PLAN DE PASSATION DE
MARCHES (PPM) REVISE DU PIDACC/BN COMPOSANTE COTE D'VOIRE- VERSION DÉTAILLÉE
POUR L'ACQUISITION DES SERVICES DE CONSULTANTS 2024
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Pays / Organe d'Exécution :
|
REPUBLIQUE
DE COTE D' IVOIRE
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nom du Projet/Programme :
|
Programme
Intégré de Développement Et d’Adaptation au Changement Climatique dans le
Bassin du Niger
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Numéro du Prêt/Don :
|
FEM/ABN
DON:
5550155001601 / FSC Don: 5565155001751 / EU Don: 5110155000504
/ FAD Prêt: 2100150040895/ FSC Prêt:5565130000651 / GCF Don:
5585155000002 /
GCF Prêt: 5585150000004
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Période Couverte par ce PPM :
|
01/01/2024
au 31/12/2024
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Informations de base
|
|
AMI
|
Termes de Référence
|
Liste Restreinte
|
|
Demande de Propositions (DDP)
|
Évaluation des Propositions
|
|
Finalisation
du Contrat
|
|
|
|
Ordre
|
Système de
passation de marchés+
|
Description
|
|
Mode de Sélection
|
Forfait ou Temps
Passé
|
Coût Estimatif
(000 UC)**
|
Contrôle et Audit
–Examen Préalable / à Postériori de la Banque***
|
Plan Révisé ou
Réel*+
|
Date de
publication
|
Date de Clôture
|
Date de
Soumission
|
Date de l'Avis de
Non-Objection
|
Date de
Soumission
|
Date de l'Avis de
Non-Objection
|
Plan Révisé ou
Mis à Jour
|
Date de
Soumission des Documents de DDP
|
Date de l'Avis de
Non-Objection
|
Date d'Émission
de la DDP
|
Date de limite de
de dépôt /d'ouverture des Propositions
|
Date de
soumission du Rapport technique
|
Date de l'Avis de
Non-Objection
|
Date d'Ouverture
des Propositions financières
|
Date de
Soumission du Rapport combiné
|
Date de l'Avis de
Non-Objection
|
Plan Révisé ou
Mis à Jour
|
Date
d'Attribution du Contrat
|
Montant du
Contrat (000 de F CFA) *++
|
Date de Signature
du Contrat
|
Date d'Achèvement
du Contrat
|
|
|
|
1
|
Banque
|
ASSISTANCE
TECHNIQUE A L'ELABORATION DES PROJETS ET SOUS-PROJETS
|
|
SBQC
|
Forfait
|
624
|
Examen Préalable
|
Plan
|
15/09/2018
|
30/09/2018
|
08/10/2018
|
22/10/2018
|
08/10/2018
|
22/10/2018
|
Plan
|
08/10/2018
|
22/10/2018
|
27/10/2018
|
26/11/2018
|
06/12/2018
|
11/12/2018
|
18/12/2018
|
25/12/2018
|
08/01/2019
|
Plan
|
13/01/2019
|
487,199
|
18/01/2019
|
23/11/2022
|
|
|
|
Assistance technique à l'élaboration des projets et sous projets
|
SBQC
|
Forfait
|
294.50
|
Examen Préalable
|
Réel
|
12/10/2020
|
27/10/2020
|
11/08/2020
|
08/09/2020
|
15/02/2021
|
20/04/2021
|
Réel
|
15/02/2021
|
20/04/2021
|
29/04/2021
|
31/05/2021
|
26/08/2021
|
08/10/2021
|
20/10/2021
|
28/01/2022
|
01/04/2022
|
Réel
|
01/04/2022
|
233,073
|
05/05/2022
|
31/12/2024
|
|
|
|
Formation de 40 groupements de paysans sur la mise en place et
la gestion des pépinières
|
SBQC
|
Forfait
|
51.48
|
Examen Préalable
|
Réel
|
12/10/2020
|
27/10/2020
|
11/08/2020
|
08/09/2020
|
15/02/2021
|
20/04/2021
|
Réel
|
15/02/2021
|
20/04/2021
|
29/04/2021
|
31/05/2021
|
26/08/2021
|
08/10/2021
|
20/10/2021
|
28/01/2022
|
01/04/2022
|
Réel
|
01/04/2022
|
40,743.50
|
05/05/2022
|
31/12/2024
|
|
|
|
Appui à la mise en oeuvre des mesures ES
|
SBQC
|
Forfait
|
170.58
|
Examen Préalable
|
Réel
|
12/10/2020
|
27/10/2020
|
11/08/2020
|
08/09/2020
|
15/02/2021
|
20/04/2021
|
Réel
|
15/02/2021
|
20/04/2021
|
29/04/2021
|
31/05/2021
|
26/08/2021
|
08/10/2021
|
20/10/2021
|
28/01/2022
|
01/04/2022
|
Réel
|
01/04/2022
|
135,000
|
05/05/2022
|
31/12/2024
|
|
|
|
Organisation et formation des acteurs du sous-secteur de la
pêche
|
SBQC
|
Forfait
|
38.29
|
Examen Préalable
|
Réel
|
12/10/2020
|
27/10/2020
|
11/08/2020
|
08/09/2020
|
15/02/2021
|
20/04/2021
|
Réel
|
15/02/2021
|
20/04/2021
|
29/04/2021
|
31/05/2021
|
26/08/2021
|
08/10/2021
|
20/10/2021
|
28/01/2022
|
01/04/2022
|
Réel
|
01/04/2022
|
30,300
|
05/05/2022
|
31/12/2024
|
|
|
|
Campagne de sensibilisation des usagers sur la lutte contre la
pollution
|
SBQC
|
Forfait
|
6.64
|
Examen Préalable
|
Réel
|
12/10/2020
|
27/10/2020
|
11/08/2020
|
08/09/2020
|
15/02/2021
|
20/04/2021
|
Réel
|
15/02/2021
|
20/04/2021
|
29/04/2021
|
31/05/2021
|
26/08/2021
|
08/10/2021
|
20/10/2021
|
28/01/2022
|
01/04/2022
|
Réel
|
01/04/2022
|
5,256
|
05/05/2022
|
31/12/2024
|
|
|
|
Organisation et formation des comités de 28 unités de gestion
des infrastructures
|
|
|
114.86
|
Examen Préalable
|
Réel
|
12/10/2020
|
27/10/2020
|
11/08/2020
|
08/09/2020
|
15/02/2021
|
20/04/2021
|
Réel
|
15/02/2021
|
20/04/2021
|
29/04/2021
|
31/05/2021
|
26/08/2021
|
08/10/2021
|
20/10/2021
|
28/01/2022
|
01/01/2022
|
Réel
|
01/04/2022
|
90,900
|
05/05/2022
|
31/12/2024
|
|
|
|
Accompagnement agro-climatique des producteurs
|
SBQC
|
Forfait
|
31.59
|
Examen Préalable
|
Réel
|
12/10/2020
|
27/10/2020
|
11/08/2020
|
08/09/2020
|
15/02/2021
|
20/04/2021
|
Réel
|
15/02/2021
|
20/04/2021
|
29/04/2021
|
31/05/2021
|
26/08/2021
|
08/10/2021
|
20/10/2021
|
28/01/2022
|
01/04/2022
|
Réel
|
01/04/2022
|
25,000
|
05/05/2022
|
31/12/2024
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2
|
Banque
|
ELABORATION
DU SCHEMA DIRECTEUR DU SOUS BASSIN
|
SBQC
|
Forfait
|
159
|
Examen Préalable
|
Plan
|
15/10/2018
|
30/10/2018
|
07/11/2018
|
21/11/2018
|
07/11/2018
|
21/11/2018
|
Plan
|
07/11/2018
|
21/11/2018
|
26/11/2018
|
26/12/2018
|
05/01/2019
|
10/01/2019
|
17/01/2019
|
24/01/2019
|
07/02/2019
|
Plan
|
12/02/2019
|
125,837
|
17/02/2019
|
11/08/2019
|
|
|
|
SBQC
|
Forfait
|
128.56
|
Examen Préalable
|
Réel
|
23/06/2020
|
14/07/2020
|
28/05/2020
|
08/06/2020
|
15/02/2021
|
20/04/2021
|
Réel
|
29/04/2021
|
20/04/2021
|
29/04/2021
|
31/05/2021
|
23/07/2021
|
24/08/2021
|
02/09/2021
|
01/10/2021
|
06/11/2021
|
Réel
|
13/11/2021
|
101,750
|
17/12/2021
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3
|
Banque
|
AUDIT
COMPTABLE , FINANCIER DES COMPTES ET DE LA PASSATION DES MARCHES DE L'UGP
|
|
SMC
|
Forfait
|
62
|
Examen Préalable
|
Plan
|
15/07/2019
|
30/07/2019
|
07/08/2019
|
21/08/2019
|
07/08/2019
|
21/08/2019
|
Plan
|
07/08/2019
|
21/08/2019
|
26/08/2019
|
25/09/2019
|
05/10/2019
|
10/10/2019
|
17/10/2019
|
24/10/2019
|
07/11/2019
|
Plan
|
12/11/2019
|
49,068.7
|
17/11/2019
|
25/02/2020
|
|
|
|
AUDIT
COMPTABLE , FINANCIER DES COMPTES ET DE LA PASSATION DES MARCHES DE L'UGP
(Exercice 2019-2020 et 2021
|
SMC
|
Forfait
|
15.18
|
Examen Préalable
|
Révisé
|
20/04/2021
|
06/05/2021
|
27/01/2021
|
12/04/2021
|
14/06/2021
|
10/07/2021
|
Réel
|
14/06/2021
|
14/07/2021
|
15/07/2021
|
16/08/2021
|
14/09/2021
|
27/09/2021
|
07/10/2021
|
15/10/2021
|
06/11/2021
|
Réel
|
07/11/2021
|
12,010
|
12/11/2021
|
|
|
|
|
AUDIT
COMPTABLE , FINANCIER DES COMPTES ET DE LA PASSATION DES MARCHES DE L'UGP
(Exercice 2022 , 2023 et 2024)
|
SMC
|
Forfait
|
11.37
|
Examen Préalable
|
Réel
|
22/11/22
|
19/12/22
|
17/07/22
|
25/08/22
|
27/12/22
|
26/03/23
|
Réel
|
27/12/22
|
26/03/22
|
25/03/22
|
08/09/22
|
25/01/23
|
23/02/23
|
08/09/22
|
23/03/23
|
05/04/2023
|
Réel
|
25/05/2023
|
9,000
|
07/04/2023
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4
|
Banque
|
ETUDE ET CONTRÔLE DES TRAVAUX D'INFRASTRUCTURES
|
|
SBQC
|
Forfait
|
211
|
Examen Préalable
|
Plan
|
15/10/2018
|
30/10/2018
|
07/11/2018
|
21/11/2018
|
07/11/2018
|
21/11/2018
|
Plan
|
07/11/2018
|
21/11/2018
|
26/11/2018
|
26/12/2018
|
05/01/2019
|
10/01/2019
|
17/01/2019
|
24/01/2019
|
07/02/2019
|
Plan
|
12/02/2019
|
167,000
|
17/02/2019
|
25/10/2020
|
|
|
|
Recrutement du consultant pour la réalisation des études, du
suivi et contrôle des infrastructures
|
SBQC
|
Forfait
|
211.01
|
Examen Préalable
|
Réel
|
13/10/2020
|
27/10/2020
|
12/03/2020
|
29/09/2020
|
24/02/2021
|
18/08/2021
|
Réel
|
24/02/2021
|
18/08/2021
|
24/08/2021
|
28/09/2021
|
23/10/20221
|
07/12/2021
|
14/12/2021
|
13/04/2023
|
09/05/2023
|
Réel
|
12/05/2023
|
167,000
|
21/06/2023
|
30/11/2024
|
|
|
|
Réhabilitation de 10 retenues d'eau
|
SBQC
|
Forfait
|
175.69
|
Examen Préalable
|
Réel
|
13/10/2020
|
27/10/2020
|
12/03/2020
|
29/09/2020
|
24/02/2021
|
18/08/2021
|
Réel
|
24/02/2021
|
18/08/2021
|
24/08/2021
|
28/09/2021
|
23/10/20221
|
07/12/2021
|
14/12/2021
|
13/04/2023
|
09/05/2023
|
Réel
|
12/05/2023
|
139,050
|
21/06/2023
|
30/11/2024
|
|
|
|
Empoissonnement de 10 retenues d'eau
|
SBQC
|
Forfait
|
16.36
|
Examen Préalable
|
Réel
|
13/10/2020
|
27/10/2020
|
12/03/2020
|
29/09/2020
|
24/02/2021
|
18/08/2021
|
Réel
|
24/02/2021
|
18/08/2021
|
24/08/2021
|
28/09/2021
|
23/10/20221
|
07/12/2021
|
14/12/2021
|
13/04/2023
|
09/05/2023
|
Réel
|
12/05/2023
|
12,950
|
21/06/2023
|
30/11/2024
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5
|
Banque
|
ETUDE
DE FAISABILITE POUR L'OPERALISATION DES PSE
|
SQC
|
Forfait
|
13
|
Examen Préalable
|
Plan
|
15/09/2018
|
30/09/2018
|
08/10/2018
|
22/10/2018
|
08/10/2018
|
22/10/2018
|
Plan
|
08/10/2018
|
22/10/2018
|
27/10/2018
|
26/11/2018
|
06/12/2018
|
11/12/2018
|
18/12/2018
|
25/12/2018
|
08/01/2019
|
Plan
|
13/01/2019
|
10,289
|
18/01/2019
|
10/09/2019
|
|
|
|
CI
|
Forfait
|
12.99
|
Examen Préalable
|
Réel
|
22/11/2022
|
08/12/2022
|
27/07/2022
|
25/08/2022
|
28/12/2022
|
15/02/2023
|
Réel
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
31/05/2023
|
07/07/2023
|
Réel
|
10/07/2023
|
10,278.66
|
21/08/2023
|
22/09/2023
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6
|
Banque
|
ETUDE
ET CONTRÔLE DES TRAVAUX MECANIQUES (DESENSABLEMENT)
|
SBQC
|
Temps Passé
|
83
|
Examen Préalable
|
Plan
|
15/09/2018
|
30/09/2018
|
08/10/2018
|
22/10/2018
|
08/10/2018
|
22/10/2018
|
Plan
|
08/10/2018
|
22/10/2018
|
27/10/2018
|
26/11/2018
|
06/12/2018
|
11/12/2018
|
18/12/2018
|
25/12/2018
|
08/01/2019
|
Plan
|
13/01/2019
|
65,689
|
18/01/2019
|
27/10/2020
|
|
|
|
SBQC
|
Temps Passé
|
|
Examen Préalable
|
Révisé
|
24/01/2023
|
09/02/2023
|
30/11/2022
|
12/01/2023
|
14/03/2023
|
15/05/2023
|
Réel
|
14/03/2023
|
15/05/2023
|
26/05/2023
|
27/06/2023
|
07/08/2023
|
|
|
|
|
Réel
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7
|
Banque
|
APPUI
A LA MISE A NIVEAU DES STATIONS HYDROMETRIQUES SUR LE FLEUVE NIGER ET SES
AFFLUENTS CÔTE CÔTE D'IVOIRE (En entente Directe
avec la Direction de l’Hydrologie)
|
SBQC
|
Forfait
|
38
|
posteriorie
|
Plan
|
15/02/2019
|
02/03/2019
|
10/03/2019
|
24/03/2019
|
10/03/2019
|
24/03/2019
|
Plan
|
10/03/2019
|
24/03/2019
|
29/03/2019
|
28/04/2019
|
08/05/2019
|
13/05/2019
|
20/05/2019
|
27/05/2019
|
10/06/2019
|
Plan
|
15/06/2019
|
30,074
|
20/06/2019
|
13/09/2019
|
|
|
|
ED
|
Forfait
|
38
|
Examen Préalable
|
Révisé
|
NA
|
NA
|
22/02/2024
|
07/03/2024
|
NA
|
NA
|
Révisé
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
Révisé
|
14/03/2024
|
30,074
|
19/03/2024
|
03/08/2022
|
|
|
|
|
|
|
|
Réel
|
|
|
|
|
|
|
Réel
|
|
|
|
|
|
|
|
|
|
Réel
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8
|
Banque
|
ETUDE
ET CONTRÔLE DES INFRASTRUCTURES COMMUNAUTAIRES
|
SBQC
|
Temps Passé
|
162
|
Examen Préalable
|
Plan
|
15/10/2018
|
30/10/2018
|
07/11/2018
|
21/11/2018
|
07/11/2018
|
21/11/2018
|
Plan
|
07/11/2018
|
21/11/2018
|
26/11/2018
|
26/12/2018
|
05/01/2019
|
10/01/2019
|
17/01/2019
|
24/01/2019
|
07/02/2019
|
Plan
|
12/02/2019
|
89,657.28
|
17/02/2019
|
25/10/2020
|
|
|
|
SBQC
|
Temps Passé
|
111.09
|
Examen Préalable
|
Réel
|
01/03/2022
|
17/03/2022
|
16/09/2021
|
29/01/2022
|
19/10/2022
|
15/02/2023
|
Réel
|
19/10/2022
|
15/02/2023
|
20/02/2023
|
28/03/2023
|
12/05/2023
|
18/07/2023
|
01/08/2023
|
19/09/2023
|
|
Réel
|
|
87,920
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
9
|
Banque
|
ELABORATION
ET ACTUALISATION DE 7,5 PLANS COMMUNAUTAIRES D'ADAPTATION AUX CHANGEMENTS
CLIMATIQUES
|
SBQC
|
Forfait
|
96
|
Examen Préalable
|
Plan
|
15/12/2018
|
30/12/2018
|
07/01/2019
|
21/01/2019
|
07/01/2019
|
21/01/2019
|
Plan
|
07/01/2019
|
21/01/2019
|
26/01/2019
|
25/02/2019
|
07/03/2019
|
12/03/2019
|
19/03/2019
|
26/03/2019
|
09/04/2019
|
Plan
|
14/04/2019
|
75,977
|
19/04/2019
|
Elabi
|
|
|
|
SBQC
|
Forfait
|
|
Examen Préalable
|
Réel
|
01/11/2022
|
17/11/2022
|
27/05/2022
|
05/07/2022
|
28/12/2022
|
22/03/2023
|
Réel
|
28/12/2022
|
22/03/2023
|
27/03/2023
|
10/05/2023
|
29/06/2023
|
13/09/2023
|
26/09/2023
|
|
|
Réel
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
10
|
Banque
|
ELABORATION
DU MANUEL DE PROCEDURES DU PROJET
|
SQC
|
Forfait
|
14
|
Examen Préalable
|
Plan
|
15/12/2018
|
30/12/2018
|
07/01/2019
|
21/01/2019
|
07/01/2019
|
21/01/2019
|
Plan
|
07/01/2019
|
21/01/2019
|
26/01/2019
|
25/02/2019
|
07/03/2019
|
12/03/2019
|
19/03/2019
|
26/03/2019
|
09/04/2019
|
Plan
|
14/04/2019
|
11,080
|
19/04/2019
|
12/08/2019
|
|
|
|
|
|
|
|
Réel
|
|
|
|
|
|
|
Réel
|
|
|
|
|
|
|
|
|
|
Réel
|
|
|
|
|
|
|
|
CONSULTANT INDIVIDUEL
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
11
|
Banque
|
ELABORATION
DU CADRE DE GESTION ENVIRONNEMENTAL ET SOCIAL DE LA COMPOSANTE CÔTE
D'IVOIRE
|
SBQC
|
Forfait
|
32.00
|
Examen Préalable
|
Plan
|
15/02/2019
|
02/03/2019
|
10/03/2019
|
24/03/2019
|
10/03/2019
|
24/03/2019
|
Plan
|
10/03/2019
|
24/03/2019
|
29/03/2019
|
28/04/2019
|
08/05/2019
|
13/05/2019
|
20/05/2019
|
27/05/2019
|
10/06/2019
|
Plan
|
15/06/2019
|
25,326
|
20/06/2019
|
28/09/2019
|
|
|
|
CI
|
Forfait
|
19.11
|
Examen Préalable
|
Réel
|
15/12/2020
|
15/01/2021
|
13/06/2020
|
14/11/2019
|
29/04/2021
|
18/08/2021
|
Réel
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
30/09/2021
|
07/10/2021
|
Réel
|
14/10/2021
|
15,124
|
19/10/2021
|
14/01/2021
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
12
|
Banque
|
ELABORATION
DU MANUEL DE FINANCEMENT DES PROJETS ET DES SOUS PROJETS
|
CI
|
Forfait
|
39
|
Examen Préalable
|
Plan
|
15/12/2018
|
30/12/18
|
07/01/2019
|
21/01/19
|
07/01/19
|
17/01/19
|
Plan
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
Plan
|
28/02/2019
|
30,866
|
13/02/2019
|
14/05/2019
|
|
|
|
CI
|
Forfait
|
21.79
|
Examen Préalable
|
Réel
|
01/05/20
|
13/05/20
|
07/11/2019
|
14/11/19
|
19/11/20
|
27/11/20
|
Réel
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
18/12/20
|
01/07/2021
|
Réel
|
02/08/2021
|
17,247
|
14/07/2021
|
25/10/2021
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
13
|
Banque
|
ELABORATION
DE 3 MANUELS/CATALOGUES TECHNIQUES D'AMELIORATION DE LA RESILIENCE
(agroforesterie,technologies agricoles résilientes,bonne pratiques)
|
CI
|
Forfait
|
38
|
Examen Préalable
|
Plan
|
15/02/2019
|
02/03/19
|
10/03/2019
|
24/03/19
|
10/03/19
|
20/03/19
|
Plan
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
Plan
|
01/05/2019
|
30,074
|
16/04/2019
|
30/06/2019
|
|
|
|
CI
|
Forfait
|
17.63
|
Examen Préalable
|
Réel
|
07/05/20
|
26/05/20
|
25/10/2019
|
3/13/2020
|
29/09/20
|
23/10/20
|
Réel
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
12/17/2020
|
01/07/2021
|
Réel
|
02/08/2021
|
13,950
|
14/07/2021
|
24/09/2021
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
14
|
Banque
|
FORMATION
DES ASSISTANTS TECHNIQUES SUR LES DIFFERENTES THEMATIQUES
(agroforesterie,paquets technologiques,lutte contre les feux)
|
CI
|
Forfait
|
31
|
Examen Préalable
|
Plan
|
15/02/2019
|
02/03/19
|
10/03/2019
|
20/03/19
|
10/03/19
|
20/03/19
|
Plan
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
Plan
|
01/05/2019
|
24,209
|
16/04/2019
|
15/06/2019
|
|
|
|
CI
|
Forfait
|
2.58
|
Examen Préalable
|
Réel
|
07/07/20
|
15/07/20
|
07/05/2020
|
3/13/2020
|
29/09/20
|
23/10/20
|
Réel
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
12/17/2020
|
01/07/2021
|
Réel
|
02/08/2021
|
2,040
|
14/07/2021
|
08/10/2021
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
15
|
Banque
|
ELABORATION
DES MODES DE GESTION DES INFRASTRUCTURES HYDRO AGRICOLES ET PASTORALES
|
CI
|
Forfait
|
26
|
posteriorie
|
Plan
|
15/02/2019
|
02/03/19
|
08/01/2019
|
22/01/19
|
10/03/19
|
20/03/19
|
Plan
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
Plan
|
01/05/2019
|
20,577
|
16/04/2019
|
14/08/2019
|
|
|
|
CI
|
Forfait
|
26
|
posteriorie
|
Révisé
|
14/02/2024
|
29/02/24
|
08/03/2024
|
22/03/24
|
08/03/24
|
18/03/24
|
Révisé
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
Révisé
|
25/03/2024
|
20,305
|
30/03/2024
|
29/04/2024
|
|
|
|
|
|
|
|
Réel
|
|
|
|
|
|
|
Réel
|
|
|
|
|
|
|
|
|
|
Réel
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
16
|
Banque
|
PERSONNEL
CLE DE l'UNITE DE GESTION DU PROJET
|
CI
|
Forfait
|
332
|
Examen Préalable
|
Plan
|
15/09/18
|
30/09/18
|
08/08/2018
|
22/08/18
|
08/10/18
|
18/10/18
|
Plan
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
Plan
|
29/11/2018
|
262,755
|
14/11/2018
|
31/12/2025
|
|
|
|
CI
|
Forfait
|
327.60
|
Examen Préalable
|
Réel
|
15/09/19
|
30/09/19
|
08/08/2018
|
22/08/18
|
08/10/19
|
18/10/19
|
Réel
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
Réel
|
17/11/2019
|
259,275
|
02/12/2019
|
31/12/2025
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
17
|
Banque
|
PERSONNEL
CLE DE L'ANTENNE D'ODIENNE
|
CI
|
Forfait
|
161
|
Examen Préalable
|
Plan
|
15/09/18
|
30/09/18
|
08/08/2018
|
22/08/18
|
08/10/18
|
18/10/18
|
Plan
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
Plan
|
29/11/2018
|
127,420
|
14/11/2018
|
07/01/2020
|
|
|
|
CI
|
Forfait
|
161.00
|
Examen Préalable
|
Réel
|
21/04/19
|
06/05/19
|
14/03/2019
|
28/03/19
|
14/05/19
|
24/05/19
|
Réel
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
Réel
|
05/07/2019
|
127,420
|
20/06/2019
|
12/08/2020
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
18
|
Banque
|
MISE EN PLACE SYSTÈME SUIVI-EVALUATION
AXE SUR LES RESULTATS
|
CI
|
Forfait
|
25.80
|
Examen Préalable
|
Plan
|
15/09/18
|
30/09/18
|
08/08/2018
|
18/08/18
|
08/10/18
|
18/10/18
|
Plan
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
Plan
|
29/11/2018
|
20,152
|
14/11/2018
|
12/02/2019
|
|
|
|
CI
|
Forfait
|
22.38
|
Examen Préalable
|
Réel
|
15/06/21
|
01/07/21
|
31/05/20
|
31/05/21
|
25/08/21
|
18/03/22
|
Réel
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
Réel
|
08/10/2022
|
17,711.7
|
10/10/2022
|
24/11/2022
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
19
|
Banque
|
REVUE A MI PARCOURS DU PIDACC/BN
COMPOSANTE CÔTE D'IVOIRE
|
|
|
-
|
|
Plan
|
|
|
|
|
|
|
Plan
|
|
|
|
|
|
|
|
|
|
Plan
|
|
|
|
|
|
|
|
CI
|
Forfait
|
13.11
|
Examen Préalable
|
Réel
|
22/11/22
|
19/12/22
|
17/07/22
|
25/08/22
|
27/12/22
|
26/03/23
|
Réel
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
|
Réel
|
25/05/2023
|
10,372
|
01/08/2023
|
15/12/2023
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
20
|
Banque
|
AUDIT
ENVIRONNEMENTAL ET SOCIAL DU PIDACC/BN
|
|
|
|
|
|
Plan
|
|
|
|
|
|
|
Plan
|
|
|
|
|
|
|
|
|
|
Plan
|
|
|
|
|
|
|
|
AUDIT ENVIRONNEMENTAL ET SOCIAL AU TITRE DE L'ANNEE 2023 et
2024
|
CI
|
Forfait
|
20.22
|
Examen Préalable
|
Révisé
|
22/03/24
|
06/04/24
|
22/03/2024
|
05/04/24
|
20/04/24
|
04/05/24
|
Révisé
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
09/05/24
|
NA
|
23/05/2024
|
revisé
|
28/05/2024
|
16,000
|
31/05/2024
|
30/06/2024
|
|
|
|
AUDIT ENVIRONNEMENTAL ET SOCIAL AU TITRE DE L'ANNEE 2019-2020,
2021 et 2022
|
CI
|
Forfait
|
28.88
|
Examen Préalable
|
Réel
|
07/03/23
|
23/03/23
|
03/02/23
|
28/02/23
|
16/05/23
|
18/07/23
|
Réel
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
17/08/23
|
31/08/23
|
|
Réel
|
|
22,860
|
|
|
|
|
|
FORMATION
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
21
|
|
Bourse
d'étude supérieures (doctorale) en Cacao culture sous ombrage
|
ED
|
Forfait
|
26.054
|
Examen Préalable
|
Plan
|
NA
|
NA
|
01/05/19
|
15/05/19
|
NA
|
NA
|
Plan
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
Plan
|
18/05/2019
|
20,304
|
01/02/2020
|
31/07/2020
|
|
|
|
ED
|
Forfait
|
26.054
|
Examen Préalable
|
Révisé
|
NA
|
NA
|
20/01/24
|
03/02/24
|
NA
|
NA
|
Révisé
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
Révisé
|
06/02/2024
|
20,347
|
11/02/2024
|
31/12/2024
|
|
|
|
|
|
|
Examen Préalable
|
Réel
|
|
|
|
|
|
|
Réel
|
|
|
|
|
|
|
|
|
|
Réel
|
|
|
|
|
|
|
|
CONVENTIONS
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
22
|
Banque
|
ENCADREMENT
TECHNIQUE DES PLANTATIONS ET SUIVI DES ACTIVITES AVEC LA DIRECTION GENERALE
DES FORETS ET DE LA FAUNE (DGFF)
|
ED
|
Forfait
|
140.87
|
Examen Préalable
|
Plan
|
NA
|
NA
|
28/02/19
|
14/03/19
|
NA
|
NA
|
Plan
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
Plan
|
16/05/2019
|
111,490
|
15/05/2019
|
09/05/2020
|
|
|
|
ED
|
Forfait
|
140.87
|
Examen Préalable
|
Réel
|
NA
|
NA
|
20/05/20
|
23/03/22
|
NA
|
NA
|
Réel
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
Réel
|
23/03/22
|
111,490
|
18/04/22
|
31/12/24
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
23
|
Banque
|
ENCADREMENT
DES PRODUCTEURS DES 3000 HA DE CULTURES AGRICOLES ET DES ELEVEURS EN
CONSEIL DE GESTION AVEC L'AGENCE NATIONALE DE L'EQUIPEMENT RURAL (ANADER)
|
ED
|
Forfait
|
197.00
|
Examen Préalable
|
Plan
|
NA
|
NA
|
31/03/19
|
14/04/19
|
NA
|
NA
|
Plan
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
Plan
|
16/06/2019
|
155,912
|
15/06/2019
|
09/06/2020
|
|
|
|
ED
|
Forfait
|
160.90
|
Examen Préalable
|
Réel
|
NA
|
NA
|
05/11/21
|
01/02/22
|
NA
|
NA
|
Réel
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
Réel
|
12/10/22
|
127,340
|
26/10/22
|
31/12/24
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
24
|
Banque
|
SUIVI
DE LA SECURITE ALIMENTAIRE AVEC LA DIRECTION GENERALE DE LA SECURITE
ALIMENTAIRE (DGPSA)
|
ED
|
Forfait
|
68
|
Examen Préalable
|
Plan
|
NA
|
NA
|
30/04/19
|
14/05/19
|
NA
|
NA
|
Plan
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
Plan
|
16/07/2019
|
52,800
|
15/07/2019
|
09/07/2020
|
|
|
|
ED
|
Forfait
|
66.71
|
Examen Préalable
|
Réel
|
NA
|
NA
|
17/06/22
|
29/08/22
|
NA
|
NA
|
Réel
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
Réel
|
28/11/2022
|
52,799
|
22/12/2022
|
31/12/2024
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
25
|
Banque
|
Suivi et encadrement des travaux de Plantations de 1 700 ha
de reboisements dans les forêts classées de la portion nationale du bassin
du fleuve Niger et de l’Aménagement de 96 km des parcours de transhumance
dans la forêt classée de Palé (Par la SODEFOR)
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
ED
|
Forfait
|
98.05
|
Examen Préalable
|
Révisé
|
NA
|
NA
|
29/08/23
|
13/12/23
|
NA
|
NA
|
Révisé
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
révisé
|
05/01/2024
|
77,598.60
|
15/01/2024
|
31/12/2025
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Suivi
et surveillance environnementale par l'Agence Nationale de l'Environnement
(ANDE)
|
|
ED
|
Forfait
|
39
|
Examen Préalable
|
Plan
|
NA
|
NA
|
28/02/19
|
14/03/19
|
NA
|
NA
|
Plan
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
Plan
|
16/05/2019
|
30,457
|
15/05/2019
|
09/05/2020
|
|
|
|
|
|
|
ED
|
Forfait
|
39.00
|
Examen Préalable
|
Révisé
|
NA
|
NA
|
13/02/24
|
28/02/24
|
NA
|
NA
|
Révisé
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
NA
|
révisé
|
05/03/2024
|
30,457
|
08/03/2024
|
31/12/2025
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2,578.736
|
|
Plan
|
|
Plan
|
|
Plan
|
|
1,993,755.980
|
|
|
|
|
|
|
|
|
|
246.976
|
Révisé
|
Révisé
|
Révisé
|
194,781.300
|
|
|
|
|
|
|
|
2,372.744
|
Réel
|
Réel
|
Réel
|
1,877,860.690
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
*
|
Insérer le système ou le régime de passation de marché utilisé
pour la transaction de passation de marché dans le cadre du projet (PMPs du
SPME, de la Banque ou de Tierce Partie)
|
|
|
|
|
-
|
|
|
|
|
|
|
+
|
Si applicable
|
|
|
|
|
|
|
|
|
|
|
|
**
|
Coût total du Package, du lot ou de la transaction de
passation de marché en UC figurant dans le REP
|
|
|
|
|
|
|
|
|
|
|
|
***
|
Indiquer la modalité de contrôle - Audit des acquisitions dans
le cadre du SPME / Examen préalable / Examen a posteriori
|
|
|
|
|
|
|
|
|
|
|
|
*+
|
Conserver le « Plan » de passation de marchés convenu lors de
la négociation et approuvé par les Conseils d'administration, pendant toute
la durée du projet
|
|
|
|
|
|
|
|
|
|
|
|
|
« Révisé » inclut toutes les mises à jour et révisions
|
|
|
|
|
|
|
|
|
|
|
|
|
Enregistrer la date « réelle » d'achèvement de l'activité
|
|
|
|
|
|
|
|
|
|
|
|
*++
|
Le Modèle doit être adapté au processus d'appel d'offres en
deux étapes en ajoutant des colonnes appropriées pour la deuxième étape de
la période d'appel d'offres séquentielle et du processus d'évaluation des
soumissions
|
|
|
|
|
|
|
|
|
|
|
|
*+++
|
Indiquer la monnaie du contrat
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PLAN DE PASSATION
DE MARCHÉS - VERSION SIMPLIFIÉE POUR L'ACQUISITION DES BIENS EXERCICE 2024
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Pays / Organe d'Exécution :
|
|
REPUBLIQUE
DE COTE D' IVOIRE
|
|
|
|
|
Nom du Projet/Programme :
|
|
Programme
Intégré de Développement Et d’Adaptation au Changement Climatique dans le
Bassin du Niger
|
|
|
|
|
Numéro du Prêt/Don :
|
|
FEM/ABN
DON:
5550155001601 / FSC Don: 5565155001751 / EU Don: 5110155000504
|
|
|
|
|
|
|
|
|
FAD
Prêt: 2100150040895/ FSC Prêt:5565130000651 / GCF Don: 5585155000002 / GCF
Prêt: 5585150000004
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Période Couverte par ce PPM :
|
|
01/01/2024
au 31/12/2024
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Ordre
|
Système de
passation de marchés
|
Numéro du Package
|
Description du
Package
|
Catégorie--
|
Description du lot+
|
Coût Estimatif (000
UC)**
|
Mode de passation
de marchés
|
Contrôle et Audit -
Examen de la banque (Préalable /à Postériori)***
|
Date de publication
de l'AAO
|
Date limite de
dépôt / Date d'ouverture des Offres
|
Date d'attribution
du Contrat
|
Montant du Contrat
(000 FCFA) *+++
|
Date d'Achèvement
du Contrat
|
Commentaire pour
l'éxécution du contrat
|
|
|
|
|
|
|
|
1
|
SPMP
|
|
Acquisition et mise en circulation de 140 tricycles
|
Bien
|
Acquisition et mise en circulation de 140 tricycles
|
251
|
AOO
|
Contrôle et Audit
|
7/15/2018
|
3/11/2022
|
3/22/2022
|
196,018.00
|
5/19/2022
|
|
|
|
|
1
|
Acquisition et mise en circulation de 60 tricycles (pour doter
les GIE en tricycles (transformation d'attiéké et valorisation des PFNL)
|
106.14
|
AOO
|
Contrôle et Audit
|
4/16/2024
|
5/16/2024
|
6/7/2024
|
84,000
|
7/25/2024
|
|
|
|
|
|
Doter les groupement en (80) tricycles pour le transport des
plants en pépinière.
|
142.83
|
AOO
|
Contrôle et Audit
|
2/8/2022
|
8/14/2018
|
9/5/2018
|
113,040
|
5/19/2022
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2
|
SPMP
|
|
Acquisition de petits materiels agricoles pour l'equipement de
1000 ha de cultures maraicheres et de 1000 ha de manioc
|
Bien
|
|
256
|
AOO
|
Contrôle et Audit
|
7/15/2018
|
3/5/2023
|
3/27/2023
|
199,923.20
|
7/12/2023
|
|
|
|
|
1
|
Bien
|
Appuyer l'équipement de cultures maraîchères (1 000 ha)
|
131.95
|
CF
|
Contrôle et Audit
|
3/23/2024
|
4/22/2024
|
5/16/2024
|
104,427.12
|
8/29/2024
|
|
|
|
|
1
|
Bien
|
Appuyer l'équipement de cultures de manioc (1 000 ha)
|
131.95
|
CF
|
Contrôle et Audit
|
3/23/2024
|
4/22/2024
|
5/16/2024
|
104,427.12
|
8/29/2024
|
|
|
|
|
|
Bien
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3
|
SPMP
|
|
Acquisition de 20 machines agricoles et de 20 machines de
transformation d'attiéke et derive pour des groupements d'interet
économique
|
Bien
|
|
640
|
AOO
|
Contrôle et Audit
|
6/15/2018
|
7/25/2023
|
8/16/2023
|
499,808.00
|
9/2/2023
|
|
|
|
|
1
|
Bien
|
Equiper 20 Groupements d’Intérêt Economique (GIE) en
machinisme agricole
|
252.71
|
AOO
|
Contrôle et Audit
|
4/3/2024
|
5/3/2024
|
5/25/2024
|
200,000.00
|
6/11/2024
|
|
|
|
|
1
|
Bien
|
Doter 20 GIE de transformation d'attiéké et dérivé en
équipements de production
|
379.06
|
AOO
|
Contrôle et Audit
|
4/3/2024
|
5/3/2024
|
5/25/2024
|
300,000.00
|
6/11/2024
|
|
|
|
|
|
Bien
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4
|
SPMP
|
|
Acquisition de 94 kits pour la dissemination des technoligies
résilientes
|
Bien
|
|
239
|
AOO
|
Contrôle et Audit
|
2/15/2019
|
2/4/2022
|
2/15/2022
|
186,647.00
|
12/31/2022
|
|
|
|
|
4
|
Bien
|
Assurer la dissémination des technologies résilientes 44
kits)
|
113.79
|
CF
|
N/A
|
2/7/2023
|
1/0/1900
|
1/0/1900
|
102,338.25
|
1/0/1900
|
|
|
|
|
2
|
Bien
|
Fourniture et livraison de dix-sept (17) kits de semences
améliorées (Lot 1 : semences améliorées de Maïs, lot 2 : semences
améliorées de riz et lot 3 : boutures améliorées de manioc)
|
20.39
|
CF
|
Contrôle et Audit
|
1/25/2022
|
2/4/2022
|
2/15/2022
|
16,141
|
12/31/2022
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5
|
SPMP
|
|
Edition de 10.000 manuels techniques
|
Bien
|
Edition de 10.000 manuels techniques
|
38
|
PS
|
Contrôle et Audit
|
3/15/2019
|
1/0/1900
|
1/0/1900
|
29,676.00
|
1/0/1900
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
37.34
|
PS
|
Contrôle et Audit
|
11/9/2023
|
11/17/2023
|
11/20/2023
|
29,550.00
|
12/5/2023
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6
|
SPMP
|
|
Fourniture et mise en service de deux (02) véhicules Satation
Wagon 4X4 de 7 places et de neuf (09) véhciules bachés doubles cabines de
type 4X4
|
Bien
|
|
307
|
AOO
|
Contrôle et Audit
|
3/15/2019
|
9/16/2020
|
5/25/2021
|
239,750.60
|
1/0/1900
|
|
|
|
|
|
Fourniture et mise en service de deux (02) véhicules Satation
Wagon 4X4 de 7 places et de huit (08) véhciules bachés doubles cabines de
type 4X4
|
271.66
|
AOO
|
Contrôle et Audit
|
9/15/2020
|
9/16/2020
|
5/25/2021
|
215,000
|
|
Les deux (02) marchés issus de cette procédure d'acquisition ont
été résiliés. L'Agents Judicaire de l'Etat a été saisi
|
|
|
|
|
|
Fourniture et mise en circulation d'un (01) véhicule de type 4X4
|
25.46
|
ED
|
Contrôle et Audit
|
10/20/2023
|
N/A
|
N/A
|
20,150
|
12/15/2023
|
Le projet a acquis un véhicule par la procédure de Lettre de
Commande Valant Marché (LCVM)
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7
|
SPMP
|
|
Fourniture et mise en service de vingt (22) motos Cross de
type 150 CC pour vingt (20) Agents Techniques Forestiers et deux (02)
Agents de liaison
|
Bien
|
|
56
|
PS
|
Contrôle et Audit
|
3/16/2021
|
3/26/2021
|
5/28/2021
|
43,733.20
|
7/9/2021
|
|
|
|
|
|
Bien
|
Doter les AT en matériel roulant (22 motos)
|
41.70
|
PS
|
Contrôle et Audit
|
3/16/2021
|
3/30/2019
|
5/15/2019
|
33,000
|
9/11/2019
|
|
|
|
|
|
|
Doter les AT en matériel roulant (04 motos)
|
8.34
|
PS
|
Contrôle et Audit
|
1/19/2023
|
2/3/2023
|
4/6/2023
|
6,600
|
5/8/2023
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8
|
SPMP
|
|
Acquisition de petits matériels techniques pour équiper 700
comités de lutte contre les feux de brousse
|
Bien
|
|
90
|
PS
|
Contrôle et Audit
|
3/15/2019
|
1/0/1900
|
1/0/1900
|
70,285.50
|
1/0/1900
|
|
|
|
|
|
Bien
|
Doter les comités de lutte contre les feux de brousse en
matériel technique (700 comités)
|
82.13
|
PS
|
Contrôle et Audit
|
12/13/2023
|
12/28/2023
|
1/5/2023
|
65,000.00
|
1/7/2024
|
Procédure encours de
réalisation
|
|
|
|
|
Bien
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
9
|
SPMP
|
|
Acquisition de 1 kit d'analyse et équipements pour
l'opérationnalisation du dispositif gire en côte d'ivoire
|
Bien
|
|
128
|
AOO
|
Contrôle et Audit
|
3/15/2019
|
1/0/1900
|
1/0/1900
|
99,961.60
|
1/0/1900
|
|
|
|
|
|
Bien
|
Acquisition de 1 kit d'analyse pour l'opérationnalisation du
dispositif gire en côte d'ivoire
|
56.63
|
AOO
|
Contrôle et Audit
|
8/31/2023
|
10/17/2023
|
11/9/2023
|
44,821.00
|
12/24/2023
|
|
|
|
|
|
Bien
|
Acquisition d'équipements pour l'opérationnalisation du
dispositif gire en côte d'ivoire
|
63.03
|
AOO
|
Contrôle et Audit
|
8/31/2023
|
10/17/2023
|
11/9/2023
|
49,886.00
|
12/24/2023
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
10
|
SPMP
|
|
Acquisition de 5 pirogues, de 50 lots de petits matériels pour
les comités de gestion des infrastructures, 1 lot d'équipements pour 30
groupes vulnérables et 4 lots d'équipement pour les pme de GRN
|
Bien
|
|
531
|
AOO
|
Contrôle et Audit
|
3/15/2019
|
11/16/2023
|
12/8/2023
|
414,684.40
|
12/25/2023
|
|
|
|
|
|
Bien
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
11
|
SPMP
|
|
Acquisition de 1 lot de matériels informatique et
péri-informatique pour l’UGP et l'antenne
|
Bien
|
|
11
|
PSC
|
Contrôle
et Audit
|
3/15/2019
|
3/5/2021
|
3/22/2021
|
8,590
|
4/19/2021
|
|
|
|
|
|
Acquisitsion de 30 disques dur externe 01 gros serveur pour
Equiper les Agents Rureaux
|
5.4
|
PSC
|
Contrôle et Audit
|
1/26/2024
|
2/2/2024
|
2/4/2024
|
4,293
|
2/22/2024
|
Voir ANO de la BAD Réf : AHAI.2/LT/BAI/2023/02/032
Date : 23/02/2023 relatif à l'équipement des Agents Rureaux.
|
|
|
|
|
Acquisitsion de 24 ordinateurs portables pour Equiper les Agents
Rureaux
|
1.08
|
PSC
|
Contrôle et Audit
|
3/1/2021
|
3/5/2021
|
3/22/2021
|
7,735
|
4/19/2021
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
12
|
SPMP
|
|
Acquisition de 1 lot de matériels et de mobiliers de bureaux
pour l’UGP et l'antenne
|
Bien
|
|
11
|
PSC
|
Contrôle et Audit
|
3/15/2019
|
3/10/2021
|
3/22/2021
|
8,590
|
4/7/2021
|
|
|
|
|
|
|
16.37
|
PSC
|
Contrôle et Audit
|
3/5/2021
|
3/10/2021
|
3/22/2021
|
12,959
|
4/7/2021
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
13
|
|
|
Acquisition
d'un (01) lot d’équipements pour les animateurs ruraux
|
|
|
26.73
|
CF
|
Contrôle et Audit
|
|
|
|
21,153
|
|
|
|
|
|
|
|
|
Gros Serveur +Disque dur externe + Bureau ,et Table
+Fauteuil+Appareil photo numérique
|
7.38
|
CF
|
Contrôle et Audit
|
2/26/2024
|
3/2/2024
|
3/10/2024
|
5,840
|
3/28/2024
|
|
|
|
|
|
|
|
Acquisitsion d'un lot d'équipement (Matériel de protection
individuels, 14 GPS pour les Agents Rureaux.
|
19.35
|
CF
|
Contrôle et Audit
|
12/7/2022
|
12/13/2022
|
12/14/2022
|
15,313
|
12/30/2022
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
14
|
SPMP
|
|
Acquisition de 1 logiciel comptable y compris paramétrage et
formation
|
Bien
|
|
13
|
PSC
|
Contrôle et Audit
|
5/15/2019
|
5/30/2019
|
6/27/2019
|
10,152
|
8/12/2019
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Coût Total
|
|
|
|
|
2,571
|
|
|
2,007,820
|
|
|
|
|
|
|
|
|
|
|
1,203.1
|
964,485.5
|
|
|
|
|
|
|
|
|
786.31
|
629,195.00
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
*
|
Insérer le système ou le régime de passation de marché utilisé
pour la transaction de passation de marché dans le cadre du projet (PMPs du
SPME, de la Banque ou de Tierce Partie)
|
|
|
|
|
+
|
Si applicable
|
|
|
|
|
**
|
Coût total du Package, du lot ou de la transaction de
passation de marché en UC figurant dans le REP
|
|
|
|
|
***
|
Indiquer la modalité de contrôle - Audit des acquisitions dans
le cadre du SPME / Examen préalable / Examen a posteriori
|
|
|
|
|
*+
|
Conserver le « Plan » de passation de marchés convenu lors de
la négociation et approuvé par les Conseils d'administration, pendant toute
la durée du projet
|
|
|
|
|
|
« Révisé » inclut toutes les mises à jour et révisions
|
|
|
|
|
|
Enregistrer la date « réelle » d'achèvement de l'activité
|
|
|
|
|
*++
|
Le Modèle doit être adapté au processus d'appel d'offres en
deux étapes en ajoutant des colonnes appropriées pour la deuxième étape de
la période d'appel d'offres séquentielle et du processus d'évaluation des
soumissions
|
|
|
|
|
*+++
|
Indiquer la monnaie du contrat
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
[Disclaimer: The
below text is machine translated. For accurate information kindly refer the
above text in original language.]
|
PROCUREMENT PLAN -
SIMPLIFIED VERSION FOR THE ACQUISITION OF WORKS FY 2024
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Country / Executing Agency:
|
|
REPUBLIC
OF CÔTE D'IVOIRE
|
|
|
|
Name of Project/Program:
|
|
Integrated
Program for Development and Adaptation to Climate Change in the Niger Basin
|
|
|
|
Loan/Grant number:
|
|
GEF/ABN
GRANT :
5550155001601 / FSC Grant: 5565155001751 / EU
Grant: 5110155000504
|
|
|
|
|
|
|
|
FAD
Loan: 2100150040895 / FSC Loan: 5565130000651 / GCF Grant: 5585155000002 /
GCF Loan: 5585150000004
|
|
|
|
|
|
|
|
|
|
|
|
|
Period Covered by this PPM:
|
|
01/01/2024
to 12/31/2024
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Order
|
Procurement system
|
Package Number
|
Package Description
|
Category--
|
Description of the
lot+
|
Estimated Cost (000
UA)**
|
Procurement method
|
Control and Audit -
Examination of the bank (Prior/Posterior)***
|
AAO Publication
Date
|
Submission deadline
/ Bid opening date
|
Contract award date
|
Contract Amount
(000 FCFA) **++
|
Contract Completion
Date
|
Comment for the
execution of the contract
|
|
|
|
|
1
|
SPMP
|
|
Development of 20 rest parks for 200 ha of improved pasture
(10 ha + 1 water point)
|
Works
|
not applicable
|
256
|
AOO
|
Control and Audit
|
4/15/2019
|
5/30/2019
|
7/29/2019
|
199,923
|
2/9/2020
|
|
|
|
SPMP
|
1
|
Works
|
Development of 20 rest parks for 200 ha of improved pasture
(10 ha + 1 water point)
|
256.00
|
AOO
|
Control and Audit
|
4/24/2024
|
5/24/2024
|
6/23/2024
|
199,923
|
10/13/2024
|
|
|
|
SPMP
|
|
Works
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2
|
SPMP
|
|
Construction and equipment of farms for grasscutter farming,
heliculture, beekeeping and mushroom production (80 farms)
|
Works
|
not applicable
|
270
|
AOO
|
Control and Audit
|
4/15/2019
|
5/30/2019
|
7/29/2019
|
210,856.00
|
11/11/2019
|
|
|
|
SPMP
|
1
|
Works
|
Build and equip farms for grasscutter farming (20)
|
151.62
|
AOO
|
Control and Audit
|
1/16/2024
|
3/1/2024
|
3/16/2024
|
120,000
|
9/20/2023
|
7/6/2024
|
|
|
SPMP
|
1
|
Works
|
Build and equip farms for heliculture (20)
|
37.91
|
AOO
|
Control and Audit
|
1/16/2024
|
3/1/2024
|
3/16/2024
|
30,000
|
9/20/2023
|
7/6/2024
|
|
|
SPMP
|
1
|
Works
|
Build and equip farms for beekeeping (20)
|
37.91
|
AOO
|
Control and Audit
|
1/16/2024
|
3/1/2024
|
3/16/2024
|
30,000
|
9/20/2023
|
7/6/2024
|
|
|
SPMP
|
1
|
Works
|
Build and equip farms for mushroom production (20)
|
37.91
|
AOO
|
Control and Audit
|
1/16/2024
|
3/1/2024
|
3/16/2024
|
30,000
|
9/20/2023
|
7/6/2024
|
|
|
|
|
Works
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3
|
SPMP
|
|
Mechanical treatment (removing sand) over 50 km
|
Works
|
not applicable
|
64
|
P.S.
|
Control and Audit
|
6/15/2019
|
7/30/2019
|
9/24/2019
|
49,980.80
|
2/10/2020
|
|
|
|
|
|
Works
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4
|
BPM
|
|
Rehabilitation of 27 water reservoirs
|
Works
|
not applicable
|
379.80
|
AOO
|
Prior Examination
|
3/15/2020
|
4/29/2020
|
6/28/2020
|
300,586.00
|
9/1/2022
|
|
|
|
|
|
Works
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5
|
SPMP
|
|
Development of 96 km of route between PALE and LOKPOHO
|
Works
|
not applicable
|
205
|
AOO
|
Control and Audit
|
6/15/2019
|
7/30/2019
|
9/24/2019
|
160,094.70
|
10/2/2021
|
|
|
|
|
|
Works
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6
|
BPM
|
|
Construction of the KOUBAN dam
|
Works
|
not applicable
|
917
|
AOO
|
Prior Examination
|
3/15/2020
|
4/29/2020
|
6/28/2020
|
716,131
|
9/1/2022
|
|
|
|
|
|
Works
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7
|
SPMP
|
|
Construction of 2 landing stages
|
Works
|
not applicable
|
220
|
AOO
|
Control and Audit
|
8/15/2019
|
9/29/2019
|
11/24/2019
|
171,809
|
12/2/2021
|
|
|
|
|
|
Works
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8
|
SPMP
|
|
Establishment of 1 rearing station
|
Works
|
not applicable
|
327
|
AOO
|
Control and Audit
|
8/15/2019
|
9/29/2019
|
11/24/2019
|
255,370
|
12/2/2021
|
|
|
|
|
|
Works
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
9
|
SPMP
|
|
Construction of 17 community infrastructures to adapt to
climate change
|
Works
|
not applicable
|
384
|
AOO
|
Control and Audit
|
8/15/2019
|
9/29/2019
|
11/24/2019
|
299,884.80
|
12/2/2021
|
|
|
|
SPMP
|
1
|
Works
|
Construction of 04 autonomous drinking water points equipped
with solar energy system and 03 water boreholes equipped with human motor
pump with fence
|
378.92
|
AOO
|
Control and Audit
|
5/19/2024
|
6/18/2024
|
7/18/2024
|
299,884,800
|
11/7/2024
|
|
|
|
SPMP
|
1
|
Works
|
Reprofiling of 03 tracks, 01 road crossing infrastructure
and 01 irrigated perimeter
|
|
|
SPMP
|
1
|
Works
|
Construction of 05 Storage and conservation infrastructures
for agricultural products, 02 Sales areas and 01 Livestock exhibition stand
|
|
|
SPMP
|
|
Works
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
10
|
SPMP
|
|
Upgrade/installation of 3 agro meteorological stations
|
Works
|
not applicable
|
74
|
P.S.
|
Control and Audit
|
8/15/2019
|
9/14/2019
|
11/9/2019
|
57,790
|
12/2/2021
|
|
|
|
SPMP
|
1
|
Works
|
not applicable
|
74
|
P.S.
|
Control and Audit
|
2/20/2024
|
3/6/2024
|
4/5/2024
|
57,790
|
7/26/2024
|
|
|
|
|
|
Works
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
COMMUNITY MARKETS
|
|
|
|
|
|
|
|
|
|
|
|
|
|
11
|
BMP
|
|
Acquisition of 5,630,000 plants of local species for
agroforestry plots, forest plantations and wooded firebreaks
|
Works
|
not applicable
|
2,997
|
MC
|
Prior Examination
|
N / A
|
N / A
|
5/9/2019
|
2,340,507
|
4/15/2023
|
|
|
|
BPM
|
1
|
Works
|
Acquire 1,000,000 forest species plants for the plots
|
388.77
|
MC
|
Prior Examination
|
N / A
|
N / A
|
3/14/2024
|
307,683.00
|
9/25/2742
|
|
|
|
|
|
Works
|
Purchase of 476,939 forest species plants
|
87.38
|
MC
|
Prior Examination
|
N / A
|
N / A
|
6/30/2023
|
69,156.15
|
9/30/2023
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
12
|
BPM
|
|
Support for the establishment of 9,000 ha of agroforestry
plots (density of 50 stems)
|
Works
|
not applicable
|
416
|
MC
|
Prior Examination
|
N / A
|
N / A
|
7/9/2019
|
324,875.00
|
11/13/2019
|
|
|
|
BPM
|
1
|
Works
|
Support the establishment of 250 HA of agroforestry plots
(density 50 stems/ha)
|
8.92
|
MC
|
Prior Examination
|
N / A
|
N / A
|
3/9/2024
|
7,061.79
|
7/14/2024
|
|
|
|
|
|
Works
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
13
|
BPM
|
|
Support for the creation of 1,700 ha of high-value
reforestation (Tek, frake, framire, etc.)
|
Works
|
not applicable
|
640
|
MC
|
Prior Examination
|
N / A
|
N / A
|
7/9/2019
|
499,808
|
11/13/2019
|
|
|
|
BPM
|
1
|
Works
|
Support the creation of 300 HA of high-value reforestation
(teak, fraké, framiré, etc.)
|
106.82
|
MC
|
Prior Examination
|
N / A
|
N / A
|
3/9/2024
|
84,537.90
|
8/25/2023
|
|
|
|
|
|
Works
|
Support for the creation of
399.5 Ha of high-value reforestation
|
140.07
|
MC
|
Prior Examination
|
N / A
|
N / A
|
6/30/2023
|
110,856.08
|
12/31/2024
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
14
|
BPM
|
|
Support for the creation of 1,700 ha of energy wood
reforestation (acacia mangium, acasia auriculiformis, cassia siemea,
albizia SPP, etc.)
|
Works
|
not applicable
|
640
|
MC
|
Prior Examination
|
N / A
|
N / A
|
9/8/2019
|
499,808
|
1/13/2020
|
|
|
|
BPM
|
1
|
Works
|
Support the creation of reforestation of 100 HA of energy
wood (acacia mangium, acacia auriculiformis, cassia siamea, albizia spp.
Etc.).
|
90.36
|
MC
|
Prior Examination
|
N / A
|
N / A
|
3/9/2024
|
28,226.34
|
7/14/2024
|
|
|
|
|
|
Works
|
Support for the creation of
31.5 Ha of wood energy reforestation
|
11.14
|
MC
|
Prior Examination
|
N / A
|
N / A
|
6/30/2023
|
8,819.68
|
12/31/2023
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
15
|
BPM
|
|
Support for the establishment and maintenance of 2000 ha of
firebreaks for agroforestry plots
|
Works
|
not applicable
|
890.40
|
MC
|
Prior Examination
|
N / A
|
N / A
|
9/8/2019
|
704,692.80
|
1/13/2020
|
|
|
|
BPM
|
1
|
Works
|
Support the establishment and maintenance of 100 HA of
firebreaks on agroforestry plots.
|
28.53
|
MC
|
Prior Examination
|
N / A
|
N / A
|
3/9/2024
|
22,581.10
|
7/14/2024
|
|
|
|
|
|
Works
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
16
|
BMP
|
|
Support for the
development of 120 ha of urban forest in Yamoussoukro
|
Works
|
not applicable
|
154
|
MC
|
Prior Examination
|
N / A
|
N / A
|
11/8/2019
|
120,266.00
|
3/14/2020
|
|
|
|
BPM
|
1
|
Works
|
Support the development of the Yamoussoukro urban forest -
25 ha
|
35.48
|
MC
|
Prior Examination
|
N / A
|
N / A
|
3/9/2024
|
28,080.50
|
8/25/2023
|
|
|
|
BPM
|
|
Works
|
Realization of a sub-project for a green fence of 6,200
linear meters around the FUY
|
201.35
|
MC
|
Prior Examination
|
N / A
|
N / A
|
3/26/2024
|
159,350.70
|
7/24/2024
|
|
|
|
BPM
|
|
Carrying out 60 ha of reforestation work in the urban forest of
Yamoussoukro - 60 ha
|
31.97
|
MC
|
Prior Examination
|
N / A
|
N / A
|
7/8/2022
|
25,299
|
10/31/2022
|
|
|
|
|
|
Supply of 60,048 plants in bags for reforestation work on 60 Ha
of urban forest in Yamoussoukro
|
20.11
|
MC
|
Prior Examination
|
N / A
|
N / A
|
7/8/2022
|
15,915.7
|
8/7/2022
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
17
|
BPM
|
|
Support for the creation of 1,500 ha of perennial agricultural
plantations
|
Works
|
not applicable
|
768.00
|
MC
|
Prior Examination
|
N / A
|
N / A
|
11/8/2019
|
599,769.60
|
6/12/2020
|
|
|
|
BPM
|
1
|
Works
|
Support the creation of 500 HA of perennial agricultural
plantations.
|
189.53
|
MC
|
Prior Examination
|
N / A
|
N / A
|
3/9/2024
|
150,000
|
7/14/2024
|
|
|
|
|
|
Works
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
18
|
BPM
|
|
Support for the
rehabilitation of 1,000 ha of old plantations
|
Works
|
not applicable
|
620
|
MC
|
Prior Examination
|
N / A
|
N / A
|
1/9/2020
|
360,189
|
8/13/2020
|
|
|
|
BPM
|
1
|
Works
|
Support the rehabilitation of 60 HA of old plantations.
|
8.34
|
MC
|
Prior Examination
|
N / A
|
N / A
|
3/9/2024
|
6,600
|
7/14/2024
|
|
|
|
|
|
Works
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
19
|
BPM
|
|
Creation of conservation measures for 50 km of bank (bunds)
|
Works
|
not applicable
|
32
|
MC
|
Prior Examination
|
N / A
|
N / A
|
1/9/2020
|
24,990
|
5/15/2020
|
|
|
|
|
|
Works
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
20
|
BPM
|
|
Water and soil conservation work in 1,197 ha of cultivated
plots
|
Works
|
not applicable
|
1027
|
MC
|
Prior Examination
|
N / A
|
N / A
|
5/9/2020
|
802,035.60
|
1/11/2021
|
|
|
|
BPM
|
1
|
Works
|
Water and soil conservation work in 150 HA of cultivated
plots.
|
130.44
|
MC
|
Prior Examination
|
N / A
|
N / A
|
2/16/2024
|
103,230.60
|
6/22/2024
|
|
|
|
BPM
|
1
|
Works
|
Carrying out 80 HA of water
and soil conservation works in cultivated plots
|
24.26
|
MC
|
Prior Examination
|
N / A
|
N / A
|
6/30/2022
|
19,200.40
|
12/31/2022
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
21
|
BPM
|
|
Plantation of 1,726 ha in classified, municipal and village
forests
|
Works
|
not applicable
|
883.34
|
MC
|
Prior Examination
|
N / A
|
N / A
|
5/9/2020
|
699,101.40
|
4/11/2021
|
|
|
|
BPM
|
1
|
Works
|
Planting of 250 HA in classified, community and village
forests
|
142.15
|
MC
|
Prior Examination
|
N / A
|
N / A
|
3/7/2024
|
112,500
|
7/12/2023
|
|
|
|
BPM
|
|
Works
|
Carrying out Planting work
in classified, municipal and village forests (21 Ha)
|
3.18
|
MC
|
Prior Examination
|
N / A
|
N / A
|
6/30/2022
|
2,520
|
12/31/2024
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
22
|
BPM
|
|
Expansion of forest cover by 168 ha through the promotion of
voluntary nature reserves
|
Works
|
not applicable
|
487.00
|
MC
|
Prior Examination
|
N / A
|
N / A
|
5/9/2020
|
380,322.6
|
3/12/2021
|
|
|
|
BPM
|
1
|
Works
|
Expansion of forest cover through the promotion of voluntary
nature reserves 50 ha)
|
142.15
|
MC
|
Prior Examination
|
N / A
|
N / A
|
4/9/2024
|
112,500
|
8/14/2024
|
|
|
|
|
|
Works
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
23
|
BPM
|
|
Stocking of 27 water reservoirs with 500,000 fry
|
Works
|
|
47
|
MC
|
Prior Examination
|
N / A
|
N / A
|
5/9/2020
|
37,030.80
|
9/13/2020
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
24
|
BPM
|
|
Fight against invasive plants (100 km)
|
Works
|
not applicable
|
77
|
MC
|
Prior Examination
|
N / A
|
N / A
|
5/9/2020
|
60,133
|
9/13/2020
|
|
|
|
BPM
|
1
|
Works
|
Fight against invasive plants (100 km)
|
75.98
|
MC
|
Prior Examination
|
N / A
|
N / A
|
11/9/2024
|
60,133.00
|
3/16/2025
|
|
|
|
|
|
Works
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
25
|
BPM
|
|
Completion of 234 ha of bank reforestation work
|
Works
|
not applicable
|
576
|
MC
|
Prior Examination
|
N / A
|
N / A
|
5/9/2020
|
449,827.00
|
10/13/2020
|
|
|
|
BPM
|
1
|
Works
|
Carrying out reforestation work on the banks 150 ha)
|
321.22
|
MC
|
Prior Examination
|
N / A
|
N / A
|
3/9/2024
|
254,224.65
|
7/14/2023
|
|
|
|
BPM
|
1
|
Works
|
Realization of 223 HA of reforestation of the banks
|
176.45
|
MC
|
Prior Examination
|
N / A
|
N / A
|
6/30/2022
|
139,645
|
12/31/2022
|
|
|
|
|
Total cost
|
|
|
|
|
13,351
|
|
|
10,325,781
|
|
|
|
|
|
|
|
|
|
2,642.9
|
2,044,956.7
|
|
|
|
|
|
|
|
494.56
|
534,847.01
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
*
|
Insert the procurement system or regime used for the
procurement transaction within the project (SPME, Bank or Third Party PMPs)
|
|
|
|
+
|
If applicable
|
|
|
|
**
|
Total cost of the Package, lot or procurement transaction in
UA appearing in the REP
|
|
|
|
***
|
Indicate the control method - Audit of acquisitions within the
framework of the SPME / Prior examination / Post-examination
|
|
|
|
*+
|
Maintain the procurement “Plan” agreed during negotiation and
approved by the Boards of Directors, throughout the duration of the project
|
|
|
|
|
“Revised” includes all updates and revisions
|
|
|
|
|
Record the “actual” activity completion date
|
|
|
|
*++
|
The Template must be adapted to the two-stage bidding process
by adding appropriate columns for the second stage of the sequential
bidding period and bid evaluation process
|
|
|
|
*+++
|
Indicate the contract currency
|
|
|
REVISED PROCUREMENT
PLAN (PPM) OF PIDACC/BN COTE D’VOIRE COMPONENT – DETAILED VERSION FOR THE
ACQUISITION OF CONSULTANT SERVICES 2024
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Country / Executing Agency:
|
REPUBLIC
OF CÔTE D'IVOIRE
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Name of Project/Program:
|
Integrated
Program for Development and Adaptation to Climate Change in the Niger
Basin
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Loan/Grant number:
|
GEF/ABN
GRANT :
5550155001601 / FSC Grant: 5565155001751 / EU
Grant: 5110155000504 / FAD Loan: 2100150040895/ FSC Loan
: 5565130000651 / GCF Grant: 5585155000002 /
GCF Loan: 55 85150000004
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Period Covered by this PPM:
|
01/01/2024
to 12/31/2024
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Basic information
|
|
FRIEND
|
Terms of reference
|
Restricted List
|
|
Request for Proposals (RFP)
|
Evaluation of Proposals
|
|
Finalization
of the Contract
|
|
|
|
Order
|
Procurement
system+
|
Description
|
|
Selection Mode
|
Package or Time
Spent
|
Estimated Cost
(000 UA)**
|
Control and
Audit – Prior / Post-Examination of the Bank***
|
Revised or
Actual Plan*+
|
Publication
date
|
Closing
Date
|
Date of
submission
|
Date of Notice
of No Objection
|
Date of
submission
|
Date of Notice
of No Objection
|
Revised or
Updated Plan
|
Date of
Submission of RFP Documents
|
Date of Notice
of No Objection
|
RFP Issue Date
|
Deadline for
submission/opening of Proposals
|
Technical
Report Submission Date
|
Date of Notice
of No Objection
|
Opening Date of
Financial Proposals
|
Combined Report
Submission Date
|
Date of Notice
of No Objection
|
Revised or
Updated Plan
|
Contract Award
Date
|
Contract Amount
(000 F CFA) *++
|
Date of
Contract Signing
|
Contract
Completion Date
|
|
|
|
1
|
Bank
|
TECHNICAL
ASSISTANCE IN THE DEVELOPMENT OF PROJECTS AND SUB-PROJECTS
|
|
SBQC
|
Package
|
624
|
Prior
Examination
|
Plan
|
09/15/2018
|
09/30/2018
|
08/10/2018
|
10/22/2018
|
08/10/2018
|
10/22/2018
|
Plan
|
08/10/2018
|
10/22/2018
|
10/27/2018
|
11/26/2018
|
06/12/2018
|
11/12/2018
|
12/18/2018
|
12/25/2018
|
01/08/2019
|
Plan
|
01/13/2019
|
487,199
|
01/18/2019
|
11/23/2022
|
|
|
|
Technical assistance in the development of projects and
sub-projects
|
SBQC
|
Package
|
294.50
|
Prior Examination
|
Real
|
12/10/2020
|
10/27/2020
|
08/11/2020
|
09/08/2020
|
02/15/2021
|
04/20/2021
|
Real
|
02/15/2021
|
04/20/2021
|
04/29/2021
|
05/31/2021
|
08/26/2021
|
08/10/2021
|
10/20/2021
|
01/28/2022
|
01/04/2022
|
Real
|
01/04/2022
|
233,073
|
05/05/2022
|
12/31/2024
|
|
|
|
Training of 40 farmer groups on the establishment and
management of nurseries
|
SBQC
|
Package
|
51.48
|
Prior Examination
|
Real
|
12/10/2020
|
10/27/2020
|
08/11/2020
|
09/08/2020
|
02/15/2021
|
04/20/2021
|
Real
|
02/15/2021
|
04/20/2021
|
04/29/2021
|
05/31/2021
|
08/26/2021
|
08/10/2021
|
10/20/2021
|
01/28/2022
|
01/04/2022
|
Real
|
01/04/2022
|
40,743.50
|
05/05/2022
|
12/31/2024
|
|
|
|
Support for the implementation of ES measures
|
SBQC
|
Package
|
170.58
|
Prior Examination
|
Real
|
12/10/2020
|
10/27/2020
|
08/11/2020
|
09/08/2020
|
02/15/2021
|
04/20/2021
|
Real
|
02/15/2021
|
04/20/2021
|
04/29/2021
|
05/31/2021
|
08/26/2021
|
08/10/2021
|
10/20/2021
|
01/28/2022
|
01/04/2022
|
Real
|
01/04/2022
|
135,000
|
05/05/2022
|
12/31/2024
|
|
|
|
Organization and training of stakeholders in the fishing
sub-sector
|
SBQC
|
Package
|
38.29
|
Prior Examination
|
Real
|
12/10/2020
|
10/27/2020
|
08/11/2020
|
09/08/2020
|
02/15/2021
|
04/20/2021
|
Real
|
02/15/2021
|
04/20/2021
|
04/29/2021
|
05/31/2021
|
08/26/2021
|
08/10/2021
|
10/20/2021
|
01/28/2022
|
01/04/2022
|
Real
|
01/04/2022
|
30,300
|
05/05/2022
|
12/31/2024
|
|
|
|
User awareness campaign on the fight against pollution
|
SBQC
|
Package
|
6.64
|
Prior Examination
|
Real
|
12/10/2020
|
10/27/2020
|
08/11/2020
|
09/08/2020
|
02/15/2021
|
04/20/2021
|
Real
|
02/15/2021
|
04/20/2021
|
04/29/2021
|
05/31/2021
|
08/26/2021
|
08/10/2021
|
10/20/2021
|
01/28/2022
|
01/04/2022
|
Real
|
01/04/2022
|
5,256
|
05/05/2022
|
12/31/2024
|
|
|
|
Organization and training of committees of 28 infrastructure
management units
|
|
|
114.86
|
Prior Examination
|
Real
|
12/10/2020
|
10/27/2020
|
08/11/2020
|
09/08/2020
|
02/15/2021
|
04/20/2021
|
Real
|
02/15/2021
|
04/20/2021
|
04/29/2021
|
05/31/2021
|
08/26/2021
|
08/10/2021
|
10/20/2021
|
01/28/2022
|
01/01/2022
|
Real
|
01/04/2022
|
90,900
|
05/05/2022
|
12/31/2024
|
|
|
|
Agro-climatic support for producers
|
SBQC
|
Package
|
31.59
|
Prior Examination
|
Real
|
12/10/2020
|
10/27/2020
|
08/11/2020
|
09/08/2020
|
02/15/2021
|
04/20/2021
|
Real
|
02/15/2021
|
04/20/2021
|
04/29/2021
|
05/31/2021
|
08/26/2021
|
08/10/2021
|
10/20/2021
|
01/28/2022
|
01/04/2022
|
Real
|
01/04/2022
|
25,000
|
05/05/2022
|
12/31/2024
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2
|
Bank
|
DEVELOPMENT
OF THE SUB-BASIN MASTER PLAN
|
SBQC
|
Package
|
159
|
Prior
Examination
|
Plan
|
10/15/2018
|
10/30/2018
|
07/11/2018
|
11/21/2018
|
07/11/2018
|
11/21/2018
|
Plan
|
07/11/2018
|
11/21/2018
|
11/26/2018
|
12/26/2018
|
01/05/2019
|
10/01/2019
|
01/17/2019
|
01/24/2019
|
07/02/2019
|
Plan
|
02/12/2019
|
125,837
|
02/17/2019
|
08/11/2019
|
|
|
|
SBQC
|
Package
|
128.56
|
Prior Examination
|
Real
|
06/23/2020
|
07/14/2020
|
05/28/2020
|
08/06/2020
|
02/15/2021
|
04/20/2021
|
Real
|
04/29/2021
|
04/20/2021
|
04/29/2021
|
05/31/2021
|
07/23/2021
|
08/24/2021
|
02/09/2021
|
01/10/2021
|
06/11/2021
|
Real
|
13/11/2021
|
101,750
|
12/17/2021
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3
|
Bank
|
ACCOUNTING,
FINANCIAL AUDIT OF PMU ACCOUNTS AND PROCUREMENT
|
|
SMC
|
Package
|
62
|
Prior
Examination
|
Plan
|
07/15/2019
|
07/30/2019
|
07/08/2019
|
08/21/2019
|
07/08/2019
|
08/21/2019
|
Plan
|
07/08/2019
|
08/21/2019
|
08/26/2019
|
09/25/2019
|
05/10/2019
|
10/10/2019
|
10/17/2019
|
10/24/2019
|
07/11/2019
|
Plan
|
12/11/2019
|
49,068.7
|
11/17/2019
|
02/25/2020
|
|
|
|
ACCOUNTING,
FINANCIAL AUDIT OF PMU ACCOUNTS AND PROCUREMENT (FY 2019-2020 and 2021
|
SMC
|
Package
|
15.18
|
Prior Examination
|
Revised
|
04/20/2021
|
05/06/2021
|
01/27/2021
|
04/12/2021
|
06/14/2021
|
07/10/2021
|
Real
|
06/14/2021
|
07/14/2021
|
07/15/2021
|
08/16/2021
|
09/14/2021
|
09/27/2021
|
07/10/2021
|
15/10/2021
|
06/11/2021
|
Real
|
07/11/2021
|
12,010
|
12/11/2021
|
|
|
|
|
ACCOUNTING,
FINANCIAL AUDIT OF PMU ACCOUNTS AND PROCUREMENT (FY 2022, 2023 and 2024)
|
SMC
|
Package
|
11.37
|
Prior Examination
|
Real
|
11/22/22
|
12/19/22
|
07/17/22
|
08/25/22
|
12/27/22
|
03/26/23
|
Real
|
12/27/22
|
03/26/22
|
03/25/22
|
08/09/22
|
01/25/23
|
02/23/23
|
08/09/22
|
03/23/23
|
04/05/2023
|
Real
|
05/25/2023
|
9,000
|
04/07/2023
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4
|
Bank
|
STUDY AND CONTROL OF
INFRASTRUCTURE WORKS
|
|
SBQC
|
Package
|
211
|
Prior
Examination
|
Plan
|
10/15/2018
|
10/30/2018
|
07/11/2018
|
11/21/2018
|
07/11/2018
|
11/21/2018
|
Plan
|
07/11/2018
|
11/21/2018
|
11/26/2018
|
12/26/2018
|
01/05/2019
|
10/01/2019
|
01/17/2019
|
01/24/2019
|
07/02/2019
|
Plan
|
02/12/2019
|
167,000
|
02/17/2019
|
10/25/2020
|
|
|
|
Recruitment of the consultant for carrying out studies,
monitoring and control of infrastructures
|
SBQC
|
Package
|
211.01
|
Prior Examination
|
Real
|
10/13/2020
|
10/27/2020
|
03/12/2020
|
09/29/2020
|
02/24/2021
|
08/18/2021
|
Real
|
02/24/2021
|
08/18/2021
|
08/24/2021
|
09/28/2021
|
10/23/20221
|
07/12/2021
|
14/12/2021
|
04/13/2023
|
05/09/2023
|
Real
|
05/12/2023
|
167,000
|
06/21/2023
|
11/30/2024
|
|
|
|
Rehabilitation of 10 water reservoirs
|
SBQC
|
Package
|
175.69
|
Prior Examination
|
Real
|
10/13/2020
|
10/27/2020
|
03/12/2020
|
09/29/2020
|
02/24/2021
|
08/18/2021
|
Real
|
02/24/2021
|
08/18/2021
|
08/24/2021
|
09/28/2021
|
10/23/20221
|
07/12/2021
|
14/12/2021
|
04/13/2023
|
05/09/2023
|
Real
|
05/12/2023
|
139,050
|
06/21/2023
|
11/30/2024
|
|
|
|
Stocking of 10 water reservoirs
|
SBQC
|
Package
|
16.36
|
Prior Examination
|
Real
|
10/13/2020
|
10/27/2020
|
03/12/2020
|
09/29/2020
|
02/24/2021
|
08/18/2021
|
Real
|
02/24/2021
|
08/18/2021
|
08/24/2021
|
09/28/2021
|
10/23/20221
|
07/12/2021
|
14/12/2021
|
04/13/2023
|
05/09/2023
|
Real
|
05/12/2023
|
12,950
|
06/21/2023
|
11/30/2024
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5
|
Bank
|
FEASIBILITY
STUDY FOR THE OPERATIONALIZATION OF PES
|
SQC
|
Package
|
13
|
Prior
Examination
|
Plan
|
09/15/2018
|
09/30/2018
|
08/10/2018
|
10/22/2018
|
08/10/2018
|
10/22/2018
|
Plan
|
08/10/2018
|
10/22/2018
|
10/27/2018
|
11/26/2018
|
06/12/2018
|
11/12/2018
|
12/18/2018
|
12/25/2018
|
01/08/2019
|
Plan
|
01/13/2019
|
10,289
|
01/18/2019
|
10/09/2019
|
|
|
|
THIS
|
Package
|
12.99
|
Prior Examination
|
Real
|
11/22/2022
|
08/12/2022
|
07/27/2022
|
08/25/2022
|
12/28/2022
|
02/15/2023
|
Real
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
05/31/2023
|
07/07/2023
|
Real
|
07/10/2023
|
10,278.66
|
08/21/2023
|
09/22/2023
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6
|
Bank
|
STUDY
AND CONTROL OF MECHANICAL WORK (DE-SANDING)
|
SBQC
|
Time spent
|
83
|
Prior
Examination
|
Plan
|
09/15/2018
|
09/30/2018
|
08/10/2018
|
10/22/2018
|
08/10/2018
|
10/22/2018
|
Plan
|
08/10/2018
|
10/22/2018
|
10/27/2018
|
11/26/2018
|
06/12/2018
|
11/12/2018
|
12/18/2018
|
12/25/2018
|
01/08/2019
|
Plan
|
01/13/2019
|
65,689
|
01/18/2019
|
10/27/2020
|
|
|
|
SBQC
|
Time spent
|
|
Prior
Examination
|
Revised
|
01/24/2023
|
02/09/2023
|
11/30/2022
|
01/12/2023
|
03/14/2023
|
05/15/2023
|
Real
|
03/14/2023
|
05/15/2023
|
05/26/2023
|
06/27/2023
|
07/08/2023
|
|
|
|
|
Real
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7
|
Bank
|
SUPPORT
FOR THE UPGRADE OF HYDROMETRIC STATIONS ON THE NIGER RIVER AND ITS
TRIBUTORIES COAST COTE D’IVOIRE (In Direct
Agreement with the Hydrology Department)
|
SBQC
|
Package
|
38
|
posterior
|
Plan
|
02/15/2019
|
02/03/2019
|
03/10/2019
|
03/24/2019
|
03/10/2019
|
03/24/2019
|
Plan
|
03/10/2019
|
03/24/2019
|
03/29/2019
|
04/28/2019
|
08/05/2019
|
05/13/2019
|
05/20/2019
|
05/27/2019
|
10/06/2019
|
Plan
|
06/15/2019
|
30,074
|
06/20/2019
|
09/13/2019
|
|
|
|
ED
|
Package
|
38
|
Prior
Examination
|
Revised
|
N / A
|
N / A
|
02/22/2024
|
03/07/2024
|
N / A
|
N / A
|
Revised
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
Revised
|
03/14/2024
|
30,074
|
03/19/2024
|
03/08/2022
|
|
|
|
|
|
|
|
Real
|
|
|
|
|
|
|
Real
|
|
|
|
|
|
|
|
|
|
Real
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8
|
Bank
|
STUDY
AND CONTROL OF COMMUNITY INFRASTRUCTURES
|
SBQC
|
Time spent
|
162
|
Prior
Examination
|
Plan
|
10/15/2018
|
10/30/2018
|
07/11/2018
|
11/21/2018
|
07/11/2018
|
11/21/2018
|
Plan
|
07/11/2018
|
11/21/2018
|
11/26/2018
|
12/26/2018
|
01/05/2019
|
10/01/2019
|
01/17/2019
|
01/24/2019
|
07/02/2019
|
Plan
|
02/12/2019
|
89,657.28
|
02/17/2019
|
10/25/2020
|
|
|
|
SBQC
|
Time spent
|
111.09
|
Prior Examination
|
Real
|
03/01/2022
|
03/17/2022
|
09/16/2021
|
01/29/2022
|
10/19/2022
|
02/15/2023
|
Real
|
10/19/2022
|
02/15/2023
|
02/20/2023
|
03/28/2023
|
05/12/2023
|
07/18/2023
|
01/08/2023
|
09/19/2023
|
|
Real
|
|
87,920
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
9
|
Bank
|
DEVELOPMENT
AND UPDATING OF 7.5 COMMUNITY PLANS FOR ADAPTATION TO CLIMATE
CHANGE
|
SBQC
|
Package
|
96
|
Prior
Examination
|
Plan
|
15/12/2018
|
12/30/2018
|
07/01/2019
|
01/21/2019
|
07/01/2019
|
01/21/2019
|
Plan
|
07/01/2019
|
01/21/2019
|
01/26/2019
|
02/25/2019
|
07/03/2019
|
03/12/2019
|
03/19/2019
|
03/26/2019
|
04/09/2019
|
Plan
|
04/14/2019
|
75,977
|
04/19/2019
|
Elabi
|
|
|
|
SBQC
|
Package
|
|
Prior Examination
|
Real
|
01/11/2022
|
11/17/2022
|
05/27/2022
|
05/07/2022
|
12/28/2022
|
03/22/2023
|
Real
|
12/28/2022
|
03/22/2023
|
03/27/2023
|
05/10/2023
|
06/29/2023
|
09/13/2023
|
09/26/2023
|
|
|
Real
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
10
|
Bank
|
DEVELOPMENT
OF THE PROJECT PROCEDURES MANUAL
|
SQC
|
Package
|
14
|
Prior
Examination
|
Plan
|
15/12/2018
|
12/30/2018
|
07/01/2019
|
01/21/2019
|
07/01/2019
|
01/21/2019
|
Plan
|
07/01/2019
|
01/21/2019
|
01/26/2019
|
02/25/2019
|
07/03/2019
|
03/12/2019
|
03/19/2019
|
03/26/2019
|
04/09/2019
|
Plan
|
04/14/2019
|
11,080
|
04/19/2019
|
08/12/2019
|
|
|
|
|
|
|
|
Real
|
|
|
|
|
|
|
Real
|
|
|
|
|
|
|
|
|
|
Real
|
|
|
|
|
|
|
|
INDIVIDUAL CONSULTANT
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
11
|
Bank
|
DEVELOPMENT
OF THE ENVIRONMENTAL AND SOCIAL MANAGEMENT FRAMEWORK FOR THE IVORY COAST
COMPONENT
|
SBQC
|
Package
|
32.00
|
Prior
Examination
|
Plan
|
02/15/2019
|
02/03/2019
|
03/10/2019
|
03/24/2019
|
03/10/2019
|
03/24/2019
|
Plan
|
03/10/2019
|
03/24/2019
|
03/29/2019
|
04/28/2019
|
08/05/2019
|
05/13/2019
|
05/20/2019
|
05/27/2019
|
10/06/2019
|
Plan
|
06/15/2019
|
25,326
|
06/20/2019
|
09/28/2019
|
|
|
|
THIS
|
Package
|
19.11
|
Prior Examination
|
Real
|
15/12/2020
|
01/15/2021
|
06/13/2020
|
14/11/2019
|
04/29/2021
|
08/18/2021
|
Real
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
09/30/2021
|
07/10/2021
|
Real
|
14/10/2021
|
15,124
|
10/19/2021
|
01/14/2021
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
12
|
Bank
|
PREPARATION
OF THE PROJECT AND SUB-PROJECT FINANCING MANUAL
|
THIS
|
Package
|
39
|
Prior
Examination
|
Plan
|
15/12/2018
|
12/30/18
|
07/01/2019
|
01/21/19
|
01/07/19
|
01/17/19
|
Plan
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
Plan
|
02/28/2019
|
30,866
|
02/13/2019
|
05/14/2019
|
|
|
|
THIS
|
Package
|
21.79
|
Prior Examination
|
Real
|
01/05/20
|
05/13/20
|
07/11/2019
|
11/14/19
|
11/19/20
|
11/27/20
|
Real
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
12/18/20
|
01/07/2021
|
Real
|
02/08/2021
|
17,247
|
07/14/2021
|
10/25/2021
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
13
|
Bank
|
PREPARATION
OF 3 TECHNICAL MANUALS/CATALOGS FOR IMPROVING RESILIENCE (agroforestry,
resilient agricultural technologies, good practices)
|
THIS
|
Package
|
38
|
Prior Examination
|
Plan
|
02/15/2019
|
02/03/19
|
03/10/2019
|
03/24/19
|
03/10/19
|
03/20/19
|
Plan
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
Plan
|
01/05/2019
|
30,074
|
04/16/2019
|
06/30/2019
|
|
|
|
THIS
|
Package
|
17.63
|
Prior
Examination
|
Real
|
07/05/20
|
05/26/20
|
10/25/2019
|
3/13/2020
|
09/29/20
|
10/23/20
|
Real
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
12/17/2020
|
01/07/2021
|
Real
|
02/08/2021
|
13,950
|
07/14/2021
|
09/24/2021
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
14
|
Bank
|
TRAINING
OF TECHNICAL ASSISTANTS ON DIFFERENT THEMATICS (agroforestry,
technological packages, firefighting)
|
THIS
|
Package
|
31
|
Prior
Examination
|
Plan
|
02/15/2019
|
02/03/19
|
03/10/2019
|
03/20/19
|
03/10/19
|
03/20/19
|
Plan
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
Plan
|
01/05/2019
|
24,209
|
04/16/2019
|
06/15/2019
|
|
|
|
THIS
|
Package
|
2.58
|
Prior Examination
|
Real
|
07/07/20
|
07/15/20
|
05/07/2020
|
3/13/2020
|
09/29/20
|
10/23/20
|
Real
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
12/17/2020
|
01/07/2021
|
Real
|
02/08/2021
|
2,040
|
07/14/2021
|
08/10/2021
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
15
|
Bank
|
DEVELOPMENT
OF MANAGEMENT MODES FOR HYDRO AGRICULTURAL AND PASTORAL INFRASTRUCTURES
|
THIS
|
Package
|
26
|
posterior
|
Plan
|
02/15/2019
|
02/03/19
|
01/08/2019
|
01/22/19
|
03/10/19
|
03/20/19
|
Plan
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
Plan
|
01/05/2019
|
20,577
|
04/16/2019
|
08/14/2019
|
|
|
|
THIS
|
Package
|
26
|
posterior
|
Revised
|
02/14/2024
|
02/29/24
|
08/03/2024
|
03/22/24
|
08/03/24
|
03/18/24
|
Revised
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
Revised
|
03/25/2024
|
20,305
|
03/30/2024
|
04/29/2024
|
|
|
|
|
|
|
|
Real
|
|
|
|
|
|
|
Real
|
|
|
|
|
|
|
|
|
|
Real
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
16
|
Bank
|
KEY
PERSONNEL OF THE PROJECT MANAGEMENT UNIT
|
THIS
|
Package
|
332
|
Prior
Examination
|
Plan
|
09/15/18
|
09/30/18
|
08/08/2018
|
08/22/18
|
08/10/18
|
10/18/18
|
Plan
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
Plan
|
11/29/2018
|
262,755
|
14/11/2018
|
12/31/2025
|
|
|
|
THIS
|
Package
|
327.60
|
Prior
Examination
|
Real
|
09/15/19
|
09/30/19
|
08/08/2018
|
08/22/18
|
08/10/19
|
10/18/19
|
Real
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
Real
|
11/17/2019
|
259,275
|
02/12/2019
|
12/31/2025
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
17
|
Bank
|
KEY
PERSONNEL OF THE ODIENNE ANTENNA
|
THIS
|
Package
|
161
|
Prior
Examination
|
Plan
|
09/15/18
|
09/30/18
|
08/08/2018
|
08/22/18
|
08/10/18
|
10/18/18
|
Plan
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
Plan
|
11/29/2018
|
127,420
|
14/11/2018
|
01/07/2020
|
|
|
|
THIS
|
Package
|
161.00
|
Prior Examination
|
Real
|
04/21/19
|
06/05/19
|
03/14/2019
|
03/28/19
|
05/14/19
|
05/24/19
|
Real
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
Real
|
05/07/2019
|
127,420
|
06/20/2019
|
08/12/2020
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
18
|
Bank
|
IMPLEMENTATION OF A
RESULTS-ORIENTED MONITORING-EVALUATION SYSTEM
|
THIS
|
Package
|
25.80
|
Prior
Examination
|
Plan
|
09/15/18
|
09/30/18
|
08/08/2018
|
08/18/18
|
08/10/18
|
10/18/18
|
Plan
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
Plan
|
11/29/2018
|
20,152
|
14/11/2018
|
02/12/2019
|
|
|
|
THIS
|
Package
|
22.38
|
Prior
Examination
|
Real
|
06/15/21
|
01/07/21
|
05/31/20
|
05/31/21
|
08/25/21
|
03/18/22
|
Real
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
Real
|
08/10/2022
|
17,711.7
|
10/10/2022
|
11/24/2022
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
19
|
Bank
|
MID-TERM REVIEW OF THE
PIDACC/BN IVORY COAST COMPONENT
|
|
|
-
|
|
Plan
|
|
|
|
|
|
|
Plan
|
|
|
|
|
|
|
|
|
|
Plan
|
|
|
|
|
|
|
|
THIS
|
Package
|
13.11
|
Prior
Examination
|
Real
|
11/22/22
|
12/19/22
|
07/17/22
|
08/25/22
|
12/27/22
|
03/26/23
|
Real
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
|
Real
|
05/25/2023
|
10,372
|
01/08/2023
|
15/12/2023
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
20
|
Bank
|
ENVIRONMENTAL
AND SOCIAL AUDIT OF PIDACC/BN
|
|
|
|
|
|
Plan
|
|
|
|
|
|
|
Plan
|
|
|
|
|
|
|
|
|
|
Plan
|
|
|
|
|
|
|
|
ENVIRONMENTAL AND SOCIAL AUDIT FOR THE YEARS 2023 and 2024
|
THIS
|
Package
|
20.22
|
Prior
Examination
|
Revised
|
03/22/24
|
06/04/24
|
03/22/2024
|
05/04/24
|
04/20/24
|
04/05/24
|
Revised
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
05/09/24
|
N / A
|
05/23/2024
|
revised
|
05/28/2024
|
16,000
|
05/31/2024
|
06/30/2024
|
|
|
|
ENVIRONMENTAL AND SOCIAL AUDIT FOR THE YEARS 2019-2020, 2021
and 2022
|
THIS
|
Package
|
28.88
|
Prior
Examination
|
Real
|
07/03/23
|
03/23/23
|
03/02/23
|
02/28/23
|
05/16/23
|
07/18/23
|
Real
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
08/17/23
|
08/31/23
|
|
Real
|
|
22,860
|
|
|
|
|
|
TRAINING
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
21
|
|
Postgraduate
scholarship (doctoral) in Cocoa grown under shade
|
ED
|
Package
|
26.054
|
Prior Examination
|
Plan
|
N / A
|
N / A
|
01/05/19
|
05/15/19
|
N / A
|
N / A
|
Plan
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
Plan
|
05/18/2019
|
20,304
|
02/01/2020
|
07/31/2020
|
|
|
|
ED
|
Package
|
26.054
|
Prior
Examination
|
Revised
|
N / A
|
N / A
|
01/20/24
|
03/02/24
|
N / A
|
N / A
|
Revised
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
Revised
|
06/02/2024
|
20,347
|
02/11/2024
|
12/31/2024
|
|
|
|
|
|
|
Prior
Examination
|
Real
|
|
|
|
|
|
|
Real
|
|
|
|
|
|
|
|
|
|
Real
|
|
|
|
|
|
|
|
AGREEMENTS
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
22
|
Bank
|
TECHNICAL
SUPERVISION OF PLANTATIONS AND MONITORING OF ACTIVITIES WITH THE GENERAL
DIRECTORATE OF FORESTS AND WILDLIFE (DGFF)
|
ED
|
Package
|
140.87
|
Prior
Examination
|
Plan
|
N / A
|
N / A
|
02/28/19
|
03/14/19
|
N / A
|
N / A
|
Plan
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
Plan
|
05/16/2019
|
111,490
|
05/15/2019
|
05/09/2020
|
|
|
|
ED
|
Package
|
140.87
|
Prior Examination
|
Real
|
N / A
|
N / A
|
05/20/20
|
03/23/22
|
N / A
|
N / A
|
Real
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
Real
|
03/23/22
|
111,490
|
04/18/22
|
12/31/24
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
23
|
Bank
|
SUPERVISION
OF PRODUCERS OF 3000 HA OF AGRICULTURAL CROPS AND BREEDERS IN MANAGEMENT
CONSULTING WITH THE NATIONAL AGENCY FOR RURAL EQUIPMENT (ANADER)
|
ED
|
Package
|
197.00
|
Prior
Examination
|
Plan
|
N / A
|
N / A
|
03/31/19
|
04/14/19
|
N / A
|
N / A
|
Plan
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
Plan
|
06/16/2019
|
155,912
|
06/15/2019
|
06/09/2020
|
|
|
|
ED
|
Package
|
160.90
|
Prior Examination
|
Real
|
N / A
|
N / A
|
05/11/21
|
01/02/22
|
N / A
|
N / A
|
Real
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
Real
|
12/10/22
|
127,340
|
10/26/22
|
12/31/24
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
24
|
Bank
|
MONITORING
FOOD SAFETY WITH THE GENERAL DIRECTORATE OF FOOD SAFETY (DGPSA)
|
ED
|
Package
|
68
|
Prior
Examination
|
Plan
|
N / A
|
N / A
|
04/30/19
|
05/14/19
|
N / A
|
N / A
|
Plan
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
Plan
|
07/16/2019
|
52,800
|
07/15/2019
|
07/09/2020
|
|
|
|
ED
|
Package
|
66.71
|
Prior Examination
|
Real
|
N / A
|
N / A
|
06/17/22
|
08/29/22
|
N / A
|
N / A
|
Real
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
Real
|
11/28/2022
|
52,799
|
12/22/2022
|
12/31/2024
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
25
|
Bank
|
Monitoring and supervision of Plantation works of 1,700 ha
of reforestation in the classified forests of the national portion of the
Niger River basin and the Development of 96 km of transhumance routes in
the classified forest of Palé (By SODEFOR)
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
ED
|
Package
|
98.05
|
Prior
Examination
|
Revised
|
N / A
|
N / A
|
08/29/23
|
13/12/23
|
N / A
|
N / A
|
Revised
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
revised
|
01/05/2024
|
77,598.60
|
01/15/2024
|
12/31/2025
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Environmental
monitoring and surveillance by the National Environment Agency
(ANDE)
|
|
ED
|
Package
|
39
|
Prior
Examination
|
Plan
|
N / A
|
N / A
|
02/28/19
|
03/14/19
|
N / A
|
N / A
|
Plan
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
Plan
|
05/16/2019
|
30,457
|
05/15/2019
|
05/09/2020
|
|
|
|
|
|
|
ED
|
Package
|
39.00
|
Prior
Examination
|
Revised
|
N / A
|
N / A
|
02/13/24
|
02/28/24
|
N / A
|
N / A
|
Revised
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
N / A
|
revised
|
03/05/2024
|
30,457
|
08/03/2024
|
12/31/2025
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2,578,736
|
|
Plan
|
|
Plan
|
|
Plan
|
|
1,993,755,980
|
|
|
|
|
|
|
|
|
|
246,976
|
Revised
|
Revised
|
Revised
|
194,781,300
|
|
|
|
|
|
|
|
2,372,744
|
Real
|
Real
|
Real
|
1,877,860,690
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
*
|
Insert the procurement system or regime used for the
procurement transaction within the project (SPME, Bank or Third Party
PMPs)
|
|
|
|
|
-
|
|
|
|
|
|
|
+
|
If applicable
|
|
|
|
|
|
|
|
|
|
|
|
**
|
Total cost of the Package, lot or procurement transaction in
UA appearing in the REP
|
|
|
|
|
|
|
|
|
|
|
|
***
|
Indicate the control method - Audit of acquisitions within
the framework of the SPME / Prior examination / A posteriori examination
|
|
|
|
|
|
|
|
|
|
|
|
*+
|
Maintain the procurement “Plan” agreed during negotiation
and approved by the Boards of Directors, throughout the duration of the
project
|
|
|
|
|
|
|
|
|
|
|
|
|
“Revised” includes all updates and revisions
|
|
|
|
|
|
|
|
|
|
|
|
|
Record the “actual” activity completion date
|
|
|
|
|
|
|
|
|
|
|
|
*++
|
The Template must be adapted to the two-stage bidding
process by adding appropriate columns for the second stage of the
sequential bidding period and bid evaluation process
|
|
|
|
|
|
|
|
|
|
|
|
*+++
|
Indicate the contract currency
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PROCUREMENT PLAN
– SIMPLIFIED VERSION FOR THE ACQUISITION OF GOODS FY 2024
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Country / Executing Agency:
|
|
REPUBLIC
OF CÔTE D'IVOIRE
|
|
|
|
|
Name of Project/Program:
|
|
Integrated
Program for Development and Adaptation to Climate Change in the Niger
Basin
|
|
|
|
|
Loan/Grant number:
|
|
GEF/ABN
GRANT :
5550155001601 / FSC Grant: 5565155001751 / EU
Grant: 5110155000504
|
|
|
|
|
|
|
|
|
FAD
Loan: 2100150040895 / FSC Loan: 5565130000651 / GCF Grant: 5585155000002
/ GCF Loan: 5585150000004
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Period Covered by this PPM:
|
|
01/01/2024
to 12/31/2024
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Order
|
Procurement
system
|
Package Number
|
Package
Description
|
Category--
|
Description of
the lot+
|
Estimated Cost
(000 UA)**
|
Procurement
method
|
Control and Audit
- Examination of the bank (Prior/Posterior)***
|
AAO Publication
Date
|
Submission
deadline / Bid opening date
|
Contract award
date
|
Contract Amount
(000 FCFA) **++
|
Contract
Completion Date
|
Comment for the
execution of the contract
|
|
|
|
|
|
|
|
|
|
1
|
SPMP
|
|
Acquisition and putting into circulation of 140 tricycles
|
GOOD
|
Acquisition and putting into circulation of 140 tricycles
|
251
|
AOO
|
Control and Audit
|
7/15/2018
|
3/11/2022
|
3/22/2022
|
196,018.00
|
5/19/2022
|
|
|
|
|
1
|
Acquisition and circulation of 60 tricycles (to provide
GIEs with tricycles (processing of attiéké and valorization of NTFPs)
|
106.14
|
AOO
|
Control and
Audit
|
4/16/2024
|
5/16/2024
|
6/7/2024
|
84,000
|
7/25/2024
|
|
|
|
|
|
Provide the groups with (80) tricycles for transporting plants
to the nursery.
|
142.83
|
AOO
|
Control and Audit
|
2/8/2022
|
8/14/2018
|
9/5/2018
|
113,040
|
5/19/2022
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2
|
SPMP
|
|
Acquisition of small agricultural equipment to equip 1000 ha
of market gardening and 1000 ha of cassava
|
GOOD
|
|
256
|
AOO
|
Control and Audit
|
7/15/2018
|
3/5/2023
|
3/27/2023
|
199,923.20
|
7/12/2023
|
|
|
|
|
1
|
GOOD
|
Support market gardening equipment (1,000 ha)
|
131.95
|
CF
|
Control and
Audit
|
3/23/2024
|
4/22/2024
|
5/16/2024
|
104,427.12
|
8/29/2024
|
|
|
|
|
1
|
GOOD
|
Support cassava cultivation equipment (1,000 ha)
|
131.95
|
CF
|
Control and
Audit
|
3/23/2024
|
4/22/2024
|
5/16/2024
|
104,427.12
|
8/29/2024
|
|
|
|
|
|
GOOD
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3
|
SPMP
|
|
Acquisition of 20 agricultural machines and 20 attiéke and
derivative processing machines for economic interest groups
|
GOOD
|
|
640
|
AOO
|
Control and Audit
|
6/15/2018
|
7/25/2023
|
8/16/2023
|
499,808.00
|
9/2/2023
|
|
|
|
|
1
|
GOOD
|
Equipping 20 Economic Interest Groups (EIGs) with
agricultural machinery
|
252.71
|
AOO
|
Control and
Audit
|
4/3/2024
|
5/3/2024
|
5/25/2024
|
200,000.00
|
6/11/2024
|
|
|
|
|
1
|
GOOD
|
Equip 20 GIEs for processing attiéké and derivatives with
production equipment
|
379.06
|
AOO
|
Control and
Audit
|
4/3/2024
|
5/3/2024
|
5/25/2024
|
300,000.00
|
6/11/2024
|
|
|
|
|
|
GOOD
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4
|
SPMP
|
|
Acquisition of 94 kits for the dissemination of resilient
technologies
|
GOOD
|
|
239
|
AOO
|
Control and Audit
|
2/15/2019
|
2/4/2022
|
2/15/2022
|
186,647.00
|
12/31/2022
|
|
|
|
|
4
|
GOOD
|
Ensuring the dissemination of resilient technologies 44
kits)
|
113.79
|
CF
|
N / A
|
2/7/2023
|
1/0/1900
|
1/0/1900
|
102,338.25
|
1/0/1900
|
|
|
|
|
2
|
GOOD
|
Supply and delivery of seventeen (17) improved seed kits (Lot
1: improved corn seeds, lot 2: improved rice seeds and lot 3: improved
cassava cuttings)
|
20.39
|
CF
|
Control and Audit
|
1/25/2022
|
2/4/2022
|
2/15/2022
|
16,141
|
12/31/2022
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5
|
SPMP
|
|
Edition of 10,000 technical manuals
|
GOOD
|
Edition of 10,000 technical manuals
|
38
|
P.S.
|
Control and Audit
|
3/15/2019
|
1/0/1900
|
1/0/1900
|
29,676.00
|
1/0/1900
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
37.34
|
P.S.
|
Control and Audit
|
11/9/2023
|
11/17/2023
|
11/20/2023
|
29,550.00
|
12/5/2023
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6
|
SPMP
|
|
Supply and commissioning of two (02) Satation Wagon 4X4
vehicles with 7 seats and nine (09) double cabin covered vehicles of the
4X4 type
|
GOOD
|
|
307
|
AOO
|
Control and Audit
|
3/15/2019
|
9/16/2020
|
5/25/2021
|
239,750.60
|
1/0/1900
|
|
|
|
|
|
Supply and commissioning of two (02) Satation Wagon 4X4
vehicles with 7 seats and eight (08) double cabin covered vehicles of
type 4X4
|
271.66
|
AOO
|
Control and Audit
|
9/15/2020
|
9/16/2020
|
5/25/2021
|
215,000
|
|
The two (02) contracts resulting from this acquisition
procedure have been terminated. The State Judicial Agents were
contacted
|
|
|
|
|
|
Supply and putting into circulation of one (01) 4X4 type
vehicle
|
25.46
|
ED
|
Control and Audit
|
10/20/2023
|
N / A
|
N / A
|
20,150
|
12/15/2023
|
The project acquired a vehicle through the Market Value Order
Letter (LCVM) procedure.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7
|
SPMP
|
|
Supply and commissioning of twenty (22) 150 CC type Cross
motorcycles for twenty (20) Forestry Technical Agents and two (02)
Liaison Agents
|
GOOD
|
|
56
|
P.S.
|
Control and Audit
|
3/16/2021
|
3/26/2021
|
5/28/2021
|
43,733.20
|
7/9/2021
|
|
|
|
|
|
GOOD
|
Provide the AT with rolling stock (22 motorcycles)
|
41.70
|
P.S.
|
Control and Audit
|
3/16/2021
|
3/30/2019
|
5/15/2019
|
33,000
|
9/11/2019
|
|
|
|
|
|
|
Provide the AT with rolling stock (04 motorcycles)
|
8.34
|
P.S.
|
Control and Audit
|
1/19/2023
|
2/3/2023
|
4/6/2023
|
6,600
|
5/8/2023
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8
|
SPMP
|
|
Acquisition of small technical equipment to equip 700 bush
fire fighting committees
|
GOOD
|
|
90
|
P.S.
|
Control and Audit
|
3/15/2019
|
1/0/1900
|
1/0/1900
|
70,285.50
|
1/0/1900
|
|
|
|
|
|
GOOD
|
Provide bushfire control committees with technical equipment
(700 committees)
|
82.13
|
P.S.
|
Control and Audit
|
12/13/2023
|
12/28/2023
|
1/5/2023
|
65,000.00
|
1/7/2024
|
Procedure currently
being carried out
|
|
|
|
|
GOOD
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
9
|
SPMP
|
|
Acquisition of 1 analysis kit and equipment for the
operationalization of the IRM system in Ivory Coast
|
GOOD
|
|
128
|
AOO
|
Control and Audit
|
3/15/2019
|
1/0/1900
|
1/0/1900
|
99,961.60
|
1/0/1900
|
|
|
|
|
|
GOOD
|
Acquisition of 1 analysis kit for the operationalization of
the IRM system in Ivory Coast
|
56.63
|
AOO
|
Control and Audit
|
8/31/2023
|
10/17/2023
|
11/9/2023
|
44,821.00
|
12/24/2023
|
|
|
|
|
|
GOOD
|
Acquisition of equipment for the operationalization of the IRM
system in Ivory Coast
|
63.03
|
AOO
|
Control and Audit
|
8/31/2023
|
10/17/2023
|
11/9/2023
|
49,886.00
|
12/24/2023
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
10
|
SPMP
|
|
Acquisition of 5 canoes, 50 lots of small equipment for
infrastructure management committees, 1 lot of equipment for 30
vulnerable groups and 4 lots of equipment for GRN SMEs
|
GOOD
|
|
531
|
AOO
|
Control and Audit
|
3/15/2019
|
11/16/2023
|
12/8/2023
|
414,684.40
|
12/25/2023
|
|
|
|
|
|
GOOD
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
11
|
SPMP
|
|
Acquisition of 1 batch of computer and peri-computer
equipment for the UGP and the antenna
|
GOOD
|
|
11
|
PSC
|
Control
and Audit
|
3/15/2019
|
3/5/2021
|
3/22/2021
|
8,590
|
4/19/2021
|
|
|
|
|
|
Acquisition of 30 external hard drives 01 large server to
equip Rureaux Agents
|
5.4
|
PSC
|
Control and Audit
|
1/26/2024
|
2/2/2024
|
2/4/2024
|
4,293
|
2/22/2024
|
See ADB ANO Ref: AHAI.2/LT/BAI/2023/02/032
Date: 02/23/2023 relating to the equipment of Rureaux Agents.
|
|
|
|
|
Acquisition of 24 laptops to equip rural agents
|
1.08
|
PSC
|
Control and Audit
|
3/1/2021
|
3/5/2021
|
3/22/2021
|
7,735
|
4/19/2021
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
12
|
SPMP
|
|
Acquisition of 1 batch of office equipment and furniture for
the UGP and the antenna
|
GOOD
|
|
11
|
PSC
|
Control and Audit
|
3/15/2019
|
3/10/2021
|
3/22/2021
|
8,590
|
4/7/2021
|
|
|
|
|
|
|
16.37
|
PSC
|
Control and Audit
|
3/5/2021
|
3/10/2021
|
3/22/2021
|
12,959
|
4/7/2021
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
13
|
|
|
Acquisition
of one (01) batch of equipment for rural facilitators
|
|
|
26.73
|
CF
|
Control and Audit
|
|
|
|
21,153
|
|
|
|
|
|
|
|
|
Big Server + External hard drive + Desk, and Table +
Armchair + Digital camera
|
7.38
|
CF
|
Control and
Audit
|
2/26/2024
|
3/2/2024
|
3/10/2024
|
5,840
|
3/28/2024
|
|
|
|
|
|
|
|
Acquisition of a batch of equipment (individual protective
equipment, 14 GPS for Rureaux Agents.
|
19.35
|
CF
|
Control and Audit
|
12/7/2022
|
12/13/2022
|
12/14/2022
|
15,313
|
12/30/2022
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
14
|
SPMP
|
|
Acquisition of 1 accounting software including configuration
and training
|
GOOD
|
|
13
|
PSC
|
Control and Audit
|
5/15/2019
|
5/30/2019
|
6/27/2019
|
10,152
|
8/12/2019
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total cost
|
|
|
|
|
2,571
|
|
|
2,007,820
|
|
|
|
|
|
|
|
|
|
|
1,203.1
|
964,485.5
|
|
|
|
|
|
|
|
|
786.31
|
629,195.00
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
*
|
Insert the procurement system or regime used for the
procurement transaction within the project (SPME, Bank or Third Party
PMPs)
|
|
|
|
|
+
|
If applicable
|
|
|
|
|
**
|
Total cost of the Package, lot or procurement transaction in
UA appearing in the REP
|
|
|
|
|
***
|
Indicate the control method - Audit of acquisitions within
the framework of the SPME / Prior examination / A posteriori examination
|
|
|
|
|
*+
|
Maintain the procurement “Plan” agreed during negotiation
and approved by the Boards of Directors, throughout the duration of the
project
|
|
|
|
|
|
“Revised” includes all updates and revisions
|
|
|
|
|
|
Record the “actual” activity completion date
|
|
|
|
|
*++
|
The Template must be adapted to the two-stage bidding
process by adding appropriate columns for the second stage of the
sequential bidding period and bid evaluation process
|
|
|
|
|
*+++
|
Indicate the contract currency
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|