PVC Conduit /casing capping casing capping using 2x1.5mm (Phase & Neutral) & 1x1.0 mm 2 (Earth wire) FRLS multi strand PVC insulated copper wire (confirming to IS-694: and latest amendments) with a 6A, flush type SP control switch shall be fixed on the existing plastic sheet/ gang box, the other end of the wires shall be terminated with sufficient loose length in a wood/PVC round block. complete for each outlet. - Medium point above - 3Mtr up to 6Mtr from tapping point to out let via switch ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Point394.0394.093.0FalseNoneNoneFalseNoneFalse36642.00
3996848154639None2.1.3 of Part III Utilization (PWD Electrical)Supplying and wiring adopting loop system in existing PVC Conduit /casing capping casing capping using 2x1.5mm (Phase & Neutral) & 1x1.0 mm 2 (Earth wire) FRLS multi strand PVC insulated copper wire (confirming to IS-694: and latest amendments) with a 6A, flush type SP control switch shall be fixed on the existing plastic sheet/ gang box, the other end of the wires shall be terminated with sufficient loose length in a wood/PVC round block. complete for each outlet. - Long point above 6Mtr up to 10Mtr from tapping point to out let via switch ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Point570.0570.0129.0FalseNoneNoneFalseNoneFalse73530.00
3996849154639None2.1.4 of Part III Utilization (PWD Electrical)Supplying and wiring adopting loop system in existing PVC Conduit /casing capping casing capping using 2x1.5mm (Phase & Neutral) & 1x1.0 mm 2 (Earth wire) FRLS multi strand PVC insulated copper wire (confirming to IS-694: and latest amendments) with a 6A, flush type SP control switch shall be fixed on the existing plastic sheet/ gang box, the other end of the wires shall be terminated with sufficient loose length in a wood/PVC round block. complete for each outlet. - Two outlet in a row, above 3Mtr upto 6Mtr from tapping point to out let via switches. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Point708.0708.0213.0FalseNoneNoneFalseNoneFalse150804.00
3996850154639None2.1.5 of Part III Utilization (PWD Electrical)Supplying and wiring adopting loop system in existing PVC Conduit /casing capping casing capping using 2x1.5mm (Phase & Neutral) & 1x1.0 mm 2 (Earth wire) FRLS multi strand PVC insulated copper wire (confirming to IS-694: and latest amendments) with a 6A, flush type SP control switch shall be fixed on the existing plastic sheet/ gang box, the other end of the wires shall be terminated with sufficient loose length in a wood/PVC round block. complete for each outlet. - Three outlet in a row, above 6Mts upto 10Mtr from tapping point to out let via switches. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Point1035.01035.0123.0FalseNoneNoneFalseNoneFalse127305.00
3996851154639None3.4.1 of Part III Utilization (PWD Electrical)Supplying and fixing surface/flush mounting powder coated / galvanized metal box suitable for mounting modular switch plates. The box should be firmly flush mounted after due groove cutting in Brick/Stone/C.C wall. 1-3 Way. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each159.0159.0943.0FalseNoneNoneFalseNoneFalse149937.00
3996852154639None3.4.2 of Part III Utilization (PWD Electrical)Supplying and fixing surface/flush mounting powder coated / galvanized metal box suitable for mounting modular switch plates. The box should be firmly flush mounted after due groove cutting in Brick/Stone/C.C wall. 4-5 Way. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each177.0177.0225.0FalseNoneNoneFalseNoneFalse39825.00
3996853154639None3.4.3 of Part III Utilization (PWD Electrical)Supplying and fixing surface/flush mounting powder coated / galvanized metal box suitable for mounting modular switch plates. The box should be firmly flush mounted after due groove cutting in Brick/Stone/C.C wall. 6 Way ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each220.0220.0108.0FalseNoneNoneFalseNoneFalse23760.00
3996854154639None3.4.4 of Part III Utilization (PWD Electrical)Supplying and fixing surface/flush mounting powder coated / galvanized metal box suitable for mounting modular switch plates. The box should be firmly flush mounted after due groove cutting in Brick/Stone/C.C wall. 8 Way ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each261.0261.082.0FalseNoneNoneFalseNoneFalse21402.00
3996855154639None3.4.5 of Part III Utilization (PWD Electrical)Supplying and fixing surface/flush mounting powder coated / galvanized metal box suitable for mounting modular switch plates. The box should be firmly flush mounted after due groove cutting in Brick/Stone/C.C wall. 10-12Way ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each319.0319.068.0FalseNoneNoneFalseNoneFalse21692.00
3996856154639None3.4.6 of Part III Utilization (PWD Electrical)Supplying and fixing surface/flush mounting powder coated / galvanized metal box suitable for mounting modular switch plates. The box should be firmly flush mounted after due groove cutting in Brick/Stone/C.C wall. 16Way ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each363.0363.042.0FalseNoneNoneFalseNoneFalse15246.00
3996857154639None3.5.1 of Part III Utilization (PWD Electrical)Supplying and fixing superior quality modular switch mounting polycarbonate plate with necessary supporting back plate with required nos. of machine screws, bolts nuts etc, complete on the existing metal/PVC box. 1 to 3 Module ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each161.0161.0943.0FalseNoneNoneFalseNoneFalse151823.00
3996858154639None3.5.2 of Part III Utilization (PWD Electrical)Supplying and fixing superior quality modular switch mounting polycarbonate plate with necessary supporting back plate with required nos. of machine screws, bolts nuts etc, complete on the existing metal/PVC box. 4 Module ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each175.0175.0225.0FalseNoneNoneFalseNoneFalse39375.00
3996859154639None3.5.3 of Part III Utilization (PWD Electrical)Supplying and fixing superior quality modular switch mounting polycarbonate plate with necessary supporting back plate with required nos. of machine screws, bolts nuts etc, complete on the existing metal/PVC box. 6 Module ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each234.0234.0108.0FalseNoneNoneFalseNoneFalse25272.00
3996860154639None3.5.4 of Part III Utilization (PWD Electrical)Supplying and fixing superior quality modular switch mounting polycarbonate plate with necessary supporting back plate with required nos. of machine screws, bolts nuts etc, complete on the existing metal/PVC box. 8 Module ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each284.0284.082.0FalseNoneNoneFalseNoneFalse23288.00
3996861154639None3.5.5 of Part III Utilization (PWD Electrical)Supplying and fixing superior quality modular switch mounting polycarbonate plate with necessary supporting back plate with required nos. of machine screws, bolts nuts etc, complete on the existing metal/PVC box. 10 Module ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each344.0344.068.0FalseNoneNoneFalseNoneFalse23392.00
3996862154639None3.5.6 of Part III Utilization (PWD Electrical)Supplying and fixing superior quality modular switch mounting polycarbonate plate with necessary supporting back plate with required nos. of machine screws, bolts nuts etc, complete on the existing metal/PVC box. 12 Module ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each344.0344.068.0FalseNoneNoneFalseNoneFalse23392.00
3996863154639None3.5.7 of Part III Utilization (PWD Electrical)Supplying and fixing superior quality modular switch mounting polycarbonate plate with necessary supporting back plate with required nos. of machine screws, bolts nuts etc, complete on the existing metal/PVC box. 16 Modulee ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each397.0397.042.0FalseNoneNoneFalseNoneFalse16674.00
3996864154639None3.6.1 of Part III Utilization (PWD Electrical)Supplying and fixing of modular switch/ Socket/Stepped electronic fan regulator/ dimmer / telephone socket etc on existing modular switch plate as per IS 3854 and IS 1293. 6Amps One Way. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each102.0102.0504.0FalseNoneNoneFalseNoneFalse51408.00
3996865154639None3.6.2 of Part III Utilization (PWD Electrical)Supplying and fixing of modular switch/ Socket/Stepped electronic fan regulator/ dimmer / telephone socket etc on existing modular switch plate as per IS 3854 and IS 1293. 6Amps Two Way.\ ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each166.0166.074.0FalseNoneNoneFalseNoneFalse12284.00
3996866154639None3.6.3 of Part III Utilization (PWD Electrical)Supplying and fixing of modular switch/ Socket/Stepped electronic fan regulator/ dimmer / telephone socket etc on existing modular switch plate as per IS 3854 and IS 1293. 6Amps 3way socket. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each171.0171.0504.0FalseNoneNoneFalseNoneFalse86184.00
3996867154639None3.6.4 of Part III Utilization (PWD Electrical)Supplying and fixing of modular switch/ Socket/Stepped electronic fan regulator/ dimmer / telephone socket etc on existing modular switch plate as per IS 3854 and IS 1293. 'Stepped Fan Regulator. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each357.0357.0208.0FalseNoneNoneFalseNoneFalse74256.00
3996868154639None3.6.9 of Part III Utilization (PWD Electrical)Supplying and fixing of modular switch/ Socket/Stepped electronic fan regulator/ dimmer / telephone socket etc on existing modular switch plate as per IS 3854 and IS 1293. 6 Amps Bell Push ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each177.0177.013.0FalseNoneNoneFalseNoneFalse2301.00
3996869154639None3.6.11 of Part III Utilization (PWD Electrical)Supplying and fixing of modular switch/ Socket/Stepped electronic fan regulator/ dimmer / telephone socket etc on existing modular switch plate as per IS 3854 and IS 1293. 6/16Amps Universal Socket ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each236.0236.072.0FalseNoneNoneFalseNoneFalse16992.00
3996870154639None3.6.7 of Part III Utilization (PWD Electrical)Supplying and fixing of modular switch/ Socket/Stepped electronic fan regulator/ dimmer / telephone socket etc on existing modular switch plate as per IS 3854 and IS 1293. 16A One Way Switch ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each180.0180.072.0FalseNoneNoneFalseNoneFalse12960.00
3996871154639None3.6.12 of Part III Utilization (PWD Electrical)Supplying and fixing of modular switch/ Socket/stepped electronic fan regulator/ dimmer/telephone socket etc on existing modular switch plate as per IS 3854 and IS 1293 TV/Telephone socket ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each156.0156.046.0FalseNoneNoneFalseNoneFalse7176.00
3996872154639None3.6.13 of Part III Utilization (PWD Electrical)Supplying and fixing of modular switch/ Socket/stepped electronic fan regulator/ dimmer/telephone socket etc on existing modular switch plate as per IS 3854 and IS 1293 RJ45/I.O Outlet Cat-6 Socket ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each337.0337.022.0FalseNoneNoneFalseNoneFalse7414.00
3996873154639None8.2.2 of Part III Utilization (PWD Electrical)Supplying and drawing PVC flexible two pair telephone unarmoured tinned copper cable. 2 Pair ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr21.021.01380.0FalseNoneNoneFalseNoneFalse28980.00
3996874154639None8.3 of Part III Utilization (PWD Electrical)Supplying and drawing PVC insulated gas injected physical foam jelly flooded co-axial TV cable.RG- 6 ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr44.044.0920.0FalseNoneNoneFalseNoneFalse40480.00
3996875154639None8.1 of Part III Utilization (PWD Electrical)Supplying and drawing UTP-CAT 6E LAN cable ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr34.034.060.0FalseNoneNoneFalseNoneFalse2040.00
3996876154639None2.3.2 of Part III Utilization (PWD Electrical)Wiring for lighting/power circuit using one of FRLS PVC insulated 1100V grade, multistrand Copper with low conductor resistance single core wire in open or concealed system of wiring. with specified IS-694:1990 & conforming to GTP 1.5 sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr26.026.0570.0FalseNoneNoneFalseNoneFalse14820.00
3996877154639None2.3.3 of Part III Utilization (PWD Electrical)Wiring for lighting/power circuit using one of FRLS PVC insulated 1100V grade, multistrand Copper with low conductor resistance single core wire in open or concealed system of wiring. with specified IS-694:1990 & conforming to GTP 2.5 sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr42.042.01140.0FalseNoneNoneFalseNoneFalse47880.00
3996878154639None2.3.4 of Part III Utilization (PWD Electrical)Wiring for lighting/power circuit using one of FRLS PVC insulated 1100V grade, multistrand Copper with low conductor resistance single core wire in open or concealed system of wiring. with specified IS-694:1990 & conforming to GTP 4 sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr63.063.02350.0FalseNoneNoneFalseNoneFalse148050.00
3996879154639None2.3.5 of Part III Utilization (PWD Electrical)Wiring for lighting/power circuit using one of FRLS PVC insulated 1100V grade, multistrand Copper with low conductor resistance single core wire in open or concealed system of wiring. with specified IS-694:1990 & conforming to GTP 6 sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr92.092.03000.0FalseNoneNoneFalseNoneFalse276000.00
3996880154639None3.10.3 of Part III Utilization (PWD Electrical)Extra for supplying 4mm thick white plastic plate and covering for junction boxes of size 110 mm conduit using necessary machine screws. 110mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No21.021.0616.0FalseNoneNoneFalseNoneFalse12936.00
3996881154639None1.13 of Part III Utilization (PWD Electrical)Supplying and Fixing Metal Fan Box with Round Hook. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No117.0117.0208.0FalseNoneNoneFalseNoneFalse24336.00
3996882154639None12.45 of Part III Utilization (PWD Electrical)Supplying & Fixing of 230 V 20/40 W Fluorescent Lamp holder ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each33.033.01045.0FalseNoneNoneFalseNoneFalse34485.00
3996883154639None11.15 of Part III Utilization (PWD Electrical)Supplying and fixing of LED Bulkhead of 10W with IP65 protection and IK 08 impact resistance suitable for surface and wall mounting applications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each842.0842.025.0FalseNoneNoneFalseNoneFalse21050.00
3996884154639None11.11.7 of Part III Utilization (PWD Electrical)Supplying & fixing of retrofit type - LED bulb . W with OPAL acrylic diffuser comprising of LED source with CCT 6500 degree K, CRI 70%. efficacy 80 lumen per W, life 25000 burning hours and Compliance to IS 10322/IEC 60598, LM 79 & LM 80. The LED are driven by HF electronic driver integrated in the system, with PF 0.95, power loss should 5% of lamp Wage., short circuit & open circuit protection to be integrated in the circuit, THD less than 20%, Life as per LM 79. The operating input voltage should be between 130 to 275 V. BIS Approved and Tested by NABL/CPRI accredited laboratory with 2 years Warranty against any manufacturing defect working under standard electrical condition. - 18W, 6500K ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No426.0426.0256.0FalseNoneNoneFalseNoneFalse109056.00
3996885154639None11.11.5 of Part III Utilization (PWD Electrical)Supplying & fixing of retrofit type - LED bulb . W with OPAL acrylic diffuser comprising of LED source with CCT 6500 degree K, CRI 70%. efficacy 80 lumen per W, life 25000 burning hours and Compliance to IS 10322/IEC 60598, LM 79 & LM 80. The LED are driven by HF electronic driver integrated in the system, with PF 0.95, power loss should 5% of lamp Wage., short circuit & open circuit protection to be integrated in the circuit, THD less than 20%, Life as per LM 79. The operating input voltage should be between 130 to 275 V. BIS Approved and Tested by NABL/CPRI accredited laboratory with 2 years Warranty against any manufacturing defect working under standard electrical condition. - 12W, 6500K ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No269.0269.0289.0FalseNoneNoneFalseNoneFalse77741.00
3996886154639None11.2.1 of Part III Utilization (PWD Electrical)Supplying & fixing retrofit type-PL- LED Lamp . W LED linear source with CCT 6500 degree K, CRI 70%. efficacy 80 lumen per W, life 25000 burning hours and Compliance to IS 10322/IEC 60598, LM 79 & LM 80. The LED are driven by HF electronic driver integrated in the system, with PF 0.95, power loss should 5% of lamp Wage., short circuit & open circuit protection to be integrated in the circuit, THD less than 20%, Life as per LM 79. The operating input voltage should be between 130 to275 V. Tested by NABL/CPRI accredited laboratory with 2 years Warranty against any manufacturing defect working under standard electrical condition. - 8-9 W ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No623.0623.054.0FalseNoneNoneFalseNoneFalse33642.00
3996887154639None11.3.32 of Part III Utilization (PWD Electrical)Supplying of .feet -PVC Batten with integrated LED tube . W with high quality diffuser with Life of 25000 burning hours & 70% lumen maintenance with CRI 80. Power Input: 220-240V@ 50/60Hz & Power factor 0.9 along with CE approved. 2 years Warranty against any manufacturing defect working under standard electrical condition. - LED light fitting 1 x 4' - 20/22 W ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each690.0690.0468.0FalseNoneNoneFalseNoneFalse322920.00
3996888154639None11.9.1 of Part III Utilization (PWD Electrical)Supply of LED floodlight luminaire with pressure die cast aluminium housing body for optimal thermal dissipation. Lamp compartment comprising of anti glare clear diffuser with Injection moulded polycarbonate/clear glass material, delivering superior light output Rated life Burning Hrs 50000 hr @ Lumen Maintenance of 70%, CCT 5500K, IP 66 optical and electrical compartment & impact resistance of complete luminaire IK08. Power Factor 0.9 with mains, Surge Protection- Min 5KV along with Over voltage/ Overload, short circuit/ miss-wiring protection. Compatible for pole mauling with outer dia of 40mm to 50mm. Universal voltage driver to operate wide voltage range from 100 V to 270V 50/60Hz application. Compliance to IS 10322/ IEC 60598, LM 79 & LM 80 Adherence with RoHS. UL approved MCPCB. Top access street light with single screw to ensure ease of maintenance at the sight site location with minimized minimal tools. LED Light fixture with . W System Power consumption. LED Efficiency 1301m/w, nominal CRI 75. Luminaire manufacturer should have in- house facility accredited by NABL / CPRI & any Government certified agency & Design & Development facility certified by ISO 9001:2008. Housing with supplier word mark / name shall be Engraved / Embossing on the die cast housing / Body part Warranty of 2 Years against any manufacturing defect working under standard electrical conditions as mentioned above should be given by LED manufacturer & Cree/Nichia/ Lumileds/Osram make LED Source. - LED Floodlight 70W ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each6768.06768.035.0FalseNoneNoneFalseNoneFalse236880.00
3996889154639None13.7.1 of Part III Utilization (PWD Electrical)Fixing all types and all capacities of fluorescent /false ceiling / spot light / CFL / LED fittings indoor on the wall/ ceiling / rafters / girders using 23/0.0076" twin twisted PVC insulated wires, required Nos of round blocks and clamps. - On wall / celilin / Rafter / Girders ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each122.0122.01092.0FalseNoneNoneFalseNoneFalse133224.00
3996890154639None13.5 of Part III Utilization (PWD Electrical)Fixing halogen/metal halide /SVL/IL/LED floodlight fitting over existing pole / wall ceiling including clamps, bolts, nuts and wiring using suitable capacity wires. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each162.0162.035.0FalseNoneNoneFalseNoneFalse5670.00
3996891154639None6.2.1 of Part III Utilization (PWD Electrical)Supplying of 1440rpm heavy duty exhaust fan bracket blades suitable to operate on 230V 50Hz, AC Supply complete.12"Sweep(300mm) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each2969.02969.0104.0FalseNoneNoneFalseNoneFalse308776.00
3996892154639None13.14 of Part III Utilization (PWD Electrical)Fixing one exhaust fan in the nitch already left in the wall with bolts and nuts and 5 amps ceiling rose with sufficient length of 23 / 0.0076 inch PVC insulated twin core wire of approved make. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each492.0492.0104.0FalseNoneNoneFalseNoneFalse51168.00
3996893154639None6.4.1 of Part III Utilization (PWD Electrical)Supplying of Ceiling Fan with Capacitor rating As per guideline of BEE 5 star rating and IS:374/19 and also comply with IS: 1709/1984 with latest amendment, rated voltage 220 V/50 Hz, Rated power upto 35 W +/- 10 %, Rated current As per IS:374/19, Rated power factor 0.9 lagging(min), Rated speed 350 +/- 10% RPM, rated air delivery 210 +/- 10% Cubic Meter Minimum, Rated service value 6.2 CMM / W, Three Blades of blade leaf 1.05 mm thick Aluminium Alloy sheet, Class B motor insulation, Bearing Two ball bearings, Top 6202, Bottom 6201, as per IS specification, Motor winding. Temp rise Shall not exceed 75 deg C over and ambient of 40 0C by resistance method at 245 V, Insulation resistance Shall not be less than Two Mega Ohms (2M Ohms), Leakage current Should not exceed 210 micro Amp, Power input, W& current, Air Delivery & Fan Speed as per IS:374/2019 with latest amendment, 2year manufacturer Warranty. (BLDC fans) - 48"" Sweep 5 Star (1200 mm) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each2677.02677.0208.0FalseNoneNoneFalseNoneFalse556816.00
3996894154639None13.10 of Part III Utilization (PWD Electrical)Fixing a ceiling/Wall mounting fan of all capacities and all types to the existing 'S' hook with fan regulator to the existing board together with supplying and fixing a 5 amps, ceiling rose, necessary length of 23 / 0.0076 inch PVC insulated twin twisted copper wire and wiring ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each171.0171.0208.0FalseNoneNoneFalseNoneFalse35568.00
3996895154639None5.6.5 of Part III Utilization (PWD Electrical)Supply and fixing polished wood board made of not less than 15mm thick plank on both sides of not more than 2 pieces and fixing the same to the wall using tapered inverted wooden plugs screws. - 15"" x 12"" x 2"" ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each201.0201.06.0FalseNoneNoneFalseNoneFalse1206.00
3996896154639None5.7.4 of Part III Utilization (PWD Electrical)Supplying & fixing of Porcelain fuse channel with cut out on existing wooden/panel using necessary nuts, bolts and washers. - 100A ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each691.0691.024.0FalseNoneNoneFalseNoneFalse16584.00
3996897154639None5.9.3 of Part III Utilization (PWD Electrical)Supplying and fixing HRC fuse units base on existing switch / panel board - 100 to 300A ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each919.0919.024.0FalseNoneNoneFalseNoneFalse22056.00
3996898154639None5.10.2 of Part III Utilization (PWD Electrical)Supplying and fixing HRC fuse link on existing switch fuse base with W loss as per IS-13703. - Above 63 A to 200 A ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each381.0381.024.0FalseNoneNoneFalseNoneFalse9144.00
3996899154639None5.42.2 of Part III Utilization (PWD Electrical)Fabricating supplying and mounting MS box made out 16 SWG suitable for floor / wall mounting, fully weather proof with provision for better heat dissipation, provided with hinged front cover, equipped with tamper proof locking arrangements, with suitable size clamps with necessary cable entry pipe with gland and box should be finished with 2 coats of red oxide primer paint and finally finished with approved colour enameled metal paint etc., complete. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sq CM0.430.43108000.0FalseNoneNoneFalseNoneFalse46440.00
3996900154639None5.40.1 of Part III Utilization (PWD Electrical)Supplying 100 amps rated 4x30x6mm Alluminium Strips 3phase with neutral bus bar using required capacity electrolytic alluminium strips covered with heat shrinkable coloured PVC sleeve, mounted on phenolic/FRP/DMC insulator which are mounted on powder coated 40x6mm M.S.flat frame work in existing MDB. The bus bar shall have suitable holes for termination of incoming and outgoing cables as per IS specification with necessary botls,nuts and washers etc., complete - 100 A 4 x 30 x 6 mm Aluminium Strips ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr2465.02465.024.0FalseNoneNoneFalseNoneFalse59160.00
3996901154639None3.9 of Part III Utilization (PWD Electrical)Supplying and fixing hylum plastic sheet 3mm thick with necessary nitches for fixing switches, regulators etc., and fixing on existing wood or metal box using N.F screws. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sq CM0.350.3527000.0FalseNoneNoneFalseNoneFalse9450.00
3996902154639None5.38 of Part III Utilization (PWD Electrical)Supplying and fixing of LED type panel board indicating lamp with required colour suitable for 220v A.C. 50 Hz 12/24v D.C. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each515.0515.020.0FalseNoneNoneFalseNoneFalse10300.00
3996903154639None5.31 of Part III Utilization (PWD Electrical)Supplying and fixing Electronic Trivector Meter (ETV) suitable for operation LT operation and -CT operated meter in polycarbonate body in class 0.5 accuracy as per IS 14697 and completely wired. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each4390.04390.05.0FalseNoneNoneFalseNoneFalse21950.00
3996904154639None5.30 of Part III Utilization (PWD Electrical)Supplying, fixing and wiring Electronic Trivector Meter (ETV) 5 to 20A single phase Class-1 Accuracy with Temper Proof Energy Meter ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1380.01380.08.0FalseNoneNoneFalseNoneFalse11040.00
3996905154639None5.21 of Part III Utilization (PWD Electrical)Supplying, fixing and wiring earth leakage relay with core balanced current transformer suitable for single phase 50 Hz AC with latest microcontroller based, digital readout of percentage leakage current, programmable delay/auto/ manual reset facility suitable to mount on DIN rail/ flush mounting on panel board. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each9255.09255.06.0FalseNoneNoneFalseNoneFalse55530.00
3996906154639None5.11.2 of Part III Utilization (PWD Electrical)Supplying of on load change over switches 4 poles, AC-23A Duty, 415V, 50Hz, AC Supply. (Open Execution) - 100A ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each7090.07090.05.0FalseNoneNoneFalseNoneFalse35450.00
3996907154639None5.15.9 of Part III Utilization (PWD Electrical)Supplying and fixing Moulded Case Circuit Breaker (MCCB) over the existing wood/panel board using necessary screws, bolts, nuts, necessary phase separators, handle and wiring complete. Protection of Overload and Short circuitwith adjustable thermal magnetic release, Micro processor release shall have Earth Fault as per IS/IEC 60947-2 . (Icu=100% lcs). In 4P MCCB, all Poles should have protection for Short-Cicrcuit/Over Load. For Microprocessor MCCBS Facility for segregating Priority and Non-Priority loads must be available in the MCCB. MCCB shall be provided with double insulation (insulation between front cover and internal power circuits to avoid any accidental contact with live current carrying path with the front cover open). Multi-pole breakers shall be designed to break all the poles simultaneously and they shall have a single mechanism. - 100A, 25kA, 4 Pole ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each8487.08487.06.0FalseNoneNoneFalseNoneFalse50922.00
3996908154639None5.16 of Part III Utilization (PWD Electrical)Supplying and fixing of Shunt trip suitable for MCCB.CBCT ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1703.01703.06.0FalseNoneNoneFalseNoneFalse10218.00
3996909154639None5.34 of Part III Utilization (PWD Electrical)Supplying, fixing and wiring 50/5 to 400/5A 5VA burden Current Transformer Class 0.5 accuracy with Tape Wound. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each562.0562.033.0FalseNoneNoneFalseNoneFalse18546.00
3996910154639None5.33 of Part III Utilization (PWD Electrical)Supplying of multi function digital meter with three line back light LCD type display for voltage, Current, frequency, Power, power factor, kVA, kWH, kVAR suitable for 3 phase, 4 wire LT network with IP 54 degree of protection and completely wired as required with communication Port and Class 0.5s accuracy ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each9315.09315.06.0FalseNoneNoneFalseNoneFalse55890.00
3996911154639None5.18.9 of Part III Utilization (PWD Electrical)Supplying and fixing miniature circuit breakers on existing MCB distribution boards using necessary fixing materials and 'C' Type curve , indicator ON/OFF, energy cross-3 with Short circuit breaking capacity of 10K and complete wiring as required. c) 63Amps TPN ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each3088.03088.023.0FalseNoneNoneFalseNoneFalse71024.00
3996912154639None5.18.4 of Part III Utilization (PWD Electrical)Supplying and fixing miniature circuit breakers on existing MCB distribution boards using necessary fixing materials and 'C' Type curve , indicator ON/OFF, energy cross-3 with Short circuit breaking capacity of 10K and complete wiring as required. c) 6 - 32Amps DP ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each739.0739.031.0FalseNoneNoneFalseNoneFalse22909.00
3996913154639None5.1 of Part III Utilization (PWD Electrical)Supplying push button operated direct online starter with an antiweld silver cadmium oxide contactor with replaceable fixed and moving contacts and bimetallic thermal overload relay help in anticorrosion treated sheet steel or iron clad enclosure and fixing the same to suitable capacity wires for 230/440 V 1/3 phase motor upto 5 HP ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1927.01927.011.0FalseNoneNoneFalseNoneFalse21197.00
3996914154639None5.19.13 of Part III Utilization (PWD Electrical)Supplying and fixing regular MCB distribution boards on wall / wood board / flush mounting using required clamps, bolts, nuts etc., with provision for fixing suitable type capacity MCB's single phase / 3 phase / single door with powder coated painting. Made out of 14 SWG MS enclosure. III- Double Door 12way TP & N ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each8735.08735.012.0FalseNoneNoneFalseNoneFalse104820.00
3996915154639None5.19.10 of Part III Utilization (PWD Electrical)Supplying and fixing regular MCB distribution boards on wall / wood board / flush mounting using required clamps, bolts, nuts etc., with provision for fixing suitable type capacity MCB's single phase / 3 phase / single door with powder coated painting. Made out of 14 SWG MS enclosure. III- Double Door 16way SP & N ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each2908.02908.08.0FalseNoneNoneFalseNoneFalse23264.00
3996916154639None5.18.9 of Part III Utilization (PWD Electrical)Supplying and fixing miniature circuit breakers on existing MCB distribution boards using necessary fixing materials and 'C' Type curve, indicator ON/OFF, energy cross-3 with Short circuit breaking capacity of 10K and complete wiring as required. 50-63Amps TPN ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each3088.03088.03.0FalseNoneNoneFalseNoneFalse9264.00
3996917154639None5.18.7 of Part III Utilization (PWD Electrical)Supplying and fixing miniature circuit breakers on existing MCB distribution boards using necessary fixing materials and 'C' Type curve , indicator ON/OFF, energy cross-3 with Short circuit breaking capacity of 10K and complete wiring as required. c) 5-32Amps TPN ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1717.01717.09.0FalseNoneNoneFalseNoneFalse15453.00
3996918154639None5.20.10 of Part III Utilization (PWD Electrical)Supplying, fixing and wiring Earth Leakage Miniature Circuit Breaker [ELMCB] 240/450V up to 300mA sensitivity on existing wood/panel board. - 63 A 4 pole ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each5147.05147.09.0FalseNoneNoneFalseNoneFalse46323.00
3996919154639None5.20.4 of Part III Utilization (PWD Electrical)Supplying, fixing and wiring Earth Leakage Miniature Circuit Breaker [ELMCB] 240/450V up to 300mA sensitivity on existing wood/panel board. - 32 to 40 Amps 2 pole ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each4559.04559.035.0FalseNoneNoneFalseNoneFalse159565.00
3996920154639None5.18.1 of Part III Utilization (PWD Electrical)Supplying and fixing miniature circuit breakers on existing MCB distribution boards using necessary fixing materials and 'C' Type curve , indicator ON/OFF, energy cross-3 with Short circuit breaking capacity of 10K and complete wiring as required. c) 5-32Amps SP ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each415.0415.0384.0FalseNoneNoneFalseNoneFalse159360.00
3996921154639None12.56 of Part III Utilization (PWD Electrical)Supplying, fixing, wiring, earth electrode for grounding conduits, I.C. cutouts and other equipment's on the meter board using 40 mm dia 2.90 mm thick GI pipe 2.5m long buried in a pit . The pit should be filled with equal proportion of salt and charcoal 150 mm all-round the pipe to complete depth. The connection from the pipe to the conduit etc., is to be established through GI wire of size as per lSI specification 7.3.3. of IS 732 using 12 mm dia bolts, nuts, washers and check nuts etc., the pipe shall have 16 through holes of 12 mm dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No3510.03510.012.0FalseNoneNoneFalseNoneFalse42120.00
3996922154639None32.18, of Standard Stock Material (11kV System) - Supplying of 1.1 kV, XLPE or Heat resistant PVC insulated, PVC exutruted Inner Seath Armoured LTUG Cable as per IS-1554 (Part1) or IS-7098 Part-1, Armouring strip thickness and resistivity as per IS-3975 - 3.5 core 240sqmm (2Runs) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr862.67862.67100.0FalseNoneNoneFalseNoneFalse86267.00
3996923154639None32.13, of Standard Stock Material (11kV System) - Supplying of 1.1 kV, XLPE or Heat resistant PVC insulated, PVC exutruted Inner Seath Armoured LTUG Cable as per IS-1554 (Part1) or IS-7098 Part-1, Armouring strip thickness and resistivity as per IS-3975 - 3.5 core 70sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr317.91317.91670.0FalseNoneNoneFalseNoneFalse212999.70
3996924154639None32.07, of Standard Stock Material (11kV System) - Supplying of 1.1 kV, XLPE or Heat resistant PVC insulated, PVC exutruted Inner Seath Armoured LTUG Cable as per IS-1554 (Part1) or IS-7098 Part-1, Armouring strip thickness and resistivity as per IS-3975 - 3.5core 25sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr139.55139.5560.0FalseNoneNoneFalseNoneFalse8373.00
3996925154639None32.03, of Standard Stock Material (11kV System) - Supplying of 1.1 kV, XLPE or Heat resistant PVC insulated, PVC exutruted Inner Seath Armoured LTUG Cable as per IS-1554 (Part1) or IS-7098 Part-1, Armouring strip thickness and resistivity as per IS-3975 4core 10sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr20.8920.8940.0FalseNoneNoneFalseNoneFalse835.60
3996926154639None21.06, of Labour Charges (11kV System) - Part II DLabour charges for laying of 1.1 KV class UG cable in existing trench GI pipe / stoneware pipe / on wall / on pole as required - In exixting trench/duct. 35 sqmm to 95 sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr31.1431.14670.0FalseNoneNoneFalseNoneFalse20863.80
3996927154639None21.07, of Labour Charges (11kV System) - Part II DLabour charges for laying of 1.1 KV class UG cable in existing trench GI pipe / stoneware pipe / on wall / on pole as required - In exixting trench/duct. 120 to 240 Sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr32.2832.28100.0FalseNoneNoneFalseNoneFalse3228.00
3996928154639None1.6.1Earth work excavation for pipelines/cables by Manual means upto 600 mm trench width, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter, including dressing of excavated surfaces, disposing off or leveling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m. Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering and lift upto 1.5 m including cost of labour, tools, usage& other appurtenances required to complete the work. In all kinds of soils. Depth upto 1.50m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum484.0484.054.0FalseNoneNoneFalseNoneFalse26136.00
3996929154639None11.2.6Providing, Laying and Fixing of GI pipes conforming to IS 1239:1990 with latest amendments complete with GI fittings (excluding the cost of fittings) with cuts and threads wherever necessary, including testing for water tightness, with all lead and commissioning. (contractor will make his own arrangements for procuring water for testing) For:Heavy Duty GI Pipe etc. complete. Medium Duty GI pipe of 50mm dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr584.0584.060.0FalseNoneNoneFalseNoneFalse35040.00
3996930154639None30.12, of Major Work Materials- Equipments (Part Supplying and fixing of class B (medium duty) GI pipe of wall thickness not less than 3.25mm on pole/wall/drain crossing with necessary clamping arrangements for UG cable of 1.1 KV class - 100 mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr1350.01350.0200.0FalseNoneNoneFalseNoneFalse270000.00
3996931154639None35.04, of Standard Stock Material (11kV System) - Supplying and fixing Epoxy Terminating Kit (Pothead) suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 3.5 x 225/240/300 Sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each588.0588.02.0FalseNoneNoneFalseNoneFalse1176.00
3996932154639None35.02, of Standard Stock Material (11kV System) - Supplying and fixing Epoxy Terminating Kit (Pothead) suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 3.5 x 70/95/120 Sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each382.0382.012.0FalseNoneNoneFalseNoneFalse4584.00
3996933154639None35.01, of Standard Stock Material (11kV System) - Supplying and fixing Epoxy Terminating Kit (Pothead) suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - Up to 4C x 50 Sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each324.0324.014.0FalseNoneNoneFalseNoneFalse4536.00
3996934154639None59.10, of Standard Stock Material (11kV System) - Supplying and fixing Heavy Duty Copper Terminal Long Barrel suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 240 Sqmm Copper Terminal, Apprx Wt: 218 Gm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each355.0355.012.0FalseNoneNoneFalseNoneFalse4260.00
3996935154639None59.06, of Standard Stock Material (11kV System) - Supplying and fixing Heavy Duty Copper Terminal Long Barrel suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 120 Sqmm Copper Terminal, Apprx Wt: 64 Gm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each140.0140.06.0FalseNoneNoneFalseNoneFalse840.00
3996936154639None59.04, of Standard Stock Material (11kV System) - Supplying and fixing Heavy Duty Copper Terminal Long Barrel suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 70 Sqmm Copper Terminal, Apprx Wt: 38 Gm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each89.089.036.0FalseNoneNoneFalseNoneFalse3204.00
3996937154639None59.02, of Standard Stock Material (11kV System) - Supplying and fixing Heavy Duty Copper Terminal Long Barrel suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 35 Sqmm Copper Terminal, Apprx Wt: 17 Gm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each40.040.012.0FalseNoneNoneFalseNoneFalse480.00
3996938154639None59.01, of Standard Stock Material (11kV System) vSupplying and fixing Heavy Duty Copper Terminal Long Barrel suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 25 Sqmm Copper Terminal, Apprx Wt: 11 Gm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each27.027.048.0FalseNoneNoneFalseNoneFalse1296.00
3996939154639None60.12, of Standard Stock Material (11kV System) - Supplying and fixing Aluminium End Terminal (Lug) suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 240 Sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each61.061.012.0FalseNoneNoneFalseNoneFalse732.00
3996940154639None60.08, of Standard Stock Material (11kV System) - Supplying and fixing Aluminium End Terminal (Lug) suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 120 Sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each20.020.06.0FalseNoneNoneFalseNoneFalse120.00
3996941154639None60.06, of Standard Stock Material (11kV System) - Supplying and fixing Aluminium End Terminal (Lug) suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 70 Sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each13.013.036.0FalseNoneNoneFalseNoneFalse468.00
3996942154639None60.04, of Standard Stock Material (11kV System) - Supplying and fixing Aluminium End Terminal (Lug) suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 35 Sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each4.04.012.0FalseNoneNoneFalseNoneFalse48.00
3996943154639None60.03, of Standard Stock Material (11kV System) - Supplying and fixing Aluminium End Terminal (Lug) suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 25 Sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each3.03.036.0FalseNoneNoneFalseNoneFalse108.00
3996944154639None60.02, of Standard Stock Material (11kV System) - Supplying and fixing Aluminium End Terminal (Lug) suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 16 Sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each2.02.012.0FalseNoneNoneFalseNoneFalse24.00
3996945154639None60.01, of Standard Stock Material (11kV System) - Supplying and fixing Aluminium End Terminal (Lug) suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 10 Sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each2.02.08.0FalseNoneNoneFalseNoneFalse16.00
3996946154639None63.01, of Standard Stock Material (11kV System) - Supplying and fixing Brass Cable Gland suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 25mm dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each79.079.014.0FalseNoneNoneFalseNoneFalse1106.00
3996947154639None63.03, of Standard Stock Material (11kV System) - Supplying and fixing Brass Cable Gland suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 40mm dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each148.0148.012.0FalseNoneNoneFalseNoneFalse1776.00
3996948154639None63.04, of Standard Stock Material (11kV System) - Supplying and fixing Brass Cable Gland suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 45mm dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each197.0197.04.0FalseNoneNoneFalseNoneFalse788.00
3996949154639None12.58.5 of Part III Utilization (PWD Electrical)Supplying and running of GI/Copper strips for grounding connections, using necessary fixing materials as required. GI Strip 50 x 6 ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr218.0218.0150.0FalseNoneNoneFalseNoneFalse32700.00
3996950154639None12.58.4 of Part III Utilization (PWD Electrical)Supplying and running of GI/Copper strips for grounding connections, using necessary fixing materials as required. GI Strip 40 x 6 ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr181.0181.050.0FalseNoneNoneFalseNoneFalse9050.00
3996951154639None12.58.3 of Part III Utilization (PWD Electrical)Supplying and running of GI/Copper strips for grounding connections, using necessary fixing materials as required. GI Strip 25x6mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr128.0128.0350.0FalseNoneNoneFalseNoneFalse44800.00
3996952154639None12.58.2 of Part III Utilization (PWD Electrical)Supplying and running of GI/Copper strips for grounding connections, using necessary fixing materials as required. GI Strip 25x3mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr82.082.0350.0FalseNoneNoneFalseNoneFalse28700.00
3996953154639None8.02 of Standard Stock Material (11kV System) - PaSupplying and running GI/Copper conductor for grounding and (along with other wires in conduit systm of wiring) using necessary suitable size clamps, nails, guttas/spacers etc. GI Wire 8SWG ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr9.839.83410.0FalseNoneNoneFalseNoneFalse4030.30
3996954154639None19.3, of Major Work Materials - Equipments (Part ISupplying and fixing of DANGER / CAUTION board ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos318.0318.06.0FalseNoneNoneFalseNoneFalse1908.00
3996955154639None5.37, of Part III Utilization (PWD Electrical)Suplying fixing and wiring heavy duty low voltage capacitors conforming to IS 2834. 3 phase, 400/400 volts grade, for power factor improvement of roating machinery. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kvar480.0480.027.0FalseNoneNoneFalseNoneFalse12960.00
3996956154639None5.3, of Part III Utilization (PWD Electrical)Supplying and fixing single phase preventer using necessary wires over an existing panel board suitable for motor up to 20HP capacities. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each904.02904.023.0FalseNoneNoneFalseNoneFalse2712.060
3996957154639None5.6.6, of Part III Utilization (PWD Electrical)Supply and fixing polished wood board made of not less than 15mm thick plank on both sides of not more than 2 pieces and fixing the same to the wall using tapered inverted wooden plugs screws. - 20"x20"x2.5" k)Sump Tank & RWH ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each326.13326.132.0FalseNoneNoneFalseNoneFalse652.260
3996958154639None5.1 of Part III Utilization (PWD Electrical)Supplying push button operated direct online starter with an antiweld silver cadmium oxide contactor with replaceable fixed and moving contacts and bimetallic thermal overload relay help in anticorrosion treated sheet steel or iron clad enclosure and fixing the same to suitable capacity wires for 400/440 volts 3 phase motor/single phase motor upto 5 Hp. k)Sump Tank ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1927.01927.06.0FalseNoneNoneFalseNoneFalse11562.00
3996959154639None15.117 of Part III Utilization (PWD Electrical)Supplying and installation of RUBBER MAT 1mtr x 1mtr -1Omm thick. complete including cost of materials, labour, usage charges of machinery complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1900.01900.023.0FalseNoneNoneFalseNoneFalse43700.00
3996960154639None15.117 of Part III Utilization (PWD Electrical)Supplying and installation of RUBBER MAT 1mtr x 1mtr -1Omm thick. complete including cost of materials, labour, usage charges of machinery complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1900.01900.023.0FalseNoneNoneFalseNoneFalse43700.00
3996961154639None1.Materia l RateMonoblock Pump set 3HP 3Phase 21 Stage 3/2.2 ATALANTA / SUGUNA / C.R.I, KIRLOSKAR and other Equivalent Pumps(XXXXV) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos16800.016800.03.0FalseNoneNoneFalseNoneFalse50400.00
3996962154639None32.03, of Standard Stock Material (11kV System) - Supplying of 1.1 kV, XLPE or Heat resistant PVC insulated, PVC exutruted Inner Seath Armoured LTUG Cable as per IS-1554 (Part1) or IS-7098 Part-1, Armouring strip thickness and resistivity as per IS-3975 4core 10sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr118.0118.040.0FalseNoneNoneFalseNoneFalse4720.00
17262057300000NoneNoneBuildings11KV Line (Shivani)463100.5
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3996963154640None21.08, of Standard Stock Material (11kV System) - Supply and erection of Double Pole TC structural set including all hardwares suitable for 100/300 kVA 4/5 Star Rated Transformer on RCC Pole - 9 Mtr Long, 145 Kg WL - GI ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each30694.030694.01.0FalseNoneNoneFalseNoneFalse30694.00
3996964154640None24.07, of Standard Stock Material (11kV System) - Supplying and Fixing H - Frame Set for fixing 11 kV, 200 Amps Single Break GOS - (For DP structure for providing New GOS for sectionalisation) - GI ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each6071.06071.01.0FalseNoneNoneFalseNoneFalse6071.00
3996965154640None24.01, of Standard Stock Material (11kV System) - Supplying and Fixing …. including all Hardwares etc complete as per the standard technical specification.of BESCOM - 11 kV, 200 Amps Single Break GOS ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each9450.09450.01.0FalseNoneNoneFalseNoneFalse9450.00
3996966154640None20.01, of Standard Stock Material (11kV System) - Supplying and Fixing …. including all Hardwares etc complete as per the standard technical specification.of BESCOM - 11 kV, HG Fuse Unit with Solid Core Insulator ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1069.01069.01.0FalseNoneNoneFalseNoneFalse1069.00
3996967154640None19.02, of Standard Stock Material (11kV System) - Supplying and Fixing …. including all Hardwares etc complete as per the standard technical specification of BESCOM. - 10 kV, 5 kA Lightning Arrester Polymeric type with GROUND DISCONNECTOR ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1584.01584.01.0FalseNoneNoneFalseNoneFalse1584.00
3996968154640None1.02, of Standard Stock Material (11kV System) - PSupply and erection of 9 Mtr RCC Pole including earth work etc,. complete as per the standard technical specification of BESCOM. RCC Pole - 9 Mtr Long, 150 Kg WL Sq Section ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each8316.08316.033.0FalseNoneNoneFalseNoneFalse274428.00
3996969154640None2.02, of Standard Stock Material (11kV System) - PSupply and fixing of …….cross arm including all Hardwares complete as per the standard technical specification BESCOM - 11 kV, Horizontal Cross Arm - Galvanised Iron (GI) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each487.0487.033.0FalseNoneNoneFalseNoneFalse16071.00
3996970154640None2.12, of Standard Stock Material (11kV System) - PSupplying and Fixing …. including all Hardwares etc complete as per the standard technical specification BESCOM - HT ST Support 50x8 mm Flat - GI ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each121.0121.033.0FalseNoneNoneFalseNoneFalse3993.00
3996971154640None2.04, of Standard Stock Material (11kV System) - PSupplying and Fixing …. including all Hardwares etc complete as per the standard technical specification BESCOM - 11 kV, Special 3 Pin Cross Arm - GI ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1151.01151.04.0FalseNoneNoneFalseNoneFalse4604.00
3996972154640None5.02, of Standard Stock Material (11kV System) - PSupplying and Fixing …. including all Hardwares etc complete as per the standard technical specification - RCC Pole Clamp - GI ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each109.0109.033.0FalseNoneNoneFalseNoneFalse3597.00
3996973154640None9.03, of Standard Stock Material (11kV System) - PSupplying and fixing of P.G Clamp inluding all Hardware's etc. complete as per the standard technical specification of BESCOM ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each86.086.033.0FalseNoneNoneFalseNoneFalse2838.00
3996974154640None5.16, of Standard Stock Material (11kV System) - PSupplying and Fixing Strain Clamp, 3 Bolt type for 70/90 kN Disc Insulator including all Hardwares etc complete as per the standard technical specification of BESCOM ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each707.0707.018.0FalseNoneNoneFalseNoneFalse12726.00
3996975154640None6.06, of Standard Stock Material (11kV System) - PSupplying and Fixing ….including all Hardwares etc complete as per the standard technical specification BESCOM - 11 kV, 5 kN Composite/Polymeric Pin Insulator (24 mm dia FRP Rod) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each205.0205.090.0FalseNoneNoneFalseNoneFalse18450.00
3996976154640None5.10,5.11,5.13,5.15, 5.16 & 8.02 of Standard StockSupplying and Fixing …. including all Hardwares etc complete as per the standard technical specification BESCOM - GUY Set ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1628.451628.4510.0FalseNoneNoneFalseNoneFalse16284.50
3996977154640None2.16, of Labour Charges (11kV System) - Part II DiProviding Spiral Earth Electrode type earthing (without charcoal, salt etc.,) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each93.093.033.0FalseNoneNoneFalseNoneFalse3069.00
3996978154640None2.06 of Standard Stock Material (11kV System) - PaSupply and fixing of …….cross arm including all Hardwares complete as per the standard technical specification BESCOM - LT 4 Pin Cross Arm - GI ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each379.0379.04.0FalseNoneNoneFalseNoneFalse1516.00
3996979154640None7.02 of Standard Stock Material (11kV System) - PaSupplying and fixing of Rabbit ACSR (6/3.35 mm Al + 1/3.35 mm St), Std Wt: 214 Kg/KM ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr46.2346.231200.0FalseNoneNoneFalseNoneFalse55476.00
3996980154640None6.08 of Standard Stock Material (11kV System) - PaSupplying and Fixing ….including all Hardwares etc complete as per the standard technical specification BESCOM - No. 15 Strain Insulator ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each59.059.020.0FalseNoneNoneFalseNoneFalse1180.00
17262057300000NoneNoneBuildingsEstablishing Sub Station (Shivani)1816176.0
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3996981154641None21.08, of Standard Stock Material (11kV System) - Supply and erection of Double Pole TC structural set including all hardwares suitable for 100/300 kVA 4/5 Star Rated Transformer on RCC Pole - 9 Mtr Long, 145 Kg WL - GI ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each30694.030694.01.0FalseNoneNoneFalseNoneFalse30694.00
3996982154641None24.07, of Standard Stock Material (11kV System) - Supplying and Fixing H - Frame Set for fixing 11 kV, 200 Amps Single Break GOS - (For DP structure for providing New GOS for sectionalisation) - GI ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each6071.06071.01.0FalseNoneNoneFalseNoneFalse6071.00
3996983154641None2.12, of Standard Stock Material (11kV System) - PSupplying and Fixing …. including all Hardwares etc complete as per the standard technical specification BESCOM - HT ST Support 50x8 mm Flat - GI ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each121.0121.04.0FalseNoneNoneFalseNoneFalse484.00
3996984154641None2.02, of Standard Stock Material (11kV System) - PSupply and fixing of …….cross arm including all Hardwares complete as per the standard technical specification BESCOM - 11 kV, Horizontal Cross Arm - Galvanised Iron (GI) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each487.0487.02.0FalseNoneNoneFalseNoneFalse974.00
3996985154641None24.01, of Standard Stock Material (11kV System) - Supplying and Fixing …. including all Hardwares etc complete as per the standard technical specification.of BESCOM - 11 kV, 200 Amps Single Break GOS ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each9450.09450.01.0FalseNoneNoneFalseNoneFalse9450.00
3996986154641None20.01, of Standard Stock Material (11kV System) - Supplying and Fixing …. including all Hardwares etc complete as per the standard technical specification.of BESCOM - 11 kV, HG Fuse Unit with Solid Core Insulator ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1069.01069.01.0FalseNoneNoneFalseNoneFalse1069.00
3996987154641None19.02, of Standard Stock Material (11kV System) - Supplying and Fixing …. including all Hardwares etc complete as per the standard technical specification of BESCOM. - 10 kV, 5 kA Lightning Arrester Polymeric type with GROUND DISCONNECTOR ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1584.01584.01.0FalseNoneNoneFalseNoneFalse1584.00
3996988154641None5.16, of Standard Stock Material (11kV System) - PSupplying and Fixing Strain Clamp, 3 Bolt type for 70/90 kN Disc Insulator including all Hardwares etc complete as per the standard technical specification of BESCOM ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each707.0707.06.0FalseNoneNoneFalseNoneFalse4242.00
3996989154641None6.06, of Standard Stock Material (11kV System) - PSupplying and Fixing ….including all Hardwares etc complete as per the standard technical specification BESCOM - 11 kV, 5 kN Composite/Polymeric Pin Insulator (24 mm dia FRP Rod) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each205.0205.03.0FalseNoneNoneFalseNoneFalse615.00
3996990154641None1.02, of Standard Stock Material (11kV System) - PSupply and erection of 9 Mtr RCC Pole including earth work etc,. complete as per the standard technical specification of BESCOM. RCC Pole - 9 Mtr Long, 150 Kg WL Sq Section ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each8316.08316.02.0FalseNoneNoneFalseNoneFalse16632.00
3996991154641None5.10,5.11,5.13,5.15, 5.16 & 8.02 of Standard StockSupplying and Fixing …. including all Hardwares etc complete as per the standard technical specification BESCOM - GUY Set ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1628.451628.452.0FalseNoneNoneFalseNoneFalse3256.90
3996992154641None12.57, of Part III Utilization (PWD Electrical)Supplying fixing and wiring earth electrode for grounding of lifts, transformers, DG sets etc. using 40 mm dia 2.9 mm thick 2.5m long GI pipe with GI funnel with mesh and suitable size reducer fixed on the top of the earth electrode.The funnel should be enclosed in a CC chamber of 400x400x400 mm with a cast iron cover. The earth electrode shall have staggered holes of 12 mm dia and the electrode should be covered 150 mm all-round with alternate layers of salt and charcoal from the bottom of the CC chamber. The connection from the electrode is to be established through GI strip using GI bolts and nuts ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos4256.04256.08.0FalseNoneNoneFalseNoneFalse34048.00
3996993154641None30.12, of Major Work Materials Equipments (Part Supplying and fixing of class B GI pipe on pole/wall/drain crossing with necessary clamping arrangements for UG cable of 1.1 KV class - 100 mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr1350.01350.015.0FalseNoneNoneFalseNoneFalse20250.00
3996994154641None25.02, of Standard Stock Material (11kV System) -Supplying and fixing of 11 kV, DOLO Cutout REC Specification(Dwg No. BESCOM/GM/QS&S/20 Dtd 24.11.2018) on pole/wall/drain crossing with necessary clamping arrangements for UG cable of 1.1 KV class ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Set4241.04241.03.0FalseNoneNoneFalseNoneFalse12723.00
3996995154641None45.07, of Standard Stock Material (11kV System) -Supplying and making 11KV (E) Extruded "X" linked for tubing & moulded & cross-linked components using Heat Shrink Stress Control tube having High Permittivity XLPE Terminations- INDOOR & OUTDOOR JOINTING KIT & conforming to th GTP. OUTDOOR 3cx95sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kit4067.04067.02.0FalseNoneNoneFalseNoneFalse8134.00
3996996154641None45.04, of Standard Stock Material (11kV System) -Supplying and making 11KV (E) Extruded "X" linked for tubing & moulded & cross-linked components using Heat Shrink Stress Control tube having High Permittivity XLPE Terminations- INDOOR & OUTDOOR JOINTING KIT & conforming to th GTP.INDOOR 3cx95sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kit3744.03744.02.0FalseNoneNoneFalseNoneFalse7488.00
3996997154641None36.01, of Standard Stock Material (11kV System) -HT Cable - Supplying and laying of high tension 11KV cable, Dry Curing & Dry Cooling with true triple extrusion, simultaneously through a single common head, 3 core under ground XLPE (E) cable having stranded comapact circular aluminium conductor, screened insulated, insulation screened with extruded semiconduting compound in combination with copper tape, core laid up inner sheate of PVC tape GI flat strip armoured and overall PVC sheathed with specified IS 7098/11/85 with latest amendments of conforming to the GTP . 3 Core x 95 Sqmm, (54 GI Wires - 2.5 mm Dia) (2 Runs) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr889.67889.6750.0FalseNoneNoneFalseNoneFalse44483.50
3996998154641None12.16, of Standard Stock Material (11kV System) -Supply,erection, testing and commissioning of Distribution Transformer - 3 Phase, 11kV/433V - Stacked CRGO Core with Oil as per IS-1180 (Part-1): 2014 tap switch Butchholtz relay winding Temperature indicator, oil temperature indicator, marshalling box with wiring, magnetic oil level indicator with +5% to-10% Steps of 2.5% with HT and LT cable and boxes including all standard accessories as per latest IS Standard Technical Specification. - 100 kVA, Aluminium Wdg, Star 2 (5 Star) with cable entry type ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each225576.0225576.01.0FalseNoneNoneFalseNoneFalse225576.00
3996999154641None11.59Providing and fixing G.I. chain link fabric fencing of required width in mesh size 50x50 mm including strengthening with 2 mm dia wire or nuts, bolts and washers as required complete as per the direction of Engineerin- charge. (Made of G.I. wire of dia. 4 mm, PVC coated to achieve outer dia not less than 5 mm in required colour and shade) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm841.0841.093.6FalseNoneNoneFalseNoneFalse78717.60
3997000154641None37.4Providing and fixing M.S.Block pipe of 38mm dia, of heavy guage of 14 including removing the bends, cutting the pipe and fixing pipe in between the existing two verticle poles (M.S rectangular poles) and spot welding the chain link with M.S block pipe including cost of all materials wastage in cutting, and scaffolding wherever necessary with all lead and lifts as directed by the Engineer-in-charge of eork etc.,complete including two coats of approved quality paint over one coat of shop paint.(Top Length 10+8+10+8=36& Bottom Length 10+8+10+8=36=72) (PW,P & IWTD, North Zone, Dharwad Circle 2016-17, Page No 262 , Item No.37.4) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m322.0322.072.0FalseNoneNoneFalseNoneFalse23184.00
3997001154641None1, of Civil works - Part IV)Jelly Spreading (20-25 mm) : Supplying and providing jelly in the station yard of uniform thickness of 100 mm including the cost of materials, labour charges, required tools and plants etc., complete. Work shall be carried out as per the instructions of Engineer- in-charge of works as per the standard procedure. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum1773.01773.08.0FalseNoneNoneFalseNoneFalse14184.00
3997002154641None51.5.2, of Major Work Materials - Equipments (PartSupplying and installing of CO2 -4-5 Kgs capacity Fire Extinguishers ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each8691.08691.01.0FalseNoneNoneFalseNoneFalse8691.00
3997003154641None15.111 of Part III Utilization (PWD Electrical)Supplying of four bucket stand alongwith buckets. Complete ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1850.01850.01.0FalseNoneNoneFalseNoneFalse1850.00
3997004154641None15.113 of Part III Utilization (PWD Electrical)Supplying of Rubber HAND GLOVES ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Pair975.0975.01.0FalseNoneNoneFalseNoneFalse975.00
3997005154641None15.116 of Part III Utilization (PWD Electrical)Supplying of FIRST AID CHART with lamination. Complete ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each400.0400.01.0FalseNoneNoneFalseNoneFalse400.00
3997006154641None35.50, of Major Work Materials - Equipments (Part 11 KV Hickery rod set ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Seedl5399.05399.01.0FalseNoneNoneFalseNoneFalse5399.00
3997007154641None35.51, of Major Work Materials - Equipments (Part Grounding sticks extendable upto 18 ft : 3 nos. of each 6 ft Sticks of 3 phase R, Y, B (3 nos. of 1 set) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Set1755.01755.01.0FalseNoneNoneFalseNoneFalse1755.00
3997008154641None15.114 of Part III Utilization (PWD Electrical)Supplying of first aid box. complete ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each600.0600.01.0FalseNoneNoneFalseNoneFalse600.00
3997009154641None19.3, of Major Work Materials - Equipments (Part )Supplying and fixing of DANGER / CAUTION board ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each318.0318.06.0FalseNoneNoneFalseNoneFalse1908.00
3997010154641None15.117 of Part III Utilization (PWD Electrical)Supplying and installation of RUBBER MAT 1mtr x 1mtr -1Omm thick. complete including cost of materials, labour, usage charges of machinery complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1900.01900.02.0FalseNoneNoneFalseNoneFalse3800.00
3997011154641None1.6.1Earth work excavation for pipelines/cables by Manual means upto 600 mm trench width, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, removal of stumps and other deleterious matter, including dressing of excavated surfaces, disposing off or leveling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m. Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering and lift upto 1.5 m including cost of labour, tools, usage& other appurtenances required to complete the work. In all kinds of soils. Depth upto 1.50m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum484.0484.019.5FalseNoneNoneFalseNoneFalse9438.00
3997012154641None2.16, of Labour Charges (11kV System) - Part II DiProviding Spiral Earth Electrode type earthing (without charcoal, salt etc.,) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each93.093.04.0FalseNoneNoneFalseNoneFalse372.00
3997013154641None12.58.5 of Part III Utilization (PWD Electrical)Supplying and running of GI/Copper strips for grounding connections, using necessary fixing materials as required. GI Strip 50 x 6 ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr218.0218.0300.0FalseNoneNoneFalseNoneFalse65400.00
3997014154641None40.02, of Standard Stock Material (11kV System) - DAS Specification Compact RMU (VCB/SF6 Type) as per IEC-62271 The DAS RMUs shall have the following in addition to the Standards: - DC motors, Numerical Relays, Multifunctional meters, fault passage indicator (FPI), Metering CTs, Protection CTs, Auxiliary transformers, Potential transformer, Batteries, Battery chargers (12 V & 24 V), AC power socket and light for illumination of Control panel. Control cable from each panel shall be wired and terminated to suitable 24 pin connector in the control panel. - Suitable space for fixing the Remote Terminal Unit (RTU) and Radio Modem in Control panel. - Suitable Clamps for fixing antenna Pipe - 4 Way RMU, 2OD + 2VL (One Incomer + Two Breakers + One Outgoing) 630 Amps with Copper Busbar ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1079188.01079188.01.0FalseNoneNoneFalseNoneFalse1079188.00
3997015154641None18.01, of Standard Stock Material (11kV System) - LT Distribution Box for 100 kVA DTC with MCCB's (Sheet Metal) (Dwg No. BESCOM/GM/QS&S/58 Dtd 24.11.2018) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each22686.022686.01.0FalseNoneNoneFalseNoneFalse22686.00
3997016154641None30.02, of Standard Stock Material (11kV System) - LT Feeder Pillar - 12 Way with Poreclain Rewireable Cutout and & 1 No of 630 Amps Load Break Switch with Copper Busbar asper IS-13947 Part-1&2(Dwg No. BESCOM/GM/QS&S/41 Dtd 24.11.2018) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each62543.062543.01.0FalseNoneNoneFalseNoneFalse62543.00
3997017154641None45.16, of Standard Stock Material (11kV System) - Heat Shrinkable Straight Through Jointing Kit for XLPE Cable with Copper Lug & Al Ferrule - 3x95 Sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each7311.07311.01.0FalseNoneNoneFalseNoneFalse7311.00
17262057300000NoneNoneBuildingsStreet Lights (Shivani)711732.5
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3997018154642None1.03, of Standard Stock Material (11kV System) - PSupply of 8Mtr RCC Pole including earth work etc,. complete as per the standard technical specification BESCOM - b) 8Mtr 115Kg WL ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each5129.05129.025.0FalseNoneNoneFalseNoneFalse128225.00
3997019154642None2.01, of Labour Charges (11kV System) - Part II DiErection of RCC/PSCC Pole of 7.5 to 8 Mtr long in a pit of 1.5 Mtr depth ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each922.0922.025.0FalseNoneNoneFalseNoneFalse23050.00
3997020154642None2.06 of Standard Stock Material (11kV System) - PaSupply and fixing of …….cross arm including all Hardwares complete as per the standard technical specification BESCOM - LT 4 Pin Cross Arm - GI ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each379.0379.025.0FalseNoneNoneFalseNoneFalse9475.00
3997021154642None2.08 of Standard Stock Material (11kV System) - PaSupply and fixing of …….cross arm including all Hardwares complete as per the standard technical specification BESCOM. b) 2 Pin GI ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each173.0173.025.0FalseNoneNoneFalseNoneFalse4325.00
3997022154642None5.02, of Standard Stock Material (11kV System) - PSupplying and Fixing …. including all Hardwares etc complete as per the standard technical specification - RCC Pole Clamp - GI ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each109.0109.050.0FalseNoneNoneFalseNoneFalse5450.00
3997023154642None5.10,5.11,5.13,5.15, 5.16 & 8.02 of Standard StockSupplying and Fixing …. including all Hardwares etc complete as per the standard technical specification BESCOM - GUY Set ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1628.451628.4510.0FalseNoneNoneFalseNoneFalse16284.50
3997024154642None6.05 of Standard Stock Material (11kV System) - PaSupplying and Fixing ….including all Hardwares etc complete as per the standard technical specification. 1.1 kV Polymeric Pin Insulator ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each87.087.0100.0FalseNoneNoneFalseNoneFalse8700.00
3997025154642None6.07 of Standard Stock Material (11kV System) - PaSupplying and Fixing ….including all Hardwares etc complete as per the standard technical specification BESCOM - No. 8 Strain Insulator ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each27.027.030.0FalseNoneNoneFalseNoneFalse810.00
3997026154642None42.08 of Standard Stock Material (11kV System) - P1.1 kV, LT Aerial Bunched Cable, XLPE insulation confirming to IS-14255: 1995 3x16 + 1x25 + 1x16 Sqmm Street light (Insulated Messenger cum Neutral) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr108.77108.771650.0FalseNoneNoneFalseNoneFalse179470.50
3997027154642None2.16, of Labour Charges (11kV System) - Part II DiProviding Spiral Earth Electrode type earthing (without charcoal, salt etc.,) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each93.093.025.0FalseNoneNoneFalseNoneFalse2325.00
3997028154642None1.1.2 of Part III Utilization (PWD Electrical)Open Conduit System Supplying heavy gauge PVC conduit pipe 25mm dia 2mm thick confirming to IS 2509 with suitable size bends, junction boxes, adhesive paste etc., and fixing using inverted wood plugs in case of RCC ceiling and RCC wall / stone structure or rawl plugs in case of brick walls and cement plastering the damaged portion using heavy gauge saddles at an interval of 700mm using NF screws. 19/20mm dia 2mm thick. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr81.081.0250.0FalseNoneNoneFalseNoneFalse20250.00
3997029154642None2.3.4 of Part III Utilization (PWD Electrical)Wiring for lighting/power circuit using one of FRLS PVC insulated 1100V grade, multistrand Copper with low conductor resistance single core wire in open or concealed system of wiring. with specified IS-694:1990 & conforming to GTP 4 sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr63.063.0750.0FalseNoneNoneFalseNoneFalse47250.00
3997030154642None11.8.3 of Part III Utilization (PWD Electrical)Supply of LED Streetlight luminaire with pressure die cast aluminium housing body for optimal thermal dissipation. Lamp compartment comprising of anti glare clear diffuser with Injection moulded polycarbonate material, delivering superior light output Rated life Burning Hrs 50000 hr @ Lumen Maintenance of 70%, maximum light intensity should be between 60 degrees to 70 degrees. CCT 5500K, IP66 optical and electrical compartment & impact resistance of complete luminaire IK08. Power Factor 0.9 with mains, Surge Protection- Min 5KV along with Over voltage/ Overload, short circuit/ miss-wiring protection. Compatible for pole mounting with outer dia of 40mm to 50mm. Universal Voltage driver to operate wide voltage range from 100V to 270V 50/60Hz application. Compliance to IS 10322/IEC 60598, LM 79 & LM 80 Adherence with RoHS. UL approved MCPCB. Top access street light with single screw to ensure ease of maintenance at the sight site location with minimized minimal tools. LED Light fixture with .W System Power consumption. LED Efficiency1301m/w, nominal CRI 75. Luminaire manufacturer should have in-house facility accredited by NABL/CPRI & any Government certified agency & Design & Development facility certified by ISO 9001:2008. Housing with supplier word mark /name shall be Engraved / Embossing on the die cast housing/ Body part. Warranty of 2 Years against any manufacturing defect working under standard electrical conditions as mentioned above should be given by LED manufacturer & Cree/Nichia/ Lumileds/Osram make LED Source. - LED Streetlight 70W ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each5992.05992.025.0FalseNoneNoneFalseNoneFalse149800.00
3997031154642None32.03, of Standard Stock Material (11kV System) - Supplying of 1.1 kV, XLPE or Heat resistant PVC insulated, PVC exutruted Inner Seath Armoured LTUG Cable as per IS-1554 (Part1) or IS-7098 Part-1, Armouring strip thickness and resistivity as per IS-3975 4core 10sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr118.0118.0750.0FalseNoneNoneFalseNoneFalse88500.00
3997032154642None21.05, of Labour Charges (11kV System) - Part II DLabour charges for laying of 1.1 KV class UG cable in existing trench GI pipe / stoneware pipe / on wall / on pole as required - In exixting trench/duct. 2.5 sqmm to 25 sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Mtr20.8920.89750.0FalseNoneNoneFalseNoneFalse15667.50
3997033154642None35.01, of Standard Stock Material (11kV System) - Supplying and fixing Epoxy Terminating Kit (Pothead) suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - Up to 4C x 50 Sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each324.0324.025.0FalseNoneNoneFalseNoneFalse8100.00
3997034154642None60.01, of Standard Stock Material (11kV System) - Supplying and fixing Aluminium End Terminal (Lug) suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 10 Sqmm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each2.02.050.0FalseNoneNoneFalseNoneFalse100.00
3997035154642None63.01, of Standard Stock Material (11kV System) - Supplying and fixing Brass Cable Gland suitable for 1.1 kV, LTUG Cable filled with necessary bituumen/insulating compound complete with terminals, clamps, bolts, nuts and washers etc - 25mm dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each79.079.050.0FalseNoneNoneFalseNoneFalse3950.00
17262057300000NoneNoneBuildingsCC Road (Shivani)6895144.71
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3997036154643None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m For Drains ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.0599.675FalseNoneNoneFalseNoneFalse61166.850
3997037154643None2.1.3Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates PCC for Drains. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5448.05448.071.0FalseNoneNoneFalseNoneFalse386808.00
3997038154643None2.4.2Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6955.36955.357.0FalseNoneNoneFalseNoneFalse396452.10
3997039154643None6.33Providing and constructing load bearing wall with Solid Concrete blocks of size 400x150x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1058.01058.01453.0FalseNoneNoneFalseNoneFalse1537274.00
3997040154643None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm304.0304.02158.0FalseNoneNoneFalseNoneFalse656032.00
3997041154643None1.9Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum266.0266.083.0FalseNoneNoneFalseNoneFalse22078.00
3997042154643None2.11 hSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. All other type of structures. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Tonne79011.079011.03.3779FalseNoneNoneFalseNoneFalse266891.25690
3997043154643NoneVOL - 3, C - 3 3.7 MoRT&H 305.3.4Compacting original ground supporting embankment Loosening, leveling and Compacting original ground supporting embankment to facilitate placement of first layer of embankment, scarified to a depth of 150 mm, mixed with water at OMC and then compacted by rolling so as to achieve minimum dry density as given in Table 300-2 for embankment construction. 7 M Wide Road ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum105.0105.0871.5FalseNoneNoneFalseNoneFalse91507.50
3997044154643NoneVOL - 3, C - 4 4.17 MoRT&H 406A.Wet Mix Macadam (Plant mix method) Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver/grader in sub-base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. 3.75 M Wide Road ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum2559.02559.0234.0FalseNoneNoneFalseNoneFalse598806.00
3997045154643NoneVOL - 3, C - 6 6.5 Pavement Quality M30 grade Concrete (RMC) with OPC & GGBS laid using Paver Construction of M30 Grade un-reinforced, dowel jointed, plain cement concrete pavement over a prepared sub base with OPC @ 270 kg/m3 and GGBS@ 90 kg/m3, coarse and fine aggregate conforming to IS 383:2016, maximum size of coarse aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per approved mix design transported to site, laid with a paver finisher, spread, compacted and finished in a continuous operation including provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane, sealant primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures, curing compound, steel channels, finishing to lines and grades as per drawing. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum7839.07839.0312.0FalseNoneNoneFalseNoneFalse2445768.00
3997046154643NoneVOL - 3, C - 3 3.6 MoRT&H 305Construction of Subgrade and Earthen Shoulders Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2 ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum493.0493.0877.0FalseNoneNoneFalseNoneFalse432361.00
17262057300001NoneNoneBuildingsCompound Wall - 650 Mtrs Barbed Wire Fencing - 190 Mtrs (Shivani)7862943.67
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3997047154644NoneVOL - 3, C - 2 2.5 (ii) b MoRT&H 201Clearing and Grubbing Road Land. Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness. (ii) By Mechanical Means using Dozer B. In area of thorny jungle. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm484.0484.042.0FalseNoneNoneFalseNoneFalse20328.00
3997048154644None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m Hard soil 40% ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.0199.0FalseNoneNoneFalseNoneFalse20298.00
3997049154644None1.15.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In ordinary/soft rock without blasting upto 1.5 m depth Soft rock 60% ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum363.0363.0298.2FalseNoneNoneFalseNoneFalse108246.60
3997050154644None1.9Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum266.0266.0302.05FalseNoneNoneFalseNoneFalse80345.30
3997051154644None2.1.3Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5448.05448.062.0FalseNoneNoneFalseNoneFalse337776.00
3997052154644None2.5.1Providing and laying in position Reinforced cement concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/ trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement, dowel bars & formwork to be paid separately) M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9042.09042.035.0FalseNoneNoneFalseNoneFalse316470.00
3997053154644None2.4.2Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9484.59484.546.0FalseNoneNoneFalseNoneFalse436287.00
3997054154644None2.4.2Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Footings ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6828.846828.84104.66FalseNoneNoneFalseNoneFalse714706.39440
3997055154644None2.4.2Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Columns Below Plinth ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10749.110749.120.04FalseNoneNoneFalseNoneFalse215411.9640
3997056154644None2.5.1Providing and laying in position Reinforced cement concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/ trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement, dowel bars & formwork to be paid separately) M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Columns above Plinth ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10247.610247.638.91FalseNoneNoneFalseNoneFalse398734.1160
3997057154644None2.11 hSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. All other type of structures ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Tonne79011.079011.024.481FalseNoneNoneFalseNoneFalse1934268.2910
3997058154644None6.33Providing and constructing load bearing wall with Solid Concrete blocks of size 400x150x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1058.01058.0974.0FalseNoneNoneFalseNoneFalse1030492.00
3997059154644None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. Solid Block below plinth beam ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1192.01192.0354.0FalseNoneNoneFalseNoneFalse421968.00
3997060154644None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm304.0304.02862.0FalseNoneNoneFalseNoneFalse870048.00
3997061154644None8.30Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm174.0174.02862.0FalseNoneNoneFalseNoneFalse497988.00
3997062154644None11.57.1Fencing with G.I. barbed wire Angle iron post placed at required distance embedded in cement concrete blocks, every 15th post, last but one end post and corner post shall be strutted on both sides and end post on one side only and provided with horizontal lines and two diagonals interwoven with horizontal wires, of barbed wire weighing 9.38 kg per 100 m (minimum), between the two posts fitted and fixed with G.I. staples, turn buckles etc. complete. (Cost of posts, struts, earth work and concrete work to be paid for separately). Payment to be made per metre cost of total length of barbed wire used.With G.I. barbed wire. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m18.018.07370.0FalseNoneNoneFalseNoneFalse132660.00
3997063154644None11.25.2Providing and fixing Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs118.0118.02182.0FalseNoneNoneFalseNoneFalse257476.00
3997064154644None11.62Providing and fixing RCC precast fencing pole of size 0.15mx0.15mx2.0m casted in M 20 with 20mm down size aggregates making holes for drawing barbed wire at 30 cm c/c using 8 mm dia vertical 4 TMT steel rods and 6 mm dia stirups at 15 cm c/c fixed 1.5 m above Ground level using steel moulding , curing , transportation to work spot including excavation in all types of soil, fixing in plain cement concrete M15 using 20 mm downsize aggregate including aligning to plumb and line providing including cost of all materials, labour,usage charges of machinery complete. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each1085.01085.064.0FalseNoneNoneFalseNoneFalse69440.00
17262057300000NoneNoneBuildingsEntrance Arch (Shivani)885450.5
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3997065154645None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.016.0FalseNoneNoneFalseNoneFalse1632.00
3997066154645None1.15.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In ordinary/soft rock without blasting upto 1.5 m depth Soft Rock 60% ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum363.0363.023.1267FalseNoneNoneFalseNoneFalse8394.99210
3997067154645None1.9Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum266.0266.027.1311FalseNoneNoneFalseNoneFalse7216.87260
3997068154645None2.1.3Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5448.05448.04.0FalseNoneNoneFalseNoneFalse21792.00
3997069154645None5.4Providing Size Stone masonry with hard stone in foundation & plinth with Cement mortar 1:6 (1 cement : 6 coarse sand) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5315.05315.04.0FalseNoneNoneFalseNoneFalse21260.00
3997070154645None2.4.2Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6828.846828.847.56FalseNoneNoneFalseNoneFalse51626.03040
3997071154645None2.4.2Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Columns Concrete Upto PB ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10749.110749.10.8967FalseNoneNoneFalseNoneFalse9638.717970
3997072154645None2.4.2Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Plinth Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9484.59484.51.7554FalseNoneNoneFalseNoneFalse16649.09130
3997073154645None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10237.410237.44.1103FalseNoneNoneFalseNoneFalse42078.785220
3997074154645None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates For Beams ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9635.29635.212.1873FalseNoneNoneFalseNoneFalse117427.072960
3997075154645None2.5.2Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M25 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Roof Slab ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9033.09033.01.08FalseNoneNoneFalseNoneFalse9755.640
3997076154645None2.11 hSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. All other type of structures ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Tonne79011.079011.02.759FalseNoneNoneFalseNoneFalse217991.3490
3997077154645None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1192.01192.067.0FalseNoneNoneFalseNoneFalse79864.00
3997078154645None12.13.1Providing Salwood frames of doors, windows, clerestory windows, ventilators and other frames, wrought, framed or assembled including making plaster groves (excluding cost of cement concrete and side clamps), but including cost of materials, labour, usage charges complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum98815.098815.00.0608FalseNoneNoneFalseNoneFalse6007.9520
3997079154645None12.57.3Providing and fixing flush door shutter made out of solid core block board type, well seasoned , chemicaly treated hard wood battens and internal frame with minimum 45 mm wide wooden frame alround door shutters covered with cross bonded wooden sheets (core veneer) hot pressed and fastened on both sides of the door useing liquid phenol formaldehyde resin as per IS specifications 2202 (part-I) 1991. from manufacturer complete as per spcification.-do- 30 mm thick both side commercial ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm3005.03005.02.0FalseNoneNoneFalseNoneFalse6010.00
3997080154645None12.88Providing & fixing of 2-track x 2-panel sliding windows made out of multi chambered UPVC(Matching to RAL-9016) sections and with minimum TiO2(Titanium Dioxide) at 6PHR with TPE(Thermo Plastic Elastomer) and lead free, gaskets -grey colour having isolated drainage and reinforced with Galvanized Iron profile through-out the window frame. The outer frame having a overall size of 60mm width x 45mmheight with reinforcement of 1mm thickness and Sash with overall size of 39mm X 58mm with GI reinforcement of 1mm for the frame and 1.5 mm for the sash. Coextruded Glazing bead for fixing of glass shall be of size 20mm x 24mm. Windows shall be provided with 5mm plain float glass, standard hardware& single point locking system with touch lock. Wall thickness of frame & sash shall be of 2-2.5 mm. Maximum possible size 1819mm x 1819mm (The cost is inclusive of all fixtures and separate charges for minor T&P's shall not be made) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5390.05390.04.0FalseNoneNoneFalseNoneFalse21560.00
3997081154645None11.34BProviding and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to openings /wooden frames with rawl plugs screws etc. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs154.0154.065.0FalseNoneNoneFalseNoneFalse10010.00
3997082154645None9.17.2Providing and laying Vitrified tiles with thickness 9-10 mm in different sizes with water absorption less than 0.08 % and conforming to I.S. 15622, of approved make, in all colours & shade, over 12 mm thick bed of cement mortar 1:3 (1 cement: 3 coarse sand), jointing with grey cement slurry @ 3.3 kg/ m2 including grouting the joint with white cement & matching pigments etc. complete. Size of Tile 600x600 mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1097.01097.09.0FalseNoneNoneFalseNoneFalse9873.00
3997083154645None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm244.0244.029.0FalseNoneNoneFalseNoneFalse7076.00
3997084154645None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm304.0304.0374.0FalseNoneNoneFalseNoneFalse113696.00
3997085154645None8.12Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers including cost of material etc as per specifications and as per directions of the Engineerin- Charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs64.064.057.0FalseNoneNoneFalseNoneFalse3648.00
3997086154645None8.51Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete as per specifications and as per directions of Engineer in charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm100.0100.036.2FalseNoneNoneFalseNoneFalse3620.00
3997087154645None8.54.2Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 g/L of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour. Two coats as per specifications and as per directions of Engineer in charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm110.0110.036.2FalseNoneNoneFalseNoneFalse3982.00
3997088154645None8.55.2Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content. With water thinnable cement primer on wall surface having VOC content less than 50 g/L as per specifications and as per directions of Engineer in charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.053.036.2FalseNoneNoneFalseNoneFalse1918.60
3997089154645None8.25Distempering with oil bound washable distemper of approved brand and manufacture to give an even shade :New work (two coats) over and including water thinnable priming coat with cement primer after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm137.0137.07.2FalseNoneNoneFalseNoneFalse986.40
3997090154645None8.30Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two coat applied @ 1.67L/10 m² over and including priming coat of exterior primer applied @ 2.20 kg/10 m²) with paint of approved quality to give an even shade, after thoroughly brooming the surface to remove all dirt, dust, mortar drops and foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.053.0374.0FalseNoneNoneFalseNoneFalse19822.00
3997091154645None8.34.1Applying priming coat: With ready mixed pink or Grey primer of approved brand and manufacture on wood work (hard and soft wood) including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm53.053.05.0FalseNoneNoneFalseNoneFalse265.00
3997092154645None8.33.2Painting wood work with Deluxe Multi Surface Paint of required shade. Two coat applied @ 0.90L/10 m² over an under coat of primer applied @0.75 L/10 m² of approved brand and manufacture to give an even shade including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, sand papering and knotting , cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm138.0138.05.0FalseNoneNoneFalseNoneFalse690.00
3997093154645None8.34.3Applying priming coat: With ready mixed red oxide zinc chromate primer of approved brand and manufacture on steel galvanised iron/ steel works including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm50.050.018.0FalseNoneNoneFalseNoneFalse900.00
3997094154645None8.33.3Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two coat applied @ 0.90 ltr/10 m² over an under coat of primer applied @ 0.80 ltr/10 m² of approved brand and manufacture including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm139.0139.018.0FalseNoneNoneFalseNoneFalse2502.00
3997095154645None12.51Fixing of door frame in an existing opening including embedding frame in floor and walls after cutting masonry for holdfasts for embedding holdfast in cement concrete 1:3:6 of 20mm and down size granite metal painting two coats of coal tar to sides of frame, making good the damages to walls and floor as required and disposal of the debris with lead upto 50 m. including cost of materials, labour charges, complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1477.01477.01.0FalseNoneNoneFalseNoneFalse1477.00
3997096154645None11.25.2Providing and fixing Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs118.0118.0560.0FalseNoneNoneFalseNoneFalse66080.00
17262057300000NoneNoneBuildingsBasket Ball Court (Shivani)1607382.13
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3997097154646None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.0309.88FalseNoneNoneFalseNoneFalse31607.760
3997098154646None2.1.3Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum / KM5448.05448.00.392FalseNoneNoneFalseNoneFalse2135.6160
3997099154646None2.4.2Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6828.846828.84122.824FalseNoneNoneFalseNoneFalse838745.444160
3997100154646None2.5.1Providing and laying in position Reinforced cement concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/ trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement, dowel bars & formwork to be paid separately) M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10247.610247.60.7466FalseNoneNoneFalseNoneFalse7650.858160
3997101154646NoneVOL - 3, C - 4 4.17 MoRT&H 406A.Wet Mix Macadam (Plant mix method) Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver/grader in sub-base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum2559.02559.091.2FalseNoneNoneFalseNoneFalse233380.80
3997102154646None8.6.2Providing 20 mm cement plaster with cement mortar 1:3 (1 cement: 3 coarse sand) finished with a floating coat of neat cement to brick/stone masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. Basket ball court Base Flooring ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm361.0361.0608.0FalseNoneNoneFalseNoneFalse219488.00
3997103154646None2.11 hSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. All other type of structures 8MM@ 200 C/C ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Tonne79011.079011.02.5595FalseNoneNoneFalseNoneFalse202228.65450
3997104154646NoneVOL - 3, C - 8 8.10 MoRT&H 803Painting Two Coats on New Concrete Surfaces Providing and applying two coats of ready mix paint of approved brand on steel surface after thorough cleaning of surface to give an even shade ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm109.0109.0120.0FalseNoneNoneFalseNoneFalse13080.00
3997105154646NoneVOL - 3, C-17C MoRT&H 602.6.3Cutting transverse contraction joints 3 to 4 mm wide and depth 60mm in concrete slab using concrete cutting machine with diamond studded saw within 48 hours of casting of bay / slab etc. complete including subsequent widening of the groove 8 to 10 mm. wide at top having depth of 15 mm. as directed by Engineer incharge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm70.070.0242.0FalseNoneNoneFalseNoneFalse16940.00
3997106154646NoneVOL - 3, C-16 16.15.aProviding and Laying Reinforced Cement Concrete Pipe NP3 as per design in Single Row Providing and laying reinforced cement concrete pipe NP3 for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls and parapets Clause 1101.6. 1200 mm dia ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m8425.08425.05.0FalseNoneNoneFalseNoneFalse42125.00
17262057300000NoneNoneBuildingsVolley ball Court (Shivani)18646.4
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3997107154647None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.080.3645FalseNoneNoneFalseNoneFalse8197.1790
3997108154647NoneVOL - 3, C - 3 3.7 MoRT&H 305.3.4Compacting original ground supporting embankment Loosening, leveling and Compacting original ground supporting embankment to facilitate placement of first layer of embankment, scarified to a depth of 150 mm, mixed with water at OMC and then compacted by rolling so as to achieve minimum dry density as given in Table 300-2 for embankment construction. Volley ball court earth filling ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum105.0105.080.0FalseNoneNoneFalseNoneFalse8400.00
3997109154647None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates Volley ball pilller ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5622.05622.00.3645FalseNoneNoneFalseNoneFalse2049.2190
17262057300000NoneNoneBuildingsKho-Kho Court (Shivani)145462.6
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3997110154648None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.0171.3645FalseNoneNoneFalseNoneFalse17479.1790
3997111154648NoneVOL - 3, C - 3 3.7 MoRT&H 305.3.4Compacting original ground supporting embankment Loosening, leveling and Compacting original ground supporting embankment to facilitate placement of first layer of embankment, scarified to a depth of 150 mm, mixed with water at OMC and then compacted by rolling so as to achieve minimum dry density as given in Table 300-2 for embankment construction. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum105.0105.0171.0FalseNoneNoneFalseNoneFalse17955.00
3997112154648None1.11Supplying and filling in plinth with sand under floors, foundation of Bridges including watering, ramming, consolidating and dressing complete. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum2177.02177.049.6FalseNoneNoneFalseNoneFalse107979.20
3997113154648None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5622.05622.00.3645FalseNoneNoneFalseNoneFalse2049.2190
17262057300000NoneNoneBuildingsKabadi Court (Shivani)35009.0
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3997114154649None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m Kabaddi court excavation ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.039.0FalseNoneNoneFalseNoneFalse3978.00
3997115154649NoneVOL - 3, C - 3 3.7 MoRT&H 305.3.4Compacting original ground supporting embankment Loosening, leveling and Compacting original ground supporting embankment to facilitate placement of first layer of embankment, scarified to a depth of 150 mm, mixed with water at OMC and then compacted by rolling so as to achieve minimum dry density as given in Table 300-2 for embankment construction. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum105.0105.026.0FalseNoneNoneFalseNoneFalse2730.00
3997116154649None1.11Supplying and filling in plinth with sand under floors, foundation of Bridges including watering, ramming, consolidating and dressing complete. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum2177.02177.013.0FalseNoneNoneFalseNoneFalse28301.00
17262057300000NoneNoneBuildingsBall Badminton Court (Shivani)42276.73
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3997117154650None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.045.1365FalseNoneNoneFalseNoneFalse4603.9230
3997118154650NoneVOL - 3, C - 3 3.7 MoRT&H 305.3.4Compacting original ground supporting embankment Loosening, leveling and Compacting original ground supporting embankment to facilitate placement of first layer of embankment, scarified to a depth of 150 mm, mixed with water at OMC and then compacted by rolling so as to achieve minimum dry density as given in Table 300-2 for embankment construction. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum105.0105.029.848FalseNoneNoneFalseNoneFalse3134.040
3997119154650None1.11Supplying and filling in plinth with sand under floors, foundation of Bridges including watering, ramming, consolidating and dressing complete. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum2177.02177.014.924FalseNoneNoneFalseNoneFalse32489.5480
3997120154650None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5622.05622.00.3645FalseNoneNoneFalseNoneFalse2049.2190
17262057300000NoneNoneBuildingsLong Jump (Shivani)42294.0
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3997121154651None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.094.5FalseNoneNoneFalseNoneFalse9639.00
3997122154651None1.11Supplying and filling in plinth with sand under floors, foundation of Bridges including watering, ramming, consolidating and dressing complete. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum2177.02177.015.0FalseNoneNoneFalseNoneFalse32655.00
17262057300000NoneNoneBuildingsHigh Jump (Shivani)74067.5
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3997123154652None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.032.5FalseNoneNoneFalseNoneFalse3315.00
3997124154652None1.11Supplying and filling in plinth with sand under floors, foundation of Bridges including watering, ramming, consolidating and dressing complete. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum2177.02177.032.5FalseNoneNoneFalseNoneFalse70752.50
17262057300000NoneNoneBuildingsWashing Platform (Shivani)1849586.52
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3997125154653None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.046.0FalseNoneNoneFalseNoneFalse4692.00
3997126154653None1.15.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In ordinary/soft rock without blasting upto 1.5 m depth ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum363.0363.068.3321FalseNoneNoneFalseNoneFalse24804.55230
3997127154653None1.9Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum266.0266.0113.8868FalseNoneNoneFalseNoneFalse30293.88880
3997128154653None1.8Construction of Embankment by excavating the available approved Gravel/Murrum deposited at a place or borrow pits during or prior excavation with all lifts and lead, transportation to site, spreading, grading to required slope and compacting to meet the requirement complete as per specifications, including cost of labour,rolling,water,all materials,usage& all other appurtenaces required to complete the work. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum474.0474.011.0FalseNoneNoneFalseNoneFalse5214.00
3997129154653None2.1.3Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5448.05448.039.0FalseNoneNoneFalseNoneFalse212472.00
3997130154653None2.4.2Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Footing Concrete ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6828.846828.844.8FalseNoneNoneFalseNoneFalse32778.4320
3997131154653None2.4.2Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Drains Concrete ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6639.156639.152.9FalseNoneNoneFalseNoneFalse19253.5350
3997132154653None2.4.2Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates Pedastal Concrete ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum10749.110749.11.0FalseNoneNoneFalseNoneFalse10749.10
3997133154653None2.11 hSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. All other type of structures ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Tonne79011.079011.00.7828FalseNoneNoneFalseNoneFalse61849.81080
3997134154653None5.4Providing Size Stone masonry with hard stone in foundation & plinth with Cement mortar 1:6 (1 cement : 6 coarse sand) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5315.05315.03.0FalseNoneNoneFalseNoneFalse15945.00
3997135154653None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1192.01192.010.0FalseNoneNoneFalseNoneFalse11920.00
3997136154653None6.34Providing and constructing load bearing wall with Solid Concrete blocks of size 400x100x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm937.0937.021.0FalseNoneNoneFalseNoneFalse19677.00
3997137154653None2.1.4Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm5622.05622.02.0FalseNoneNoneFalseNoneFalse11244.00
3997138154653None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm304.0304.0148.0FalseNoneNoneFalseNoneFalse44992.00
3997139154653None13.31.6Providing and fixing Chorinated Poly Venyl Chloride (CPVC) pipes, having thermal stability for hot and cold water supply including all CPVC plain and brass threaded fittings including fixing the pipe with clamp at 1.00 mtr spacing. This includes jointing of pipes and fittings with one step CPVC solvent cement and testing of joints complete. (internal work exposed on wall) - 50mm nominal OD pipes ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m781.0781.040.0FalseNoneNoneFalseNoneFalse31240.00
3997140154653None13.2.2Providing and fixing brass bib cock of approved quality : 20 mm nominal bore ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos305.0305.024.0FalseNoneNoneFalseNoneFalse7320.00
3997141154653None11.16.1Providing and fixing Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete. Hot finished welded type tubes including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kg136.0136.07432.0FalseNoneNoneFalseNoneFalse1010752.00
3997142154653None7.38Providing and fixing precoated galvanised iron profile sheets (size, shape and pitch of corrugation as approved by Engineer-in-charge) 0.50 mm (+ 0.05 %) total coated thickness with zinc coating 120 grams per m2 as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns. Sheet should have protective guard film of 25 microns minimum to avoid scratches during transportation and should be supplied in single length upto 12 m or as desired by Engineer-in-charge. The sheet shall be fixed using self drilling/self tapping screws of size (5.5x 55 mm) with EPDM seal, complete upto any pitch in horizontal/ vertical or curved surfaces, excluding the cost of purlins, rafters and trusses and including cutting to size and shape wherever required. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm568.0568.0292.4FalseNoneNoneFalseNoneFalse166083.20
3997143154653None7.4.1Providing & fixing ridges or hips of width 60 cm overall width plain G.S. sheet fixed with polymer coated J or L hooks, bolts and nuts 8 mm dia G.I. limpet and bitumen washers complete as per design drawings. 0.63 mm thick with zinc coating not less than 275 g/m² ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m639.0639.034.0FalseNoneNoneFalseNoneFalse21726.00
3997144154653None7.6Providing and fixing 15 cm wide, 45 cm overall semi-circular plain G.S. sheet gutter with iron brackets 40x3mm size, bolts, nuts and washers etc., including making necessary connections with rain water pipes complete. (0.63 mm thick with zinc coating not less than 275 g/m²) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m645.0645.068.0FalseNoneNoneFalseNoneFalse43860.00
3997145154653None9.1Providing and laying Cement concrete flooring 40 mm thick with 20 mm nominal size stone aggregate using 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate) finished with a floating coat of neat cement, including cement slurry complete. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm392.0392.0160.0FalseNoneNoneFalseNoneFalse62720.00
17262057300000NoneNoneBuildingsBox Culvert (Shivani)488343.28
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3997146154654None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.058.0FalseNoneNoneFalseNoneFalse5916.00
3997147154654None1.15.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In ordinary/soft rock without blasting upto 1.5 m depth Soft Rock 60% ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum363.0363.086.0FalseNoneNoneFalseNoneFalse31218.00
3997148154654None2.1.3Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5448.05448.05.0FalseNoneNoneFalseNoneFalse27240.00
3997149154654None2.4.2Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6828.846828.8422.0FalseNoneNoneFalseNoneFalse150234.480
3997150154654None2.5.1Providing and laying in position Reinforced cement concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/ trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement, dowel bars & formwork to be paid separately) M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9042.09042.03.0FalseNoneNoneFalseNoneFalse27126.00
3997151154654None2.11 hSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. All other type of structures ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Tonne79011.079011.03.0002FalseNoneNoneFalseNoneFalse237048.80220
3997152154654NoneVOL - 3, C - 14 14.4 A MoRT&H 2504Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in front of toe of embankment complete as per drawing and Technical specifications. Stone/Boulder ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum1912.01912.05.0FalseNoneNoneFalseNoneFalse9560.00
17262057300001NoneNoneBuildingsRain Water Harvesting (Shivani)1170465.26
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3997153154655None1.14.1SUMP TANK Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.095.16FalseNoneNoneFalseNoneFalse9706.320
3997154154655None1.15.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In ordinary/soft rock without blasting upto 1.5 m depth Soft Rock 60% ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum363.0363.0143.0FalseNoneNoneFalseNoneFalse51909.00
3997155154655None1.9Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum266.0266.0107.0FalseNoneNoneFalseNoneFalse28462.00
3997156154655None1.18Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or stacked materials. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum87.087.097.5FalseNoneNoneFalseNoneFalse8482.50
3997157154655None2.1.3Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5448.05448.06.0FalseNoneNoneFalseNoneFalse32688.00
3997158154655None2.4.2Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6955.36955.327.0FalseNoneNoneFalseNoneFalse187793.10
3997159154655None2.5.1Providing and laying in position Cement Concrete for all Super structures of building , Road works, Water works, Irrigation works & super structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers laid in layers, well compacted using needle vibrators. The cost includes all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes , labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications.M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum9644.89644.88.0FalseNoneNoneFalseNoneFalse77158.40
3997160154655None2.11 hSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. All other type of structures ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Tonne79011.079011.03.85FalseNoneNoneFalseNoneFalse304192.350
3997161154655None8.36.1Finishing with Epoxy paint (two coats) at all locations prepared and applied as per manufacturer's specifications including appropriate priming coat, preparation of surface, etc. complete. On steel work including preparing the surface after thorougly cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per specifications and as per directions of Enginer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm176.0176.0142.3416FalseNoneNoneFalseNoneFalse25052.12160
3997162154655None15.1Polyurethane based Single Component for New Surface Providing and laying water proofing treatment to the Roof with PU based single component elastomeric pure polyurethane based coating on New terrace/Chajjas/Sunken portion of WC:Bathroom, cold applied PU waterproofing membrane that is highly elastic with elongation greater than 400% and tensile strength greater than 2MPa as per ASTM D412. The waterproofing membrane to be applied in 2coats @ 1.6 kg/m2 to achieve final DFT (Dry Film Thickness) of 1mm including prime coat of epoxy primer @150 g/m2 and protection with 120gsm Geo-textile over the waterproofing membrane. The finished cost to include surface preparation, making coving at Junction, Bore Packing, treatment of construction joints completely as per specification. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm817.0817.077.5FalseNoneNoneFalseNoneFalse63317.50
3997163154655NoneVOL - 5, 7.3 Providing and fixing MS inspection door of size 60 cms x 60 cms, including MS frame made of 50x50x6mm angle, shutters made of 3mm thick MS sheets, with hinges, locking arrangements at top etc. including painting with anticorrosive approved paint etc. complete including all lead and lifts etc. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each2140.02140.01.0FalseNoneNoneFalseNoneFalse2140.00
3997164154655NoneVOL - 5, 10.6RCC hume pipe Circular pump house: Supplying precast RCC Circular Hume pipe pump house with M.S door and RCC conical roof as per specification and drawings - Internal dia Mtr. 1200 mm & height of 2.5 Mtr. With Wall thickness 65mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each16401.016401.01.0FalseNoneNoneFalseNoneFalse16401.00
3997165154655NoneVOL - 5 7.1.1 Providing and fixing MS ladder between landings, 45 cms wide using angle iron of specified sizes, 20mm MS bars at 25 cms. centre to centre, with necessary supports of same angle iron etc. as directed, including hand railing on both sides with 25mm dia. GI pipes with angle iron props at 2 mtrs. intervals and 0.5M heigh, including fixing in ground with CC 1:2:4 and two coats of anticorrosive bituminous paint etc. with all lead and lifts etc. complete with: MS angle of 65 x 65 x 8mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr4377.04377.03.0FalseNoneNoneFalseNoneFalse13131.00
3997166154655None1.14.1RWH FILTER Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.0130.5095FalseNoneNoneFalseNoneFalse13311.9690
3997167154655None2.1.3Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5448.05448.00.6149FalseNoneNoneFalseNoneFalse3349.97520
3997168154655None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1192.01192.08.2FalseNoneNoneFalseNoneFalse9774.40
3997169154655None1.9Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum266.0266.0128.1901FalseNoneNoneFalseNoneFalse34098.56660
3997170154655None2.4.2Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6955.36955.30.486FalseNoneNoneFalseNoneFalse3380.27580
3997171154655NoneVOL - 5, 16.8Constructing brick masonry chamber of internal dimension 600x450mm and depth of 600mm (inner dimensions) with modular bricks of CD 75 in cement mortar 1:6, bed concrete 150mm thick with 1:3:6, plastering 12 mm thick with cement mortar 1:4, CC 1:2:4 coping 75mm thk for fixing CI cover & frame etc. excluding the cost of CI frame and cover. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each4791.04791.010.0FalseNoneNoneFalseNoneFalse47910.00
3997172154655NoneVOL - 5, 7.3Providing and fixing MS inspection door of size 60 cms x 60 cms, including MS frame made of 50x50x6mm angle, shutters made of 3mm thick MS sheets, with hinges, locking arrangements at top etc. including painting with anticorrosive approved paint etc. complete including all lead and lifts etc. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each2140.02140.02.0FalseNoneNoneFalseNoneFalse4280.00
3997173154655NoneVOL - 5, 10.14.5 Providing and installing at site of work P.V.C. pipes including cost of pipes and specials and labour, including lowering into trenches, laying true to line, level and perfect linking at joints leak proof including jointing of approved type with all labour charges and all lift charges, handling charges including encasing the pipe around to a depth not less than 15 cms with gravel or selected earth available from the excavation etc. complete. 4 Kg/m2: 140mm(weight of pipe -2.131 kg) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr398.0398.0280.0FalseNoneNoneFalseNoneFalse111440.00
3997174154655NoneVOL - 5, 10.14.6 Providing and installing at site of work P.V.C. pipes including cost of pipes and specials and labour, including lowering into trenches, laying true to line, level and perfect linking at joints leak proof including jointing of approved type with all labour charges and all lift charges, handling charges including encasing the pipe around to a depth not less than 15 cms with gravel or selected earth available from the excavation etc. complete. 4 Kg/m2: 160mm(weight of pipe -2.753 kg) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr489.0489.0100.0FalseNoneNoneFalseNoneFalse48900.00
3997175154655None8.2.1Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm244.0244.09.0FalseNoneNoneFalseNoneFalse2196.00
3997176154655None8.3.2Providing 20 mm cement plaster of mix :1:6 (1 cement: 6 fine sand) to brick/stone masonary including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm274.0274.012.0FalseNoneNoneFalseNoneFalse3288.00
3997177154655NoneVOL - 5, 10.1.7 Supplying PVC ringtite pipes conforming to IS 4985:2000 with latest amendments and conveying to worksite, rolling and lowering into trenches, laying true to line and level and perfect linking at joints, testing and commissioning, including loading unloading at both destinations and cuts of pipes wherever necessary including jointing of PVC pipes and specials (excluding cost of specials) with jointing of approved type, with all labour with all lead & lift including encasing the pipe alround to a depth of not less than 15 cms. with soft gravel or selected earth available from the excavation etc. complete and giving necessary hydraulic test to the required pressure as per ISS (Contractor will make his own arrangements for procuring water for testing) etc. for: PVC pipes 110mm dia., 6 kg/sqcm & class 3 ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.m411.0411.0120.0FalseNoneNoneFalseNoneFalse49320.00
3997178154655None13.6.3.2Providing and fixing gun metal non- return valve of approved quality (screwed end) : 40 mm nominal bore Vertical ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Nos1225.01225.02.0FalseNoneNoneFalseNoneFalse2450.00
3997179154655NoneVOL - 5, 10.14.2 Providing and installing at site of work P.V.C. pipes including cost of pipes and specials and labour, including lowering into trenches, laying true to line, level and perfect linking at joints leak proof including jointing of approved type with all labour charges and all lift charges, handling charges including encasing the pipe around to a depth not less than 15 cms with gravel or selected earth available from the excavation etc. complete. 4 Kg/m2: 75mm ( weight of pipe -0.651 kg) ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr161.0161.080.0FalseNoneNoneFalseNoneFalse12880.00
3997180154655None2.11 hSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. All other type of structures ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Tonne79011.079011.00.0437FalseNoneNoneFalseNoneFalse3452.78070
17262057300000NoneNoneBuildingsFlagpost (Shivani)135809.29
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3997181154656None1.14.1Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work. In all kinds of soils Depth upto 3 m ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum102.0102.06.0638FalseNoneNoneFalseNoneFalse618.50760
3997182154656None1.9Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum266.0266.00.5771FalseNoneNoneFalseNoneFalse153.50860
3997183154656None2.1.3Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machinery, curing, and all the other appurtenances required to complete the work as per technical specifications. Mix 1:3:6 Using 40 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum5448.05448.01.7284FalseNoneNoneFalseNoneFalse9416.32320
3997184154656None2.4.2Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works from 0.50m to 3.50 m height. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticisers, laid in layers, well compacted using needle vibrators, providing weep holes wherever necessary, including all lead & lifts, cost of all materials of quality, confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Cum6828.846828.841.458FalseNoneNoneFalseNoneFalse9956.448720
3997185154656None2.11 hSupplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tying with binding wire / soft annealed steel wire and other ancilary operations complete as per drawing and technical specification. All other type of structures ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Tonne79011.079011.00.1166FalseNoneNoneFalseNoneFalse9212.68260
3997186154656None6.32Providing and constructing load bearing wall with Solid Concrete blocks of size 400x200x200mm having block density more than 1800kg/m3 and minimum compressive strength of 4.00 N/mm2 conforming to IS 2185 (Part - I) - 2005 and constructed with CM 1:4 as per IS 2572:2005 including cost of all materials, labour, scaffolding and curing, usage charges of machinery etc complete as per specifications. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm1192.01192.018.18FalseNoneNoneFalseNoneFalse21670.560
3997187154656None8.8Providing 18 mm cement plaster in two coats under layer 12 mm thick cement plaster with cement mortar 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster with cement mortar 1:6 (1 cement : 6 fine sand) to brick masonry including rounding off corners wherever required smooth rendering, providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications and as per directions of Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm304.0304.031.11FalseNoneNoneFalseNoneFalse9457.440
3997188154656None9.24Providing and laying Polished Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge. ** Polished Granite stone slab Black, Cat Eye, River Pink or equivalent. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sqm2864.02864.010.5675FalseNoneNoneFalseNoneFalse30265.320
3997189154656None10.2Providing edge moulding to 18mm thick Granite stone counters, vanities etc including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineer-in-charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Rmtr Per cm Height328.0328.018.0FalseNoneNoneFalseNoneFalse5904.00
3997190154656None11.28Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners, stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in- charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.) including cost of materials, labour, usage charges of machinery complete as per specifications and as per directions of the Engineer-in-Charge. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Kgs565.0565.069.3FalseNoneNoneFalseNoneFalse39154.50
17262057300000NoneNoneBuildingsProcurement Of Furnitures, Kitchen Equipments, Furnishing, Computers, Cctv & Internet Connect Etc, (Shivani)9930529.0
idtenderSubEstimateIdcategoryNameitemCodedescriptionuomNamebaseRatefinalRatequantitymodifyQuantityYnminQuantitymaxQuantitybuyBackYnbuyBackValuehideYnnetAmounttaxCount
3997191154657NoneData RateTwo tier cot to MDRS/KRCRS / P U MDRS Size: 1980L X 760W X 1980mmH. The verticals shall be made out of 38mm square MS tubes of 16G thick on all the four corners & 19mm square MS tubes in-between. A single CRCA sheet of 14G thick and uniformly bent on all sides vertically and further inside and with one lengthwise rib of 18G in the middle underneath for both the cots shall be provided. For the upper cot 25mm dia pipe to be bent and fixed in the middle on either sides as obstacle to avoid dropping of the person while sleeping to the side. The height for bottom tier from the floor shall be 460mm. The distance between bottom tier and top tier shall be 1000mm. The ladder shall be provided on one side to enable the person to climb to upper tier. Curtain hooks at the top corners for both the cots shall be welded for tying mosquito curtains. Strong rubber bushes shall be fixed for the verticals at the bottom. The entire cot shall be neatly de rusted, powder coated with epoxy polyesterpowder. Name of the institution i.e., KREIS Should be embossed on the material. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No14950.014950.0125.0FalseNoneNoneFalseNoneFalse1868750.00
3997192154657NoneData RateDesk cum Bench Dimensions: Size : 1800 (L) * 787 (W) * 787mm (H) Specification: Made using 25mm*25mm & 25mm*50mm 16g MS ERW tubular section frame & book shelf of 20 swg CRCA sheet, fitted with 25mm thick PLPB & 2mm thick PVC edge binding for all the exposed edges for sitting & writing planks & 18mm thick PLPB for back rest planks respectively. The desk frame shall be epoxy powder coated upto 40microns with siemens grey colour. Part Details:- 1) Writing Plank: Size: 1800 Mm(L) * 355mm(W)*25mm(T) 2) Sitting Plank: Size: 1800 Mm(L) * 305mm(W)*25mm(T) 3) Backrest Plank: Size: 1800 Mm(L) * 203mm(W)*18mm(T) 4) Book Shelve: Made Out Of MS 20swg. Name of the institution i.e, KREIS Should be embossed on the material. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No12600.012600.062.0FalseNoneNoneFalseNoneFalse781200.00
3997193154657NoneData RateSteel Almirah plain with shelves &Door 6.6 Feet with 20 Guage doors & 22 Guage body. Size : 198cm H x 915cm W x 48cm D (including leg of 15.24cm) , fitted with four fixed shelves making five compartments with double door with three way locking device and duplicate keys, all joints outside and inside should be spot or co2 welded and neatly finished by sandering. The outside corners should be rounded off to give good appearance. The edges of doors and shelves should be properly bent to U shape of 25mm width to ensure good strength and the outer edge of U bent of the door length wise should be double folded and neatly finished. The shelves front side should be bent to U shape neatly and finished to avoid any possible cuts to fingers and hand when handled. Longitudinal rib of 15.24cm wide including bent to required shape should be provided and fixed to each door at its centre. The breadth of the shelf in the Almirah should be to the entire width leaving above 12mm gap from the shutter when it is closed. Locking Device: Three ways locking device with 10 Gauge M.S. sheet for locking and lever plate, and with locking rod of 10mm dia with strong bracket at top and bottom to hold the locking rod with six lever lock should be provided. 65mm size 6 lever strong lock to be fixed. Handle should be made out of cast alloy with nickel chrome plated. The entire almirah shall be derusted, powder coated with epoxy polyester powder Name of the institution i.e, KREIS should be embossed on the material. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No21823.021823.012.0FalseNoneNoneFalseNoneFalse261876.00
3997194154657NoneData RateS Type continuous armrest chair: SEAT/BACK ASSEMBLY: The seat and back are made from well seasoned& polished wood. CANE FOR SEAT/BACK: Cane is made from mix of LDPE+HDPE MIX material. The caning used for seat/back shall have high tensile strength. ARMREST TUBE: The armrest tube is made of MS ERW tube of dia.2.54cm x 16G thick and powder coated. The armrest is gas-assisted injection moulded from black polypropylene. Name of the institution KREIS should be embossed on the material ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No3492.03492.025.0FalseNoneNoneFalseNoneFalse87300.00
3997195154657NoneData RATEStaff Table Size: 1365mm W X 680mm D X 750mm H the Table Top work surface to be manufactured using 25mm thick pre laminated particle board (PLPB). All work surface edges are to be duly sealed with 2mm thick PVC edge banding. The understructure C- frame to be made using CRCA MS sheet 20 gauge Thick and Tubular Frame to be made using MS ERW Square Tube with dia 25.4 mm X 1.2mm Thick. The MS ERW Square Tubes: 25.4 mm X 25.4mm X 1.2mm Thickness. The modesty panel is to be made using 20 gauge thick CRCA MS sheet. The table should contain 1 drawer & cupboard unit to the left hand side and 3 drawer units on the right hand side of the table. The metal drawer unit with shell made out of 0.5mm thick CRCA sheet and MS Drawer Tray made out of 0.5mm Thick CRCA MS sheet and the drawer facia to be made out of 22 gauge Thick CRCA sheet. The drawer to be provided with MS Lock with 10 Lever Cam Lock. The handles to be fixed made out of Built in Plastic. The table should have connecting leg rest made out of MS tube. The entire table shall be neatly derusted, powder coated with epoxy polyester powder Name of the institution i.e., KREIS Should be embossed on the material. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No12990.012990.012.0FalseNoneNoneFalseNoneFalse155880.00
3997196154657NoneData RateShoe Cabinet: Shoe racks with shelves 8.1ft with uniformly welded 18 gauge pipes for verticals & 16 gauge sheet folded L angles for horizontals and covered with 20guage thick CRCA sheet on top, sides and back. Size 1371H,2463W,381D fitted with pipes consisting of 30 shelvesof size 203H & 381 W in inclined position to stock footwear. The rack will be provided with 4 castors. The entire rack will be derusted, powder coated with epoxy polyster power. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No16810.016810.012.0FalseNoneNoneFalseNoneFalse201720.00
3997197154657NoneData RateClass Room Tables: Under structure: C frame shall be made up of 0.9 +/- 0.09mm thick powder coated 50 microns (+/- 10) CRCA MS. Tubular frame is made up of Sq. 25.4 (+/- 0.3mm) X 1.2 (+/- 0.096mm) Thick MS ERW tube. The modesty panel is made up from 1.0 (+/- 0.09mm) thick powder coated 50 microns (+/- 10mm) CRCA MS. The work surface shall be made up of 18 (+/-0.5mm ) thick pre laminated particle board as per with 2 mm thick PVC edge banding on all sides. Shell of the storage unit shall be made up of 0.5 (+/-0.07mm) thick CRCA steel. The drawer tray shall be made up of 0.5 (+/-0.07mm) thick CRCA steel. Drawer front shall be made up of 0.8 (+/- 0.1mm ) thick CRCA steel. Lock shall be of 10 lever cam lock. Handles shall be of plastic handle. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No10480.010480.08.0FalseNoneNoneFalseNoneFalse83840.00
3997198154657NoneData Rate Library Racks: a Product Size: Width 900mm, Height: 1850mm, Depth: 300mm (DMX Drg. - PL13-A4-20825 R0) b. Construction: Rigid Knockdown construction. c. Material: CRCA 0.8mm Thickness d Finish: Epoxy Polyester Powder coated to the thickness of 50 microns (+/-1) e. Number of Adjustable shelf: Five adjustable shelves (Total 6 Loading levels). Uniformly Distributed Load Capacity per each shelf shall be 80 Kg maximum. f. Shelf back stiffener At the rear side of the shelves back stiffeners are provided. These act as separators between front & rear books. g. Label holder & range indicator Label Holder & Range indicator on each main unit for inserting labels. h. Accessories: Optional stand of 125 mm Height with levelling screws. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No15416.015416.010.0FalseNoneNoneFalseNoneFalse154160.00
3997199154657NoneData RatePLATE & TUMBLER STAND: 125 plates Supply of plate & tumbler stand with heavy duty wheels of size 8ft W x 2ft D x 6ft H to stack plates in five rows and tumblers in two rows as per Drawing. MS powder coated to60 microns welded main frame 25mmx50mmx2mm rectangular tubes vertically and horizontally with 6mm rod spaced 1.5” vertically to stack plates individually. Tumbler stand made of 2mm thick MS sheet powder coated to 60 microns on either side with holes to insert tumblers all as directed by the engineer in charge and sample to be approved before supply. The entire stand shall be neatly derusted, powder coated with epoxy polyester powder. Name of the institution i.e., KREIS Should be embossed on the material. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No15000.015000.02.0FalseNoneNoneFalseNoneFalse30000.00
3997200154657NoneData RateSmart Class Projector with Integrated Computer and other accessories with 1 year Onsite Service Warranty Video Conferencing Software for the above integrated Computer system Virtual Classroom Software for the integrated Computer system Ceiling mount kit for the Projector system USB extenders with 5 meter cable length for fixing to Projector system Antiglare White Board Server System Content Access Software and 3D Virtual Interactive experiments Desktops for students (15 x 1 Locations) Headsets Audio Splitter USB Keyboard and Optical Mouse Installation charges of all equipment’s, including fixing the white board and ceiling mount kit, Internal wiring of LAN, Networking of computers, projector and server system Warranty of 1 year onsite, comprehensive end-to-end AMC for the hardware’s and software’s with visit to schools every 3 months with successful utilization report from vendor Training Cost 2 days divisional level hands on and assignment based training for 2 teachers Providing Onsite Warranty and AMC Support for all the hardware and software with visit to schools every 3 months with successful utilization report from vendor : 4 years Portable Electronic equipment insurance as per the specification for 1 Year Renewal charges of Portable Electronic equipment insurance for Server System - 1 No.,Desktop Computer system 15 Nos., provided for usage by students, Projector System with integrated PC1 Noincluding Physical loss theft for a period of 4 Years Name Boards and Instruction sheet for ELearning Centre Supplying and drawing of UTP 6E LAN cable Computer Table for E- learning centre Computer chair with armrest for Elearning centre Supplying and fixing of 2 meters Cat 6 Patch cable (272 + 85) Supplying and fixing of 9 U with 650 mm depth switch mounting rack with power manager and cable manager as standard specification Supplying and fixing of I/O socket with back box Supplying and fixing of Network switches 24 port Supplying and fixing of Patch panel for LAN cabling 24 port ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No2646000.02646000.01.0FalseNoneNoneFalseNoneFalse2646000.00
3997201154657NoneData RateMattress type Pocket Spring Mattresses 1. Mattress Size 189 x 67 x 15 cm (29099 Numbers) & 176 x 74 x 15 cm (3275 Numbers) 2. Coil Count 189 x 67 x 15 cm= 28X 10 176 x 74 x 15 cm =26X 9 3. Construction a) 120mm high pocket spring (dia) core covered with 5mm cotton felt & plastic mesh from top & bottom b) Entire pocket spring core surrounded by border of 75mm shorter side and 84 mmlonger side made out of 28 density hard foam c) Above this core 10mm or 12mm (thickness) 28 density P.U foam pasted on top. d) Above final carcass covered with 20 to 24mm 18density P.U foam quilted fabric from top and bottom 4. Raw Material Specification 1. Spring Coil with 1.8mm dia 5 turns, dia of the spring 55 mm, Flexibility 2.7, Hardness IS 4454 grade part- 2,2003. Spring Material carbonised steel of grade IS-4453 part-1, 2001 & the centre to centre distance of spring 60mm. 2.Spring Coil is pocketed with 80 GSM white Non woven fabric. Fabric type 130 GSM Knitted Cotton felt (1000 GSM) Air Vents 4 nos. individually packed and sealed with LDPE 80 microns Corner fitments 3 Ply corrugated corner guards to prevent any transit damage Tensile strength 170kg/sq mm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No5000.05000.0250.0FalseNoneNoneFalseNoneFalse1250000.00
3997202154657NoneData RATEPillow Specification Fibers 50:50 recycled & hollow Fiber Weight 500 Grm Fabric Peach polyester 85Gsm and one cotton pillow cover Packing LDPE 250 Gauge Size 17''x27'' recorn pack of 1 pillow ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No400.0400.0250.0FalseNoneNoneFalseNoneFalse100000.00
3997203154657NoneData RATEZamkana Width 91 CMs+/- 2cms Color fatness to washing 2-3 or better Weight/piece 1000 Grm+/-5% Count warp 2/30 to 2/34s +/ -10% Weft 25 to 6s +/-10% Composition Polyster,viscose,cotton Length 198 Cms +/- 2 cm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No315.0315.0250.0FalseNoneNoneFalseNoneFalse78750.00
3997204154657NoneData RATEBed Spread Width 147 CMs+/- 2cms Color fatness to washing 2-3 or better Weight/piece 600 Grm+/-5% Count warp 8s to 12s +/ -10% Weft 2s to 6s +/-10% Composition Polyster,viscose,cotton Length 198 Cms +/- 2 cm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No147.0147.0250.0FalseNoneNoneFalseNoneFalse36750.00
3997205154657NoneData RATEBed Sheet Width 147 CMs+/- 2cms Color fatness to washing 2-3 or better Weight/piece 1000 Grm +/-5% Count warp 2/18s to 2/20s +/ -10% Weft 6s to 10s +/-10% Composition Polyster,viscose,cotton Length 223Cms +/- 2 cm ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No420.0420.0250.0FalseNoneNoneFalseNoneFalse105000.00
3997206154657NoneData RateSuppying & Installing reputed brand 55 inch LED TV with android supports. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No75000.075000.02.0FalseNoneNoneFalseNoneFalse150000.00
3997207154657NoneData RATEMosquito net GSM-min 28, colour-white,Typing loop-6 loops,polyolefin 100, Tolerance limit+-10% for all above parameters ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No582.0582.0250.0FalseNoneNoneFalseNoneFalse145500.00
3997208154657None10.1.3 of Part III Utilization (PWD Electrical)Supply and installation of 25 KVA Diesel Generator Set, 3Phase, 1500 RPM DG Set: Diesel engine and alternator of the same make shall be close coupled and mounted on a base plate of robust construction with standard accessories. 1) DIESEL ENGINE: a) Diesel Engine shall be air cooled, electric start, developing required B.H.P at 1500 RPM with Class G-2 Governing or better for alternator to deliver specified continuous 25 KVA output as per IS/ISO 8528. b) The Diesel Engine should be capable of providing 10% overload for one hour for every 12 hours continuous running at full load. c) Naturally aspirated engines shall conform to IS: 10000-2/81 d) The Diesel Engine shall be complete with the following standard accessories: i) Fuel tank with capacity for 12 hours continuous running at full load. ii) Exhaust silencer of Residential type. iii) 12V or 24V starting system complete with starter motor, charging alternator with Cutout. iv) Lead Acid Battery/ies of suitable ratings with connecting cables. The battery/ies shall be supplied in charged condition and shall conform to relevant IS Specification. v) Standard set of tools consisting of a set of 3 spanners, one screw driver, one standard plier and one nose plier of appropriate size shall be provided along with DG sets free of cost for each of DG sets. 2) ALTERNATOR: a) The Alternator shall be self excited and self regulated of specified KVA rating in three phase at 415 Volt, 50 Hz, 1500 RPM and 0.8 power factor and shall conform to latest IS/ISO Specification and Standards. The alternators shall be of brush less type with VG-1 Grade of voltage regulation. b) The alternators shall be screen-protected drip proof with Min.IP-21 degree of protection as per latest IS/ISO Specification and Standards. The class of insulation of the Alternator would be 'H'. The rated voltage of Alternator will be 415 V, three phase. 3) MANUAL CONTROL PANEL/INTEGRATED DIGITAL CONTROLLER: a) The Control Panel shall be fabricated from steel/metal sheet of 1.5 mm thickness minimum duly pretreated and aesthetically finished or integrated with the DG set in the form of Digital Controller. b) The Control Panel shall be totally enclosed, dust and vermin proof, floor mounted or wall mounted/skid mounted or integral type with IP-53 degree of protection as per latest IS/ISO Specification and Standards. c) The Control Panel shall have the instrumentation/indicators for speed status, current status, voltage status, Load status, Oil Pressure, low fuel indicator and other operational/safety controls. 4) OPERATION: Manual On-off Push Button Switch on DG set and Change over Switch 5) ACCOUSTIC ENCLOSER a) DG sets shall be provided with integrated acoustic enclosure which shall conform to norms of Central Pollution Control Board (CPCB) as per updated provision. b) The acoustic enclosure supplied shall be in accordance with as per latest IS/ISO or equivalent IEC code for conformity to noise norms. This aspect shall also be verified at the time of delivery. 6) PRE-DESPATCH TESTING a) Supplier shall furnish complete & satisfactory TTC(Type test certificate) for engines, alternators complete with enclosure to be used by them for this rating of DG sets clearly indicating make, model and ratings of the DG sets tested at the time of delivery of the DG set. The TTC of three phase alternators shall cover ‘unbalanced load test’ as per latest IS/ISO Specification and Standards as applicable. However the engine models/rating shall need relevant certifications as per norms. b) Either of the following types of TTC shall be acceptable: i) Type Test Certificate issued by recognized Government Lab. Type Test Certificate issued by recognized Government Lab irrespective of whether engines and alternators were tested at firm’s lab or some other lab, but witnessed by Government representative. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Set451101.0451101.01.0FalseNoneNoneFalseNoneFalse451101.00
3997209154657NoneData RATENetwork Video Recorder: Up to 16 channel IP camera input ,H.265/H.264/MJPEG dual codec decoding, Max 256Mbps incoming bandwidth, Up to 8ch@1080P(4ch@H.265+4ch@H.264) real-time live-view Up to 12Mp resolution preview playback, HDMI/VGA simultaneous video output, 8/16 channel synchronous real-time playback, GRID interface Support Multi-brand network cameras, ONVIF Version 2.4 conformance 3D intelligent positioning, Support 2 SATA HDDs up to 12TB, 2 USB(1 USB3.0), Support IPC UPnP, 8PoE ports Support P2P, QR code scan & add Multiple network monitoring: Web viewer. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No11200.011200.01.0FalseNoneNoneFalseNoneFalse11200.00
3997210154657NoneData RATEIR Dome camera (Indoor) 2Megapixel progressive scan CMOS, varifocal lenses 3.3 12MM or better ,H.264&MJPEG dual stream encoding, Min 20fps 1080PMinimum WDR, Day/Night(ICR), 3DNR,AWB,AGC,BLC,Multiplenetwork monitoring: Web viewer, Flexible cropping, On-camera real-time motion detection and privacy mask with 1024 detection zones;Backlight compensation, privacy masking Ma IR LEDs Length20m, IP66, Po ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No8700.08700.05.0FalseNoneNoneFalseNoneFalse43500.00
3997211154657NoneData RATEIR Bullet camera (OutdoorEntrance)2Megapixel progressive scan CMOS, varifocal lenses 3.6-12MM or better, H.264&MJPEG dual-stream encoding, Min20fps1080P(19201080Minimum WDR, Day/Night(ICR), 3DNR,AWB,AGC,BLC ,Multiple network monitoring: Web viewerFlexible cropping, On-camera realtime motion detection and privacy mask with 1024 detection zones; Backlight compensation, privacy masking Ma. IR LEDs Length20m, IP66, PoE ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No8500.08500.03.0FalseNoneNoneFalseNoneFalse25500.00
3997212154657NoneData RATE18.5 Inch Display Monitor ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No9450.09450.01.0FalseNoneNoneFalseNoneFalse9450.00
3997213154657NoneData RateSTORAGE Hard disk 4 TB Surveillance Hard Drives - Surveillance Storage is built for 24/7 always-on surveillance in high-definition security systems for the Videos Footages generated by all the Cameras installed within the network for a period of 3 months in case of Boys' Residential Schools and for a period of 6 months in case of Girls' /Co-education Residential Schools. Off-line Backup: The system should capable of compressing the video footages stored beyond the capacity of online storage capacity of the NVR, and upload the same to Private Cloud Servers via network. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No11800.011800.01.0FalseNoneNoneFalseNoneFalse11800.00
3997214154657NoneData Rate6 u server rack with 500 depth wall mounted 1 fan ,1 self and spike card 6 output ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No3500.03500.01.0FalseNoneNoneFalseNoneFalse3500.00
3997215154657NoneData Rate8 port 10/100 switch with 4 port POE with more than 50 watts POE budget or 8 port 10/100 switch with 4 port POE with more than 40 watts POE budget ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No9450.09450.01.0FalseNoneNoneFalseNoneFalse9450.00
3997216154657NoneData RateRJ 45 Connectors with 4X4" Boxes for Cameras. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No729.0729.08.0FalseNoneNoneFalseNoneFalse5832.00
3997217154657NoneData RatePower variation controller unit ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No13500.013500.01.0FalseNoneNoneFalseNoneFalse13500.00
3997218154657NoneData RateCAT Cable with Including 25 mm Round Pvc White Conduit ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No340.0340.0100.0FalseNoneNoneFalseNoneFalse34000.00
3997219154657NoneData RateElectrical cable to connect all equipments ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No334.0334.0100.0FalseNoneNoneFalseNoneFalse33400.00
3997220154657NoneData RATEDining table: 6 seater The overall dimensions of the table should be 1800mm(W) X 800mm(D) X750mm(H).The table top should be made of SS-204 grade 1mm thick brush finish stainless steel. The top frame assembly should be rectangular tube of dimensions 50.8mm X 25.4mm X 1.6mm thick MS ERW and cylindrical socket which are welded and powder coated. The side frame assembly should be fixed to the top with screws. The side frame assembly should be made of combination of circular and rectangular tubes of MS ERW. The circular tube should be of diameter 38.1mm and thickness 1.6mm.The rectangular tube should be of dimensions 50.8mm X 25.4mm and thickness 1.6mm.Circular and rectangular tubes should be welded together to form the assembly. Side frame assembly should be fixed to top frame assembly. The stool top should be made SS-204 grade 1mm thick brush finish stainless steel with MS Ribs for strength. The stool top should have an height of 450mm and the diameter of the stool top should be 300mm.The stool assembly should be foldable above the side frame. Cross members should be provided between side frame assembly. Cross members should be made of 50.8mm X 25.4mm X 1.6mm thick MS ERW of 1.6mm thickness and should be powder coated. Finish should be epoxy polyester powder coated of 40-60 micron thickness. Shoe should be provided at the bottom. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No13000.013000.032.0FalseNoneNoneFalseNoneFalse416000.00
3997221154657NoneData RATEGalvanized Iron Storage Trunks The GI Steel trunk shall be as per IS 72571973 (Reaffirmed 2006) as per the drawing enclosed. The body of the steel trunk shall be made in three panel construction viz. frontbottom and back in one piece and the two sides in two separate pieces. The top portion of the box (Lid cover) is in one piece construction. MetalGalvanized Iron Sheet Thickness: 0.80 mm. Dimension in mm:675 L X 370 W X 330 D Padlock: Front, 1 No. Side Handles: 2 Nos Front Handle: 1 No 1All joints shall be double seamed. 2. All dimensions in mm. 3. Tolerance L +/ 5mm, H =+/ 5mm, All other tolerance as per relevant IS. 4. Method of component fixing By riveting. 5. Hasp & Staple size 150mm as per IS 363:1993 (Reaffirmed 2003), typeII. 6. Material: GI Sheet 0.80mm thick to Class 3 of IS 2771969 2nd revision for Body, Lid, Cover, Pocket & Channels. 7. Trunk weight Min 11.2 Kgs. 8. Steel Trunk shall be properly cleaned, de-greased, pickled. 9. Name of the institution KREIS should be embossed on the material ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.No1700.01700.0250.0FalseNoneNoneFalseNoneFalse425000.00
3997222154657None10.3.2Supplying, erecting, testing & commissioning of ON-LINE UPS system suitable for operation on 230V, 50Hz, A/C supply, with isolation transformer all accessories complete and Excluding batteries and wiring complete ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each42480.042480.02.0FalseNoneNoneFalseNoneFalse84960.00
3997223154657None10.5.9Supplying, installation, testing & commissioning of 12V DC, AH batteries in poly propylene container for U.P.S. Sealed maintenance free batteries. ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Each14100.014100.012.0FalseNoneNoneFalseNoneFalse169200.00
3997224154657NoneData RATEProviding & fixing AD-12 Yellow ACP with Red, Blue & White Acrylic combined 2D Board with 3 years warranty. LED Modules & 25mmx50mmx18SWG MS frame. IP65 Power supply 400watts, Installation Outdoor type, 9000 Lumen, White (exact colour will be confirmed in the work order) Colour, Protection class IP65, Rated life of LEDs 40000 hrs, Working voltage of 230 V, single phase AC, 50 Hz, Height of Characters as per enclosed design, ambient temperature up to 55 degree celsius, letters in Kannada, English Font size shall be as per Govt of Karnataka order ---- Including all lead and lift charges, loading and unloading charges, labour charges, all incidental charges, hire charges of all men and machinery and equipments required for successful completion of work etc., complete. The work shall be executed as per standard technical specifications and as per the directions of the Engineer in charge of the work.Sft850.0850.054.6FalseNoneNoneFalseNoneFalse46410.00
generalCriterionList
createdTsversioncreatedDatemodifiedDatecriterionTypedescriptiontenderEligibilityCriterionDocumentList
17262057320001NoneNoneELIGIBILITYTenders from Joint ventures are not acceptable.None
17262057320001NoneNoneELIGIBILITYBidders shall not be under a declaration of ineligibility for corrupt and fraudulent practices issued by any State Government/Government of India /Union Territory.None
17262057320001NoneNoneELIGIBILITYThe bidder is required to ensure browser compatibility of the computer well in advance to the last date and time for receipt of tenders. The departments shall not be responsible for non-accessibility of e-Procurement portal due to internet connectivity issues and technical glitches at bidders end.None
17262057320000NoneNoneELIGIBILITYIt shall be the responsibility of the Bidder to ensure credit of Tender Processing Fee and EMD into the respective receiving bank accounts of e-Procurement on or before the last date and time of bid submission.None
17262057320000NoneNoneELIGIBILITYEMD Payments through e-Payment mode shall be made as one single transaction and payments made in part are liable for rejection.None
17262060850000NoneNoneELIGIBILITYThe tenderer has to furnish the details of the Head Office including Telephone No.s, E-mail address, the fax and the mobile numbers of the person whom to be contacted.None
17262061070000NoneNoneELIGIBILITYConditional tenders will not be acceptedNone
17262061320000NoneNoneELIGIBILITYThe tenderer shall bear all costs associated with the preparation and submission of his tender, and the employer will in no case be responsible and liable for those costs.None
17262061420000NoneNoneELIGIBILITYThe employer is not responsible for any delay in accessing E - Procurement Portal.None
17262061620000NoneNoneELIGIBILITYRoyalty on construction materials and other taxes will be deducted as per prevailing Govt orders.None
17262061700000NoneNoneELIGIBILITYMaterials like bitumen,steel,cement etc.,required for the work shell be procured by the tenderer themselves and should got tested by the quality Assurance authority before use on the work.None
17262061760000NoneNoneELIGIBILITYAll the formats prescribed in the bid document shall be filled by the tenderer in complete manner otherwise it will be rejected.None
17262061830000NoneNoneELIGIBILITYAll scanned documents to be uploaded shall be in original, Submit the original document at the time of technical bid opening or next day and the Executive Director reserves the right to verify the original documents before approval.None
17262061910000NoneNoneELIGIBILITYIf any, additional information required, the same may be obtained from the office of the Executive Director, 8, M S B-1, 6th & 7th Floor, Cunningham Road, Bangalore-52 during office hours on all working days. It may be noted that if any of the dates mentioned above happened to be a General Holiday , the next working day will be consideredNone
17262063540000NoneNoneELIGIBILITYThe employer reserves the rights to Reject or accept any or all the tenders without assigning any reasonsNone
17262063650000NoneNoneELIGIBILITYThe contractors assessed available tender capacity shall be more than the tender value, it will be calculated as per the STD tender document Attached.None
17262063720000NoneNoneELIGIBILITYThe Tender processing fee shall not be refundable.None
17262063780000NoneNoneELIGIBILITYTenderer who qualifying in the technical bid such tenderer financial bid will be opened.None
17262063840000NoneNoneELIGIBILITYContractor should establish a fully functional laboratory at site at no extra cost in order to carry out all the required tests for the materials being used in the project.None
17262063970000NoneNoneELIGIBILITYContractor should take all precautions to ensure that no damage is caused to the existing similar structures which have been constructed by other agencies during project execution. If any damage is caused, it has to be rectified at his own risk and cost. Contractor should carryout additional test required to test the suitability of materials before using the same to the work.None
17262064220000NoneNoneELIGIBILITYFormation levels and other data furnished are bare minimum the contractor should make all efforts to validate and to get additional data if required at his own cost. Contractor should execute the project with least impact to the environment.None
17262064290000NoneNoneELIGIBILITYWhen Structure constructed disputes arising on account of damages to the existing bunds, Structure and other private properties, if any, has to be resolved by the contractor. All precautions should be taken by the contractor so that there are no damages to such public /private properties.None
17262064430000NoneNoneELIGIBILITYContractor should take all precautionary measures to avoid any damage to the utilities during excavation as well as utility shifting. To that extent the contractor should indemnify the client.None
17262064520000NoneNoneELIGIBILITYContractor should follow strictly the prevailing rules of labour act.None
17262064590000NoneNoneELIGIBILITYThe Bidder shall not furnish any fake/fabricated/false information or withhold facts etc., if the bidder is found to have violated any of these above (found either during evaluation or after awarding the tender), the tender shall be rejected and action as per rules and regulations shall be taken against the Bidder.None
17262065020000NoneNoneELIGIBILITYIf the Successful Bidder has quoted lesser rates than the estimated rates then he should without fail remit the Unbalanced Tender Amount along with the Security Deposit within the stipulated time as that shall be specified in the Letter of Acceptance, failing which the tender of the Successful Bidder shall be rejectedNone
17262065090000NoneNoneELIGIBILITYThe bidders should submit the Bid capacity compulsorily. The details of balance work B value (works on hand & works for which tender submitted). Should be submitted in the prescribed format & should be signed by the concerned Executive Engineer / District level officer. In case the bidder does not furnish the above details/suppresses the actual facts/ produces false facts, along with the Technical bid, the technical bid of such bidder shall be considered for rejection.None
17262065170000NoneNoneELIGIBILITYWith regard to tenders where lesser rates are quoted by the tenderer as per Standard Tender Document the contractor along with his financial bid shall furnish a detailed rate analysis for such of the items where has quoted lesser rates than the estimated rates. The rate analysis must indicated break up of rates for various components such as materials, labour, machinery and other relevant components. He shall also explain & substantiate how such lesser quoted rates would work out for him from the point of view of doing quality work. He shall also give undertaking that the rates quoted by me are workable to execute quality wok as per specifications and to the full satisfaction of the department Any failure on the part of the contractor in not submitting the above said information along with his financial bid in E-proc will be viewed seriously during evaluation of his financial bidNone
17262065260000NoneNoneELIGIBILITYWith regard to tenders where lesser rates are quoted by the tenderer as per Standard Tender Document the contractor along with his financial bid shall furnish a detailed rate analysis for such of the items where has quoted lesser rates than the estimated rates. The rate analysis must indicated break up of rates for various components such as materials, labour, machinery and other relevant components. He shall also explain & substantiate how such lesser quoted rates would work out for him from the point of view of doing quality work. He shall also give undertaking that the rates quoted by me are workable to execute quality wok as per specifications and to the full satisfaction of the department Any failure on the part of the contractor in not submitting the above said information along with his financial bid in E-proc will be viewed seriously during evaluation of his financial bidNone
17262065500000NoneNoneELIGIBILITYThe Defect liability period of the work is 24 Months from the date of submision of final bill.None
17262065640000NoneNoneELIGIBILITYTerms and condition of Contract as per Approved STD KW-4.None
17262065720000NoneNoneELIGIBILITYQAP & PERT chart should be submitted by the successful bidder within 3 Days From date of Agreement.None
17262065790000NoneNoneELIGIBILITYDesign mix For Concrete shall be obtained from the approved NABL acredated laboratories and same shall be got approved from the department before incorporating in the work.None
17262065860000NoneNoneELIGIBILITYOnly One package/work will be considered in this notification.None
17262065990000NoneNoneELIGIBILITYThe intended bidders shall visit the site and quote his offer accordingly and for having visited the site, they should upload the Geo-tag Photos and Document for having visited the site duly certified by concerned Assistant Executive Engineer KREIS, while submitting the tenders.None
17262066440000NoneNoneELIGIBILITYThe rates are Exclusive of GST. GST will be paid seperately.None
preQualCriterionListNone
technicalCriterionList
createdTsversioncreatedDatemodifiedDatedescriptioncriterionCategoryTextcriterionTypeOthersValuetenderTechnicalCriterionDocumentList
NoneNoneNoneNone3.2 (b) Tenderer should Satisfactorily completed as prime contractor, atleast one similar work such as Building work of value not less than Rs 1666.50 Lakhs. The workdone certificate duly signed not below the Rank of Executive Engineer.Past ExperienceNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneWork Done Certificate
NoneNoneNoneNone3.2 (c) Executed in any one year, the following minimum quantities of work:(2019-20 to 2023-24) RCC 5098.00 Cum Steel 456.00 MT BBM/Laterite Stone/Solid Block 15090.00 Sqm Flooring 8971.00 Sqm Tenderer Shall submit Workdone Certificate stating the above quantities executed issued by not below the rank of executive Engineer.Past ExperienceNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneWork Done Certificate
NoneNoneNoneNone3.2 (d) The Tenderer or his identified sub-contractor should possess required valid electrical license for executing building electrification works and should have executed similar electrical works amounting to Rs 103.00 Lakhs in any one year during 2019-20 to 2023-24Past ExperienceNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneOthers -- RELEVANT DOCUMENTS
NoneNoneNoneNone3.2 (e) The Tenderer or his identified sub-contractor should possess valid license for executing water supply/sanitary engineering works and should have executed similar water supply/sanitary engineering works amounting to Rs 66.00 Lakhs in any one year during 2019-20 to 2023-24Past ExperienceNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneOthers -- RELEVANT DOCUMENTS
NoneNoneNoneNone3.3 (a) The tenderer shall produce Critical Machineries (50pec to be owned & 50pec to be hired with supporting documents) Trucks/Tipper/Dumpers - 4 Nos Excavators/Dozers- 4 Nos Mechanical Concrete Mixer with Hopper - 4 Nos Centering Sheet - 5400 Sqm Water Tanker of minimum Capacity 6000 Liters - 4 Nos Laboratory Equipments 2 UnitsCapabilities of VendorNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneOthers -- RELEVANT DOCUMENTS
NoneNoneNoneNoneTenderer has to furnish Annual turnover for the last 5 years i.e. 2019-20, 2020-21, 2021-22, 2022-23 & 2023-24 Duly certified by CA with UDIN.Financial StatusNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneAudited CA Certificate of Annual Turnover
NoneNoneNoneNone3.2 (a) Achieved in at least two financial years a minimum financial turnover (in all classes of civil engineering construction works only) of Rs 6666.00 Lakhs. Duly certified by CA with UDIN.Financial StatusNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneAudited CA Certificate of Annual Turnover
NoneNoneNoneNone3.3 (b) The tenderer has to furnish liquid assets and /or availability of credit facilities of no less than Rs: 833.30 Lakhs Credit lines/ letter of credit/ certificates from Nationalized/ Scheduled banks.Financial StatusNone
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneLine of Credit
NoneNoneNoneNoneThe Tenderer shall have valid Class-I KPWD/CPWD/MES/Railways/Public sectors licence.OthersRELEVANT DETAILS
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNonePWD Registration Certificate (Class I/II/III/IV)
NoneNoneNoneNoneThe tenderer has to furnish Company Profile and details of Technical Personnel working/Associated with him the qualification and experience of individual are to be mentioned.OthersRELEVANT DETAILS
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneOthers -- RELEVANT DOCUMENTS
NoneNoneNoneNoneThe Tenderer shall give details of the works on hand (Present contract commitment) duly signed by the bidder.OthersRELEVANT DETAILS
createdTsversioncreatedDatemodifiedDatedocumentName
NoneNoneNoneNoneOthers -- RELEVANT DOCUMENTS
tenderCriterionDocumentList
documentNameoptionaldocumentTypeText
Annual Turnover CertificateTrueTechnical Bid
Company Registration CertificateTrueTechnical Bid
tenderWorkLocationList
tenderAddress
createdTs1726218655000
version0
createdDateNone
modifiedDateNone
blockNumberOffice of the Superintending Engineer 1st floor KREIS Cunningham Road Bangalore
streetNone
cityBangalore
stateKarnataka
pin560052
tenderRecallDTONone