Tender Details
Deptt./Rly. Unit DANAPUR DIVISION-ENGINEERING/EAST CENTRAL RLY
Tender No. W7ETender01OpenDNR24-25-4
Tender Title Construction of Sick Line shed and other required facility at ARA Coaching Complex of Danapur Division.
Contract Type Works
Tender Type Open
Advertised Value32805981.06
Bidding Style [ Decision at Schedule level ]
Bidding System Single Packet System
Pre-Bid Required No
Pre-Bid Query Date Time Not Applicable
Tendering Section SRDEN3
Bidding Unit
Publishing Date / Time 06/05/2024 22:22
Period Of Completion 11 Months
Bidding Start Date 15/05/2024
Closing Date Time29/05/2024 12:00
Validity of Offer ( Days)60
Are Joint Venture (JV) firms allowed to bid-
Tender Doc. Cost (Rs.)0.00
Earnest Money (Rs.)314000.00
DescriptionProviding and fixing of self supported arch shaped mechanically seamed trussless galvalume roofing system such as proflex or similar as approved by Engineer-in-charge, made of superior quality structural grade steel, having 350 MPA yield strength, pre coated galvalume sheet as per ASTM A 792 M of base thickness 1.0mm (tolerance +/- 0.02mm) with minimum coating mass as per AZM 150. Total coated thickness 1.075mm (tolerance +/- 0.02mm). Roofing should be designed as per ASCE 7-20 international bui...
More DetailsClick Here To Open
Tender No:  W7ETender01OpenDNR24-25-4 Dept/Rly:  DANAPUR DIVISION-ENGINEERING/EAST CENTRAL RLY Closing Date/Time:   29/05/2024 12:00
 
Tender Title: Construction of Sick Line shed and other required facility at ARA Coaching Complex of Danapur Division. Tender Type: Open
 
Tender Status Published
List of documents attached with the tender
S.No File Name Document Description
1 CorrigenduminGCCforGST.pdf Corrigendum in GCC for GST
2 AnnexureVandVArevised.pdf ANNEXURE V AND VA REVISED
3 Spl.Conditionsteelfabrication.pdf SPECIAL CONDITION FOR FABRICATION OF STEEL
4 GeneralConditionGeneralObligationBaseduponGCC-2022Rev..pdf General Condition General Obligation Based upon GC......
5 ACS-2toGCC-2022_2022-CE-1-CT-GCC-2022-POLICY_13.12.2022_1.pdf ACS 2
6 CorrigenduminGCCforGST1.pdf Corrigendum in GCC for GST
7 GuidelineforSteelReinforcement.pdf Guideline for Steel Reinforcement
8 2018_CE-I_CT_9Date04_06_2018_1.pdf Annexure-B
9 2018_CE-I_CT_9Date04_06_2018.pdf Letter of Credit
10 AnnexureVIB.pdf Annexure VIB
11 BidSecurityAnnexureVIA.pdf Bid Security Annexure VIA
12 GCC_April-2022_2022_CE-I_CT_GCC-2022_POLICY_27.04.22.pdf IRSGCC April 2022
13 AdvanceCorrectionSlipNo_5ACS-5.pdf Correction silip 5 of GCC-2022
14 ACS1ofGCC2022.pdf ACS 1
15 ImplementationofContractore-MeasurementBook.pdf IMPLEMENTATION OF CONTRACTOR E MB
16 2022_CE-I_CT_GCC-2022Policy14.07.2022.pdf Advance Correction Slip No.1 of GCC-2022
17 ACS3ofGCC2022.pdf ACS 3
18 CorrectionSlipNo_6ACS-6GCC-2022.pdf ACS 6
19 acs4.pdf ACS 4
20 TenderDocumentofSickLineARA.pdf Tender Document
Corrigenda
Details of corrigendum are shown below. However, data/details in NIT/Tender document is updated duly incorporating all corrigenda issued. 
S.No Name Date/Time Action
No Corrigendum Issued