Tender Details
Deptt./Rly. Unit DYCE-C-CATR-ENGINEERING/WEST CENTRAL RLY
Tender No. DYCEC-II-STA-05-2024
Tender Title Construction of Steel Foot Over Bridge (3.66m wide) including foundation and roof sheeting at Karhi, Barethiya, Nagod, Devendranagar and 6.0m wide FOB at Panna and provision of side pathway in Major Bridge No. 15, 32 etc. in connection with Satna-Panna New Line Project.
Contract Type Works
Tender Type Open
Advertised Value282287434.36
Bidding Style Single Rate for Each Schedule
Bidding System Two Packet System
Pre-Bid Required No
Pre-Bid Query Date Time Not Applicable
Tendering Section DY CE CATR
Bidding Unit
Publishing Date / Time 16/09/2024 20:30
Period Of Completion 12 Months
Bidding Start Date 30/09/2024
Closing Date Time14/10/2024 15:00
Validity of Offer ( Days)90
Are Joint Venture (JV) firms allowed to bid-
Tender Doc. Cost (Rs.)0.00
Earnest Money (Rs.)1561400.00
DescriptionUSSOR-2021 ITEMS S.No. Item Code Item Qty Qty Unit Unit Rate Basic Value Escl.(%) Amount Bidding Unit Schedule B-CEMENT 9682051.08 Above/ Below/Par 1 Please see Item Breakup for details. 9396400.50 3.04 9682051.08
More DetailsClick Here To Open
Tender No:  DYCEC-II-STA-05-2024 Dept/Rly:  DYCE-C-CATR-ENGINEERING/WEST CENTRAL RLY Closing Date/Time:   14/10/2024 15:00
 
Tender Title: Construction of Steel Foot Over Bridge (3.66m wide) including foundation and roof sheeting at Karhi, Barethiya, Nagod, Devendranagar and 6.0m wide FOB at Panna and provision of side pathway in Major Bridge No. 15, 32 etc. in connection with Satna-Panna New Line Project. Tender Type: Open
 
Tender Status Published
List of documents attached with the tender
S.No File Name Document Description
1 UpdatedTenderDocumentFOB16-09-2024.pdf TENDER DOCUMENT
2 UpdatedSpecialConditionFOB16-09-2024.pdf SPECIAL CONDITIONS
3 GCC_April-2022__27_04_22.pdf GENERAL CONDITION OF CONTRACT 2022
4 GCCACS1-6_compressed.pdf GCC ACS 2022 1 to 6
5 TopSheet.pdf TOP SHEET
Corrigenda
Details of corrigendum are shown below. However, data/details in NIT/Tender document is updated duly incorporating all corrigenda issued. 
S.No Name Date/Time Action
No Corrigendum Issued