Tender Details |
Deptt./Rly. Unit | NAGPUR CR DIVISION-ENGINEERING/CENTRAL RLY |
Tender No. | DRMWNGP-69-2024-01 |
Tender Title | 1) Proposed balance work of 3rd and 4th line between Ajni-Khapri section under ADEN(S) NGP sub-division. 2) Proposed balancer work of 3rd and 4th line between Bitibori-Khapri section under ADEN(S) NGP sub-division. |
Contract Type | Works |
Tender Type | Open |
Advertised Value | 43943239.73 |
Bidding Style | Single Rate for Each Schedule |
Bidding System | Single Packet System |
Pre-Bid Required | No |
Pre-Bid Query Date Time | Not Applicable |
Tendering Section | CTL |
Bidding Unit | |
Publishing Date / Time | 26/07/2024 19:31 |
Period Of Completion | 8 Months |
Bidding Start Date | 05/08/2024 |
Closing Date Time | 19/08/2024 15:00 |
Validity of Offer ( Days) | 60 |
Are Joint Venture (JV) firms allowed to bid | - |
Tender Doc. Cost (Rs.) | 0.00 |
Earnest Money (Rs.) | 369700.00 |
Description | MS item (USSOR 2021) S.No. Item Code Item Qty Qty Unit Unit Rate Basic Value Escl.(%) Amount Bidding Unit Schedule 02-PART (1)B(i) -Construction of Concrete Drain - Proposed balance work of 3rd and 4th line between Ajni-Khapri section under ADEN(S) NGP sub-division. 12353623.22 Above/ Below/Par 01 Please see Item Breakup for details. 11993808.95 3.00 12353623.22 |
More Details | Click Here To Open |