Tender Details
Deptt./Rly. Unit RATLAM DIVISION-ENGINEERING/WESTERN RLY
Tender No. RTM-2024-25-81
Tender Title Ratlam-Neemach section :Construction of RUB between Br.No. 429 and 430 by inserting relieving girder and laying the box(es) by pushing the box below the relieving girder.
Contract Type Works
Tender Type Open
Advertised Value59658163.04
Bidding Style Single Rate for Each Schedule
Bidding System Single Packet System
Pre-Bid Required No
Pre-Bid Query Date Time Not Applicable
Tendering Section WA SECTION
Bidding Unit
Publishing Date / Time 29/08/2024 11:45
Period Of Completion 10 Months
Bidding Start Date 16/09/2024
Closing Date Time30/09/2024 15:00
Validity of Offer ( Days)60
Are Joint Venture (JV) firms allowed to bid-
Tender Doc. Cost (Rs.)0.00
Earnest Money (Rs.)448300.00
DescriptionUSSOR Items S.No. Item Code Item Qty Qty Unit Unit Rate Basic Value Escl.(%) Amount Bidding Unit Schedule B-USSOR Item 5421241.87 Above/ Below/Par 2 Please see Item Breakup for details. 6913967.44 (-) 21.59 5421241.87
More DetailsClick Here To Open
Tender No:  RTM-2024-25-81 Dept/Rly:  RATLAM DIVISION-ENGINEERING/WESTERN RLY Closing Date/Time:   30/09/2024 15:00
 
Tender Title: Ratlam-Neemach section :Construction of RUB between Br.No. 429 and 430 by inserting relieving girder and laying the box(es) by pushing the box below the relieving girder. Tender Type: Open
 
Tender Status Published
List of documents attached with the tender
S.No File Name Document Description
1 LETTEROFCREDITASMODEOFPAYMENT062018.pdf LETTER OF CREDIT
2 Safetyrules.pdf safety rules
3 ProcedureforpaymentofContractorbillasperGSTImplementation_GST_290617.pdf PROCEDURE FOR PAYMENT OF CONTRACTORS BILL AS PER G......
4 PROCEDUREORDERFORENSURINGSAFETYATWORKSITE.pdf SAFETY AT WORK SITE
5 PBGproforma.pdf PBG PERFORMA
6 NOrelativecertificate.pdf NORELATIVECERTIFICATE
7 certificateforrailwayemployeereengagement_1.pdf engagement of retd. rly employee
8 TERMINATIONCONTRACT.pdf Termination preforma
9 ACS5GCC2022.pdf ACS 5 of GCC 2022
10 07.08.23ACS4.pdf ACS4dt 07Aug23
11 07.08.23LAUNCHEMB.pdf contractor e-measurement book
12 BidCapacity-AnnexureVI.pdf Bid Capacity Annexure VI
13 OffloadingPartSofworkRBLetterNo2022-CE-I-CT-GCC-2020-Polociydt27Apr2022.pdf Offloading Part-S-of Work
14 BidsecurityAnnexure-VIA.pdf Annexure VIA- Bid security Format
15 FormatforAnnualcontractualturnoverAnnexure-VIB.pdf Annexure VIB-Annual Cobntractual Turnover
16 GCCAPRIL2022.pdf GCC April 2022
17 MOUFORJVGCCAPRIL22WITHALLACS.pdf MOU for JV
18 AnnexureVasperACS4dt07.08.2023.pdf AnnexureV as per ACS4dt 07Aug23
19 AnnexureVA.pdf Annexure V -A for signature of constituent firm or......
20 ACS6GCC2022.pdf ACS 6 of GCC 2022
21 ACS2dt13Dec22.pdf ACS 2 dt 13Dec22
22 ACS1GCCAPR2022.pdf Advance Correction Slip 2 date 14.07.2022 for GCC ......
23 ACS3dt26APR23.pdf ACS 3 date 26.04.2023
24 LetterNo.2017-CE-I-CT-9date31May2023.pdf Contractor s e-measurement book -e-MB
25 SPECIALCONDITIONforRUB.pdf Special Condition
Corrigenda
Details of corrigendum are shown below. However, data/details in NIT/Tender document is updated duly incorporating all corrigenda issued. 
S.No Name Date/Time Action
No Corrigendum Issued